CPM and Pert Analysis
CPM and Pert Analysis
CPM and Pert Analysis
INTRODUCTION
NETWORK PLANNING
ESTIMATING TIME
CPM
PERT
Project Management
Project
A project is an interrelated set of activities that has a definite
starting and ending point and that results in a unique product
or service.
Project management
Project management is a scientific way of planning, implementing,
monitoring & controlling the various aspects of a project such as time,
money, materials, manpower & other resources.
Network Planning Methods
Concepts
Activity
Precedence relationship
Successor
Event
Guidelines for network diagram
ACTIVITY ON ARC(AOA):
Uses arcs to represent activities and nodes
to represent events.
It is Event Oriented.
3
1 2 6 7 8
4 5
DUMMY ACTIVITY
2
2) When two or more activities share the same
precedence activity but not all the precedence
are shared.
1 3 5
2 4 6
ACTIVITY ON NODE(AON):
3) EF-Earliest finish time: equals to the earliest start time for the activity
plus the time required to complete the activity.
4) LF- Latest finish time: the latest time in which the activity can be
completed without delaying the project.
5) LS- Latest start time: equal to the latest finish time minus the time
required to complete the activity.
6) FORWARD PASS:
The early start and early finish times are calculated by
moving forward through the network and considering the
predecessor activities Considers maximum
7) BACKWARD PASS:
The latest start and finish times are calculated by moving backward
through the network.
Considers minimum
8) SLACK TIME:
Slack time for an activity is the difference between its earliest and
latest start time or between the earliest and latest finish time.
Critical path is the path of activities having zero Slack time.
A Simple Project
HISTORY :
It was developed by J.E.KELLY of REMINGTON-RAND
and M.R.WALKER of DU PONT and the emphasis was
on the trade-off between the cost of project
and its overall completion time. The first test was
made in 1958,when CPM was applied to the
construction of a new chemical plant.
DEFINITION:
Critical path is the sequence of activities between a
project’s start and finish that takes the longest time to
complete.
STEPS IN DETERMINING
CRITICAL PATH
A - 3 300
B A 3 30
C A 7 420
D A 9 720
E D 5 250
F B,C,E 6 320
G F 4 400
H F 13 780
I G 10 1000
Total 4220
4 7
1 2 5 6
3
8
Overhead cost as per the given data- Rs.50
Paths in the network diagram :
A-D-F-G-I = 32
A-D-F-H = 31
A-C-F-H = 29
A-C-F-G-I = 30
A-B-E-F-H = 30
A-B-E-F-G-I = 31
ical path – A-D-F-G-I = 32
4 7
1 2 5 6
3
8
TIME ESTIMATES
A Initial - 12 16 26 17
design
B Survey A 6 9 18 10
market
C Build A 8 10 18 11
prototype
D Test C 2 3 4 3
prototype
E Redesign B,D 3 4 11 5
ing
F Market E 6 8 10 8
testing
G Set up F 15 20 25 20
productio
n
1 2 4 5 6 7
A-B-E-F-G = 60
A-C-D-E-F-G = 64 (CRITICAL PATH)
Advantages of PERT
• The activities that have slack time and that can lend
resources to critical path activities.
CPM PERT
• CPM works with fixed • PERT works with probabilistic
deterministic time time
• CPM is useful for repetitive • PERT is useful for non
and non complex projects with repetitive and complex
a certain degree of time projects with uncertain time
estimates. estimates.
• CPM includes time-cost trade • PERT is restricted to time
off. variable.