Ethiopian Roads Administration: Dimtu Town
Ethiopian Roads Administration: Dimtu Town
Ethiopian Roads Administration: Dimtu Town
Dimtu Town
START OF
PROJECT
Ethiopian Roads
Administration
Airfield
Compound road
1 facility to be design
Ceremonial area.
PURPOSE OF THE REPORT
5
KICK-OFF MEETING
Kick-Off Meeting was held on July22/2022 at ERA
Horizontal alignment
Based on the design traffic, the project road is classified as DC5
road standard and all review has been made accordingly.
MAIN ACCESS ROAD
Radius of curvature.
Due to the flat terrain type of the project area all radius of
AIRFIELD
HORIZONTAL ALIGNMENT
Physical requirement of the runway has been checked in
respective of ICAO, Aerodrome design manual doc
9157 AN/901
The design runway has been noticed lack of runway end
safety area provision.
The starting point of the runway is situated at 6.5meter fill
REVIEW OF GEOMETRIC
15
DESIGN
As per the requirement of annex 14 and ICAO standard
runway end safety area, RESA with a length of 240 meter
shall be proposed.
Due to previously fixed orientation of the runway alignment
there is space limitation at the start and end point of the
runway which governed the total available length.
The main control point at the two ends of the runway is
The existing access road Alignment
The BILATE river bank which is found closer to the end of
the runway.
REVIEW OF GEOMETRIC
16
DESIGN
The designed runway is limited to a total length of 3.3km while the original
design length was 3.12km.
As per the referred UNIFIED FACILITES CRITREA, UFC
requirement.
To provide all required facilities ,the paved part of the revised runway is
standard.
Issues related to relocation of taxiway and apron had been raised by the
To make the apron out of the compound for security reasons if there is an
consent.
The newly located taxiway and apron, will have additional access road with
a length of 238m.
REVIEW OF GEOMETRIC
19
DESIGN
Length of Taxiway.
In the original design the total length of taxiway is found as 260meter long.
As per the ICAO standard for code letter 4D the recommended length is 176meter.
Runway Marking.
The quantities are underestimated BUT all marking types are proposed
Indicator and Signaling Device
In the engineering design report
wind direction indicators,
Signaling lamp , signal panels and signal area ARE proposed to be provided
26
HYDROLOGICAL AND HYDRAULICS RECOMMENDATION REVIEW
27
HYDROLOGICAL AND HYDRAULICS RECOMMENDATION REVIEW
28
29
HYDROLOGICAL AND HYDRAULICS
RECOMMENDATION REVIEW
30
HYDROLOGICAL AND HYDRAULICS
RECOMMENDATION REVIEW
31
HYDROLOGICAL AND HYDRAULICS RECOMMENDATION REVIEW
32
HYDROLOGICAL AND HYDRAULICS RECOMMENDATION REVIEW
33
SOIL AND MATERIAL INVESTIGATION REVIEW
34
SOIL AND MATERIAL INVESTIGATION REVIEW
35
SOIL AND MATERIAL INVESTIGATION REVIEW
36
SOIL AND MATERIAL INVESTIGATION REVIEW
37
SOIL AND MATERIAL INVESTIGATION
REVIEW
38
SOIL AND MATERIAL
INVESTIGATION REVIEW
39
SOIL AND MATERIAL INVESTIGATION REVIEW
40
SOIL AND MATERIAL INVESTIGATION REVIEW
41
REVIEW OF MEASUREMENT AND CONTRACT COST
42
1000 GENERAL
All items in this series are reviewed and found that
the same has been proposed as per ERA standard
specification.
2000 SITE CLEARANCE
Minor difference between the design and the revised
quantity has been seen.
The reason is due to vertical alignment revision made
on main access, compound road and airfield section.
REVIEW OF MEASUREMENT AND CONTRACT COST
43
3000 DRAINAGE
Underestimated quantity for vehicular crossing and overestimated
quantity of curb stone size of 20 by 25,
4000 Earthworks
The major quantity difference has been seen from the revision of
the airfield section.
The main reason is due to inclusion of additional section namely
RESA.
5000 SUBBASE, ROAD BASE
The change in quantity has been noticed due to the reduced
44
runway section.
Due to revised pavement thickness of asphalt concrete the quantity in revised
Runway marking is considered and the quantity for the same item is
revised.
Summary of cost comparison for design quantity and actual estimated
45
The project design document has a design concept difference on the airfield
section in relation to the end safety area facility.
The pavement structure thickness proposed for the airfield is higher than
the required thickness.
From the engineering design report, it is learnt that the reason for higher
thickness recommendation of Asphalt concrete is assumption of 80% CBR
requirement for base course.
According to the current practice and specification of base course material
the CBR requirement for base course is 100% and above.
REVIEW OF MEASUREMENT AND CONTRACT COST
46
THANK YOU