Construction of Aqueduct
Construction of Aqueduct
Construction of Aqueduct
On
Industrial case study
CONSTRUCTION OF AQUEDUCT
Presented by
Mr. Pratik A. Thaware
(CED15085)
B.E. VII semester
2018-19
2. Description of project
3. Ownership details
4. Work Experience
6. Reference 2
1. Introduction
• What is Industrial case study ..?
The industrial case study is the 20 days training taken by
student in the field or in company to get detailed knowledge of
activity regarding the construction, management, execution of work
etc ….
• Why it is important .?
1. To get knowledge of construction technique
2. To get Idea of execution of work
3. How to carry out work according to drawings
4. Various Tests and its importance
3
• Duration of industrial case study
24 may 2018 to 11 june 2018 (18 Days )
2.Description of project
The Industrial Case Study is carried out at Bramhapuri. The
project was construction of Aqueduct the detail information about
the project is given below,
Name of the project : Construction of Aqueduct
Superintended Engineer
(Gosekhurd project circle Nagpur)
Executive Engineer
(Gosikhurd Right Bank canal Division, Bramhapuri)
Sectional Engineer
Company chart
Mr. P.N. Devalkar (contractor)
Project manager
Site Incharge/Engineer
Super Visor
Labour contractor
Labour
7
Description Of Materials And
Equipment
material used :
1.Cement : Cement is a binding material it has good cohesive and
adhesive properties. At site, 53 grade was used and the
weight of each cement bag was 50kg. Cement used at site
was ‘PCC’. Specification are used from IS269-1976.
2. Sand : Source of sand was Vainganga River Desaiganj
(Warsa).
3. Water : The source of water was bore well constructed on
site
4. Shuttering : The Shuttering used is steel Shuttering.
8
It was well durable. It was easy to handle and
removal.
Equipment's used
1. Needle Vibrater: This is used for compaction of
concrete after casting of concrete.
11
Day 8
Filling of earthwork were going on site beside downstream
side wing wall by roller n power excavator .Due to rain no concreting
were done . 12
Day 9
Soil test were carried out
Murom filling : sand replacement
13
Fig no. 2 : core cutter method
Day 10
The work was closed due to payment day .
Day 11
Concrete mix grade and ratio of mix were observed of batch mixer
Water : 86 liter
17
Fig No. 05 Inspection of formwork
Day 14
casting of concrete of upstream side wing wall
observed and cubes were taken for compression testing .
18
Fig No.06 concreting in U/S side Fig No. 07 concrete cubes
wing wall.
Day 15 & Day 16
within this 2 days casting of concrete in pier of 1 meter lift and
cubes were taken, Gunny bag curing were provided to the pier and
quality control engineer had visited to the site to check the structure
and in-situ test results
19
Fig No. 08 casting of concrete in Fig No. 09 Gunny bag curing
pier
Day 17
The concreting of abutment was observed needle vibrator
were used for the compaction of concrete the concrete were
transported by the transit mixer and directly placed into the formwork
20
Fig No. 10 Concreting in abutment
Day 18
Due to the rainy season the work were closing the excavation
of stream were started for flow of water which was filled for work .
Pipes were provided for air release from sand filling in sub-structure
.
21
Fig No. 11 Pipes for air release from sand
5. Observations and discussions
1. I found on site that the some extra adjustment has to be done
to carry out work which is not found in the books, which
come from experience only.
22
6. Reference
23
THANK YOU