Cronograma Valorizado de Obra (A2)

Descargar como xlsx, pdf o txt
Descargar como xlsx, pdf o txt
Está en la página 1de 3

Item Descripción Und. Metrado Precio (S/.) Parcial (S/.

)
01 TRABAJOS PRELIMINARES 130,914.08
01.01 TRABAJOS PRELIMINARES 130,914.08
02 MOVIMIENTO DE TIERRAS 254,025.50
02.01 CONFORMACIÓN DE PLATAFORMAS 47,046.00
02.02 CONSTRUCCIÓN DE CAJA DE CANAL 206,979.50
03 CANAL CON TUBERIA 851,960.12
03.01 MOVIMIENTO DE TIERRAS 6,654.00
03.02 ENTUBADO 801,295.20
03.03 ACCESORIOS 44,010.92
04 OBRAS DE CONCRETO SIMPLE 672.56
04.01 CAMARA DE CONCRETO P/TRANSICION ENTRE CANAL DE CONCRETO Y TUBERIA 672.56
05 OBRAS DE CONCRETO ARMADO 14,390.41
05.01 CAPTACIÓN LATERAL DE FONDO (05 UND) 9,226.39
05.02 CANOAS (04 UNIDADES) 5,164.02
06 TOMAS LATERALES (34 UNIDADES) 84,900.33
06.01 EN CANAL ENTUBADO 84,900.33
07 CAMARA DE TRANSICION 7,599.55
07.01 TIPO I 7,599.55
08 PUENTE AEREO PARA PASE DE CANAL ENTUBADO 126,637.67
08.01 PUENTE AEREO PARA PASE DE CANAL ENTUBADO 126,637.67
1,471,100.22
CRONOGRAMA DE EJECUCION DE OBRA VALORIZADO
PROYECTO: "CREACION DEL CANAL DE RIEGO, LOCALIDAD DE MIRAFLORES, DISTRITO DE CHINCHAO, DISTRITO PROVINCIA DE HUANUCO - HUANUCO"
MOD. DE EJECT. : CONTRATA
PLAZO DE EJECUCION : 120 DIAS CALENDARIO
PRESUPUESTO : S/. 2,249,724.15 FECHA: SET 2017

MES 1 MES 2 MES 3 MES 4


ITEM PARTIDAS PARCIAL SUB TOTAL
1 SEM 2 SEM 3 SEM 4 SEM 1 SEM 2 SEM 3 SEM 4 SEM 1 SEM 2 SEM 3 SEM 4 SEM 1 SEM 2 SEM 3 SEM 4 SEM

PROYECTO:
"CREACION DEL CANAL DE RIEGO, LOCALIDAD DE MIRAFLORES, DISTRITO DE CHINCHAO, 1,471,100.22
DISTRITO PROVINCIA DE HUANUCO - HUANUCO"

01 TRABAJOS PRELIMINARES 130,914.08 0.00


0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
30.00% 40.00% 30.00%
01.01 TRABAJOS PRELIMINARES 130,914.08 130,914.08
39,274.22 52,365.63 39,274.22 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00%
02 MOVIMIENTO DE TIERRAS 254,025.50 0.00
0.00 0.00 0.00 0.00
30.00% 40.00% 30.00%
02.01 CONFORMACIÓN DE PLATAFORMAS 47,046.00 47,046.00
14,113.80 18,818.40 14,113.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.00% 25.00% 25.00% 25.00% 15.00%
02.02 CONSTRUCCIÓN DE CAJA DE CANAL 206,979.50 206,979.50
0.00 20,697.95 51,744.88 51,744.88 51,744.88 31,046.93 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

03 CANAL CON TUBERIA 851,960.12 0.00


0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
100.00%
03.01 MOVIMIENTO DE TIERRAS 6,654.00 6,654.00
0.00 0.00 6,654.00 0.00 0.00 0.00 0.00
5.00% 5.00% 10.00% 10.00% 15.00% 15.00% 15.00% 15.00% 10.00%
03.02 ENTUBADO 801,295.20 801,295.20
0.00 0.00 40,064.76 40,064.76 80,129.52 80,129.52 120,194.28 120,194.28 120,194.28 120,194.28 80,129.52 0.00 0.00 0.00 0.00
30.00% 40.00% 30.00%
03.03 ACCESORIOS 44,010.92 44,010.92
0.00 0.00 0.00 0.00 0.00 13,203.28 17,604.37 13,203.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00

04 OBRAS DE CONCRETO SIMPLE 672.56 0.00


0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
50.00% 50.00%
04.01 CAMARA DE CONCRETO P/TRANSICION ENTRE CANAL DE CONCRETO Y TUBERIA 672.56 672.56
0.00 0.00 0.00 0.00 0.00 0.00 336.28 336.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00

05 OBRAS DE CONCRETO ARMADO 14,390.41 0.00


0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
30.00% 30.00% 40.00%
05.01 CAPTACIÓN LATERAL DE FONDO (05 UND) 9,226.39 9,226.39
0.00 0.00 0.00 0.00 0.00 2,767.92 2,767.92 3,690.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00
50.00% 50.00%
05.02 CANOAS (04 UNIDADES) 5,164.02 5,164.02
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,582.01 2,582.01 0.00 0.00 0.00 0.00 0.00

06 TOMAS LATERALES (34 UNIDADES) 84,900.33 0.00


0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
40.00% 30.00% 30.00%
06.01 EN CANAL ENTUBADO 84,900.33 84,900.33
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 33,960.13 25,470.10 25,470.10 0.00 0.00 0.00

07 CAMARA DE TRANSICION 7,599.55 0.00


0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
100.00%
07.01 TIPO I 7,599.55 7,599.55
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7,599.55 0.00 0.00

08 PUENTE AEREO PARA PASE DE CANAL ENTUBADO 126,637.67 0.00


0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
20.00% 20.00% 20.00% 20.00% 20.00%
08.01 PUENTE AEREO PARA PASE DE CANAL ENTUBADO 126,637.67 126,637.67
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 25,327.53 25,327.53 25,327.53 25,327.53 25,327.53
COSTO DIRECTO 1,471,100.22 337,186.43 571,864.03 427,669.98 134,379.79 1,471,100.22
GASTOS GENERALES 10.00% 147,110.02 33,718.64 57,186.40 42,767.00 13,437.98 147,110.02
UTILIDAD 10.00% 147,110.02 33,718.64 57,186.40 42,767.00 13,437.98 147,110.02
PARCIAL 1,765,320.26 404,623.71 686,236.84 513,203.97 161,255.74 1,765,320.26
IGV 18.00% 317,757.65 72,832.27 123,522.63 92,376.72 29,026.03 317,757.65
SUB TOTAL 2,083,077.91 477,455.98 809,759.47 605,580.69 190,281.78 2,083,077.91
EXPEDIENTE TECNICO 3.00% 62,492.34 14,323.68 24,292.78 0.00 5,708.45 44,324.92
SUPERVISION 5.00% 104,153.90 23,872.80 40,487.97 30,279.03 9,514.09 104,153.90
TOTAL 2,249,724.15 515,652.46 874,540.23 635,859.72 205,504.32 2,231,556.72
% DE INCIDENCIA 22.92% 38.87% 28.26% 9.13% 99%