Under Ground Metal Mining Assignment: Topic:-Support System Submitted To
Under Ground Metal Mining Assignment: Topic:-Support System Submitted To
Under Ground Metal Mining Assignment: Topic:-Support System Submitted To
VIVEK SINHA
DURGESH KURREY
SWAPNIL THAWAIT, DHEERAJ SINGH, PRADEEP CHANDEL, PRADEEP
KUMAR, SANDEEP BHAGAT, RAJU TANNDI, SHAILESH RANGRARI,LOKAS
GROUTing
&
SHOTCRETE
Introduction
There are three main phases in the “life” of an underground mine where
some form of grouting for the control of groundwater may be required:
1) Development & Commissioning – during the construction of shafts,
surface drifts & preliminary underground developments to gain access to
the ore body.
2) Production/Operations – dealing with groundwater problems at the
production face and when driving additional underground roadways,
shafts, etc.
3) “Shut-down” – initial sealing of shafts and roadways and continuing
remedial work as necessary.
Within these general areas different forms of grouting will be
required to solve the various groundwater problems that are
encountered.
Purpose of Grouting
Although grouting has a number of quite different
applications, the main purpose is always to eliminate
or reduce the flow of groundwater into an existing or
proposed underground excavation. Grouting is only
one of several methods of ground treatment for
excluding water which have to be assessed on their
respective merits for each situation. However,
grouting does provide the benefits of a permanent
or at least semi-permanent, ground treatment and
the bonus of increased stability in some situations,
as compared with purely temporary expedients such
as dewatering and ground freezing.
Grouting Methods &
materials
Permeation Grouting
In permeation grouting the grout material penetrates the
interconnected porous structure of the soil or rock which may
compromise both the intergranular voids & the fissure network. Whilst
in most instances the fissure permeability represents the major
contribution to the total permeability of the ground and, hence the
main agent for transmitting groundwater flow to the excavation, there
are instances where intergranular permeability is equally important.
Hydrofracture Grouting
In both intergranular and fissure the injection is carried out at
pressures insufficient to disturb the ground structure. The grout
advances steadily displacing air and water outwards with the
predominant direction of flow being that offering the least resistance,
ie. the path of highest permeability. In some circumstances, usually in
relatively shallow alluvials, it is permissible to use hydrofracture
grouting where deliberate overpressuring is used to either widen
existing fissures or create new fissures. This procedure has the
advantage of rapidly creating direct access through low permeability
ground to a more permeable and treatable zone from the widely
spaced array of injection holes.
Squeeze Grouting
The squeeze grouting technique is used to apply high pressures to
the ground to squeeze out excess pore water and consolidate the
unstable material by increasing its density and shear strength.
Consolidation is achieved by either forming a grout “bulb” which does
not penetrate the soil or preferably by deliberate hydrofracture using a
grout of limited capability to penetrate far.
Shotcrete
Massive rock Fault gouge may be Provision of Remove weak material to a depth equal to
with single wide weak and erodible support and width of fault or shear zone and grout rebar
fault or shear and may cause surface sealing into adjacent sound rock. Weldmesh can be
zone. stability problems in in vicinity of used if required to provide temporary rockfall
adjacent jointed weak fault of support. Fill void with plain shotcrete. Extend
rock. shear zone. steel fibre reinforced shotcrete laterally for at
least width of gouge
zone.
Rock mass Rock mass Support Shotcrete application
description behaviour requirements
Massive Surface slabbing, Retention of broken Apply 50 mm shotcrete over weldmesh
metamorphic spalling and rock and control of anchored behind bolt faceplates,or apply 50
or igneous rock. Possible rockburst rock mass dilation. mm of steel fibre reinforced shotcrete on rock
High stress damage. and install rockbolts with faceplates; then
conditions. apply second 25 mm shotcrete layer.
Extend shotcrete application down sidewalls
where required.
Massive Surface slabbing, Retention of broken Apply 75 mm layer of fibre reinforced
sedimentary spalling and rock and control of shotcrete directly on clean rock.
rock. High Possible squeezing squeezing. Rockbolts or dowels are also needed
stress in shales and soft for additional support.
conditions. rocks.
Apply 75 mm Potential for Provision of Apply 50 mm of steel fibre reinforced
layer of fibre wedges or blocks support in addition shotcrete to rock surfaces on which
reinforced to fall or slide due to that joint traces are exposed.
shotcrete to gravity loading. available from
directly on rockbolts or cables.
clean rock.
Rockbolts or
dowels are also
needed for
additional
support.
Rock mass Rock mass Support Shotcrete application
description behaviour requirements
Sedimentary rock Potential for wedges Provision of support Apply 50 mm of steel fibre
with a few widely or blocks to fall or in addition to that reinforced shotcrete on rock surface
spaced bedding slide due to gravity available from on which discontinuity traces are
planes and joints. loading. Bedding rockbolts or cables. exposed,with particular attention to
Low stress plane exposures may Sealing of weak bedding plane traces.
conditions. deteriorate in time. bedding plane
exposures.
Bedded and Slabbing, spalling Control of rock mass Apply 75 mm of steel fibre
jointed and possibly failure and squeezing. reinforced shotcrete to clean rock
weak sedimentary squeezing. surfaces as soon as possible, install
rock. High stress rockbolts, with faceplates, through
conditions. shotcrete, apply second 75 mm
shotcrete layer.
Rock mass Rock mass Support Shotcrete application
description behaviour requirements
Highly jointed Ravelling of small Prevention of Apply 50 mm of steel fibre reinforced
metamorphic or wedges and blocks Progressive shotcrete on clean rock surface in roof
igneous rock. defined by ravelling. of excavation. Rockbolts or dowels may be
Low stress intersecting joints. needed for additional support for large blocks.
conditions.
Highly jointed Bed separation in Control of bed Rockbolts or dowels required to control bed
and bedded wide span separation and separation. Apply 75 mm of fibre reinforced
sedimentary excavations and ravelling. shotcrete to bedding plane traces before
rock. Low stress ravelling of bedding bolting.
conditions. traces in inclined
faces.
Heavily jointed Squeezing and Control of rock Apply 100 mm of steel fibre reinforced
igneous or 'plastic' flow of rock mass failure and shotcrete as soon as possible and install
metamorphic mass around dilation. rockbolts, with face-plates, through shotcrete.
rock, opening. Apply additional 50 mm of shotcrete if
conglomerates or required. Extend support down sidewalls if
cemented necessary.
rockfill. High
stress
conditions.
Rock mass Rock mass Support Shotcrete application
description behaviour requirements
Heavily jointed Squeezing and Control of rock mass Apply 50 mm of steel fibre reinforced
sedimentary rock 'plastic' flow of failure and dilation. shotcrete as soon as possible, install
with clay coated rock lattice girders or light steel sets, with
surfaces. mass around invert struts where required, then more
High stress opening. Clay rich steel fibre reinforced shotcrete to cover
conditions. rocks may swell. sets or girders. Forepoling or spiling
may be required to stabilise face ahead
of excavation. Gaps may be left in
final shotcrete to allow for movement
resulting from squeezing or swelling.
Gap should be closed once opening is
stable.
Mild rockburst Spalling, slabbing Retention of broken Apply 50 to 100 mm of shotcrete over
conditions in and mild rock and control of mesh or cable lacing which is firmly
massive rock rockbursts. failure propagation. attached to the rock surface by means
subjected to high of yielding rockbolts or cablebolts.
stress conditions.
When designing a shotcrete program the following issues need to taken into
consideration:-
· Amount of shotcreting required;
· Shotcrete strength;
· Shotcrete thickness;
· Presence of groundwater (eg. quantity, chemistry, pressure);
Surface Rock Support for Underground Mines 7
Code of Practice
· Need for drainage of groundwater from behind the shotcrete;
· Water quality (potable);
· Type of shotcrete mix (wet or dry);
· Use of microsilica;
· Admixtures (plasticisers, etc);
· Accelerators (for wet mix);
· Fibre reinforcement;
· Curing (external or internal);
· Testing and monitoring;
· Correct shotcrete application.
CODE OF
TIMBERING
CODE OF TIMBERING RULES
1. Stulls shall be set at a maximum of 2 metres between the same row and also
between row of stulls.the front row is not more than 4.2 metres from the face.
2. Cogs or pigstys shall be set at all entrance to the stoping areas and also at a
interval of not more than 4.5 metres for working height 3 metres.
1.The back of all cut and fill method stopes shall be supported with pigysts at a
distance of 3 m between pigysts in the same row and 1.8 m between the last row of
pigysts and the wall ,nearest row of pigysts being not more than 4 m from the face.
2.Between the face and the last row of pigysts ,the back shall be supported with
props at interval of not more than 1.5 m.
3.The lids and wedge ,used with the prop shall have a width not less than the
diameter of the prop,a thickness of not less than 6 cm,and a length of not less than .
5 m.
4. The prop shall not set on packing.a flat base piece ,not less than 5 cm thick, 25 cm
wide,and .75 m long long shall be used.
5.The timber used for the construction of pigysts shall not be less than 1.2 m in length
and at least two opposite sides joggled flat so as to provide a suitable bearing
surface.
6.Weak patches of back and hanging wall shall be supported by additional support of
pigysts and props.
Square set method
Where the ore bed is weak and friable so the stope block is not self
supporting .it shall be systematically supported with square set of the
approved size.
Erection of sets:-
a.As the set used for cap butting sets ,the cap shall be laid at right angles
to the general strike of the ore body ,because it has to give maximum
support of the walls.
b.Durind dressing .timber form a proper joint.
c.All open dressing shall be tightly blocked and wedged to prevent sideway
movement.
d.Side lagging board shall be placed from post to post and the gap
between the lagging board and the walls shall be tightly packed either
with the junks or fill material.
• Stengthing of set :-
a.Angle braces –they shall be fixed to reinforce the sets against the side
pressure.
b.Doubling will be done in necessary condition.
• These pipelines can range from low pressure (less than 1MPa) turbulent flow
systems for deslimed slurries to high pressure (greater than 5MPa) laminar flow
systems for pastefill.
• Sometimes backfill only acts as a void filler and needs only sufficient strength to
preventany form of remobilisation.
• Where backfill is used as an engineering material it requires sufficient strength be
exposed by ore pillar mining in tall vertical faces or undercuts.
· Paste backfill : -
Total mill tailings filtered or thickened to around 80%Cwto
which cement and water is then added to achieve
therequired rheological and strength characteristics.
Anyrejects to the dam are at the full tailings sizing range.
· Rock backfill :-
Waste rock from surface or underground and crushed to
a typical top size of around 40mm. This can be placed as
is or with cemented hydraulic backfill slurry or cement
water slurry.
•HYDRAULIC BACKFILL
1.Hydraulic backfill is produced by cycloning of mill tailings slurries to produce a coarse
dense underflow.Typical specifications of hydraulic backfill are: Not more than 10% by
weight of size fraction less than 10m (micrometres) in size. This ensures that acceptable
permeability of the placed fill is achieved.
2.Slurry density is greater than 70%Cw (solids by weight). The high density
minimises the drainage of transport water. The target density is a function of
particle specific gravity and the controlling parameter is %Cv (solids by volume)
which balances the requirement to transport the slurry without plugging the line
and excess drainage water.
3. The practical range is between 45%Cv and 50%Cv.
4. Hydraulic backfill slurries are transported by gravity through boreholes and pipelines to
the stopes.
5. The slurry enters the stope and the solid particles consolidate rapidly.
6.The excess transport water in the slurry will initially pond above the current solids layer,
butunder the influence of gravity will commence on a generally vertical drainage path.
downwards. The rate of drainage is a function of the permeability of the backfill and the
driving head. The quantity of water that will drain is a function of the initial slurry
density
and the residual moisture content of the backfill. The quantity of drainage resulting
from
slurry densities of around 70%Cw is as little as a quarter of the drainage resulting from
55%Cw slurries.
Free draining hydraulic backfill has a typical porosity of around 50%, can be walked on in
a few hours and is trafficable within 24 hours.
Where the hydraulic fill is to be exposed, cement addition rates of around 6% are
typically
required and this will result in unconfined compressive strengths of greater than 750kPa
within 28 days. Higher strengths and faster curing can be achieved by adding extra
cement.
At Mount Isa cemented hydraulic backfill consisting of 3% OPC, 6% ground furnace slag
(to produce 6% equivalent cement) and 91% deslimed tails are routinely exposed over
widths of 40 metres and over 100 metres high
BULK AND EXPOSABLE BACKFILLS
·Exposable Backfill:-
Engineered materials with cement and or other binder added
which has sufficient cohesion to support its self weight when
exposed either as a vertical face or in an overhang by the
blasting of adjacent pillar ore
Disadvantages:-