INTERNSHIP

PRESENTATION

Guided By Presented By
Mr ABHILASH B L SHRENIK S
ASST.PROFESSOR 1AT15CV075
CONTENT
 Introduction
 Cost of cement per bag in different shops
 Site safety lapses
 Seepage
 Reasons of seepage
 Techniques used to prevent seepage
 Plastering
 Flooring
 Rate analysis
INTRODUCTION

ABOUT THE COMPANY/ORGANISATION


RSEDGE CONSTRUCTION
• Rsedge Construction Private Limited is a Private
incorporated on 09 january 2018. It is classified as Non-
govt company and is registered at registrar of companies,
Bangalore.
• Directors of RSEDGE CONSTRUCTIONS PRIVATE
LIMITED are SRINIVAS K S and RAKESH S
• No.05, 1st Floor, 6th Main Road, Siddivinayaka Layout,
Virupakshapura, Vidyaranyapura post, Bangalore,
Karnataka-560097
COST OF CEMENT PER BAG IN
DIFFERENT SHOPS
MATERIALS PRICE PER BAG IN SRI PRICE PER BAG IN SRI PRICE PER BAG IN
AADHI SUBRAMANYA VENKATESHWARA BUILDPRO
TRADES ENTERPRISES

B Super Cement of Rs.355/- Rs.345/- Rs.360/-


53grade
UltraTech Cement of Rs.350/- Rs.345/- Rs.355/-
43 grade
Portland Pozzolanna Rs.347/- Rs.340/- Rs.350/-
cement(PPC)
Bharathi Cement of 43 Rs.322/- Rs.335/-
grade

Bharathi Cement of 53 Rs.325/- Rs.335/-


grade
SITE SAFETY LAPSES SUGGESTION TO IMPROVE LAPSES
Workers where not wearing safety helmets, Safety helmets must be worned by the
there is a chances of head injuries workers while working in the site
Workers where not wearing safety shoes, Safety shoes must be used by the workers
there is a chance of nail perforating from so that leg injuries are avoided
the bottom of the shoe and the workers will
be injured
Workers where not using protective glasses Protective glasses must be used by the
which leads to accumulation of dust in the workers so accumulation of dust in teh eye
eye and after a while eye starts to burn reduces
No time is given for the awareness of Awareness must be created to the workers
safety measures to the workers, the so that they use all the safety equipments
workers must know why the safety
equipments must be used in the site ,if not
used what are all the problems they will
face must be explained
SEEPAGE
Leakage in the water supply pipes of the upper, adjacent or
your own flat.
REASONS OF SEEPAGE IN HOMES ARE:
1. Faulty Internal Plumbing.
2. Rain water accumulation due to poor drain on roof.
3. Water tank leakage.
4. Poor water proofing at the time of construction.
5. Presence of Natural underground water (particularly after
period of heavy rainfall.
TECHNIQUES USED TO PREVENT SEEPAGE
1. Use of damp proof courses.
2. Water proof or damp proof treatments.
3. Integral damp proofing treatment.
1. USE OF DAMP-PROOF COURSES (D.P.C.)
2. WATER PROOF SURFACE TREATMENTS
The surface treatment consists in filling up the pores of the
material exposed to moisture by providing a thin film of water
repellent material over the surface (internal/external).
3. INTEGRAL DAMP-PROOFING TREATMENTS:
The integral treatment consists of adding certain compounds to
the concrete or mortar during the process of mixing.
PLASTERING
Plaster is a building material used for the protective or
decorative coating of walls and ceilings and for moulding and
casting decorative elements.
FLOORING
Flooring is the general term for a permanent covering of a
floor, or for the work of installing such a floor covering.
PLANNING OF 20X30 SITE
Sl. No PARTICULAR OF ITEM QTY UNIT RATE ₹ QTY No AMOUNT ₹

1 EARTH WORK EXCAVATION 526 ft^3 14 7364


2 PCC BED CONCRETE 1:4:8 131.5 ft^3
CONCRETE CEMENT BAGS 345 9 3105
FINE AGGREGATE TONNE 1000 2 2000
sCOARSE AGGREGATE TONNE 600 4 2400
3 SIZE STONE MASONRY IN CM 1:6 461.75 ft^3 15 1070 16050
4 PLINTH CONCRETE 1:2:4 66.75 ft^3
5 EARTH FILLING 330.45 ft^3 5 1652.25

6 BRICK MASONRY IN CM 1:6 2340.12 ft^3


BRICK 42 4100 172200
CEMENT BAGS 345 80 27600
SAND TONNE 1200 9 10800
7 RCC WORK 1:1.5:3 1025.74 ft^3
STEEL REQUIRED TONNE 54000 4.7 253800
CONCRETE CEMENT BAGS 345 232 80040
FINE AGGREGATE TONNE 1000 20.5 20500
COARSE AGGREGATE TONNE 600 39 23400
8 PLASTERING 8877.95 ft^2
CEMENT BAGS 345 81 27945
FINE AGGREGATE TONNE 1400 14.06 19684
9 PAINTING 8877.95 ft^2
10 ENAMEL PAINTING 1266.1 ft^2
11 FLOORING 1864 ft^2 68 466 31688
WOOD REQUIRED 61.77 cft 1200 74124
LABOUR 1818 ft^2 260 472680