Modularization: Standardization (Of Constituent Parts) - It Provides Opportunities For
Modularization: Standardization (Of Constituent Parts) - It Provides Opportunities For
High
P M P
M A P M A P
Outbound P M P
Postponed Flexible
Postponement
M A P
M A P
Rigid M
Low Modularized
Low
High
Inbound modularization
On this basis, it is not intuitively clear what supply chain structure best suits the
needs of a company. We see very rigid structure which is vertically integrated and
basically purchases all the raw materials used in the production of its products.
Others may be more flexible, like BMW which buys 80% of its car's components.
Rolls Royce customizes production and does not assemble or distribute a car until a
customer's order is received. Arguments in favor or against these concepts can go
in either direction: from functional specialization and operational flexibility to losing
control and information leaks. In the computer industry, for example, Apple, IBM and
Dell contract their needed components from other companies. Compaq, on the other
hand, manufactures all of its computers in-house. In the car industry, GM is the
most vertically integrated of the car companies by producing 70% of its components
in-house. Chrysler, however, buys 70% of the materials used in each car from
suppliers.
So, what supply chain structure is the most appropriate choice for a company. In
answering this question appropriately, one should note that there is an explicit trade-
off in cost and service levels that has to be accounted for. When companies
increase the level of inbound modularization (e.g., by using more modularized
contracting), it becomes possible to significantly reduce the fixed costs involved.
Dell, for example, takes $35 of sales for every dollar of fixed assets while for
Compaq the figure is $3.
The trade-off has to be in the variable cost (i.e., the per unit variable cost is higher)
since some level of margin to the subcontractors has to be accounted for. For the
postponement case the situation is reversed. By allowing for a higher outbound
postponement, companies may incur the extra fixed cost of maintaining multiple
equipment for packaging and labeling (e.g., warehouse facilities with machines to
label). However, the variable cost is reduced because of centralized inventories, less
risk associated with lower finished goods inventories, and/or bulk shipping from the
plants.
Illustration of the framework
Inbound modularization
Low High
Outbound postponement High Postponed Flexible
Texas Instruments, Dell
Computers,
Rolls Royce Benetton,
Suzuki,
Hewlett-
Packard
Low Rigid
Modularized
Compaq, IBM,
BMW,
General Motors Chrysler
Under the Rigid structure the company makes two (packaging) runs of ice cream for
each of the markets based on the expected demand for each market (i.e., incur a
fixed cost and a variable cost for labeling in one location). Under the Postponed
structure, the company postpones packaging by having a separate labeling process
in each of the countries (i.e., incur a fixed and variable cost in each country). Under
the Modularized structure the company subcontracts ice cream production to
different dairy companies though, packaging and labeling for the final markets is
performed in-house. Finally, under the Flexible structure the company subcontracts
making the ice cream, packages it in-house and has a labeling machine in each of
the countries where the postponed shipments are labeled according to the market
specifications.
The bulk of savings from postponement will arise from a reduction in the variability
of demand when the company decides to package “later”. However, a higher fixed
cost will be incurred by having two labeling processes as opposed to one. When
subcontracting with other (dairy) companies, the fixed cost of production is lower but
the variable cost will be higher. At the inbound logistics, Rigid and Postponed
structures will mainly use their existing equipment for manufacturing the products,
while the Modularized and Flexible could use different suppliers and even change
them from time to time (i.e., they have more options). At the outbound logistics, the
Rigid and Modularized structures will finish the final product earlier than the
Postponed and the Flexible structures. The Postponed and Flexible structures delay
the actual finishing of the products until more information about final demand is
known and therefore have more options for changing the mix of finished products.
s
TC (S ) F V (S ) H (S x) f ( x)dx B ( x S ) f ( x)dx
i i i
0 s
For comparison purposes, assume that the resulting fixed cost for the flexible
supply chain structure is equal to the fixed cost of the rigid supply chain
structure, so that an increase in postponement cost is equally offset by a
corresponding decrease in subcontracting expense. Similar assumptions can
also be made regarding the variable costs. The other two supply chain
structures (Modularization and Postponed) are reflective of
intermediary situations as presented in the Table.
Parameters
Resources Objects Results
of SCF
Structure Transparency
Processes Higher
Manufactur- degree of
ing/ Simplicity supply chain
Logistics flexibility
Technology Products/
Services and
Information Responsive-
Technology ness/ Agility better
Information performance
Human Security/ in various
Potentials Reliability areas
n
∑ known SC elementsj
j=1
T= X 100
m
∑ SC elementsi
i=1
Flexibility potentials in strategic supply chain networks to gain SCF
Configuration and
Co-ordination
Structural Technological
flexibility flexibility
potentials potentials
High
degree of
SCF
Configuration and Configuration and
Co-ordination Co-ordination
Human
flexibility
potentials