00 VRMP Overall
00 VRMP Overall
00 VRMP Overall
October 2020
1
BRIEF INTRODUCTION
PROJECT DETAILS:
Design Crudes:
October 2020 2
BRIEF INTRODUCTION
Existing Facility:
The Visakh Refinery of HPCL (8.33 MMTPA refinery) is one of the most
integrated refineries with:
Three crude distillation units,
MS Block (NHT/ISOM/CCR),
Diesel Hydro Desulphurization unit,
Two Fluid Catalytic Cracking units, ,
Visbreaker Unit,
Bitumen Blowing unit and
Propylene Recovery unit
The Refinery has installed Diesel Hydrotreater unit to comply with the Auto
Fuel policy to meeting the BS-IV product specifications for MS and HSD.
October 2020 3
BRIEF INTRODUCTION
New Facility:
S.No. Facility Capacity UOM
1 CDU/VDU-IV 9 MMTPA
2 SR LPG Treater (ATU & CFC) 196.8 KTPA
3 Naphtha Isomerisation Unit 0.352 MMTPA
4 Full Conversion Hydrocracker Unit 3.053 MMTPA
5 Residue upgradation facility 3.55 MMTPA
6 Hydrogen Generation Unit I & II 2 x 113 KTPA
7 Fuel Gas PSA 36 KTPA
8 Sulfur Recovery Unit I & II 2 x 360 TPD
9 SWS-I (Hydroprocessing) 270 TPH
10 SWS-II (Non- Hydroprocessing) 270 TPH
11 ARU I & II 2 x 540 TPH
October 2020 4
BRIEF INTRODUCTION
Existing Units requiring Revamp:
S.No. Facility Capacity UOM Remarks
No capacity
enhancement. But
4 Prime G 0.893 MMTPA
quality upgradation
considered.
October 2020 5
BRIEF INTRODUCTION
Utility Facilities:
Raw Water System(Includes the service water and the drinking water
system)
Re-circulating Sea Cooling Water System
Bearing Cooling Water System
Demineralised Water System
Captive Power Plant(BFW, Steam and Power generation system)
Condensate Polishing System
Compressed Air System (PA & IA) and Nitrogen System
Flare system
Integrated effluent treatment system
Internal Fuel oil and Fuel gas system
FLO system (existing)
Caustic storage & preparation system
Natural gas facility
October 2020 6
BRIEF INTRODUCTION
October 2020 7
GENERAL LESSONS LEARNT
October 2020 8
GENERAL LESSONS LEARNT
S Issue Faced Background Resolution Lesson Learnt
N
o
October 2020 9
GENERAL LESSONS LEARNT
S Issue Faced Background Resolution Lesson Learnt
N
o
2 Licensor did not In revamp job, for EIL emphasized that these For revamp Jobs,
used as built Updation of P&IDs for P&ID Updation has to be use of “As built”
P&ID’s for revamp revamp Licensor used done using “As built” P&IDs for base
Job original Licensor BDEP P&IDs as base for revamp of revamp P&IDs
P&IDs and did not used job. with suitable
the “As built” P&IDs HPCL also agreed the scope should be
Stating the reason that same. advised to client
Licensor is not responsible Later Licensor agreed to to be included
for changes by DEC in use “As built” P&IDs as in NIT/contract
Licensor P&IDs and base P&IDs for revamp scope in case EIL
backed the same with with suitable note to is not involved.
contract with HPCL. identify the scope and
responsibility of Licensor
based on changes done by
DEC in original Licensor
P&IDs
October 2020 10
GENERAL LESSONS LEARNT
S Issue Faced Background Resolution Lesson Learnt
N
o
3 Changes post BEDP In FC-HCU and NIU unit PMC identified PSV’s PMC identified
Submission : licensor has considered segregation and PSV’s segregation
Segregation of HP/LP only LP flare header. included in FEED as and included in
flare header Accordingly the PSV per Flare Design at
sizing has been later stage which FEED as per Flare
provided. However as caused PSV Design at later
per design basis backpressure change stage which
requirement, two flare and deviation request caused PSV
headers HP and LP to be to licensor backpressure
considered. change and
informed to
licensor through
deviation request.
October 2020 11