Project Integration Management Pmbok 5th Edition PPT File v1.1
Project Integration Management Pmbok 5th Edition PPT File v1.1
Project Integration Management Pmbok 5th Edition PPT File v1.1
2
Project Integration Management is . . .
3
Project Integration Management Processes
4
Develop Project Charter Process
5
4.1 Develop Project Charter
Definition: “The process of developing a document that formally authorizes
the existence of a project and provides the project manager with the
authority to apply organizational resources to the project activities”
PMBoK® Guide, 5th Edition, p. 66
6
4.1 Develop Project Charter Data Flow Diagram
7
4.1.1 Develop Project Charter Inputs
A narrative description of product or services to be supplied by the project:
Project Business need
4.1.1.1 Statement of
Work Product scope description
Strategic plan
The facts that determine whether the project is worth the investment to achieve
the project objectives:
4.1.1.2 Business Case Used to justify spending organizational assets (resources, time, money,
etc.)
Used to select projects from among a list of potential projects
Define the goal of the project. Agreements can be formal or informal:
Contract
SLA’s
4.1.1.3 Agreements
Letter of Intent and Memorandums
eMails
Verbal agreement
8
4.1.1 Develop Project Charter Inputs
External and internal environmental conditions that influence the project:
Government or industry standards
Enterprise Organization culture
4.1.1.4 Environmental
Factors Organization structure
Existing infrastructure
Marketplace conditions
Process related assets (such as plans, policies, procedures and guidelines) that
can be used for the project.
Organizational The organization’s standard and established policies and procedures
4.1.1.5
Process Assets
Document and report templates
Historical information (including lessons learned)
9
Enterprise Environmental Factors - Example
10
Organizational Process Assets - Example
11
Project Selection Methodologies
12
4.1.2 Develop Project Charter Tools and
Techniques
Expertise provided by any group or individual with specialized knowledge or
training:
Within the organization
Expert Consultants
4.1.2.1
Judgment
Professional associations and industry groups
Subject matter experts (SME)
Project Management Office (PMO)
13
4.1.3 Develop Project Charter Outputs
14
The Project Charter
The Project Charter addresses:
Project purpose or justification Business Needs
Measurable objectives and success criteria • Market Demand
High level requirements • Organizational Need
• Customer Request
Assumptions and Constraints
• Technological Advance
High level project description
• Legal Requirement
High level risks •Ecological Impacts
Summary milestone schedule • Social Need
Summary budget PMBoK® Guide, 5th Edition, p.69
Stakeholder list
Project approval requirements
Assigned Project Manager
Sponsor(s) of the project with authority level
15
The Project Charter (cont’d)
16
4.1 Develop Project Charter Miscellaneous Facts
Who can issue the A project initiator or sponsor external to the project at an
Project Charter? organizational level appropriate to funding the project.
Market demand
Organizational need
What factors are Customer request
projects taken to Technological advance
address? Legal or regulatory requirement
Ecological impacts
Social need
17
4.1 Develop Project Charter Terms
Factors that are considered to be true, real or certain without proof or
demonstration.
Assumptions Assumptions need to be identified, documented and validated
Part of progressive elaboration of the project
Factors that limit the project team’s options to complete the project and
Constraints produce the required deliverables
18
Practice Question:
A. Detailed schedule
B. Product scope description
C. Organizational need
D. Strategic plan
19
Develop Project Management Plan Process
20
4.2 Develop Project Management Plan
Definition: “The process of defining, preparing, and coordinating
subsidiary plans and integrating them into a
comprehensive project management plan.”
PMBoK® Guide, 5h Edition, p. 72
21
4.2 Develop Project Management Plan
Data Flow Diagram
22
4.2.1 Develop Project Management Plan Inputs
4.2.1.1 Project Charter Defined in Section 4.1.3.1
Outputs from
4.2.1.2 Planning Defined in Sections 5 through 13
Processes
23
4.2.2 Develop Project Management Plan Tools &
Techniques
When developing the project management plan use expert judgment to:
Decide which processes are needed for the project and to what degree do
they need to be applied
Expert
4.2.2.1 Determine resources needed and the level of involvement to complete the
Judgment
project work the plan
Develop the technical details to be included in the plan
Prioritize work to ensure resources are allocated appropriately
Facilitation
4.2.2.2 Used to guide developing the project management plan.
Techniques
24
4.2.3 Develop Project Management Plan Outputs
Integrates and consolidates all of the subsidiary management plans and baselines
from the planning processes. It documents the outputs of the subsidiary
management plans.
It includes:
Project management processes selected by the project management team
The level of implementation of each selected process
The tools and techniques to be used to accomplish the selected processes
Project
4.2.3.1 Management How the selected processes will be used to manage the project
Plan How work will be executed to accomplish the project objectives
How changes will be monitored and controlled
How configuration management will be performed
How integrity of performance baselines will be maintained and used
The need and technique for communication among stakeholders
The selected project life cycle and associated project phases
Key management reviews for content, extent and timing
25
The Project Management Plan must have:
Realistic
Formal
26
The Project Management Plan
Schedule Baseline
Cost Baseline
Scope Baseline
27
4.2 Develop Project Management Plan Terms
Persons and organizations, such as customers, sponsors, performing
organizations and the public, that are actively involved in the project, or whose
Stakeholder interests may be positively or negatively affected by execution or completion of
the project. They may also exert influence over the project and its deliverables.
Documents not part of the project management plan that are used to manage
the project such as:
Project Charter
Project
Documents Contracts, Agreements, Statements of Work, etc.
Work Performance Reports
Risk and Issue Logs
A meeting of all parties to the project (customers, sellers, project team, senior
management, agencies, functional management, sponsor) to make certain
everyone is familiar with the details of the project and the people working on the
Kickoff Meeting project.
It is held at the end of the planning process group, just before beginning work
on the project.
28
Practice Question:
29
Direct and Manage Project Execution Process
30
4.3 Direct and Manage Project Work
Definition: “The process of leading and performing the work defined
in the project management plan and implementing
approved changes to achieve project objectives.”
PMBoK® Guide, 5th Edition, p. 79
31
4.3 Direct and Manage Project Work
Data Flow Diagram
32
4.3 Direct and Manage Project Work
Directing and managing project work involves:
Performing activities to accomplish project requirements
Creating project deliverables
Staffing, training and managing project team members
Obtaining, managing, and using resources (materials, tools, equipment and facilities)
Implementing the planned methods and standards
Establishing and managing project communication channels (external and internal)
Issuing change requests (corrective, preventive and defect repair)
33
4.3 Direct and Manage Project Work
Directing and managing project work involves: (continued)
Managing risk and implementing risk response activities
Managing sellers and suppliers
Including approved changes into the project’s scope, plans and environment
Generating project data ( cost, schedule, quality and progress) for reporting and
forecasting
Implementing approved process improvement activities
Managing stakeholders
Documenting lessons learned
34
4.3.1 Direct and Manage Project Work Inputs
Project Management
4.3.1.1 See Section 4.2.3.1
Plan
Corrective Actions
Approved Change
4.3.1.2 Preventive Actions
Requests
Defect Repairs
Organizational, company or customer culture and structure
Enterprise Existing infrastructure
4.3.1.3 Environmental Personnel administration policies and guidelines
Factors Stakeholder risk tolerances
Project Management Information System (PMIS)
Standardized guidelines and work instructions
Communication requirements and policies
Organizational Issue and defect management procedures
4.3.1.4
Process Assets Process measurement database
Files and information from previous projects
Issue and defect management database
35
4.3.2 Direct and Manage Project Work Tools &
Techniques
Project Management
4.3.2.2 Information System Previously defined
(PMIS)
Meetings are held to discuss topics pertinent to the project:
Information exchange
4.3.2.3 Meetings Problem solving
Option evaluation
Decision making
36
4.3.3 Direct and Manage Project Work Outputs
4.3.3.1 Deliverables
Raw data on the activities being performed to accomplish the project work. This
typically includes, but is not limited to:
Start and finish dates of activities
Deliverables that have been completed and those not completed
Work Costs authorized and incurred
4.3.3.2 Performance
Percent physically complete of the in-progress schedule activities
Data
Documented lessons learned posted to the lessons learned knowledge base
Resource utilization detail
Number of defects
Number of change requests
37
4.3.3 Direct and Manage Project Work Outputs
(cont’d)
Corrective Action
Change Preventive Action
4.3.3.3
Requests Defect Repair
Documentation Updates
Project
4.3.3.4 Management Subsidiary project plans
Plan Updates
Project Requirements
4.3.3.5 Document Stakeholder Register
Updates Risks Register
38
4.3 Direct and Manage Project Work Terms
An action to ensure the future project performance does not deviate from the
Preventive Action project management plan.
The learning gained from the process of performing the project. Also
Lessons Learned considered a project record to be included in the lessons learned knowledge
base.
39
4.3 Direct and Manage Project Work Terms
An estimate, expressed as a percent, of the amount of work that has been
completed on an activity or a work breakdown component.
50/50 Rule: Task is 50% complete when it starts and gets credit for the
remaining 50% upon completion
Percent Complete
20/80 Rule: Task is 20% complete when it starts and gets credit for the
remaining 80% upon completion
0/100 Rule: A task does not get credit for partial completion, only full
completion
40
Practice Question:
As the Project Manager for Go Green Airlines you know that you need to
manage Project Execution. Which is the best response to, define Direct
and Manage Project Execution?
A. Project Charter
B. Quality Management Plan
C. Perform activities to accomplish project requirements
D. Managing people doing the work and implementing approved
changes
41
Monitor and Control Project Work Process
42
4.4 Monitor and Control Project Work
Definition: “The process of tracking, reviewing, and reporting the
progress to the meet the performance objectives defined
in the project management plan.”
PMBoK® Guide, 5th Edition, p. 86
43
4.4 Monitor and Control Project Work
Data Flow Diagram
44
4.4.1 Monitor and Control Project Work
Inputs
4.4.1.1 Project Management Plan Described in Section 4.2.3.1
Work Performance Analyzed data is transformed into information that can be used for
4.4.1.5
Information decision making
45
4.4.1 Monitor and Control Project Work
Inputs
Government or industry standards
Enterprise Environmental Company work authorization system
4.4.1.6
Factors Stakeholder risk tolerances
Project Management Information Systems
Organization communication requirements
Financial controls procedures
Organizational Process Issue and defect management procedures
4.4.1.7
Assets Risk control procedures
Process measurement database
Lessons learned database
46
4.4.2 Monitor and Control Project Work Tools &
Techniques
Previously defined
4.4.2.1 Expert Judgment
47
4.4.3 Monitor and Control Project Work
Outputs
Corrective action
4.4.3.1 Change Requests Preventive action
Defect repair
Forecasts
Project Document
4.4.3.4 Performance Reports
Updates
Issues log
48
4.4 Monitor and Control Project Work Terms
A management methodology for integrating scope, schedule and resources and
for objectively measuring project performance and progress:
Earned Value Performance is measured by determining the budgeted cost of work
Management performed (the earned value) and comparing it to the actual cost of worked
performed (the actual cost)
Progress is measured by comparing the earned value to the planned value
An approved plan for the project work against which project execution is
compared and deviations are measured for management control. The
Performance project measurement baseline typically integrates scope, schedule, and cost
Measurement parameters of a project, but may also include technical and quality
Baseline parameters.
The project baseline may be changed by formally approved changes
49
Practice Question:
If a Project Manager is concerned with the process of tracking, reviewing
and regulating the progress to meet performance objectives as defined in
the project management plan, which should she/he concentrate on:
A. Communication plan
B. Continuous monitoring
50
Perform Integrated Change Control Process
51
4.5 Perform Integrated Change Control
Definition: “The process of reviewing all change requests, approving changes,
and managing changes to the deliverables, organizational process
assets, project documents, and the project management plan and
communicating their disposition.”
PMBoK® Guide, 5th Edition, p. 94
52
4.5 Perform Integrated Change Control
Data Flow Diagram
53
4.5 Perform Integrated Change Control
Integrated Change Control includes the following:
Identifying that a change needs to occur or has occurred
Influencing the factors that circumvent integrated change control so that only approved
changes are implemented
Reviewing, analyzing and approving requested changes
Managing the approved changes by regulating the flow of requested changes
Maintaining the integrity of baselines by releasing only approved changes
Reviewing and approving all recommended corrective and preventive actions
Controlling and updating the scope, cost, budget, schedule, and quality requirements
based on approved changes
Documenting the impact of requested changes
Validating defect repair
Controlling project quality to standards based on quality reports
54
4.5 Perform Integrated Change Control
The Project Manager should be concerned with:
55
4.5.1 Perform Integrated Change Control
Inputs
4.5.1.1 Project Management Plan Defined in Section 4.2.3.1
Work Performance
4.5.1.2 Defined in Section 4.4.3.2
Reports
Corrective Action
4.5.1.3 Change Requests Preventive Action
Defect Repair
Enterprise Environmental
4.5.1.4 Project Management Information System
Factors
56
4.5.2 Perform Integrated Change Control
Tools & Techniques
4.5.2.1 Expert Judgment Previously defined
57
Who can approve changes?
58
The Steps for Making Changes
59
4.5.3 Perform Integrated Change Control
Outputs
Approved Change Requests
Corrective Actions
Approved Change Preventive Actions
4.5.3.1
Requests Defect Repair
Rejected Change Requests
Validated Defect Repair
Project Management
4.5.3.3
Plan Updates
Project Document
4.5.3.4
Updates
60
Configuration Management
A documented procedure used to apply technical and administrative
direction and surveillance to:
Identify and document the functional and physical characteristics of an item
or system
61
4.5 Perform Integrated Change Control Terms
Configuration
Establishing that the performance and functional requirements defined
Verification and
in the configuration documentation have been met.
Auditing
All requested changes must be either accepted or rejected by some
authority within the project management team or an external
Change Control organization representing the initiator, sponsor, or customer.
Board Oftentimes a Change Control Board is established to approve and
reject changes. The roles and responsibilities of the Change Control
Board are defined in the configuration and change control procedures.
62
Practice Question:
63
Close Project Phase Process
64
4.6 Close Project or Phase
Definition: “The process of finalizing all activities across all of the
Project Management Process Groups to formally
complete the project or phase”
65
4.6 Close Project or Phase Data Flow Diagram
66
4.6.1 Close Project or Phase Inputs
Project Management
4.6.1.1 Described in Section 4.2.3.1
Plan
Accepted
4.6.1.2 Scope Verification: Formal acceptance of the completed project deliverables
Deliverables
67
4.6.2 Close Project or Phase Tools and
Techniques
Analytical
4.6.2.2 Described in Section 4.4.2.2
Techniques
Lessons Learned
4.6.2.3 Meetings User Groups
Review Meetings
68
4.6.3 Close Project or Phase Outputs
Final Product, Transition of the project’s (or phase’s) product or result to:
4.6.3.1 Service, or Result The ongoing organization, or
Transition The next phase of the project
Lessons Learned
Organizational Corporate Knowledge Base
4.6.3.2 Process Assets Project Files
Updates Project or phase closure documents
Historical information
69
Practice Question:
A. Project archives
B. Every stakeholder on the team
C. Document Imaging system
D. Project sponsor
70
Good Luck!!
71