PCT Pep 09212017
PCT Pep 09212017
PCT Pep 09212017
Introduction
Background Information:
There will be two residential towers
AYALA TRIANGLE stacked on top of a 4-storey podium
supported by retail and office
establishments.
DEV'T SOUTH NORTH
RETAIL TOTAL AREA
SUMMARY 68 Floors 55 Floors
NSA 71,330 56,268 10,456 138,053
GFA 102,885 81,874 19,034 203,794 (68%)
CFA 134,859 107,540 35,080 277,478 (50%)
FAR 12.85
Project Identification
Stakeholders
EXTERNAL INTERNAL
• ONE ROXAS TRIANGLE • A&E CONSULTANTS
• TWO ROXAS TRIANGLE • ALL PCT SUBCONTRACTORS/SUPPLIERS
• ZUELLIG • MDC STAFF & ENGINEERS
• AYALA COMMERCIAL ESTATE • ALP STAFF & ENGINEERS
ASSOCIATION, INC. • APMC
• MAKATI COMMERCIAL ESTATE • UNIT OWNERS
ASSOCIATION, INC.
• MAKATI FIRE STATION
• MAKATI PUBLIC SAFETY AUTHORITY
• MAKATI CITY LGU
• MAKATI POLICE CENTRAL STATION
• MERALCO
• MANILA WATER
• DPWH
• TRAFFIC ENGINEERING CENTER
• GLOBE TELECOM
Project Identification
Location and Vicinity Map
• A 1.58ha ( 15,860 sq.m) property located at
Makati Ave. corner Paseo de Roxas St.
Extended rental on genset and Expedite the legworks and preparation of necessary drawings
Delayed energization by Time
3 additional diesel and lubricants and layout for the Site Power House and Meralco temporary
Meralco (temporary power)
power energization.
Safety Noise disturbance
Possible delay on testing,
Time commissioning and project hand-
Delayed energization by over Expedite the approval by Meralco. Assign a dedicated person
4
Meralco (permanent power) who will handle liason works.
Cost Extended preliminaries
Time Extended project completion Fully implement the Minimum Disturbance Plan. Prepare an
Stop work due to complaints of
5 acceleration program to catch-up with the delay due to work
nearby establishments
Cost Extended preliminaries stoppage.
Time Delay on project schedule Prepare a target production per activities. Strict monitoring of
Low productivity on self-
6 productivity. Equip the site supervisors / foreman on
performed activities
Cost Open ended admin cost productivity monitoring and control tools
Risk Management
Risk Registry – On Site Management
POTENTIAL
ITEM RISK DESCRIPTION DETAILS OF EFFECT ACTION / MEASURES TAKEN
IMPACT
Open trenches / pits and OSHS Rule 1410: Accident / Incident, (1) Enclosing the area with precautionary warnings
5
excavations Construction Safety Injury (barricades/bollards, caution tapes and signages)
Risk Management
Risk Registry – Environment, Health & Safety
ITEM RISK DESCRIPTION SOURCES RISK CURRENT CONTROL MEASURES & PERFORMANCE
In-complete pre-employment OSHS Rule 1960: (1) Proper endorsement of workers by Subcon
2 documents and records from sub- Occupational Health Project delay (2) Thorough screening of medical requirements including NBI
contractors work force Services certificate prior to deployment
Equipment operating inside the (1) Submission of 3rd party certification by DOLE-accredited
project has not been certified by a testing organization eg. TUV; for heavy equipment entering
OSHS Rule 1410:
3 DOLE-accredited testing Project delay the project site
Construction Safety
organization and local government (2) Secure all permits needed upon project execution eg. work
unit (LGU) permit requirements. permits, PTO, etc.
Unsafe
OSHS Rule 1070: (1) Implement guidelines on handling and disposal of
environment which
Disposal of scraps and hazardous Occupational Health hazardous waste
5 can lead to
wastes and Environmental (2) Collection in place and waste reduction is implemented by
unexpected
Control utilizing usable scraps
accidents
EHS Plan
Safety Committee
HAJIE SAC
CHAIRMAN
TEDDY PASAMONTE
SECRETARY
ERIK VITUG
VICE CHAIRMAN
DONNA DOMASIG JOEY QUITIL GERALD SAGUID RODEL CUSTODIO JASPER LIMBO RIA VILLAREAL
PHR Supervisor MDC Safety Associate Project Nurse MEPFS Supervisor Civil Works Supervisor QA/QC Opcen Head
MEMBER MEMBER MEMBER MEMBER MEMBER MEMBER
OBJECTIVE
• To prevent occupational injuries and
illnesses to employees as well as to
protect their lives and the company's
properties through proper training and
implementation of this Health & Safety
Program.
GENERAL
• No person shall be required to work in
the surroundings or under conditions
which are unsafe and dangerous to his
health.
EHS Plan
Safety Procedures
SAFETY MEASURES
• Provide standard road signs for roads where heavy equipment and trucks will be
crossing.
EHS Plan
Safety Procedures
ACTIVITY PROCEDURE GRAPHIC LAYOUT
FIRE SAFETY
The following Fire Safety Measures shall be put into place:
• 2 x 5-kg capacity dry chemical (multi-purpose) fire extinguisher shall be provided within
the construction site.
• A fire watch/safety enforcer shall be assigned in areas where welding and gas cutting
activities are being performed.
• The water supply and distribution facilities for fire fighting purposes shall be provided at
construction site.
• Smoking shall be prohibited in the construction site.
EHS Plan
Safety Procedures
ACTIVITY PROCEDURE GRAPHIC LAYOUT
SECURITY MEASURES
The following Security Measures shall be put into place:
• Workers will be required to wear Identification cards and color coded uniforms
before entering the construction site.
• All contractors will be required to assign skeletal force during the holidays
• Workers will be prohibited from loitering within the periphery of the project site.
• Dayshift and nightshift guards will be posted in strategic locations inside the
premises to:
Check and report any person seen loitering after working hours
Check and report any unauthorized movement of equipment
Conduct regular inspection within the project premises and report any
violation of the house rules.
• In addition, all security guards are required to frisk all employees, workers
entering and leaving the project site for security reasons.
Quality Plan
QA Procedures & Inspections
START
PRE APPROVED
MATERIALS
MATERIALS,
PLANS/DRAWINGS, FACILITATE
METHOD STATEMENT CORRECTIVE ACTION
SUBMITTALS
NO
NO
FACILITATE CONDUCT QUALITY APPROVED?
APPROVED? MOCK UP
CORRECTIVE
NO
CONDUCT PRE
ACTIVITY TRAINING MOCK UP
ACTIVITY CAN START
AND ORIENTATION ON REQUIRED
QUALITY (PATOQ)
Quality Plan
QA Procedures & Inspections
START
PRE – APPROVED MATERIALS TSD SUPERVISOR TSD – PROVIDES COMPLETE LISTING OF PRE-APRROVED MATERIALS AND SOURCING
OF MATERIALS TO BE USED IN THE PROJECT
NO REVIEW AND SUB-CON PM/PIC, SUBCON – TO COMPLY SUBMITTAL REQUIREMENTS OR COMMENTS FROM THE
APPROVED CONSULTANT/DESIGNER.
RESUBMIT TSD COORDINATOR
TSD – TO REVIEW AND RESUBMIT THE APPROVAL OF SUBMITTAL.
YES
MDC PIC, QA – INITIATE PRE ACTIVITY TRAINING AND ORIENTATION ON QUALITY (PATOQ)
CONDUCT PRE ACTIVITY QA ENGINEER,
TRAINING & ORIENTATION ON MDC PIC – TO ENSURE SUBCONS ARE READY ON THEIR PRE-ACTIVITY
FIELD QC ENGINEER, PRESENTATION (THIS INCLUDES PRESENTATION OF APPROVED PRODUCT,
QUALITY (PATOQ) MEETING SUBCON PIC/QC PLANS/DRAWINGS & DISCUSSION OF THE APPROVED METHODOLOGIES
FQCE & SUBCON – TO ARRANGE PATOQ VENUE AND ENSURE THE ATTENDANCE OF
ALL WORKERS FOR THE SPECIFIC ACTIVITY
FACILITATE
CORRECTIVE
YES NO ACTION
PATOQ YES NO
REQUIREMETS
POST ACTIVITY
REQUIRED
INSPECTION
FACILITATE
CORRECTIVE
COMPLETED
NO POST ACTIVITY
YES
NO
WORK REQUEST (WR)
APPROVED?
YES NO
FACILITATE
CORRECTIVE
ACTION
YES
FACILITATE
CORRECTIVE PROCEED ACTIVITY IN PROCESS
ACTION START INSPECTION OR TESTING
NO
Quality Plan
QA Procedures & Inspections
START
WORK ACTIVITY SUBMITTAL FIELD QC ENGINEER, FQCE & SUBCON – ENSURES WORK ACTIVITY SUBMITTAL ARE COMPLETED PRIOR
MUST BE COMPLETED SUBCON PIC/QC TO START OF WORK.
WORK ACTIVITY PERMIT FIELD QC ENGINEER, SUBCON – ROUTES THE WORK REQUEST (WAP) PART TO DIFFERENT TRADES AND
ROUTING SUBCON PIC/QC ENSURE TO COMPLETE THE SIGNATURES OF THE RELATED TRADE
FQCE – REVIEW WORK ACTIVITY
N FACILITATE
FIELD QC ENGINEER, SUBCON – RESPONSIBLE WITH THE CORRECTIVE/REMEDIAL ACTION REQUIRED TO
APPROVED CORRECTIVE/
O REMEDIAL ACTION
SUBCON PIC/QC APPROVED (WAP)
YES FIELD QC ENGINEER, SUBCON/FQCE – ENSURE SURVEY SETTING OUT AND FINAL LAY OUT (IF REQUIRED
START OF ACTIVITY SUBCON PIC/QC IN THE PLANS/DRAWING).
SUBCON PIC/QC, SUBCON – TO CONDUCT PROGRESS WORK INSPECTION AND TESTING AT PROJECT
ON PROCESS OF INSPECTION/ FIELD QC ENGINEER, SITE (REFER ON APPROVED INSPECTION TEST PLAN (ITP) AND ENSURE TO COMPLY
TESTING QA ENGINEER QUALITY CONTROL REQUIREMENTS.
FQCE – TO CHECK AND INSPECT THE QUALITY OF WORK BASED ON THE
APPROVED ITR AND INSPECTION
N FACILITATE
APPROVED CORRECTIVE/ MDC SUPERINTENDENT/
MDC SUPERINTENDENT/SUPERVISOR – TO VERIFY THE COMPLETENESS AND
O REMEDIAL ACTION SUPERVISOR,
QUALITY OF WORK DONE AND RECOMMENDS THE APPROVAL OF THE WORK
MDC PIC
ACTIVITY
YES PIC – TO ENSURE ALL QUALITY CONTROL REQUIREMENTS ARE COMPLIED
QC AND QA APPROVAL
Quality Plan
QA Procedures & Inspections
START
VERIFICATION OF PRE
FUNCTIONAL TEST
FACILITATE
CORRECTIVE COMPLETED
ACTION NO
YES NO
YES
FACILITATE NO APPROVED?
ACCEPTED
REQUEST FOR
CORRECTIVE
SBU/APMC PUNCH
ACTION
YES
UNIT ACCEPTED/
COPA/COFA
Quality Plan
QA Procedures & Inspections
START
SUBCON PIC/QC SUBCON PIC – COORDINATES ALL PRE FUNCTIONAL TEST DOCUMENTS
FIELD QC ENGINEER FQCE – REVIEW AND VALIDATE PRE FUNCTIONAL TEST AND ENSURE COMPLETENESS
VERIFICATION OF PRE QA ENGINEER OF THE TEST RECORDS ON THE APPROVED ITP
FUNCTIONAL TEST APMC QAE – ENSURES CORRECTNESS OF DOCUMENTS
APMC – VERIFIES PRE FUNCTIONAL CHECKLIST
FACILITATE SUBCON PIC, SUBCON PIC – COMPLETE PRE FUNCTIONAL TEST
COMPLETED NO CORRECTIVE/ QC FIELD ENGINEER FE – ENSURE COMPLETENESS OF THE TEST RECORDS
REMEDIAL ACTION
RECTIFICATION (IF ANY) SUBCON PIC/FE SUBCON PIC – RECTIFIES PUNCHLIST ITEMS
FE – ENSURES RECTIFICATION COMPLETE
PASSED NO
YES
Standard WAS, WIP, and WAC procedures
ISSUANCE OF COC/UNIT will be strictly implemented.
Site Conditions
Existing Utilities
LEGEND:
ENTRY/EXIT
GATE
EXISTING SEWER LINE
INSIDE PROPERTY LINE
ENTRY/EXIT
GATE
Program and Planning
Project Milestones
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51
Diaphragm
Diaphragm Wall Diaphragm Wall
Wall
Enabling Works Enabling Works Enabling Works
Building Façade
CRU Handover
TOTAL
Program and Planning
General Construction Sequence
Enabling Works
Foundation Works
Structural Works
(Basement Level)
Structural Works (Podium
and South Tower)
Watertightness 21-Nov-22
HIGH ZONE
Structural Topping-off 18-Feb-21 High Zone
(36F – 72F)
Facade Completion 01-Aug-23
Water tightness 21-Nov-22
High Zone
SKY TERRACES (HIGH) (32F – 56F)
Structural Topping-off 10-Nov-19
Facade Completion 07-Aug-21
Water tightness 22-Nov-20 Sky Terraces (High)
(32F – 35F)
MID ZONE Sky Terraces (High)
Mid Zone (28F – 31F)
Structural Topping-off 07-Sep-19
(24F – 31F)
Facade Completion 26-Apr-21 Mid Zone
Watertightness 19-Aug-20 Sky Terraces (Low) (20F – 27F)
(20F – 23F)
SKY TERRACES (LOW Sky Terraces (Low)
ZONE) (16F – 19F)
Low Zone
Structural Topping-off 10-May-19 (5F – 19F) Low Zone
Facade Completion 24-Sep-20 (5F – 15F)
Watertightness 30-Mar-20
Work Days
HT. ≥ 3.50m Item
Work
Description 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
1.0 Vertical Rebars
Column /
Shearwall
2.0 Vertical Formworks
3.0 Vertical Pouring
4.0 Slab Formworks
5.0 Slab Rebar (Bottom)
Slab &
6.0 MEPFS
Beams
7.0 Slab Rebar (Top)
8.0 Slab Conc. Pouring
Program and Planning
Structural Work Cycle – Tower Portion
Work Days
1 2 3 4 5 6 7 8 9 10 11 12
1 Vertical Rebars 1 2 3
Column / Shearwall 2 Vertical Formworks 1 2 3
3 Vertical Pouring 1 2
4 Scaffolding 1 2 3
5 Beams & Girders 1 2
S1
6 Slab Formworks 1 2
Slab & Beams 7 Slab Rebar (Bottom) 1 2
8 MEPFS 1
9 Slab Rebar (Top) 1 2
10 Slab Conc. Pouring 1 2
4 Scaffolding 1 2 3
5 Beams & Girders 1 2
6 Slab Formworks 1 2
S2 Slab & Beams 7 Slab Rebar (Bottom) 1 2
8 MEPFS 1
9 Slab Rebar (Top) 1 2
10 Slab Conc. Pouring 1 2
1 Vertical Rebars 1 2 3
Column / Shearwall 2 Vertical Formworks 1 2 3
3 Vertical Pouring 1 2
4 Scaffolding 1 2 3
5 Beams & Girders 1 2
S3
6 Slab Formworks 1 2
Slab & Beams 7 Slab Rebar (Bottom) 1 2
8 MEPFS 1
9 Slab Rebar (Top) 1 2
10 Slab Conc. Pouring 1 2
Program and Planning
Structural Work Cycle – Tower Portion
HT. ≥ 3.50m
Work Days
Item Work Description
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
1 Vertical Rebars 1 2 3
Column / Shearwall
(1st Lift)
2 Vertical Formworks 1 2 3
3 Vertical Pouring 1 2
Column / Shearwall 4 Vertical Formworks 1 2 3
(2nd Lift) 5 Vertical Pouring 1 2
6 Scaffolding 1 2 3
S1 7 Beams & Girders 1 2
8 Slab Formworks 1 2
Slab & Beams 9 Slab Rebar (Bottom) 1 2
10 MEPFS 1
11 Slab Rebar (Top) 1 2
12 Slab Conc. Pouring 1 2
6 Scaffolding 1 2 3
7 Beams & Girders 1 2
8 Slab Formworks 1 2
S2 Slab & Beams 9 Slab Rebar (Bottom) 1 2
10 MEPFS 1
11 Slab Rebar (Top) 1 2
12 Slab Conc. Pouring 1 2
1 Vertical Rebars 1 2 3
Column / Shearwall
(1st Lift)
2 Vertical Formworks 1 2 3
3 Vertical Pouring 1 2
Column / Shearwall 2 Vertical Formworks 1 2 3
(2nd Lift) 3 Vertical Pouring 1 2
6 Scaffolding 1 2 3
S3 7 Beams & Girders 1 2
8 Slab Formworks 1 2
Slab & Beams 9 Slab Rebar (Bottom) 1 2
10 MEPFS 1
11 Slab Rebar (Top) 1 2
12 Slab Conc. Pouring 1 2
Program and Planning
Manpower Loading
Program and Planning
Construction Demand (Concrete, Rebar, Formworks,
Precast)
Design Production
Design Schedule
MILESTONE DATE
SD Stage May 2015
1 100% DD Sep 21
2 50% CD Aug 1
5 100% FCD
6 IFC
2017
ITEM DESCRIPTION JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
1 100% DD
2 50% CD
3 100% CD (Substructure)
4 100% CD (Tower)
6 IFC Dec 15
Design Production
Design Schedule
BIM TIMELINE
2016 2017
WORK
ITEM DESCRIPTION MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB
PERCENTAGE
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
3 BIM Modeling of Structural and Architectural 25% Basement Podium Low Zone Mid Zone
4 CSD Modeling and Clash Detection 35% Basement Podium Low Zone Mid Zone
2017
WORK
ITEM DESCRIPTION FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
PERCENTAGE
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
3 BIM Modeling of Structural and Architectural 25% Mid Zone High Zone Roof Deck
4 CSD Modeling and Clash Detection 35% Low Zone Mid Zone High Zone Roof Deck
ZONE 4
3,432.53 m2
ZONE 3
1,404.48 m2
ZONE 2
2,300.29 m2
ZONE 1
ZONE 5
3,934.85 m2
3,419.30 m2
Temporary Works and Site Logistics
Phasing and Zoning Plans
ZONE 1
ZONE 2
ZONE 3
ZONE 3
ZONE 2
ZONE 1
Temporary Works and Site Logistics
Tower Crane Layout
MONTH MONTH
TYPE H.U.H. JIB DURATION
IN OUT
40 m RADIUS
Temporary Works and Site Logistics
Tower Crane Layout
PODIUM – LEVEL 3
WEIGHT (kg)
3.0 m 6.0 m 12.0 m
PODIUM BRIDGE
Built-up 4,239.00 8,478.00 16,956.00
W21x55 246.13 492.27 984.54
W16x26 116.69 233.38 466.76
LOUNGE BRIDGE
Built-up 4,356.75 8,713.50 17,427.00
W16x57 255.26 510.52 1,021.03
W16x36 160.94 321.88 643.76
40 m RADIUS
Temporary Works and Site Logistics
Tower Crane Layout
PODIUM – LEVEL 4
WEIGHT (kg)
3.0 m 6.0 m 12.0 m
LOUNGE BRIDGE
Built-up 3,179.25 6,358.50 12,717.00
W16x50 255.26 510.52 1,021.03
W16x26 116.69 233.38 466.76
40 m RADIUS
Temporary Works and Site Logistics
Tower Crane Layout
PODIUM – LEVEL 4
WEIGHT (kg)
3.0 m 6.0 m 12.0 m
ROOF DECK
Castellated
Beam 1,025.51 2,051.02 4,102.03
W18x192 856.91 1,713.83 3,427.66
W18x76 338.81 677.63 1,355.26
W18x130 223.35 446.70 893.39
2xW18X234 2,090.63 4,181.26 8,362.51
2xW18x192 1,713.83 3,427.66 6,855.31
W18x50 223.35 446.70 893.39
W18x211 943.51 1,887.01 3,774.03
40 m RADIUS
Temporary Works and Site Logistics
Tower Crane Layout
PENTHOUSE – 69TH FLOOR
WEIGHT (kg)
3.0 m 6.0 m 12.0 m
40 m RADIUS
Temporary Works and Site Logistics
Tower Crane Layout
ROOF DECK
WEIGHT (kg)
3.0 m 6.0 m 12.0 m
40 m RADIUS
Temporary Works and Site Logistics
Placing Boom Layout
MONTH MONTH
RADIUS DURATION
IN OUT
ME-1 2-Cager 256 m Basement 1 Sep 2018 Dec 2022 52 mos LEGEND:
MATERIAL ELEVATOR 1
ME-2 2-Cager 256 m Basement 1 Dec 2018 Jun 2022 43 mos
MATERIAL ELEVATOR 2
ME-3 1-Cager 270 m Basement 5 Jul 2019 Apr 2021 21 mos
MATERIAL ELEVATOR 3
ME-4 2-Cager 226 m Basement 1 Aug 2020 Feb 2024 43 mos
MATERIAL ELEVATOR 4
ME-5 2-Cager 226 m Basement 1 Nov 2020 May 2023 30 mos MATERIAL ELEVATOR 5
ME-6 1-Cager 240 m Basement 5 May 2021 Sep 2022 16 mos MATERIAL ELEVATOR 6
Temporary Works and Site Logistics
Traffic Management Plan
LEGEND:
TRAFFIC FLOW
PEDESTRIAN FLOW
CONSTRUCTION FENCE
Temporary Works and Site Logistics
Board Up Plan
LEGEND:
CONSTRUCTION FENCE
GATE
Temporary Works and Site Logistics
Temporary Facilities Layout
LEGEND:
MDC OFFICE
CONFERENCE ROOM
WAREHOUSE
SUBCON OFFICES
CANTEEN
ANTICIPATED
PACKAGE BID PACKAGE
AMOUNT
PCT-BT1-01 Supply of RMC 262,368,002.40
PCT-BT1-02 Supply of Construction Equipment 37,419,033.55
PCT-BT1-03 Supply & Delivery of Formworks System 23,968,313.60
PCT-BT1-04 Supply & Delivery of Rebar 332,509,227.43
PCT-BT1-05 Soil Poisoning 3,009,159.90
PCT-BT1-06 Civil Structural Works (Foundation – Basement 3) 27,688,652.60
PCT-BT1-07 Mechanical Couplers and Threaded Rebars (Foundation – B3) 1,040,980.00
PCT-BT1-08 Supply & Installation of General Electrical Works (B5 – B3) 1,655,144.24
PCT-BT1-09 Supply & Installation of Plumbing and Sanitary Works (B5 – B3) 438,444.81
PCT-BT1-10 Supply & Installation of General Fire Protection Works (B5 – B3) 21,366.95
PCT-BT1-11 Supply & Installation of General Mechanical Works (B5 – B3) 58,714.63
PCT-BT1-12 Supply & Installation of Glass and Aluminum Works 2,1555,898,762.19
Procurement
Procurement Strategy
PROCUREMENT
PACKAGE BID PACKAGE
STRATEGY
PCT-BT1-01 Supply of RMC Partnering
PCT-BT1-02 Supply of Construction Equipment Partnering
PCT-BT1-03 Supply & Delivery of Formworks System Partnering
PCT-BT1-04 Supply & Delivery of Rebar Partnering
PCT-BT1-05 Soil Poisoning Partnering
PCT-BT1-06 Civil Structural Works (Foundation – Basement 3) Self-Perform
PCT-BT1-07 Mechanical Couplers and Threaded Rebars (Foundation – B3) Paper Bid
PCT-BT1-08 Supply & Installation of General Electrical Works (B5 – B3) Partnering
PCT-BT1-09 Supply & Installation of Plumbing and Sanitary Works (B5 – B3) Partnering
PCT-BT1-10 Supply & Installation of General Fire Protection Works (B5 – B3) Project Sequel
PCT-BT1-11 Supply & Installation of General Mechanical Works (B5 – B3) Partnering
PCT-BT1-12 Supply & Installation of Glass and Aluminum Works Paper Bid
Procurement
Procurement Schedule