R2R KT SESSION – PROJECT SYSTEM

SETTLEMENT PROCESS

1 25th Nov 16 (Thursday)

Presenter :
Praveen Francis
Introduction : Project System

Project System is part of SAP‘s solution for Project and


Portfolio Management. Project System helps you
manage the project through its entire life cycle, from
setting up a structure, to drawing up detailed plans, to
execute and completing the project.

2 Because of its tight integration into financial and


logistic core enterprise processes Project System can
especially be used for large and complex projects such
as construction, production, maintenance, investment,
or costs projects in all industries.
Work Breakdown Structure (WBS)

The work breakdown structure (WBS) is a model of the project


that organizes project tasks into a hierarchy.

It is the functional basis for further planning steps in a


project, for example, for process planning, cost planning,
scheduling, capacity planning or costing, as well as
project control.
3
It gives you a clear picture of the project and facilitates
the coordination and implementation of the project from a
management standpoint.

It shows the work involved in a project.


What is a Work Breakdown Structure?

A work breakdown structure (WBS) is a model of the work to be performed in a project organized
in a hierarchical structure. The WBS is an important tool which helps you keep an overview of
the project:

 It forms the basis for organization and coordination in the project.


 It shows the amount of work, the time required, and the costs involved in the project..
 It is the functional basis for further planning steps in a project, such as process planning,
cost planning, scheduling, date and capacity planning, or costing, as well as project
control.

The project structure can be represented according to different criteria:


 By phase (logic-oriented)
 By function (function-oriented)
 By object (object-oriented)

 In a work breakdown structure (WBS), you describe the individual tasks and activities in the
project as individual elements in a hierarchy.
 Depending on the phase of your project, you continue to break down the tasks and activities in
your project, step-by-step, until you reach the level of detail necessary to carry it out. 4

CONFIDENTIAL DRAFT – For Discussion Purposes Only / Subject to Consultation 4


TO EXPLAIN IN DETAIL JUST
CONSIDER ONE EXAMPLE
5
EXAMPLE:

 Consider Govt of India wants to have Roads to be build


through out the India. So project can be defined in sap as
"Connectivity".
 WBS can be roads within different states like Roads for
Gujarat, Karnataka etc.. i.e. WBS -Gujarat, WBS -
Karnataka etc.
 We can define different networks for these WBS like Road
Between Ahmadabad to Surat OR between Bangalore
to Mysore.
 For this network we can have many activities like Land
selection, Land Preparation, Road Building, Final finishing
etc .
 For each WBS we have specified budget allocated which
is the approved cost structure for a project.

CONFIDENTIAL DRAFT – For Discussion Purposes Only / Subject to Consultation 6


BUDGET MANAGEMENT

Budget is the approved cost structure for a project. You can


allocate budget to projects in Investment Management or
directly in Project System.

Budgets can be distributed hierarchically within the project


structure. If required you can successively release budgets
and post updates, such as budget supplements or
returns.

Budget availability control enables you to control costs


actively by issuing warnings and error messages when
Tolerance limits of the budget are exceeded because of
assigned values.

CONFIDENTIAL DRAFT – For Discussion Purposes Only / Subject to Consultation 7


ORIGINAL BUDGET – SCREEN FOR PROJECT

CONFIDENTIAL DRAFT – For Discussion Purposes Only / Subject to Consultation 8


CREATE PROJECT – CJ20N

9
We will see now how to create new project for Capital & Revenue
project expenditure.
CONFIDENTIAL DRAFT – For Discussion Purposes Only / Subject to Consultation 9
PROJECT PROFILE
 The project profile contains default values and other control
parameters such as the planning method for dates and costs.
 The data that you enter in the project profile will be copied into a
project in its project definition or in the elements which can later be
overwritten.

Notes:
The values in the project profile determine the functionality of
certain areas of the Project System and cannot be changed without
careful thought. Do not change profiles and key from related functions
which are defined in the project profile, such as the costing sheet or the
results analysis key. These changes could effect existing objects.

You must maintain the following sections for the project profile:

 Basic data
 Time scheduling
 Costs/revenues/finances
 Organizational data 10

CONFIDENTIAL DRAFT – For Discussion Purposes Only / Subject to Consultation 10


WBS ELEMENTS :

The individual elements represent activities within the work breakdown


structure. The elements are called work breakdown structure elements (WBS
elements) in the Project System. WBS elements can be:

 Tasks
 Partial tasks which are subdivided further
 Work packages

For any project defined we must have at least one WBS. Within this WBS we
can have networks. Networks are nothing but the series of activities.
Material are used to perform the activities.

11

CONFIDENTIAL DRAFT – For Discussion Purposes Only / Subject to Consultation 11


CREATE WBS ELEMENT UNDER PROJECT

We will see now how to create new WBS element related to project 12
type – Assets Under Construction.
CONFIDENTIAL DRAFT – For Discussion Purposes Only / Subject to Consultation 12
DEFINITION: PROJECT TYPE & OBJECT CLASS

Project Type: Definition as per Project System (PS)

An object that groups projects according to certain criteria is defined as


project type, for example:
 Capital-investment projects
 Customer projects
 Development projects

Object Class : Definition as per Controlling (CO)

The object class categorizes Controlling objects according to their


business function and enables you to analyze cost flows within
Controlling from different business perspectives.

The following object classes are available as:


 Overhead
 Production
 Investment 13
 Profitability analysis and sales

CONFIDENTIAL DRAFT – For Discussion Purposes Only / Subject to Consultation 13


SETTLEMENT PROCESS

Settlement of Actual cost from WBS to AUC

Settlement of Actual Cost from AUC to Assets


14
Settlement of Actual cost from WBS to Cost Centre.
SETTLEMENT OF ACTUAL COST FROM WBS TO AUC
CJ88 – SETTLEMENT OF AUC

15

CONFIDENTIAL DRAFT – For Discussion Purposes Only / Subject to Consultation 15


CJ88 – SETTLEMENT OF AUC – TEST MODE

16

CONFIDENTIAL DRAFT – For Discussion Purposes Only / Subject to Consultation 16


CJ88 – SETTLEMENT OF AUC – TEST MODE

17

CONFIDENTIAL DRAFT – For Discussion Purposes Only / Subject to Consultation 17


CJ88 – SETTLEMENT OF AUC – REAL MODE

18

CONFIDENTIAL DRAFT – For Discussion Purposes Only / Subject to Consultation 18


CJ88 – SETTLEMENT OF AUC – REAL MODE

19

CONFIDENTIAL DRAFT – For Discussion Purposes Only / Subject to Consultation 19


CJ88 – SETTLEMENT OF AUC – REAL MODE

20

CONFIDENTIAL DRAFT – For Discussion Purposes Only / Subject to Consultation 20


CJ88 – SETTLEMENT OF AUC – REAL MODE

21

CONFIDENTIAL DRAFT – For Discussion Purposes Only / Subject to Consultation 21


SETTLEMENT OF ACTUAL COST
FROM WBS TO AUC
FULL SETTLEMENT
22
SETTLEMENT OF AUC – FULL SETTLEMENT

23

CONFIDENTIAL DRAFT – For Discussion Purposes Only / Subject to Consultation 23


SETTLEMENT OF AUC – FULL SETTLEMENT

24

CONFIDENTIAL DRAFT – For Discussion Purposes Only / Subject to Consultation 24


SETTLEMENT OF AUC – FULL SETTLEMENT

CONFIDENTIAL DRAFT – For Discussion Purposes Only / Subject to Consultation 25


SETTLEMENT OF AUC – FULL SETTLEMENT

CONFIDENTIAL DRAFT – For Discussion Purposes Only / Subject to Consultation 26


FULL SETTLEMENT – ACCOUNTING DOCUMENTS

CONFIDENTIAL DRAFT – For Discussion Purposes Only / Subject to Consultation 27


SETTLEMENT OF AUC TO FIXED
ASSET & COST CENTRE

28
SETTLEMENT RULE – PATH TO CHECK AUC LINK TO WBS

29

CONFIDENTIAL DRAFT – For Discussion Purposes Only / Subject to Consultation 29


WBS SETTLEMENT RULE – PATH

30

CONFIDENTIAL DRAFT – For Discussion Purposes Only / Subject to Consultation 30


WBS SETTLEMENT RULE

31

CONFIDENTIAL DRAFT – For Discussion Purposes Only / Subject to Consultation 31


SETTLEMENT OF AUC TO FXA & CTR – TEST MODE

32

CONFIDENTIAL DRAFT – For Discussion Purposes Only / Subject to Consultation 32


SETTLEMENT OF AUC TO FXA & CTR - TEST MODE

33

CONFIDENTIAL DRAFT – For Discussion Purposes Only / Subject to Consultation 33


SETTLEMENT OF AUC TO FXA & CTR – TEST MODE

34

CONFIDENTIAL DRAFT – For Discussion Purposes Only / Subject to Consultation 34


SETTLEMENT OF AUC TO FXA & CTR – REAL MODE

CONFIDENTIAL DRAFT – For Discussion Purposes Only / Subject to Consultation 35


SETTLEMENT OF AUC TO FXA & CTR – REAL MODE

CONFIDENTIAL DRAFT – For Discussion Purposes Only / Subject to Consultation 36


SETTLEMENT OF AUC TO FXA & CTR – REAL MODE

CONFIDENTIAL DRAFT – For Discussion Purposes Only / Subject to Consultation 37


SETTLEMENT OF AUC TO FXA & CTR – REAL MODE

CONFIDENTIAL DRAFT – For Discussion Purposes Only / Subject to Consultation 38


SETTLEMENT OF AUC TO FXA & CTR – ACCOUNTING DOC

CONFIDENTIAL DRAFT – For Discussion Purposes Only / Subject to Consultation 39


ASSET EXPLORER – AW01N

You can see that assets acquisition done successfully

CONFIDENTIAL DRAFT – For Discussion Purposes Only / Subject to Consultation 40


QUESTIONS

41

CONFIDENTIAL DRAFT – For Discussion Purposes Only / Subject to Consultation 41