MANAGEMENT
BITS Pilani Dr. ARUN MAITY
Pilani Campus
BITS Pilani
Pilani Campus
• TS = Lj – (Ei + d ij)
• FS = Ej – (Ei + d ij)
• FS = TS – HEAD SLACK
– Independent slack = ( Ej – Li ) – d ij
5. FIND Z = (D – Te) / St
WHERE D IS THE DUE TIME OF COMPLETION
Using Normal Distribution Table, Find The
Probability Of Completing The Project By Due
Date Using Z Values.
i j to tm tp
1 2 3 6 15
1 6 2 5 14
2 3 6 12 30
2 4 2 5 8
3 5 5 11 17
4 5 3 6 15
6 7 3 9 27
5 8 1 4 7
7 8 4 19 28
• 0.84