Coal-Clay-Sand Storage Daily Report: 4 April 2015

Download as pptx, pdf, or txt
Download as pptx, pdf, or txt
You are on page 1of 2

Coal-Clay-Sand

Storage Daily report


4 April 2015

COAL-CLAY-SAND STORAGE
Project Summarize :
1. 2 unit Bulldozer continue cut and
push the soil from the insitu area
(as figure no.1) to the clay storage
outdoor
2. 1 excavator finishing make the
good bunker (as figure no.2),

Fill
A re
a

Cut
Area 1

Heavy machine use :


Bulldozer
2 unit
Excavator
1 unit
OHT
1 unit (Stand by)
Problem:
Counter measure :
Plan next day
Finishing make the good bunker as
long as fiigure no.2. And cut on area
(as figure no.1) to make it flat (Target
is 428 MSL) then move the soil to clay
storage outdoor.
Legend of bunker progress:
: Progress was finished
: Progress was 75 %

Cut & Push to


clay storage
outdoor

The Road for


Temporary access