KSRM College of Engineering-Kadapa: Construction, Planning and Management
KSRM College of Engineering-Kadapa: Construction, Planning and Management
KSRM College of Engineering-Kadapa: Construction, Planning and Management
Course Objectives:
•Understand the importance of construction management, resource management and what the stages of construction activity are?
•To know how to prepare scheduling in construction activity. significance of PERT and CPM and make use of these two techniques how to
develop a network diagram for construction
•To know various types of equipments in construction and their usage in varied works usage of mechanization and its effect on
productivity. Applications of machinery in different types of constructions are?
•Understand importance of inspection and how to maintain quality in different stages. Recognize the standards of materials and effective
utilization of skilled persons in construction. Effect of ethical procedures in construction.
•To know the importance of safety measures in construction activity, effect of safety benefits to construction workers. Understand the
importance of organization and know how to maintain communications in construction.
Course Outcomes:
Upon completion of this course, student will be able to,
•List the various stages and implementation of management skills in construction
•Possibility usage of sophisticated equipment in construction
•The basics in quality maintains in various stages
•The importance of organization and how correspondence carried out in construing industry.
Unit - 1 Introduction
Significance of Construction Management – Objectives and Functions of Construction Management – Types of Construction –
Resources for Construction Industry –Stages of Construction – Construction Team and Engineering Drawings.
TEXT BOOKS
P S Gahlot and B M Dhir “Engineering Construction Planning and Management”, New Age International (P) Limited, Publishers, New
Delhi.
S C Sharma “Construction Equipment and Its Management”, Khanna Publishers, New Delhi.
REFERENCE BOOKS
M Govindarajan, S Natarajan and V S Senthilkumar “Engineering Ethics”, Prentice-Hall of India (P) Limited, New Delhi.
Dr. S Seetharaman “Construction Engineering and Management”, Umesh Publications, New Delhi.
Horpal Singh “Construction Management and Accounts”, Tata McGraw-Hill Companies, Inc. New York.
Unit-1
1.1 Significance of Construction Planning and Management
Without a planning it is difficult to complete with in timing
potential for problems that could significantly delay the project and cost money.
effective management of the project's schedule, cost, quality, safety, scope, and function.
A construction manager measures each design decision with careful analysis that
calculates the impact that decision will make on the budget and schedule.
Communication
Leadership
Taking sound decision at lowest cost for proceeding the work ( Equipment,
at site
Planning : Number of alternative plans , select best suited plan and it covers
Scheduling : Prepare time allotment to the each and every work and showing the
total time for completion..It deals with the “ when to do task.(Bar chart, Mile stone chart
and network techniques)
Organizing : Project Arranging meaningful tasks
Divisions
Subdivisions
Divisions are 1) Consultant ants
2) Design Engineers
4) Accountants
5) Ministerial staff
6) Executing engineers
7) Supervisors
Training
Arrangements of reviews
why it happened
Civil engineering is one of the oldest jobs in the world. Civil engineering deals with constructing,
designing, and maintaining a physical environment. This includes structures such as airports, roads,
Transportation Engineering
Environmental Engineering
Geotechnical Engineering
Materials Engineering
Ocean Engineering
Structural
Engineer : Prepare Design and Structural Drawings, Monitor the structural detailing at
sites
Transportation Engineer: Design
, Construction and Maintenance of transportation system
Water Resources Engineer: Water
retaining system, transport system
Environmental Engineer: water Treatment
system and solid waste management system.
Geotechnical
Engineer: Responsible for structures foundation and dealing land sliding, soil
erosion and earth quakes.
Remote
sensing and GIS: It is a science, making measurements of earth using sensors through
planes and satellites. GIS is a computer based tool for mapping and analyzing features on earth.
Urban
Planning and Municipal engineering: Both are involving to provide all amenities required
for a city
Materials engineering:
Focus on quality and quantity of materials
Ocean Engineering: Study
the behavior of waves, current and its influence on human society
Based on the method of construction, it is divided into three
Light construction :Does not require any heavy equipment like residential
practices should conform to the codes of practice And local building authority
regulations.
adopt IS codes and consider Environmental issues Get permissions from the central
govt bodies
Engineer:
Analyze typical plans, survey reports, maps, and other data for planning and designing of projects
DPR Preparation including construction costs, government regulations, potential environmental
hazards and other factors during the planning and risk-analysis stages of a project
Oversee and analyze the results of soil testing to determine the adequacy results and use the relevant
test results like SBC for foundations.
Analyze the results of tests on building materials, such as concrete, wood, asphalt, or steel, for use in
particular projects
Prepare cost estimates for materials, equipment, or labor to determine a project's economic feasibility
Use design software to prepare plan and design transportation systems, hydraulic systems, and
structures in line with industry and government standards
Perform or oversee surveying operations to establish building locations, site layouts, reference
points, grades, and elevations to guide construction
Prepare and Submit RA and FFbills
Quality maintenance during the execution
Manage the repair, maintenance, and replacement of public and private infrastructure
Project manager : In charge of entire work
Coordinate all staff
Maintain the progress
Maintain constant flow of funds
Contractor : May be a individual or a firm
Responsible for progress
If needed appoint subcontractor
Work force : Ensure their work allotted according to their allotted tasks
1.8 Engineering Drawings : These are Orthographical Representation
Tender Drawing
contract Drawing
Working Drawing
Manpower Weeks
1(No) 21(No) 31(No) 41(No) 51(No)
Foreman 5 5 4 4 4
Masons ( Skilled ) 10 10 10 8 8
Masons ( Semiskilled) 20 20 20 16 16
Bartenders 10 10 10 10 10
2.2 c) Preparation of Equipment Schedule : Deployment of equipment into the
construction site in advance is essential. For maintain smooth progress of the work, equipment usage
is essential. This schedule will help to reallocation of equipment.
Name of the work--------------- Prepared by------------------
Site location------------- Date --------------------
Concrete 2 2 2 2 3 3
Mixer
Elevators 2 2 2 2 2 2
Vibrators 5 5 5 5 5 5
2.3 A) Scheduling by bar charts:
Time allotment of each and every activity can be shown
It is a conventional method for showing scheduling( Henry Grantt)
It has two coordinates axis ( Activity, Time)
Time indicating with a box, line or thick line
Time allotment based on the quantity, resources and technology
These are using to check the overall progress and progress of each activity
Used for predicting the quantity of materials and manpower
5 Columns Mile
above PLB stone
-2
6 Slab Mile
2.4 Network Techniques In construction management: It is a effective tool for planning ,
scheduling and controlling construction work. Two common networks are
PERT( Program Evaluation of Review Technique)
CPM ( Critical Path Method)
PERT( Program Evaluation of Review Technique): Developed by Navy Engineer from USA, worked on
Polaris Missile Program during 1957-58.
Used For Research Program
Event Orient
Expected time evaluated by Optimistic time
Pessimistic Time Te = to+4tt+tp/6
Most Likely Time
Not related to the cost
Prior data not available
CPM ( Critical Path Method): It is developed in 1956 from USA, this method was successfully tried
sick industry( Chemical ) and it was usefully carried out repair.
Gives meaningful solution
Event oriented
Time and cost are directly depending
In India, this method was used frequently because of suitability
If any activity cramp, it clearly shows how/ and solution for cramp
Shows economical way to speed up the project
Shows schedule of materials and qty also.
2.5 Break down of structures( BDS) : It is a technique to develop
Compound wall
Activity
Event Event
Event : An instantaneous point in time marking beginning and end of the activity
Ex: Starting of earth work exaction, end of earth work excavation
Activity
Event Event
15
0
15
Network : Network is a diagrammatical representation of a work plan showing activities
and events showing step by step , leading to establish a certain goal.
Network Representation : Two systems are there
a) Activity on arrow
b) Activity on node
Activity on Arrow : An activity is graphically represented by an arrow drawn from left to
right and described on top of the arrow. Length of the arrow does not representing time.
Shuttering 2
Fix the
1 starting of both
1 Reinforcement 2 Reinforcement start after
shuttering
3 Commencement of concrete
Procure Materials
3
Activity on Node : Here activities are representing in a node and arrows shows the
dependency relation between activities. Time is representing with in node.
B
A 3
0 D
5
C
5
Classification of activities :
Activity of construction actually to be executed
Activity Involves ordering and delivery of materials
Activities are procurement of equipment to the site
Activity involving decision such as approvals and inspections.
Which involving administrative measures such as tenders, preparation of DPR
2.7 Rules for developing network:
Rule1: No activity can commence until all proceeding activities have been completed
Build a wall Plaster a wall
1 2 3
4 days 2 days
Procurement of
4 materials
7days
Procurement of Stone Pointing
5 manpower Masonry
7 8 9
10days 3days 1days
5days
6 Procurement of
Machinery
Rule 2: A dummy activity is introduced in the network either show the dependency or to
avoid duplicate numbering of activities. It is a artificial activity and it does not have any
sources and time. For controlling the network, a dummy activity is introducing in the
Network
Erect Beam
Concrete Pier
1 3 4
Precast beam
2 Dummy activity
PCC Stone
3 Masonry
Rule :4 No activity should lead back to a previous event i.e. the must not be looping
Place concrete
1 2
Cure concrete
Test concrete
3
Rule 5 ; In any network there must only one start and one finish and it has any number of activities
in between. No activity should not left dangling
3
Dismantle Temporary
shed
Erect Plant
1 2
Commissioning
of plant 4
2.8 Net work development and analysis:
a) Logic for Network Development: For Logical development of network following has
to
Known
Know about proceeding and succeeding activities ( Sequential Order)
Know about logic between activities
Know about the critical activities
Know about concurrence activities
Diverging
Convergent :
Parallel:
b) Assigning duration of activity : After developing network, time allot to the each activity,
Time estimate made
1
3
4
4
Step:3: Treat as 2,3,4 as initial event and allow “n” number of arrows and number it as
Step 2 5
2
6
1 3 7
4 8
Step 4: Number of arrows coming to end event, no arrows coming out from end event
9
1
0 12
1
1
3 5
7
1 2
4 6
Head Event Tail Event
1 2
2.9 Net work Analysis:
Earliest Event Time( Te): Earliest possible occurrence of time, i.e. Earliest possible
time when all activities leading to an event will be completed. Always be a forward pass
TE 4
2-3- 2
TE 0
7 TE 11,6,5=11
10 4 8-4-12
4 TE 2 = TE 1 +t 12 =0+4=4
1
TE 0 6 TE3 = TE 1 +t 13 = 0+0=0
0 3 5 T 4 = T 3 +t = 0+5=5
E E 34
TE4 = TE 2 +t 24 = 4+7=11
TE4 = TE 0 +t 14 = 0+6=6
Latest Event Time ( TL) : It is latest possible occurrence of event without delaying the
project completion time i.e. it is the latest time when all activity leading to an event may be
completed without delaying the project completion time. All ways be a backward pass.
2
TL= TL 3 = TL 4 – t 34 =11-5=6
Te=11 TL 2 = TL 4 – t 24 =11-7=4
4 4
1 TL 1 = TL 4 – t 14 =11-6=5
TL 6,0,5= 0 TL=11 TL 1 = TL 2 – t 12 =4-4=0
3
TL 1 = TL 3 – t 13 =6-0=6
TL=6
Earliest starting time ( EST): It is the earliest time when an activity can commence.
EST: TE of the tail event =TE I
T
E
2 = TE 1 + t12 = 0+4=4
TE 1=0 4 2
5
16
3
Earliest Finishing time ( EFT): It is the earliest time when the activity finished
EFT : EST of activity time
T 3 =
E TE 1 + t13 = 0+6=6
T 3 =
E TE 2 + t23 = 4+5=9 Finally T 3 =9
E
Latest finishing time( LFT): It is latest time when an activity may be finished without
delaying the completion time of the project
TL is less than TE
Negative slack =
Zero slack; TL is TO TE
Critical events : Where ever the zero slack at events , all are critical events and connecting of all critical events to be the critical path
1) Identify the critical events and draw critical path
TE=15
S=0
3
TE =0 TE=5 10 TL=15,237 4
S=0 S=0 TE=22,17=22 TE= 19,27,21=27
1 2 5 S=0 6 S=0
5 12 5
TL=0 TL =11,10,5 8 TE=13 TL = 22 8 TL = 27
4 S= -6
TL = 19
TL=18.3,12.3
1
0 23.7
TE=42,39.9,33.5
1 9.8 1 1 1 .
TE=0 TE=12.3,9.8 TE=30.3,20.7 TE=33.8,32.7
. . . .7
1 3 5 8
12.3 18 3.5 TL=33.8 8.2
TL=12.3 TL=30.3
TL=42
TL=1.1,0,2.5 1 10.8
9.0 1
TE=11.7
11.7 TE=21.9 18
.
4 .
6
10.2
TL=12.8,21.3 TL=24,23
S.No Event Slack ( TL-TE) Critical Event
1 1 0-0=0 Critical
2 2 12.3-9.8=2.5 Noncritical
3 3 12.3-12.3=0 Critical
4 4 12.8-11.7=1.1 Noncritical
5 5 30.3-30.3=0 Critical
6 6 23-21.9=1.1 Noncritical
7 7 33.8-33.8=0 Critical
8 8 42-42=0 Critical
6 5
3
9 4
5 10
8 6
4 5 1
1 2 9
0
2 11
8
4 2
7
6
7
2.11 Critical Path Method :
Process of CPM ; CPM is used to make schedule of a project along with planning ,
scheduling and controlling
Planning : Ascertain the logic between activities, resources( 4M)
Scheduling : Time allotment for all activity considering logic and show single time for
every activity, based on the 4M and space.
Controlling : Review of performance of each activity( Deviation of time for each activity),
if any deviation plan it freshly with sufficient time of gap
TE=10
2
TE=0
10 (PCC)
1 7( Reinforcemen
t)
5(Cover)
3
TE=5,17=17
2.12 Float : It is associated with activity times and analogous to the term slack
Slack denotes the flexibility range with in event occur
Float denotes the range which an activity start time and end
Types of floats:
Total float
Free Float
Independent Float
Interfering Float
Total Float ; It is a difference between maximum time available and actual time required
to perform the activity, its difference is called total float
FT = LST-EST
FT = LFT-EFT
FT = ( TL j- TE i ) –tij
Free float: It is a positive float , it is an activity without delaying any succeeding activity.
FF for i—j = T E j—( T E i+ t ij)
= T E j—EFT
FF = EST for successor activity---- EFT of present activity
Independent Float : It is the excess of minimum available time over the required
activity duration. It is equal to the free float minus tail event slack.
F ID = ( T E j– T L i)– t ij
F ID = F F– S I
F IT = F T – F F
1. Identify Critical activities and draw critical path
T E=10
2
T L=18,28
10 8 12
T T E=52
T E=0 T E=18 T E=18,26
E=36,22,40
1 4 5 7 8
8 10 12
T L=0,8 T L=18 T L=26,30 T L=40 T L=52
8
12 6
6
T E=12
T E=34,17
3 6
5
T L=12,29 T L=34
Activity Duration Earliest EST Latest Total Free Independen
( i---j) t ij LST LFT Float float t Float
EFT ( LST TE J (TE J -TL
EST - - I)
_ t ij
EST) EFT
1-2 10 0 10 8 18 8 0 0
1-3 12 0 0 12 0 0 0
12
2-5 8 10 18 26 8 8 0
18
2-7 12 10 28 18 18 10
22 40
3-4 6 12 12 0 0 0
18 18
3-6 5 12 29 17 17 17
17 34
4-5 8 18 0 0 0
26 18
26
5-6 8 26 26 0 0 0
34 34
2. Identify Critical Events and draw critical path with CPM
36 63,42
16,43,38 83
20 20
2 8 9
2 10
41 43 63
36 9 83
4 6 10
0 34,15 8
1 3 4 7
4 2 9
4 6,25,33 55,34
0,5 21
15
5
9
21 25
4
6
25
Activity Duration 20Earliest EST Latest Total Free Independen
( i---j) t ij LST LFT Float float t Float
EFT ( LST TE J (TE J -TL
- - I)
_ t ij
EST EST) EFT
1-2 36 0 36 5 41 5 0 0
1-3 4 0 4 0 4 0 0 0
2-8 2 36 38 41 5 5 0
43
3-4 2 4 6 4 6 0 0 0
4-5 15 6 21 6 0 0 0
21
4-7 9 6 25 19 19 19
15 34
4-8 10 6 33 27 27 27
16 43
5-6 4 21 21 0 0 0
25 25
6-7 9 25 25 0 0 0
34 34
7-8 9 34 34 0 0 0
3.Construction Equipment:
3.1 Requirement of construction equipment
A wide variety of relatively heavy machines which perform
specific construction
It is customary to classify construction machines in accordance with their
functions such as hoisting, excavating, hauling, grading, paving, drilling, or
pile driving.
Construction equipments are one of the very important resources of
modern-day construction, especially in infrastructure development projects
Need of the equipment
Based on the qty
Based on the perfection ( Quality, Proportion)
For introducing new Technology
Time
3.2 Types of Construction Equipment
1.Earth-moving equipment
2.Hauling equipment
3.Hoisting equipment
4.Conveying equipment
5.Aggregate and concrete production equipment
6.Pile-driving equipment
7.Tunneling and rock drilling equipment
8.Pumping and dewatering equipment
3.3 Operations involved in construction of any project
Excavation
Digging of large quantities of earth
Moving them to distances which are sometimes fairly long
Placement
Compacting
Leveling
Dozing
Grading
Hauling
3.4 Heavy Earth moving Equipment:
Earth moving equipments is used in the construction industry to :
• To shift amount of earth
• To dig foundations and landscape areas
Bulldozers,
Scrapers,
Loaders Shovels
Cranes
3.4.1 Bulldozers : A bulldozer is a large powerful tractor, also called as crawler tractor
(track type or chain type) equipped with a substantial (large) metal plate (known as a
blade) in front used to push( move) large quantities of soil, sand, rubble, or other such
Material and typically equipped at the rear with a claw-like device (known as a ripper) to
Loosen densely compacted materials.
APPLICATIONS
Bull dozers are mainly used for the following operations
1.For spreading the earth fill
2.For opening up pilot roads through mountainous and rocky terrains.
3.Clearing construction sites.
4.Maintaining haul roads
5.Clearing land from the trees and stumps
6.back-filling trenches at construction sites by dragging the earth from
one
place to another
3.4.2 Scrapers : The scraper is a large piece of equipment used in mining,
construction, agriculture and other earthmoving applications. The rear part has a
vertically moveable hopper (also known as the bowl) with a sharp horizontal front
edge
3.5 Compaction equipment : It is the compression of soil particles and it reduces the
total pore space between soil particles, restricting the entry and exist of air and water into
the soil strata.
Requirement of soil compaction :
• To increase the soil strength
•To improve the stability of soil
•To reduce the permeability of soil
•To reduce the erosion damage
3.5. Compaction: It will be done for compacting soil and concrete
3.5.1 Compaction for soils :
Equipment for Compaction of soil
3.5.1.1 Smooth wheel rollers: These are one of the most. common types of compaction
Equipment Used Weighing from 5 to 15 tones. They are suitable for compacting sand, gravel
and broken stones etc. They are used for compacting highway base courses.
3.5.1.2 Pneumatic rollers
• In this type, on the outer surface of a metal cylinder, metal pieces of the shape
of sheep foot are fixed
•Weight of drum is about 1.5 to 10 tone.
• It is suitable for compacting cohesive soil(clays).
3.6 Grading Equipment :A grader, also commonly referred to as a road grader, motor
grader, or simply a blade, is a form of heavy equipment with a long blade used to create a
flat surface during grading.
Graders are commonly used in the construction and maintenance of dirt roads and gravel roads
. In constructing paved roads, they prepare a wide flat base course for the final road surface.
Capacities range from a blade width of 2.50 to 7.30 m (8 to 24 ft) and engines from 93–
373 kW (125–500 hp).
3.7 Hauling Equipment:
Hauling units transport the earth, aggregate, rock, ore, coal and other
materials. Hauling units may be road vehicles or rail-road locomotives. Haulage mainly
consist of trailers pulled by tractors or trucks.
Trucks are hauling units that provide relatively low hauling costs because of their high
travel speeds.
Trucks are hauling units that provide relativity low hauling cost. The productive
capacity of a truck depends on size of load an the number of trips it can make in an hour
Truck function: in transporting excavated material, processed, aggregates and
construction material
3.8 Concrete Mixing unit :
A typical concrete mixer uses a revolving drum to mix the components. For smaller
volume works, portable concrete mixers are often used so that the concrete can be made at
the construction site
Advantages of Ready-Mix Concrete
Better quality concrete is produced as it is made from consistent methods and in advanced
equipment.
No need to store construction materials at the site.
Labour associated with the production of concrete is eliminated, thereby reducing labour cost.
Air and Noise pollution at the job site is reduced.
Wastage of basic materials at the site is avoided.
Reduce the time required for construction.
No delays in completing major projects like constructing dams, roads, bridges, tunnels, etc.
Economy in the use of raw materials results in conservation of natural resources.
Safe work practices - No disruption in the project schedules.
Environment-friendly.
Disadvantages of Ready-Mix Concrete
Requires huge initial investment.
Not suitable for small projects (less quantity of concrete is required).
Need an effective transportation system from the batching plant to the job site.
Labour should be ready at the site to cast the concrete in position without any
delay to avoid slumps in the mixture.
Concrete has limited time and should be used within 210 minutes of batching the
plant. Traffic jam or breakdown of the vehicle can create a problem.