Job Costing Vs Process Costing-1
Job Costing Vs Process Costing-1
Job Costing Vs Process Costing-1
The value of any product which is Work in progress is very common and
incomplete can be easily established to determine its value requires
anytime calculations
Normal loss and Scrap
Normal loss is an expected waste arising from manufacturing process.
Waste is discarded item that has no value; it may include materials lost in production
process.
Since normal loss in inevitable in manufacturing process its cost is absorbed by the
good units:
Cost per Unit = Total process cost (including normal loss)
Good units
Scrap is discarded material, but has some recover value without further treatment or
can be re-used into production
Accounting treatment of scrap value depends with:
If the material can be re-used elsewhere;
Dr Store (for re-issue) xxx
Cr Process A/c xxx
If it is sold;
Dr Cash xxx
Cr Process A/c xxx
Abnormal Loss and Abnormal Gain
Abnormal loss is a waste arising from production process, but beyond the
expectation (normal loss)
The abnormal loss gets a share of the production cost and its accounting
treatment is:
Dr Abnormal loss a/c xxx
Cr Process a/c xxx
If the loss experienced is below the expectation (normal loss), then it is
abnormal gain; its treatment is:
Dr Process a/c xxx
Cr Abnormal gain xxx
Thereafter the abnormal gain account will be closed to the income statement
NB: Calculation of unit cost considers only expected units, but the value of goods
transferred to another process includes abnormal gain (units); thus the process account
Example 3 (a)
ManDisk ltd is a small company manufacturing flash discs through two
processes. In the first process, the inputs are mixed to produce stiff liquid for
use in the second process where flash discs are shaped. The ratio of the input
(material) to output (flash disc) in process two is 1 to 10. The company has
extracted the following costs for the month of April, 2023.
Process One:
Materials A 2,800kgs @ Tsh.12,000; Material B 1,200kgs @ Tsh. 8000
Labour Tsh. 8,400,000; Overhead Tsh. 5,600,000
Process Two: Labour Tsh. 9,600,000; Overhead Tsh. 7,500,000
Required:
i) Prepare process Accounts and find the unit cost of a flash disc if 40,000 flash
disc were produced in process two
ii) If the company expected the normal loss (with no scrap value) in process two
to be 5% of the inputs received from process one calculate unit cost
Example 3(a) Continues…
iii) If the company expected the normal loss (with scrap value of 1000/-
per unit of output) in process two to be 5% of the inputs received from
process one calculate unit cost
iv) If the company expected the normal loss in process two to be 5% of
the inputs received from process one, but the actual production was only
37,000 flash discs calculate unit cost while assuming scraped units have
no value
v) If the company expected the normal loss in process two to be 5% of
the inputs received from process one, but the actual production was only
37,000 flash discs calculate unit cost while assuming scraped units can be
sold for Tsh,1,000 per flash disc.
vi) If the company expected the normal loss in process two to be 5% of
the inputs received from process one, but the actual production was
Equivalent Units
As identified earlier, work in progress is very common in
process costing; hence by the time when someone wants
to establish unit cost some of the products might be
partially complete.
In order to consider these partially units in calculation of
unit cost, there is a need of using equivalent unit (EU)
concept. This concepts is used to convert the amount of
resources used so far in whole complete units
Thus, cost per unit will be obtained by dividing the total
process cost by equivalent units (whole units plus EU for
Example 4 (b)
FlashD ltd is a small company manufacturing flash discs through two processes. In the first
process, the inputs are mixed to produce stiff liquid for use in the second process where flash
discs are shaped. The ratio of the input (material) to output (flash disc) in process two is 1 to
10. The company has extracted the following costs for the month of May, 2021.
Process One:
Materials A 2,800kgs @ Tsh.12,000; Material B 1,200kgs @ Tsh. 8000
Labour Tsh. 8,400,000; Overhead Tsh. 5,600,000
Process Two:
Labour Tsh. 9,600,000; Overhead Tsh. 7,500,000
Required:
i) The company expected the normal loss (with no scrap value) in process two to be 5% of the
inputs received from process one and at the end of the month when the company was about to
establish cost per flash disc 4,000 flash discs were not yet complete. They were 100% in
terms of materials and 70% complete in term of labour and overhead. Calculate cost per unit
of flash disc.
Considerations of Opening Work in Progress
Calculations of unit cost when there is opening work in progress requires
assumption on how the cost incurred in the previous period relating to
WIP should be treated.
The two methods/assumption which are used to deal with opening WIP
are FIFO and Averaging method
Under FIFO, the assumption is that those opening WIP are the first to be
accomplished before any other units; hence cost per unit are calculated
separately by adding the EU of the remaining part to the carried forward
cost to come up with unit cost for opening WIP
On the other hand, Averaging method do not distinguish finished good
either from previous period or from current period. Instead, it add the cost
incurred in the previous period with the cost incurred in the current period
then divides by finished good and EU of ending WIP
Example 4
During May 2022, process A of ABC Ltd manufactured 7000 units and
1000 units were still in process. The closing WIP consumed 100% of
materials and 40% of conversion costs.
The value of materials issued to process A in that month was Tsh.
8,000,000 while labour and overhead incurred were Tsh. 666,000 and Tsh.
592,000, respectively.
At the beginning of the month, there were 800 units in process which were
100% complete in terms of materials and half way in terms of conversion
costs. The value materials consumed was Tsh. 480,000 while for labour
and overhead were Tsh. 40,000 and Tsh.36,000, respectively.
Required:
i) Calculate the value of finished good unit using FIFO approach
ii) Calculate the value of finished good unit using Averaging approach
Cost of Production Report
It is the report showing the amount of cost incurred during
the period and how that cost is accounted for to the units
produced and WIP
There are five steps, which are:
Identifying units started to be produced
Determining the equivalent units
Determining production cost to be accounted for
Computing unit cost
Accounting for production costs