PMBOK Chapter 5 - Time
PMBOK Chapter 5 - Time
PMBOK Chapter 5 - Time
adopted from PMIs PMBOK 2000 and Textbook : Information Technology Project Management (author : Dr. Kathy Schwalbe)
planning
control
Scope statement
must be considered explicitly during Activity Definition. Project justification and objectives are especially important.
Historical information
activities required on similar projects should be considered in defining project activities.
Constraints
Factors that limit the teams options
Assumptions
factors that, for planning purposes, will be considered to be true, real, or certain.
Expert judgment
guided by historical information should be used whenever possible. subject-matter experts can help.
6
Activity definition involves developing a more detailed WBS and supporting explanations to understand all the work to be done
Chapter 5 7
Templates
previous project templates help project team to jumpstart the process.
Supporting details
includes assumptions, constraints, and anything else that is relevant.
WBS update
Missing deliverables, clarifications, or corrections. This output creates a feedback loop by which you get to tie up loose ends. Update the WBS and related documents, such as cost estimates. These updates are often called refinements.
Activity Sequencing
5th planning phase process Involves reviewing activities and determining dependencies
Mandatory dependencies: inherent in the nature of the work; hard logic Discretionary dependencies: defined by the project team; soft logic External dependencies: involve relationships between project and non-project activities
Product description
product characteristics. These often affect Activity Sequencing.
Mandatory dependencies
inherent in the nature of the work being done. They often involve physical limitations. Constraints caused by mandatory dependencies are call hard-logic.
Discretionary dependencies
defined by the project management team. Constraints caused by discretionary dependencies are called soft logic.
External dependencies
involve a relationship between project and non-project activities.
Milestones
part of activity sequencing to ensure that requirement for the milestone events are being met.
11
Network templates
Can expedite the preparation of project network diagrams
13
PDM fundamentals
14
Chapter 5 15
Project 98 file
16
AOA fundamentals
17
Chapter 5 18
and draw arrows between node 1 and those finish nodes. Put the activity letter or name and duration estimate on the associated arrow 2. Continuing drawing the network diagram, working from left to right. Look for bursts and merges. Bursts occur when a single node is followed by two or more activities. A merge occurs when two or more nodes precede a single node 3. Continue drawing the project network diagram until all activities are included on the diagram that have dependencies 4. As a rule of thumb, all arrowheads should face toward the right, and no arrows should cross on an AOA network diagram
Chapter 5 19
20
Constraints
Factors that limit the performance of the project. When constraint are involved, special considerations are often required for communications.
Assumptions
Factors that for planning purposes are considered to be true, real, or certain.
Resource requirements
controlling factors on activities duration. The duration of most activities will be significantly influenced by the resources assigned to them.
Resource capabilities
staff and material resources assigned to them will affect the duration of most activities.
Historical information
may be available for review from project records, commercial durationestimating databases, and team knowledge. 22
Analogous estimating
uses the duration of a previous, similar activity as the basis for estimating the duration of a future activity. It is also called top-down estimating.
Simulation
calculates multiple durations with different sets of assumptions. The most common is the Monte Carlo Analysis.
23
Basis of estimates
includes the assumptions made in developing your estimates, which must be documented.
24
Gantt Charts
Gantt charts provide a standard format for displaying project schedule information by listing project activities and their corresponding start and finish dates in a calendar format Symbols include:
A black diamond: milestones or significant events on a project with zero duration Thick black bars: summary tasks Lighter horizontal bars: tasks Arrows: dependencies between tasks
Chapter 5 25
Schedule development
7th of 21 planning phase process It is the process of determining the start and finish dates for all project activities The activity sequences, activity duration, and resource requirement are analyzed together to create the project schedule.
26
Schedule Development
7th of 21 planning phase process Schedule development uses results of the other time management processes to determine the start and end date of the project and its activities Ultimate goal is to create a realistic project schedule that provides a basis for monitoring project progress for the time dimension of the project Important tools and techniques include Gantt charts, PERT analysis, critical path analysis, and critical chain scheduling
Chapter 5 27
30
Support details
include at least documentation of all identified assumptions and constrains. Some examples are resource histograms, alternative schedules, and cash-flow schedules.
Project 98 file
Chapter 5 34
Project 98 file
35
Project 98 file
white diamond: slipped milestone two bars: planned and actual times
Chapter 5 36
Chapter 5 38
4 5
E=1
A=2
B=5
3
D=7 F=2
finish
1. How many paths are on this network diagram? 2. How long is each path?
40
Chapter 5 42
43
Chapter 5 44
Chapter 5 45
Multitasking Example
46
PERT uses probabilistic time estimates based on different estimates of activity durations
optimistic estimates (weighting 1) most likely estimates (weighting 4) pessimistic estimates (weighting 1)
Chapter 5 47
Allow for contingencies Dont plan for everyone to work at 100% capacity all the time Hold progress meetings with stakeholders and be clear Chapter 5 and honest in communicating schedule issues
49
Performance reports
provide information on schedule execution showing if planned dates have been met. These reports also alert project team on issues that may cause problem in future.
Change requests
any update of schedule, that may require extending or accelerating the schedule.
Additional planning:
prospective changes may require new or revised activity duration estimates, modified activity sequences, or analysis of alternative schedules.
Corrective action:
encompasses anything that brings your expected future schedule back in line with the project plan. These actions are outputs from the other knowledge areas.
Lessons learned:
document causes of variances, the reasoning behind corrective actions, and other lessons learned from schedule change.
53
Summary
importance of project schedules: IT project always over-run Time management process
definition (planning) sequence (planning) schedule estimation (planning) schedule development (planning) schedule control (control)
Chapter 5 55
Summary (2)
definition: charter and scope statement sequence: mandatory dependencies, discretionary dependencies, external dependencies schedule: ADM, PDM estimation: actual time + elapsed time. An art require experience. schedule development: Gantt chart, CPM and PERT schedule control and change control: perform checks, allow contingencies, communicate with stakeholders regularly 56