L8 - Project Implementation and Controlling
L8 - Project Implementation and Controlling
Chapter 4
Project implementation and controlling
29 January 2024
1
Project Monitoring
• Monitoring is the collecting, recording and reporting of project information
that is of importance to the project manager and other relevant stakeholders.
3
Controlling
• Controlling is the management function of comparing the actual
achievements with the planned ones at every stage and taking necessary
action if needed, to ensure the attainment of planned goals
• “Plan-Do-Review”
4
Monitoring & control cycle
Control Reporting
(taking
action) 5
• Control uses the
monitored data and
information to bring
actual performance into
agreement with the
plan.
6
Key Issue …
• The key issue in designing an effective monitoring and control
system is
• to create an information system that gives the project manager and others
the information they need to make informed and timely decisions that
will keep project performance as close as possible to the plan.
7
Monitoring: Example
(Financial Procedural Rules 2064 of GoN)
Rule 25: All the PE implementing Budget and Program shall submit quarterly the
progress report to the one level higher authority, District Treasure Controller
Office (DTCO) and in the case of district level program to the District
Development Committee (DDC) in the format given as Appendix – 2.
8
Monitoring
• Issues to be addressed
• What to monitor and evaluate?
• What monitoring tools to use?
• When to monitor and evaluate?
• Who should monitor and evaluate?
• Where should the monitoring and evaluation be carried out?
9
What to monitor and
evaluate ?
• Project planning
• Project organization
• Program management functions
• Project accomplishment
• Project information
10
What monitoring tools to use?
• Gantt chart
• CPM
• EVA
• ?
• ?
11
When to monitor and evaluate?
• During entire life cycle
• Pre-project evaluation – for selection of a project to determine if it fits the
objectives and overall strategy of the organization?
• On-going project evaluation – for measuring the status of a project during its life
cycle
• Project completion evaluation - for an immediate assessment of success upon
project completion
• Post project evaluation – for assessment of project success after project’s
activities are completed
12
Who should monitor and evaluate?
• The work package level
• The functional manager level
• The project team level
• The general manager level
• The project owners level
13
Purpose of monitoring
• It is important to ensure that projects are implemented as
efficiently and effectively as possible to accomplish the project
objectives – i.e. meeting the project time, cost and quality.
14
Types of monitoring & evaluation
• Observation
• Review the progress reports
• Third party auditing
15
Project control system
• Project controlling should be established as an independent function in project
management.
16
Tasks of project controlling
• creation of infrastructure for supply of the right information and its update
• establishment of a process to communicate disparities of project parameters
• development of project information technology based on project key
performance index system (KPI)
• divergence analyses and generation of proposals for potential project
regulations
• establishment of methods to accomplish project objectives and governance
• creation of transparency among the project parameters
17
Project controlling
• Project control is that element of a project that keeps it on-track, on-time and within
budget.
• Project control begins early in the project with planning and ends late in the project with
post-implementation review, having a thorough involvement of each step in the process.
• Each project should be assessed for the appropriate level of control needed: too much
control is too time consuming, too little control is very risky.
• Control systems are needed for cost, risk, quality, communication, time, change,
procurement, and human resources
18
Project control cycle- Basic steps
• Establishing standard (what is to be done)
• Starting point of control
Establishing
standard
Finding deviations
20
Elements of project control
• Time control
• Cost control
• Quality control
21
PROJECT SCHEDULE CONTROL
22
Time/schedule control
• Monitors and controls changes to the project schedule
• Output
• Update schedule
• Corrective action
• Lessons learned
23
Time/schedule control
• Involves :
• Determining current status
• Influencing factors that could cause schedule changes
• Identifying if the schedule has changes
• Managing changes as they occur
24
Quality control
• Quality control
• Process of monitoring specific project result to determine whether this
comply with relevant quality standards and identifying ways to eliminate
cause of poor performance
• Raw materials and intermediate stage testing
• Self inspection by operator
• Feedback process information to operators, setters and production
supervisors
25
Quality control
• Quality assurance
• Procedures and documentation for assuring the quality of products or
service
• Planned and systematic activities implemented in a quality systems so
that quality requirements for a product of service will be fulfilled
27
Cost of quality
• Cost to control quality (preventive and appraisal)
• Preventive costs: Planning cost
• Appraisal costs : Quality of material
28
Project Cost control
• Controlling changes to the project budget
• Concerned with the cost of the resources needed to complete project activities
• Concerned with the
• factors causing changes to the cost baseline to ensure that changes are
beneficial,
• determining that the cost baseline has changed,
• managing the actual changes when and as they occur
29
Cost control
• Includes:
• Monitoring cost performance to detect variances from plan
• Ensuring that all appropriate changes are recorded accurately in the cost
baseline
• Preventing incorrect, inappropriate, unauthorized changes from being
included in the cost baseline
• Informing appropriate stakeholders of authorized changes
30
Cost control
• Outputs from cost control
• Revised cost estimate
• Budget updates
• Corrective actions
• Estimate at completion
• Lessons learned
31
Cost control
• Elements of cost control
• Observation
• Comparison
• Deviations
• Corrective actions
32
Cost control – Methods
• Short-term planning and control
• Work done is compared with resources utilized and compare it with planned
values of time and resources
• If actual time taken is higher than planned, project is behind schedule
• If resources are utilized more than planned, project performance is not
efficient
37
38
Earned value analysis
• The S-curve examine the progress of the project and forecast expenditure in terms of
man-hours or money
• Assessment and precise recording of the value if the work done is crucial to project cost
control
• “Persistent 99% complete syndrome” 99% of tasks in 99% of projects are 99% complete for
99% of time
• “Remaining duration” as good measure of progress for a work package
39
• Has been adopted by oil, manufacturing, gas and process industries where man-hours
and material deliveries to the site are used to monitor projects from inception to
Progress of value of work done
40
1. Suppose an activity had 5 days duration and was expected to cost Rs. 10,000 set into
the project and prior to finishing an activity, the following data were obtained about the
progress done to that activity. Perform all parameters of EVA and comment on it.
I. Have so far worked for 3.5 days on activity
II. 60% of activity has been accomplished/completed
III. Rs. 8000 has already spent on activity
4. In a road project, budgeted cost for making 10 km road was 2 crore. It was planned
to be done in 10 weeks. But in 4 weeks only 50% of work had been completed and
the expense incurred was 1.25 crore. Find all the parameters of EVA and comment
on its performance
42
Quality control VS QUALITY ASSURANCE
• Quality control is product oriented whereas quality assurance is process oriented
practice
• QC makes sure the end product meets the quality requirement whereas QA makes
sure that the process of manufacturing the product adheres to set standard
• QC is a reactive process whereas QA is a productive process
43
Project Management Information System
(PMIS)
• PMIS consists of the tools and techniques used to gather, integrate, and
disseminate the outputs of the other project management processes.
• It is used to support all aspects of the project from initiating through closing
and includes both manual and automated systems
44
PMIS
• To reduce project duration
• To increase resource productivity
• To make better use of resources
• To decrease cost
• To reduce uncertainty in decision making
45
PMIS
• Requirements of PMIS
• Project forms are periodically filled based on the project progress
• Forms entered in PMIS generates progress report
• Corrective actions are taken based on report
46
Elements of PMIS
47
Feedback
Essential Features of PMIS
Typical PMIS has a series of tools.
• Schedule and Planning: Computes early and late schedule, slack times and the critical
path
• Resource Management: Includes resource loading, levelling, allocation, etc.
• Budget: Costs associated with individual tasks for more accurate budget estimation and
generation.
• Control and Performance: Analyze and control cost and performance, update existing
plans as actual against planned data changes and provide what-if scenarios for the
project manager.
• Reporting and Communication: Creation of graphs, reports and charts of collected and
analyzed data that can be shared with stakeholders and team members.
• Integration and Ease of Use: Some PMIS will access data from different projects for
multi-project analysis, integrating with other systems, such as payroll, inventory, etc. The 48
easier a PMIS is to use, the less time and money required to train.
S. Monitoring Evaluation
No.
1 Continuous process for the project Ex – ante -k"j{ d"Nof+sg_, Mid-term -
period and hence is considered as dWofalws_, Terminal -clGtd_ and Ex-post
internal function -;DkGg_ evaluations are in practice
2 Conducted only during Conducted during implementation as well as
implementation of the project after completion of a project also
3 An institutional process of improving It is the mechanism of lessons learning from the
implementation deficiencies or implemented projects and bringing improvement
weaknesses in the future projects/programs or decision
making
4 Directly related with the project Related to pre-determined goals & achievement
process, investment and outcomes of the project and study of its effect and impact
on the beneficiaries
5 A part of monitoring management It is a function oriented managerial tool of
system lesson learning from the past projects
6 Carried out from the implementing In general, evaluation is carried out through the
agency itself external and independent agency .
49
THANK YOU 50