CHAPTER FOUR

Defining
the Project

Copyright 2014 McGraw-Hill Education.


All Rights Reserved.
PowerPoint Presentation by Charlie Cook

Where We Are Now

42

Defining the Project


Step 1: Defining the Project Scope
Step 2: Establishing Project Priorities
Step 3: Creating the Work Breakdown Structure
Step 4: Integrating the WBS with the Organization
Step 5: Coding the WBS for the Information
System

43

Step 1: Defining the Project Scope


Project Scope
A definition of the end result or mission of the project
a product or service for the client/customerin
specific, tangible, and measurable terms.

Purpose of the Scope Statement


To clearly define the deliverable(s) for the end user.
To focus the project on successful completion
of its goals.
To be used by the project owner and participants
as a planning tool and for measuring project success.

44

Project Scope: Terms and Definitions


Scope Statements
Also called statements of work (SOW)

Project Charter
Can contain an expanded version of scope statement
A document authorizing the project manager to
initiate and lead the project.

Scope Creep
The tendency for the project scope to expand over
time due to changing requirements, specifications,
and priorities.

45

Step 2: Establishing Project Priorities


Causes of Project Trade-offs
Shifts in the relative importance of criterions related
to cost, time, and performance parameters
BudgetCost
ScheduleTime
PerformanceScope

Managing the Priorities of Project Trade-offs


Constrain: a parameter is a fixed requirement.
Enhance: optimizing a criterion over others.
Accept: reducing (or not meeting) a criterion
requirement.

46

Step 3: Creating the Work


Breakdown Structure
Work Breakdown Structure (WBS)
An hierarchical outline (map) that identifies the
products and work elements involved in a project.
Defines the relationship of the final deliverable
(the project) to its subdeliverables, and in turn,
their relationships to work packages.
Best suited for design and build projects that have
tangible outcomes rather than process-oriented
projects.

47

How WBS Helps the Project Manager


WBS
Facilitates evaluation of cost, time, and technical
performance of the organization on a project.
Provides management with information appropriate
to each organizational level.
Helps in the development of the organization
breakdown structure (OBS). which assigns project
responsibilities to organizational units and individuals
Helps manage plan, schedule, and budget.
Defines communication channels and assists
in coordinating the various project elements.
48

Work Packages
A work package is the lowest level of the WBS.
It is output-oriented in that it:
1.

Defines work (what).

2.

Identifies time to complete a work package (how


long).

3.

Identifies a time-phased budget to complete


a work package (cost).

4.

Identifies resources needed to complete


a work package (how much).

5.

Identifies a person responsible for units of work


(who).

6.

Identifies monitoring points (milestones)


for measuring success.
49

Step 4: Integrating the WBS


with the Organization
Organizational Breakdown Structure (OBS)
Depicts how the firm is organized to discharge its
work responsibility for a project.
Provides a framework to summarize

organization work unit performance.


Identifies organization units responsible

for work packages.


Ties organizational units to cost control

accounts.

410

Step 5: Coding the WBS for


the Information System
WBS Coding System
Defines:
Levels and elements of the
WBS
Organization elements
Work packages
Budget and cost information
Allows reports to be consolidated at
any level in the organization structure

411

Responsibility Matrices
Responsibility Matrix (RM)
Also called a linear responsibility chart.
Summarizes the tasks to be accomplished and
who is responsible for what on the project.
Lists project activities and participants.
Clarifies critical interfaces between units

and individuals that need coordination.


Provide an means for all participants to view

their responsibilities and agree on their


assignments.
Clarifies the extent or type of authority that

can be exercised by each participant.

412

Project Communication Plan


What information needs to be collected
and when?
Who will receive the information?
What methods will be used to gather
and store information?
What are the limits, if any, on who has
access to certain kinds of information?
When will the information be communicated?
How will it be communicated?
413

Information Needs
Project status reports
Deliverable issues
Changes in scope
Team status meetings
Gating decisions
Accepted request changes
Action items
Milestone reports

414

Key Terms
Cost account
Milestone
Organization breakdown structure (OBS)
Priority matrix
Process breakdown structure (PBS)
Project charter
Responsibility matrix
Scope creep
Scope statement
WBS dictionary
Work breakdown structure (WBS)
Work package