Bet Steel
Bet Steel
Bet Steel
Project Summary
To remain competitive in the rapidly changing global marketplace, Bethlehem Steel Corporation (BSC), the second largest producer of steel in the United States, was looking for opportunities to improve the performance of one of the steam turbine generators at their Burns Harbor Facility in Indiana. By rebuilding the turbine to incorporate the latest steam path technology, using a portion of the warm condenser cooling water exhaust stream instead of cool lake water for boiler feedwater make-up, and injecting the low-pressure steam previously used to heat the lake water into the turbine, BSC was able to significantly increase the capacity and efficiency of the steam turbine generator system. This Steam Challenge Showcase Project resulted in annual savings of approximately 40,000 MWh of electricity, 85,000 MMBtu of natural gas, and nearly $3.3 million. With a cost of $3.4 million more than a standard maintenance overhaul, the simple payback for the project is just over one year. The project also reduced high-temperature water discharge into the harbor, and decreased coke oven and blast furnace gas emissions.
A PPLICATIONS
Can be applied to almost any industrial application where steam turbines are used for shaft power or to generate electricity on site. Industrial facilities with boiler systems may be able to use the thermal energy stored in condenser water discharges and other liquid streams.
Plant Overview
The Burns Harbor Facility, located on about 1,700 acres on the shores of Lake Michigan, is BSCs largest and most efficient plant. Built in 1964, the plant, which employs 6,000 workers, is capable of an annual production of 5.3 million tons of hot-rolled sheet, cold rolled sheet, and steel plates, and is a major supplier of sheet and plate products to the automotive, machinery, and appliance markets.
Project Background
Due to stiff global competition, domestic steel producers have been forced to improve the efficiency and competitiveness of their steel-making operations, or shut down. With daily electricity, natural gas, and potable water costs of $300,00 at its Burns Harbor Facility, BSC realized that addressing the plants energy costs could save money and improve the plant's competitive position.
Project Team
Together with BSC staff, General Electric Industrial & Power Systems performed the turbine upgrades, and the U.S. Department of Energys Steam Challenge program confirmed the resulting energy savings.
OFFICE OF INDUSTRIAL TECHNOLOGIES ENERGY EFFICIENCY AND RENEWABLE ENERGY U.S. DEPARTMENT OF ENERGY
maintenance shutdown, such as cleaning buckets, would have increased the output from 42 to 44 MW. Replacement of some turbine components would have brought power output up to 46 MW. Output could have been increased to 48 MW, using the normal-operation steam flow, if the turbine were redesigned to incorporate the latest steam path technology. Because of the need for increased generation capacity, BSC elected to redesign the turbine, substantially increasing the turbines efficiency and capacity. Another system modification involved changing the source of the boiler feedwater make-up from cool lake water to a warmer condenser cooling water exhaust stream. The old system heated 42,000,000 gallons of lake water per month with low-pressure steam. Substituting the condenser cooling water exhaust stream that was 20F warmer reduced low-pressure steam usage, thus allowing the excess steam to be injected into the redesigned turbine, thereby increasing its output.
Results
The upgraded turbine and other system modifications resulted in significant energy and cost savings. Annual electricity savings of approximately 40,000 MWh were realized, and nearly 85,000 MMBtu of natural gas are conserved each year. Cost savings include $1.45 million from reduced demand charges
Alternatives Considered
BSC considered a number of options to improve the efficiency and upgrade the capacity of turbine #5. Work normally performed during a scheduled
resulting from the increase in turbine capacity, $1.3 million from efficiency gains in the turbine, $270,000 from avoided temporary power costs when other turbines are down, and $280,000 from reduced natural gas costs resulting from the switch to condenser water. Total annual cost savings are about $3.3 million, based on 1995 energy costs. With a cost of $3.4 million more than a standard maintenance overhaul, the simple payback for this project was just over one year. In addition to the energy and cost savings, the project reduced high-temperature water discharges into the ship harbor, and decreased coke oven and blast furnace gas emissions.
The Steam Challenge is a publicprivate initiative between the U.S. Department of Energy, the national non-profit Alliance to Save Energy, and several private companies and associations. It promotes the comprehensive upgrade of industrial steam systems so U.S. manufacturers can increase productivity and lower production costs. Steam Challenge assists the steel industry and other OIT Industries of the Future by identifying nearterm gains in energy efficiency these industries can achieve by adopting existing technologies.
PROJECT PARTNERS Bethlehem Steel Corporation Burns Harbor, IN General Electric Industrial & Power Systems Schenectady, NY
Lessons Learned
A number of valuable lessons were learned from this project. First, if equipment is scheduled for a maintenance overhaul, consideration should be given to making upgrades that go beyond standard maintenance to improve the performance of the equipment. Second, attention should be paid to energy rate structures in utility bills. Sometimes projects that result in efficiency gains can dramatically reduce energy costs. Finally, find ways to use waste heat streams and put the thermal energy to use.
F OR A DDITIONAL I NFORMATION , P LEASE C ONTACT: The OIT Information Clearinghouse Phone: (800) 862-2086 Fax: (360) 586-8303 http://www.oit.doe.gov/steam
Other Applications
The technology used in this case study could be applied to almost any industrial application where steam turbines are used for shaft power or to generate electricity on-site. When a turbine is scheduled for overhaul, discuss upgrade options with vendors to improve system performance. Industrial facilities with boiler systems should look for opportunities to use the thermal energy stored in condenser water discharges and other liquid streams. Process integration that matches heat sources and sinks through heat exchangers, known as pinch technology, can sometimes lead to substantial energy savings.
Visit our home page at www.oit.doe.gov Please send any comments, questions, or suggestions to webmaster.oit@ee.doe.gov
Office of Industrial Technologies Energy Efficiency and Renewable Energy U.S. Department of Energy Washington, D.C. 20585