CACEP Unit 2 Assignment Problem

This document discusses optimization techniques used in construction engineering and planning, specifically addressing assignment problems. It provides an example of solving an assignment problem using the Hungarian method to minimize total time or cost by assigning each worker to a specific job. The steps include reducing rows and columns to identify the optimal assignment with all zeros, which indicates the minimum value. It also discusses how to solve unbalanced and constrained assignment problems when the number of workers does not equal the number of jobs.

Uploaded by

Rajha Rajeswaran
Copyright
© © All Rights Reserved
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
19 views

CACEP Unit 2 Assignment Problem

This document discusses optimization techniques used in construction engineering and planning, specifically addressing assignment problems. It provides an example of solving an assignment problem using the Hungarian method to minimize total time or cost by assigning each worker to a specific job. The steps include reducing rows and columns to identify the optimal assignment with all zeros, which indicates the minimum value. It also discusses how to solve unbalanced and constrained assignment problems when the number of workers does not equal the number of jobs.

Uploaded by

Rajha Rajeswaran
Copyright
© © All Rights Reserved
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 36

BE Degree Honours with Specialization

BE Civil Engineering
Specialization in
CONSTRUCTION MANAGEMENT

21 CEB 07 T Computer Applications in Construction


Engineering and Planning

Unit 2 OPTIMIZATION TECHNIQUES


21 CEB 07 T Computer Applications in Construction
Engineering and Planning
SYLLABUS Total Periods: 45 Credits 3
UNIT I INTRODUCTION 9
Overview of IT Applications in Construction – Construction process –
Computerization in Construction – Computer aided Cost Estimation –
Developing application with database software.
UNIT II OPTIMIZATION TECHNIQUES 9
Linear, Dynamic and Integer Programming - Branch and Bound Techniques –
Application to Production Scheduling, Equipment Replacement, Material
Transportation and Work Assignment Problems – Software applications
UNIT III INVENTORY MODELS 9
Deterministic and Probabilistic Inventory Models - Software applications.
UNIT IV SCHEDULING APPLICATION 9
PERT and CPM - Advanced planning and scheduling concepts – Computer
applications – Case study.
UNIT V OTHER PROBLEMS 9
SYLLABUS Total Periods: 45 Credits 3

UNIT II OPTIMIZATION TECHNIQUES 9


Linear Programming
Dynamic Programming
Integer Programming
Branch and Bound Techniques
Application to Production Scheduling
Application to Equipment Replacement
Application to Material Transportation
Application to Work Assignment Problems
Software Applications
SYLLABUS Total Periods: 45 Credits 3

UNIT II OPTIMIZATION TECHNIQUES 9

Application to Work Assignment Problems


Assignment Problem
• A specially structured
Linear Programming Problem
Assignment Problem
Assignment Problem
Assignment Problem
• Assignment Problem techniques used to

• MINIMIZE the Total Cost / Total Time


• or to
• MAXIMIZE Total Revenue / Total Production
Assignment Problem

Example 1
Assignment Problem solved by HAM
HUNGARIAN Assignment Method

JOB
Worker A B C D
1 45 40 51 67
2 57 42 63 55
3 49 52 48 64
4 41 45 60 55

CELL VALUES areTIME taken by each worker to COMPLETE that Job


Assignment Problem
• In this problem
• No. of WORKERS = No. of JOBS

• i.e.

• No. of ROWS = No. of COLUMNS =N=4


Assignment Problem

Step 1 ROW REDUCTION

JOB

Worker A B C D A B C D
45 40 51 67 5 0 11 27
1
57 42 63 55 15 0 21 13
2
49 52 48 64 1 4 0 16
3
41 45 60 55 0 4 19 14
4
Assignment Problem

Step 2 COLUM REDUCTION

JOB

Worker A B C D A B C D
5 0 11 27
1 5 0 11 14
15 0 21 13
2 15 0 21 0
1 4 0 16
3 1 4 0 3
0 4 19 14
4 0 4 19 1
Assignment Problem

Step 3 Strike Out all Zeroes using MINIMUM Number of STRAIGHT LINES

JOB

Worker A B C D

1 5 0 11 14

2 15 0 21 0

3 1 4 0 3

4 0 4 19 1
Assignment Problem
Step 3 Strike Out all Zeroes using MINIMUM Number of STRAIGHT LINES

JOB
Worker A B C D A B C D
1 5 0 11 14 5 0 11 14
2 15 0 21 0 15 0 21 0
3 1 4 0 3 1 4 0 3
4 0 4 19 1 0 4 19 1

• No. of Straight Lines required = 4 = N


Thus it is indicates OPTIMUM Solution is achieved
Assignment Problem
SOLUTION = Choose that Assignment containing UNIT ZERO
Step 3 Strike Out all Zeroes using MINIMUM Number of STRAIGHT LINES

JOB
Worker A B C D A B C D
1 5 0 11 14 5 0 11 14
2 15 0 21 0 15 0 21 0
3 1 4 0 3 1 4 0 3
4 0 4 19 1 0 4 19 1
Solution
• Worker 1 Assign to Job B 1B +3C+4A+ 2D
• Worker 3 Assign to Job C = 40 + 48 + 41 + 55
• Worker 4 Assign to Job A = 184
• Worker 2 Assign to Job D
SOLUTION
Assignment Problem solved by HAM
HUNGARIAN Assignment Method

JOB
Worker A B C D

1
45 40 51 67

2
57 42 63 55
3
49 52 48 64

4
41 45 60 55

CELL VALUES are TIME taken by each worker to COMPLETE that Job
Assignment Problem
Assignment Problem
Assignment Problem
• Example 2
Assignment Problem
• Example 2
Assignment Problem
Assignment Problem
Assignment Problem
Assignment Problem
UNBALANCED & CONSTRAINED Assignment Problem

No. of Persons 4 ≠5 No. of JOBS


Assignment Problem
• Table AFTER Balancing
Assignment Problem
Assignment Problem
Assignment Problem
Assignment Problem
• MAXIMIZATION Model in Assignment
Assignment Problem
Assignment Problem
Assignment Problem