Assessment of Risk Factors Causing Delays in Building Construction Project in Cambodia

Published: 05 October 2021 Publication History

Abstract

This research aims to identify, investigate, rank, and mitigate delay factors perceived to affect private financed residential building construction project in Phnom Penh city, Cambodia in order to recommend actions of how to deal with such delays. To identify and rank delay factors, a questionnaire survey that matches the research preference was conducted. The first round of data collection showed the delay factors ranking through the Relative Importance Index (RII) method. The top ten (10) most critical delay factors were mitigated in the second round of data collection with recommended actions proposed by experts using the Delphi Technique and the Failure Mode and Effect Analysis (FMEA) method. The study results revealed the critical delay factors and their possible solutions. The list of delays affecting private financed building construction project in Cambodia was mainly dominated by the factors related to labor and material.

References

[1]
Council for the Development of Cambodia. (2015). Cambodia Industrial Development Policy CIDP 2015-2025.
[2]
Kikwasi, G. J. (2012). Causes and effects of delays and disruptions in construction projects in Tanzania, Australasian Journal of Construction Economics and Building, 1(2); p.52-59.
[3]
Kismayo H. Growth forecast upped by NBC | Phnom Penh Post [Internet]. Phnompenhpost.com. 2019 [cited 20 April 2019]. Available from: https://www.phnompenhpost.com/business/growth-forecast-upped-nbc.
[4]
Council for the Development of Cambodia. (2015). Cambodia Industrial Development Policy CIDP 2015-2025. [cited 4 April 2016]. Available from: http://eurochamcambodia.org/uploads/6a5ach.e.mr.sokchendasopheapresentation. pdf.
[5]
Szymański P. Risk management in construction projects. Procedia engineering. 2017 Jan 1;208:p. 174-82.
[6]
Waring A, Glendon AI, Glendon I. Managing risk. Cengage Learning EMEA; 1998.
[7]
Sambasivan M, Soon Y. Causes and effects of delays in Malaysian construction industry. International Journal of Project Management 25 (2007) p.517–526.
[8]
Mansfield N., Ugwu O., Doran T., Delay causes and cost overruns in Nigerian construction projects, International Journal of Project Management 12 (4) (1994); p.254–260.
[9]
Assaf S., Al-Khalil M., A-Hazmi M., Delay causes in large building construction projects, Journal of Management in Engineering, ASCE 11 (2) (1995); p. 45–50.
[10]
Chan DW, Kumaraswamy MM. A comparative study of causes of time overruns in Hong Kong construction projects. International Journal of project management. 1997 Feb 1;15(1); p.55-63.
[11]
Kaming PF, Olomolaiye PO, Holt GD, Harris FC. Factors influencing construction time and cost overruns on high-rise projects in Indonesia. Construction Management & Economics. 1997 Jan 1;15(1); p. 83-94.
[12]
Mezher TM, Tawil W. Causes of delays in the construction industry in Lebanon. Engineering, construction and architectural management. 1998 Mar 1;5(3); p.252-60.
[13]
Assaf SA, Al-Hejji S. Causes of delay in large construction projects. International journal of project management. 2006 May 1;24(4); p.349-57.
[14]
Abd El-Razek ME, Bassioni HA, Mobarak AM. Causes of delay in building construction projects in Egypt. Journal of construction engineering and management. 2008 Nov;134(11); p.831-41.
[15]
Koushki PA, Al‐Rashid K, Kartam N. Delays and cost increases in the construction of private residential projects in Kuwait. Construction Management and Economics. 2005 Mar 1;23(3); p. 285-94.
[16]
Fugar FD, Agyakwah-Baah AB. Delays in building construction projects in Ghana. Construction Economics and Building. 2010;10(1-2); p.103-16.
[17]
Haseeb M, Bibi A, Rabbani W. Problems of projects and effects of delays in the construction industry of Pakistan. Australian journal of business and management research. 2011 Sep 1;1(5); p.41-50.
[18]
Soliman E. Delay causes in Kuwait construction projects. Proceedings of the 7th Alexandria International Conference on Structural and Geotechnical Engineering, AICSGE 7, (MG). 2010; p.57–67.
[19]
Hamzah N, Khoiry MA, Arshad I, Badaruzzaman WH, Tawil NM. Identification of the causes of construction delay in Malaysia. In Proceedings of World Academy of Science, Engineering and Technology 2012 Dec 1 (No. 72, p. 614).
[20]
Durdyev, S., Omarov, M., & Ismail, S. (2017). Causes of delay in residential construction projects in Cambodia. Cogent Engineering, 4(1), 1291117.
[21]
Santoso, D. S., & Soeng, S. (2016). Analyzing delays of road construction projects in Cambodia: Causes and effects. Journal of Management in Engineering, 32(6), 05016020.
[22]
Gunduz M., Nielsen Y., Ozdemir M., Quantification of Delay Factors by Using Relative Importance Index (RII) Method for Construction Projects in Turkey, Journal of Management in Engineering, Posted Ahead of Print April 11, 2012. (ASCE) ME.1943-5479.0000129.
[23]
Abdelgawad M, Fayek AR. Risk management in the construction industry using combined fuzzy FMEA and fuzzy AHP. Journal of Construction Engineering and Management. 2010 Feb 26;136(9):1028-36.
[24]
Aziz RF. Ranking of delay factors in construction projects after Egyptian revolution. Alexandria Engineering Journal. 2013 Sep 1;52(3); p. 387-406.
[25]
Sopheaknichhai T, Techapeeraparnich W, Ranking of Risk Factors Causing Delays on Building Construction Project in Cambodia, Proceedings of RSU International Research Conference 2020; p. 919-928

Recommendations

Comments

Information & Contributors

Information

Published In

cover image ACM Other conferences
ICFET '21: Proceedings of the 7th International Conference on Frontiers of Educational Technologies
June 2021
241 pages
ISBN:9781450389723
DOI:10.1145/3473141
Permission to make digital or hard copies of all or part of this work for personal or classroom use is granted without fee provided that copies are not made or distributed for profit or commercial advantage and that copies bear this notice and the full citation on the first page. Copyrights for components of this work owned by others than ACM must be honored. Abstracting with credit is permitted. To copy otherwise, or republish, to post on servers or to redistribute to lists, requires prior specific permission and/or a fee. Request permissions from [email protected]

Publisher

Association for Computing Machinery

New York, NY, United States

Publication History

Published: 05 October 2021

Permissions

Request permissions for this article.

Check for updates

Author Tags

  1. Additional Keywords and Phrases: Construction
  2. Cambodia
  3. Delay
  4. FMEA
  5. Relative Importance Index

Qualifiers

  • Research-article
  • Research
  • Refereed limited

Conference

ICFET 2021

Contributors

Other Metrics

Bibliometrics & Citations

Bibliometrics

Article Metrics

  • 0
    Total Citations
  • 60
    Total Downloads
  • Downloads (Last 12 months)10
  • Downloads (Last 6 weeks)1
Reflects downloads up to 10 Nov 2024

Other Metrics

Citations

View Options

Get Access

Login options

View options

PDF

View or Download as a PDF file.

PDF

eReader

View online with eReader.

eReader

HTML Format

View this article in HTML Format.

HTML Format

Media

Figures

Other

Tables

Share

Share

Share this Publication link

Share on social media