Pert CPM
Pert CPM
Pert CPM
Jo h n C r
a T e rni da
Rec
Jay Tablo
PERT AND CPM
PLANNING
WHAT IS PERT AND CPM
CPM was used for the first time in 1966 for the major
skyscraper development of constructing the former World
Trade Center Twin Towers in New York City. Although the
original CPM program and approach is no longer used, the
term is generally applied to any approach used to analyze a
project network logic diagram.
HISTORY OF PERT
Defining the organization’s goals Establishing an overall strategy for Developing Plans for
achieving these goals Organizational Work Activities
(desired result that you commit
to achieve) (Plan of action to achieve goal) (desired result that you commit to
achieve)
(desired result that you commit to
PLANNING
LF – EF = Total Float or
LS + D – (ES + D) or
07 LS – ES = Total Float
Free Float
09
I.F. = E S – (LF - D)
Defined as the process of
translating the arrow diagram
into time table of calendar days.
1
1
The PERT/CPM diagram should be updated
periodically to account for:
1 2 3
4 5
Change Unexpected
Orders Events or
1 Conditions
2
Some of the importance of scheduling in
construction projects are the following:
3
Longest route in the network of
FUNDAMENTAL
ELEMENTS O F 1
PERT/CPM 5
2. E V E N T S
Point in time signifying beginning
or end of one or more activities.
Denotes the completion of all
the
preceding or predecessor
1 activities and the beginning of one
6 or more succeeding activities.
3. TIME
THE the duration of the
indicates
F U N DA M E N TA L project.
ELEMENTS ARE:
1
7
Dummy Activity
Shows dependent relationship
between two activities.
May be used in the network to
distinguish two or more parallel
activities.
Primary function of a dummy is to
OT H E R C O N C E P T S clarify relationships.
Duration of an Activity
Time it takes an activity to finish.
1 Normal time duration of task.
8
Path
Sequence of activities.
Predecessor
is the activity before the start of the other.
OT H E R C O N C E P T S
Successor
is the activity after doing the first activity.
19
1 – 2 – 4 - 6 IS A PATH
20
EXAMPLE P RO B L E M OF S C H E D U L I N G USING CPMs
A c e r t ai n pr oj e c t c o n s i st s o f a c t i vi t i es fr o m A t o H a s
s h o w n . T h e pr e d e c e s s o r s a n d t h e dur at i o n i n w e e k s i s st at
e d i n t h e t a b l e b el o w. Dr a w t h e n e t wo r k di a g r a m a n d f i nd
a.) t h e cr i t i c a l p a t h; b.) t h e fr e e f l o a t , t ot al f l o a t a n d i
ndependent f l oat .
2
1
D I AG R A M :
Where:
ES – Early Start
LS – Late Start
EF – Early Finish
LF – Late Finish
22
1. T H E O P T I M I ST I C TIME E ST I M AT E
is the estimated minimum time an
activity will take place.
the expected activity duration when
all breaks are right.
2. T H E M O S T L I K E LY TIME
is the estimated normal length of time
an activity takes.
the time that will most frequently be
required for an activity, if it were done
again and again under identical
23 conditions.
3. T H E P E S S I M I ST I C TIME E ST I M AT E
is the estimated maximum time an
activity would take, barring a
catastrophe.
is the expected activity duration when
there is an abnormal run of bad
breaks.
24
25
EXAMPLE P RO B L E M OF S C H E D U L I N G USING P E R T METHOD
A ll the A c tivi
tiesP redec esso
rs
O ptimistic , P essimistic , a nd Most L ikely A c ti
vityD ura tions
By u s in g “ T h e P e r t F o r m u la = (T o + 4 T m + T p )/6 ” ,
26 youc a lc ula ted the e x p e c te dd u ra tio n f
or each a c tivity.
All the inputs are listed in the following table.
2
7
After building a network diagram and estimating the activity
durations, you will determine the critical path by making
forward and backward pass calculations.
28
29
Backward Pass Calculations of Program Evaluation and
Review Technique determine the latest dates by which
each activity can be performed without increasing the
project’s minimum duration.
30
3
1
After completing the backward pass calculation, you can easily
determine the critical path.
32
When we analyze the network diagram we will see
that there are some paths and every path have
duration.
33
34
References
Project and Constructi on
Management by Max B. Fajardo Thank
htt ps://www.projectcubicle.com/p
ert-method-defi niti on-examples/ you :
CONTROLLIN
G AND
MONITORING
CONTROLLING AND
MONITORING
Flexibility and updated re-computations
brought about by changing conditions is
the key to a successful network
programming. To keep the schedule more
up to date and meaningful, it can be done
by hand but is more easier and less in cost
if it is done with the assistance of
computer to have the following output.
CONTROLLING AND
MONITORING
1. The contractor is supplied 3. The contractor is supplied
with time status reports with cost status reports
showing the overall status showing how much money
of the project in general and is being disbursed for what
in particular. type of expenses.
1 2 3 4
1
A network diagram defining the activities in the project
2
The duration of activities
4
Resource estimates
5
Trade indicators (responsibility) for activity grouping.
From the SCHEDULE PHASE, there are four output that can be obtained:
1. The schedule of the activities in the network showing the following:
2. Revised schedules.
2/26/2023 52
Three major reasons for construction failure: