TOYO - Piping Design Instruction PDF
TOYO - Piping Design Instruction PDF
TOYO - Piping Design Instruction PDF
1.1 Plant area 1.2 Safe distance 1.3 Distance 1.4 Overhead clear ante 1.5 Design of tank yard 1.6 Height of foundation 1.7 Road 2. Installation 2.1 2.2 2.3
2.4
8 9 9 9 10 10 10 11 11 .13 15 16 16 17 .17 1% 1% 19 19 22 22 23 24 25 25 27 34
of platform,
stairs
and ladder
Installation
bstaliatioti
sf sructure
of ladder
2.5 3.
of platform and ladder Staira, ladder and handrail Live load for platform
Installation
Nozzle orientation 3.1 3.2 Type and size of platform Limitation on platform installation (1) Manhole (2) Level control (3) Gauge glass (41 AP/CELL type liquid level instrument (5) Temperature instrument (6) Opening in platform (7) Installation of davit ai the top of tower Consideration on nozzle orientation 3.3,1 Nomenclature 3.3.2 Considerations required for tower nozzle orientation 3.3.3 Considerations for orientation in other vessels and heat exchangers
3.3
34486
Contents
-2 -
3. PIPING 1. Manuals relat ded to piping 1.1 1.2 2. Relation between this Related manuals rule design design instruction and other manuals
37 37 37
38 38 38
of pipes
(Double line)
39
3.
Piping
3.1
39 39
, A
of steel
i
pipe
39 39 40 41
(PWHT)
3.2
41 41 41 41 41 42 43 44 45 45 45
3.3
3.4
4.
Pitting 3.3.1 Bend 3.3.2 Blitre bend 3.3.3 Reducer 3.3.4 Tee 3.3.5 Standard application of fitting 3.3.6 Comparison of material between JIS and ASTM Flange materials
Scope of work for piping 4.1 4.2 4.3 4.4 Scope of Matching Uatching Matching work with with with
46 46 50 50 50
3448G
Contents
-3
5.
Insulation
5 .l General
Hot insulation Cold insulation Personnel protection Fire proofing poise protection
Noise and vibration 6.1 poise 6.1.1 6.1.2 6.1.3 General Noise level limitation Sources of noise
6.2
7.
Cathodic protection Grounding for static design detail Piping 8.1.1 8.1.2 8.1.3 Piping 8.2.1 8.2.2 8.2.3 8.2.4 8.2.5 8.2.6 Piping 8.3.1 8.3.2 8.3.3
protection
8.
Piping 8.1
8.2
8.3
Nozzle orientation Piping around tower around heat exchanger Type of heat exchanger Considerations required for arrangement and piping Example of piping around horizontal heat exchanger Piping around reboiltr Piping around Al-heat exchanger Piping around air cooler around rotating machine Piping around pump Piping around turbine Piping around compressor
3448G
Contents
-4 -
8.10 8.11
and Vent piping Hose station Eye washer and shower Ejector piping pump, turbine etc.
8.12
8.13
(1) Installation criteria (2) Type of valve Tank yard piping 8.13.1 Regulations and safe distance 8.13.2 Tank yard piping i.13.3 Drains-ge -system 8.13.4 Fire~ext&guishing system underground
144 146 146 148 149 149 149 149 150 150 150 150 153 153 153 153 153 155 164 178 179 179 179 184 186 186
8.14
Underground piping 8.14.1 Lines to be installed 8.14.2 Design 8.14.3 Cooling water piping 8.14.4 Sewer piping 8.114.5 Trench piping
8.15
Firefighting piping (when regulations 0.15.1 Type of rystems 8.15.2 Water extinguishing system 8.15.3 Air-foam system 8.15.4 CO2 extinguishing system 8.15.5 Cases where WFPACODEis applied
3448G
Contents
-6 -
4. PIPE SUPPORi 1. General 1.1 1.2 1.3 2. Purpose Scope of application Related manuals and manuals for reference 187 187 188 support design factor 188 188 190 192 191 191 191 192 195 195 196 200 200 202 202 203 203 204 204 205 207 207 208 208 209 210
3.
Supports for 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10
piping
Support span Pipe spacing Supports for bare pipe Supports for hot-insulated pipe Supports for cold-insulated pipe Supports for large-dia. pipe Other considerations required in design of supports Use of anti-friction agent Supporting to cope with vibration Absorption of thermal expansion 3.10.1 Model plan 3.10.2 l&en U-loops are used 3.10.3 When bellows-type expansion joints are used 3.10.4 3.10.5 3.i0.6 When Yarways gun-packed expansion joint Dissipation of heat Pressure loss around vessels is used
4.
Limitation of load Supports for discharge pipe of safety valve Vessel clips Supporting of tank piping 4.3.1 4.3.2 Supporting of tower piping
3448G
Contents
-7 -
5.
Supports for piping around compressor and turbine 5.1 5.2 5.3 5.4 General .Manuals for reference Piping provided with sxapnsion joint Piping 5.4.1 5.4.2 5.4.3
211 211 211 211 212 212 212 213 214 215 215 .219
.
6.
supports to be used in general Slliding supports Spring support Thermal-expansion-direction restraining device (Directional, stopper) 5.4.4 Directional stopper of free-in-one-direction type 5.4.5 Pipe hanger 5.4.6 Vibration atopper for piping ..:: .:- ,I.. Supports for piping arc&d pump Manuals for reference Piping around pump and location of supports
6.1 6.2
7.
Spring hanger 7.1 7.2 7.3 7.4 7.5 7.6 Variable hanger Design of variable Construction hanger
of
and material
variable
hangers hangers
Specification for placing order of variable Selection of variable hanger's type No. Supporting load of spring hanger
3448G
Contents
-8 -
5.
211 211 211 211 212 212 212 213 214' 215 215 -219 . 219 .220 230 230
6.
General .Manuals for reference Piping provided with exapnsion joint Piping supports to be used in general 5.4.1 Slliding supports 5.4.2 Spring support 5.4.3 Thermal-expansion-direction restraining device (Directional, stopper) 5.4.4 Directional stopper of free-in-one-direction type 5.4.5 Pipe hanger 5.4.6 Vibration stopper for piping _: .. .- .:. Supports for piping~around pump 6.1 6.2 Manuals for reference Piping around pump and location of supports
7.
Spring hanger 7.1 7.2 7.3 7.4 7.5 7.6 Variable hanger Design of variable hanger Construction and mater ial of variable
hangers
Specification for placing order of variable Selection of variable hanger's type No. Supporting load of spring hanger
hangers
34486
Contents
-8 -
1. GENERAL 1.1 Intent (1) layout order and scope Intent equipment by TEC, in
This design instruction is intended to standardize vays of and piping design of the plant to be designed or constructed , economical and quick plant design. to obtain correct (2) Scope This (3)
Notes:
design
instruction
applies
to all
TEC jobs.
should
be filled
out
and selections
made at
b.. If conflict, due to customer's requirements, weather arises between the requirements of this instruction, should be revised and then used so as to meet them.
c. Where there are conflicts between this instruction and otherj TEM or TES etc., such conflicts should be solved by assigned Job Engineers and if contact Standard Engineer and revisidn of other TEM, TES is necessary, Whenever revision of this instruction is required, Section Chief. contact Section Chief. d. Where applicable codes, customer's contradiction to this instruction, 1.2 Outline (1) of project : : requirements the formers etc. are in should govern.
a. Main b. (2)
I
End user
: q ENGINEERING
n F.0.B
(3)
D q tl iJ q 0 (4) Scope of engineering PROCESS FLOW DIAGRAM P&I PLOT PLAN UNDERGROUND PIPING ABOVEGROUND PIPING FIRE-FIGHTING PIPING CIVIL INFORMATION DETAIL CIVIL DESIGN 3402G -l-
TURN-KEY SUPERVISING COST PLDS FEE LDMPSUM PRICE UNIT PRICE OTHERS
1.3
Outline
of
included
I
(5) 1.4 Site of plant conditions Ambient maximum minimum yearly design design Climatic 1.4.1
I
:
temperature : : average max. min. : : : OC OC OC OC (for 'C (for equipment equipment design) disign)
3402G
-2-
relative
relative
: : : :
average relative
: :
:
xun/hr, m#W
m/hr
mm/day
1.4.4
mm kg/m2 kg/m2
N
1..
1.4.5
Direction
max.
speed
f-B
...
1.5
Topograph)tic 1.5.1
Datum
Ground 1.5.2
1.5.3
: : soil : : : :
m (=EL.OI ton/m2
Rearing
Groundwater
capacity
level depth
Max.
freezing
Seismic
Characteristic Characteristic
considerations considerations
to design) to design)
Applicable regulations, codes and standards A( Applicak.he regulations , codes and Etandards should be as indicated in the contract documents. Hake sure that the regulations, codes and standards applied are in what year's editions. If regulations, codes and standards other than indicated in the,contract are used, the names of such regulations, codes and standards and the reasons why they are used should be clearly stated.
1.6.1 Customers
requirements
34026
-3-
1.6.2
Regulations
, codes.and
standards
codes
i i ; i
0 Law for conditions of plant site 0 Petroleum Kombinat and Other's Hazard Prevention Law 0 Fire Service Law 0 High Pressure Gas Control Law Cl HIT1 ordinance on High Pressure Gas Control Cl MIT1 Ordinance on Liquefied Petroleum Gas Control D MIT1 Ordinance on High Pressure Gas Control: Concerning Kombinat and Others D Industrial Safety and Health Law 5 Law for mining industry Cl Law for gas industry CIOthers .
,a OSHA WCCDPATIONAL SAFETY AND HEALTH ADMINISTRATION) ' 0 OIA (OIL INSURANCE ASSOCXATION)
; 0 NFPA i q API RPSOOA (RECOMMENDED PRACTICE FOR CLASSIFICATION
INSTALLATION
IN
.I
(SNIP) O=W
ll.H.l-* -0
" (1
(GOST)-12.1.004-" " n CODE AND REGDRATION AS To SAFETY TECHNIQUE AND INDUSTRIAL SANITATION FOR FIRE ACCIDENT OF CHEMICAL AND PETRCCREHICAL PLAN ._' OTHERS (DDR) 0 ASAO U%TROCHEMICAL LARCDR REGULATION)
for for
34026
-4-
Items 2)PIPING
codes
CJ Codes and standareds 0 ANSI DKHK 0 JIS 1 D ASTM j z1 API j 0 JPI I Cl DIN 10 BS I 0 MSS i G OTHERS Z Codes and standards Cl Building Standards DOTHERS to piping design
item(l)
Index
of
the
contract.
(in
Japanese
and English)
..._
34026
-5
1.7
Battery
limit FLUID
conditions
! I 1 T i I 1
! t I
i
("C) Design
(KG/CM=) Design
I ! 1
1 2 3, 4 INCOMING ] I 7 I
! i
3402G
-6-
1.8
Utility
conditions
Followings are utility lines commonly used. Be aware that Fluids each having the same name may have different specs respectively (different design conditions). When detail checking, use the design conditions given in the line schedules. -. FLUID 1. SH (H.P STEAM) 2. SM (M.P STEAM) 3. SD 84.P STEAM) 4. SL (L.P 5:CH STEAM) I I .'...., .. SPEC. TEMP.(V) MAX. MIN. I ! I
i
! !
! I
I I I ! ! !
(H.P COND.)
I i 6 I *i I i I , i i
1 , t ! I
INSTRUMENT AIR
1 9. PLANT AIR 110 . NITROGEN ; ; 11. i i 12. i i 13. 1 !14. ! i 15. 1 :l,. t i 117. 18. 19. 20. 1.9 Customer's requirements COOLING WATER (IN) COOLING WATER (OUT) SEA WATER (IN) SEA (OUT)
I ! ; I 1. j .I.. 1 . ,..
I
i
1 i i 1 I 1 _. ii I I
i
IL
; i i /
iI
i i I 1 / i 1 I I t
I
.i 1 . -f -':I i
..
I .f _....
i j..! I i.
b I I
3402G
-7-
2.
PLANNING
Plant 1.1
shapes and sizes of plant areas are given by following items should always be considered as a plot plan.
ers
The plant area should be small as far as safety, operation, This maintenance and construction requirements will permit. results in considerable saving in cost of piping materials and power equipment. To layout equipment into a slender area is liable to cause difficulty in obtaining piping flexibility, which increases piping cost due to additional loops and bellows. It is recommended that a ratio 'of long side to short side of plant be 1:1~1.5:1 based on past experiences. Plant areas should be prepared so as to obtain a neat layout having minimum changes in direction of main racks and roads which are backbones of the plant. Layout of main equipment is
(2)
:. (3)
area in
1.1.2
To have layout of equipment in a sequence to suit the process flow But, safety le best rule from the view points.of economy and pressure drops. rd construction requirements dictate more or less modifications of this rule. be followings are main items of such modifications. (1) Fired heaters (boilers, reformers, heaters etc.) should be located up wind from other equipment handling flammable liquids or gases, and should be grouped together in one area as far as possible to allow centralized control for safety.
(2)
Equipment such as pumps and compressor handling flammable liquids or gases, which could easily leak out of the equipment, should be located minimum 15 meters away from fired heaters. (Conforming to Regulations for explosion preventions) For other equipment containing flammable gases minimum 8 meters. (Conforming to MIT1 Ordinance on Bigh Pressure Gas Control 12-3) Vessels silencer within vessel taller than the discharge point of fired heater stack discharging hot gases or steam should not be located SO meter radius of the discharge point to prevent the from exposing to hot winds. be reviewed close to the
or
(3)
(4)
Towers more than 30 meters heigh I- should initially from the installation point of view and located route through which towers are moved into place.
(5)
Large electrical equipment (switch room, motor, large sized switch), if installed within hazardous area, will cause considerable cost increase due to the explosion-protected construction.
1402G
-8-
(6) Control room and switch room should be located near the center of the plant and provided with exit on either one side of the room to allow easy access to and from boundary limits. Equipment or piping containing flammable substance should not be located within 15 meters from these rooms. (To keep the room outside Of hazardous areas.) MIT1 Ordinance on High Pressure Gas Control Concerning Kombinat-9 also dictates to have safe distance of 7.5 to 15 meters depending on the degree of hazard for the above case. (7) Insides of buildings housing ccanpressors handling flammable gases are classified as a hazardous area, including areas 3 meter wide around the buildings of closed type and 15 meter wide around the buildings of open type. All electrical equipment within these areas should be of explosion-protected construction.
(8) Equipment handling poisonous substance should be completely enclosed by a dike to enable collection and recovery of the spillage. Related equipment should be grouped together for this purpose.
i i .. :..
(9) Equipment cknected to underground lines such as cooling water or chemical sewer should be properly grouped so as to minimize the length and direction changes of underground pipes which reduces ce with not only piping cost but also the possibility of interfer other cables and foundations. P 1.2 Safe Safe 1.3 distance distances should conform
to
THM 2002
(Plant
Layout).
Distance 1.3.1 1.3.2 1.3.3 1.3.4 Between furnace control room, switch combustible piping) room and liquid 15m MIN. MIN. 8m
Plant equipment for and furnaces (except Equipment Indoor Passage facilities
0.9m
MIN.
0.6m
1.4
3.5m
2.lm
1.8m)
(MIN.
2.lm
1.8m)
3402G
-9-
Design 1.5.1
of tank
yard
: : I . :
codes
are *
applied;
. ..
1.5.2
'. "r
.:
. ..I..
Height 1.6.1
of
foundation
Height a. Pavement b.
C.
M/M
Pavement Cable
J-JF
MAX. 50 M/M
pit
d.
M/M
and other .rotating machine e. Compressor (horizontal type) f. Heat exchanger g- Other equipment-tower.s, structure, h. Pipe rack, 1. Cone roof tank j.
k.
etc. stairway
EL.+
EL.+
pit
(top
of
EL.+ EL.+
1.6.2
EL.+ EL.+
600 M/M (CONTROL ROOM) 1000 M/M (SWITCH ROOM) MIN.300 MAX.150
M/M
_,/ _,:
floor of equipment
house
and
EL.+ EL.+
Foundation
of
M/M
/--/
clearance
a) Access
12000 I=
/
Pavement \ ..
A z
,L,,
:.
3402G
-lO-
. .
b)Plant
road-type
.1.7.2
Turning
radius
at road _.. -
junction
Fd
gradient
Gradient IF--
12/100
and less
of platform,
stairs
and ladder
Structures may be of concrete or steel, unless otherwize specified by customers. Structures mounted with such as removal of heat with stairs or ladders.
3402G
-ll-
(3)
Selection
of in
stairs
or ladder cases;
structure
the following
of
platform
above
the
but
platform Sampling or
3) Platforms mounted with instruments etc. requiring patrol by operators 4) Platforms boilers 5) Platforms frequent mounted requiring
as level
once
least
such
mounted with equipment opening of the covers. with equi.pment material.. following
as filters frequent
requiring cases.
replace
Of
J 1) Platforms
2)
mentioned
In addition to the above mentioned stairs, should be provided at closed end of more blindalley, if any.
be
area
3402G
-12-
4) Platforms should have minimum clear width of 800 mm for but additional space is maintenance, inspection and operation, required to facilitate removal of exchanger channel covers and as shown in the drawing below. internals, Sub-ladder
A, * .
5c
Use sub-ladder where P.F. area is more than (If ladder height exceeds 10 meters, use staggered type with intermediate platform.)
5Om2
Use
sub-ladder where P.F. area is more than (If ladder height exceeds 10 meters, use staggered type with intermediate platform.) should not be required floor is needed. on this side if no
5om 2 .
f \
Poarforms operation
5) Main
for
should
be located
to permit
ready
access
2.2
be staggered
with
each ladder's
length
not
3402G
-13-
b.
If the should
length
of
ladder
Not
be provided.
intermediate
as possible.
platform
intermediate platform
(2) .. a.
Pipe
-Ti..
b.
or
sub-racks of safety
without cage
walkway
should
not
generally
require
(3)
a. Tower
Ladder without
cage
Caoe
Cage
3402G
-14-
b. Structure
i
i-l,,,,
4
V
Not requ.ired
' provided
1
under
/////////////////////////////7//////////////~f
2.3
Installation
of platform
and ladder
(1) Platforms should be provided for the following items, when such items are located 3.6 meters or more above the grade (2.1 meters or more for instruments at vessels) or 1.8 meters or more above other platforms. .. .. . .- a. $tems requiring surrounding platform underneath ,Qbj,ect 11 Control valves of all size$.
2)
type level gauges at towers tanks. blind flanges. side platform only
5) 8 figured
more requiring
2)
3) Manholes and others in horizontal vessels or heat exchangers requiring manual operaton and inspection. . 4) Sampling equipment. 5) Valves frequently operated.
6) Places in the proximity of BL, or places where valves are grouped together.
3402G -15-
(2)
Ladder should be provided for the following items, when such items are located 3.6 meters or more above the grade (2.1 meters and more for instruments at vessels) or 1.8 meters or more above other platforms. 1) All check tanks.
2) Valves
valves
at towers
and
tanks
3)
and
Gauge glasses. (Platforms should provided if gauge glass requires frequent inspection and maintenance.)
be
4) 5)
Pressure, Inspection
temperature
cocks.
instruments
at
towers
and tanks.
6)
material
7) Sampling
(3)
Only a stand or portable ladder is required for manholes, valves, instruments etc. requiring manual operation, when they are located at less than 3.6 meters above the grade (less than 2.1 meters for instrument at vessels). Platforms Hozale and ladders flanges should not be required for the followings.
(41
a.
at towers instruments
b. Temperature
C.
connections
a. c.
hangers. (when accessible and handrail and handrails platform platforms in case exchanger
works
with
a portable
ladder
or temporary
2.4
Stairs,
StairS,
should
conform
2.5
should
be designed
for
the from
the
be considered
of cold
district,
aside
Loads by pipe supports, heat loading and other maintenance Data aside from the above(l).
will
3402G
-16-
3. Nozzle 3.1
Orientation Type and size (1) Platforms of for platform ordinary vertical equipment Width B of platform Not to be used as far 1) min.600 2) 800 1 as possible. To be used as a standard 3) 1000 4) 1lOON ) With 100 mm increment max.1500;
(2)
a.
for
towers
b.
Vessel nozzles, which are normally extended through the top platform bolts or installing block valves.
c. d.
Openings should,,be made to allow tightening flange bolts spanner if the-nozzles are not extended through platforms.
using
Platforms should not be connected regidly to neighkx$ing vessels, but should he provided with a clearance approximately 20 mm or connected with slotted bolt-holes to allow for expansion. Platform for horizontal vessel
(3)
Platforms should be provided on the top or side of horizontal vessels lDounted with manholes or instruments requiring operation, inspection etc., if they are located 2.1 meters and more above grade. (3.6 meters and more if no instrument is mounted.)
the
340x
-17-
Platform
a.
for of
tank ladders (Dm) and stairs Selection Ladder Spiral with safety stairs be installed cage
Selection Height
b.
In 4 termediate platforms should height 10 meters or less. Platforms and handrails for tank
at
a uniform
interval
of
roofs
should
be minimum
required.
d.
For spiral stairs, careful study should sampling connections and other gauges, for operators to handle them.
Intermediate platform 10m . Cone 3.2 Limitation (1) Manhole foof Dome roof installation .
Spherical
on platform
i 8 4 m . 5 4.x
500 -loo0
(750 is stand
be
2. Manhole davits (or hinges) should generally be designed to allow right-hand opening.
3402G
-18-
--_ . .-_
3. Menhole davits (or hinges) should be located away from down ladders (left-hand opening) unless a distance down ladder to manhole is sufficient (1,000 as a standard) to provide a passage. (2) Level control
H silo00 A irk00
I-I
(Provide removing 4
I1
clearance internal
r-
operated I
\
from
ladder.
I-- 1. I
.I A-
H>
A distance operation
(3) a.
Gauge glass Multiple ladder. level gauges should be arranged to stagger on both sides Of
=402G
-19-
b.
on one side,
upper
level
gauge
I. i :-..:
,_
Max. 1000
Reading
of
level
from
ladder
c.
In'general, level gauges should not penetrate impracticable, level gauges may penetrate it liquid level.) to feed nozzle LIC should
60
platform. to allow
(If for
this reading
is
d. Relation
take
LG.
34026
-2O-
e. Level
gauge
in
low temperature
service
on of
Ins;a$on
Use *A* type level gauge. Use "B" Use "C" Wultiplc type type level
is located is located
of gauge. gauge.
is located should
be'installed
as follows;
the other Valve handle projecting into safety cage. f. When baffle plate is installed
in
the
Baffle
Plate
34026
-21-
g.
Level
gauges
should
be
located
away from
seal
pan as
far
as possible.
Away
as
far
as possible
h.
gauge
for
high
pressure
service
their
(4) aP/CELL
measurement
This
pipe
should
be horizontal.
Consider
a space
for
instrument
box.
two
Provide pipe of apprO~iXiately meters length to heat pipe low temperature service.
in
(5)
Temperature
a. Check to ascertain
b.
When liquid temperature is measured, pay attention sizes and insertion length. (In general, liquid measured.)
34026
-22-
+ I97
Or
c.
Length
of
temperature
instrument
150 mm
instrument in tangential
vessel
internals;
1) Install
2) If instrument interferes despite a special length instrument. (Consult Instrument Engineer) e. In many cases, temperature instruments immediately upper or lower tray. Consult Process engineer if insertion in platform should also
of
tangential
installation,
use
to an
(6) Opening
below
appear
in the
instrument b)M
type
3402G
-23-
c)Piping
(7)
Installation area
of Davit
at The Top of
Tower
a. Drop
Davits are used for lifting vessel internals when loading. An ample space for dropping and loading vessel internals should be provided on the platforms.
::
:Pipe
davit
Dropping
area
fir
Not
good
good
Davits
operated
may be either
b. Side
clearance
for
lifting
if special sized platform is required to area. In this case, the arm length should side clearance of min. 450 mm.
3402G
-24-
3.3
Consideration 3.3.1
on nozzle
orientation
Nomenclature TRAY : Trays, a large munber of equally spaced circular are devices on which efficient vertical vessel, and liquid is performed when product separation using distillation. DECK : Deck, a part of tray, mixing is performed. WEIR : Weir is mounted on the liquid on the plate. is a horizontal plate platesin mixing of'p.por is required by
on which
vapor
liquid
deck
to maintain
an even
flow
of
the
the decks allowing the while separating vapor deck underneath distances.
to
SEAL POT : Seal pot is a pot provided in the to effectively reduce deck-to-deck
downcomer
DRAW-OFF POT : Draw off pot, used when draw off from intermediate is a pot provided in the deck underneath required, It provides sufficient depth for liquid collection installation of draw-off nozzle. SEAL PAW : Seal pan is a pan located underneath Overflowed liquid from upper deck. received by the bottom of tower. the lowest liquid from
DRFLRCTOR : Deflector is a baffle plate installed against prevent liquid with high velocity from entering vessel.
340x
-25-
Single
Double \
Center
\A
downcomer
2
I m/m I 3I
=t
Width
of pot
m/m
Outlet
weir downcome
Side
View
340X
-26-
.:
:;
3.3.2 (1)
required feed
for
tower
nozzle
orientation
a. Locate
nozzle
to feed
inside
of
inlet
weir.
Approximately 150 of cross 4-P l/lOD or 10 to sectional area.
Deflector
Single
Ll
Double
flow
YInlet
weir .Internal
detail
orientation,
may be oriented
Double
flow
* Dimension straight
A does length.
not
require
3102G
-27-
c.
For
internal
piping, 2
It ii
the
elbow
special
type.
Min. % d. When the width of inlet weir is smaller tee, closed end pipe with slotted holes than that of open should be used. end
.be extended..
(2)
In case
of feed
intermediate
stage
feed.
a. Vapor
Single
flow
Double
flow
3402G
-28-
b. Liquid
Single
flow
Double
flow
. ..
:. ,:
c.
Draw off
nozzle
(3)
Bottom
feed
nozzle
iDCJ
g&d t-l I Single good Double Double
good
good
go*
good Sd
nozzles
3402G
-29-
(4)
a.
..
Pay attention to downcomer areas. when the downcomer any direction, 300 mm or smaller. good
But, width
in
Double
In
Manhole 1) Single
in
the flow
interm6diate
stage
_ 2) Double flow
Manhole
downamer
Two manholes
are
required,
when
Not god
N 9
Not good
2) When baffle
plate
is provided.
~~d~~~~~o~d
Double of large
flow tower
Reduction
of height
L 1 t1 P
b.
c/ :.
...
.:
r-I I1
of diameter
.:
-
Reduction
3402G
-32-
c.
Reduction
of
both
height
and
diameter
Note
: Check carefully for interference of downcomer determining feed nozzle and manhole orientation.
when *
Care
should
be taken
not is
internal
.
pipe in contact
(6) Relation
a. Arrangement 1)
to rcboiler
of
reboiler
flow An altern&v~
Double~flow arrangement
impingement
2) When the amount of liquid is small , arrangement as shown below may be used. In this case, attention should be paid to the location of reboiler return nozzle. Center line of reboiler return pipe should have same elevation with the top of baffle.
(7)
portion as far
of
vessel
as possible. increment
for vessel
in other
vessels
nozzles
should
be located
on
Feed 4
Vapor #
out
Do not
locate
outlet
nozzle
here.
(2)
Compressor
suction
a. Special consideration should be paid for instrument nozzle. (Improper orientation compressor. For detail. see ; 1
3402G
-34-
..,, 1.
, .:
/ t 9 :
Not good type heat exchanger by the is effected Even nuder
in the
same
sood
...
(3)
Vertical
a. Orientation
number
of baffles,
when total condensation But, consult Process Engineer, (Usually, outlet and inlet temperatures are is used. the same.) b. inlet nozzles In case of two passes, should be in the same direction. of shell side and tube side
hole
and vent
hole limitation
is no special hole
the
2) Two or more access holes in one skirt symmetrically to the center of skirt.
\rer t. \?essel
Ill gene;:2 1 .
.- ,
ALEX.
related
Realation
This design instruction is intended manuals and also to cover drafting The followings Of course, instruction. Related TEM-1005 -2001 -2002 -3001 -3002 -3004 -3006 -3007 -3015 -3017 -3025 -3036 -3037 -3038 -3039 -3047 -3048 -3063 -3069 -3074 -3082 -3101 -3102 -3104 -3105 -3106 -3107 -3108 -3109 -3112 -3113 -3114 it are existing manuals to utilize
registered
is necessary
existing
manuals
manuals General Plant Drafting Prefabrication Types Piping of spacing piping drafting layout in piping methods sampling for piping drawings rules of transportation equipment
Specifications Abbreviations
Rack piping Tower piping allowable for of piping information materials for piping span for design drawings and piping lists around compressor and turbine drawings ,= pipes Maximum Standards Checking Checking How to Design
Pump piping How to Drafting Matching Drafting Drafting Drafting Drafting Drafting Drafting Assign Drafting Design
use and
piping plan at
design
control
sheet
methods drawings of
piping
battery
limit
of key plan
steam
(or desuperheater)
3402G
-37-
(1) mm should be used as a unit. (2) In general, comma(,) should not be used in the indication should conform to job P&I and UFD. of length.
(4) Standard scales are as follows; 430, l/40, 450, 480, l/l00
NOTE : Scale column in the drawing made up of piping details should be entered with 'none', and scale column in the drawing made up of piping sections and details , should be entered with the scale of sections. 2.2 Lines to be used Lines
0.9 mm Full 0.8 mm
Application BATTERYLIMIT HWJ.'CH LINE line Pipes and flanges ZB up to l2B (single line), section of steel structure, ZB and larger in isometric drawing.
Pipes and flanges
I
'
I I
l.l/ZB and under I (single line), pipes and flanges I 14B and larger (double line), ! l.l/ZB and under in isometric drawing, indication of valve handle.! ; i f
i
Full
line
Outline of equipment, structure and building, parts of piping such as valve, strainer etc., hatching of sectional area, dimension line, indication of platform floor and pipe insulation. Centerline of equipmemt and pipe.
0.1 m--
i f I 1
0.2 mm
or others limit.
I ! 1 I ;
w-m-----
Dotted line
Dnobserved portions of equipment structure, building and piping. Size of line should be consistent with respective full line.
34026 -38-
2.3
Indication
of
pipes
(Double
line)
Scales
for
piping
drawing
I/30 L g HE0
3. Piping
3.1
l/40
1150
l/80
lilO0
-qg3
- -2 14B
E[ti
z 16~
materials Pipe 3.1.1 Equation to determine or P(1006~)/2.6 the thickness of steel pipe (KHK.S 0302)
or
P>1006n/2.6 I+ c
( l-
lOO$J-P 1006n+p
t = Xinimum required thickness of pipe (mm) P - Design internal pressure (kg/cm2) Do= Outside diameter of pipe (mm) 6= Allowable stress of material (kg/cm2) D= Coefficient of pipe's longitudinal seam, usually 0.85, for SMLS 1.0 C = Corrosion allowance (mm) and dimensional tolerance 12.5 8 3.1.2 Pipes Typical Steel grade requiring pipes JIS STPG38,42 STPT38,42 STPL39 -. STS38,42 STPY41 SM41B STPA12 STPA22 STPA23 STPA24 STPA25 STPA26 Ni STPL46 to have postweld are shown ANSI A53GrA,B A106GrA,B A333Gr6 A524Gr1,II A139GrA A139GrB,C,D A335GrPl A335GrP12 A335GrPll A335GrP22 A335GrP5 A335GrP6 A333Gr3 minimum welded heat in the treatment table (PWHT) below. Remark
Carbon
Steel
Cr-MO
216 mm 212.7 mm 212.7 mm r: 12.7 mm 2 12.7 mm 212.7 mm 219 joints mm from cost
SCr-1Mo
3.1/2Ni
3.1/2
reduction
3.1.3 !
Pipe
selection
criteria
*. 1. 'Pipe
should be ected by using the attached sheet i! The following tables are actual data for in China. i material PIPE AND FITTING LARGE DIA. ST'D PIPE PIPE FITING FITTING 1 (PLATE) SDS316 & HIGHER f SDS316 & i HIGHER
i
i I
FITTING
BOLTING BOLT/NUT
MAT'L TEMP.(OC) L
CASTING
600 I 560
i -
I i
I -,
i j SNB16 or j A193Gr.Bl6 / ; A194Gr.4 !* ! SNB7 or jA193Gr.B7 / 'S45C or : Al84Gr.2H. ; S35C/S25C ss41/ss41 ! : ' i
or;SCPH21 :
; SCPHll
. SF45 or i S25C,S28C 350 ; STPG38 or : SGP. -10 ! AL-KILLED -46 '3.5 -102 ! I 18Cr-8Ni I
I
i 1 STPL39 I STPL46
Ni
SUS304TP
3402G
-4O-
3.2
GATE 18B 148 l2B 8B 6B 6B Special and and and and and and Larger Larger Larger Larger Larger Larger
GLOBE 128 and 1OB and 8B and 6B and 4B and 4B and Larger Larger Larger Larger Larger Larger
valve
(1) Valve provided with extension stem (2) Valve provided with lock (3) Valve provided with drain nozzle 3.2.3 Valve materiai Standard Kinds of steel Carbon steel Carbon steel (Al killed) Low alloy steel C-Mo-Cr-Mo SFHV12B SFHV22B SFBV23B SFHV24B
SFHV25 of
main parts)
Steel I <
Cast
JIS SCPH2 :: .
ASTM A216Gr.WCB
: i
SF50A(2) A350Gr.LF2
t
A182Gr.Fl
A182Gr .F12
A352Gr.ICB ---I A217Gr.WCl A217Gr.UC6 A217Gr .W6 A217Gr.WC9 A217Gr.C5 A217Gr.Cl.2 A352Gr .LC3
Gray cast iron Spheroidal graphite cast iron Black heat---cast iron 3.3 3.3.1 Fitting Bend
SDSF304 A182Gr.F304 SCS13A SUSF316 A182Gr .F3 16 SCS14A Gas, iron JJS ASTM A126CL.B Fc20 FCDS40 A395 FCMBs35 A47Gr.32510
(1) Bend should be used in the following a. Lines which are subject fluid.
b.
Downstream of pressure reducing valve which is liable vibration due to high fluid velocity.
to cause
3402G -II-
inside-cleaned.
Bending radius should be SD (D is pipe outside diameter). Allowance of 7% or more should be provided in thickness to compensate for the reduction of thickness due to bending. 1) High frequency -induction bending bending machine has dimensional
: ,:. .: . ...
Mitre bends may be used for lines 16B and larger operated at f 7 kg/cm 2 and below and temperatures of 260C and below or for ind larger operated at 10 kg/cm 2 and below and 200C and below, but the followings. (1) One-weld mitre ::. _, One-weld aitre bends should,& used for air compressor suction line operated at atmospheric Pressure, and vent line which is open to atmosphere. bend
.:. ._ :. :..,.I. . .:.:.. . .........,:. _,: : ..'.... .\.. ..,. _ .. ".::: _..:,.c 1. '. .Z..' ._ -. .: ,.I
bend
bend
Two-weld mitre bends should be used for low pressure process lines. lines 248 and larger, a nd for all utility
..: . .
1402G -42-
(3)
Four
weld
mitre
bend
bends should be used for lined and for all abrasive solids,
Four
weld
mitre
bend
The angle of intersection not exceed 22.S". Mitre Refer bend for .underground 'Dnderground
between
segments
of mitre
bend
should
(4)
piping piping'
to 8.14
3.3.3 (1)
Reducer Special reducers should be used or more for requires. vibration for high prevention. pressure. which in the sizes following down. reducer is not available. cases.
a. When reduced b. Lines c. When process 1) Diffuser 2) Special (2) Examples Lines of
line
standard
l.l/ZB
available)
~lC100 m/m and ldger When beam-to-beam span is 1000 mm or larger, top elevations of of pipe deflection resulting the beams may be the same, because from small diameter.
34026
-43-
Piping
with
shoes
Verticefl
line
CON. I
,.;.. . . ._ . . .. _.
....
.-~
Branched
connection
-ECC.
will
* But, CON may be used for not hydraulic-tested. Section 3.3.4 Tee (1) Wonrightangle branch connection drawing
lines
is made by pipe-to-pi& welding, the When branch connection amount of reinforcement should be determined, considering not and pressures of piping but also external only temperatures forces which will be applied to it. The angle of intersection between the branch and the run should not be less than IS".
Reinforcemnt rovided, if
be
Welded
pipe
to pipe
connection
340x
-II-
"(2)
Welded
Tees 16B and larger should not be shop possible, but should be field fabricated amount of reinforcement. 3.3.5 Standard Application 'Standard 3.3.6 Comparison application of fitting application of material of fitting should conform of fitting'. between
to attached
sheet
Attached sheet ASTM-material' Flange (1) The use of flanges flanged equipment
a. Where dismantling of piping is required. Dismantling at the time of construction. Dismantling for cleaning of piping. (2) bended portions in the piping requiring frequent cleaning (at least once a week) should be provided with flanged connections or provided with the bend whose bending radius is SD min. (D : nominal pipe diameter). Flange-to-flange length should be up to 24 meters when pipe'is cleaned from its one end. Sufficient flanges should also be provided for piping requiring occasional cleaning.
All
(3)
Sheet gaskets should be used for use vortex type. (Check P&I for
exchanger. flanges
Do not
(4) When M and F or T and G facing is used, equipment instrument flanges should generally be female(m). .__ -._ (5) When W and F or T and G facing is used, piping as to allow easy dismantling for maintenance.
or
should
be designed
so
34026
-45-
pe
.af
work
and nuts
and gasket,
by 'Piping
Engineer)
(men though there is a spec. break in P&I, they axe by Piping Engineer,
provided that mating
flange
is
covered
-_
Engineer)
5 (Pipe, by Piping
340X
-46-
b.
Connection
between
unit
equipment
and instrument
piping
by Piping
Engineer
unit equipment
(Instrument,by
Instrument
Engineer)
and gasket,
Valvr,
by Piping
Engineer
A
/
Hanifold (For manifolds, information of main dimensions etc. should be provided by Instrumen t Engineer, and detail design and procurement by Piping Engineer.
by Piping
340x
-47-
(2)
When nonstandard flange connections between unit be as follows : In cases, only bolts
connections
equipment
are
used, should
a.
and nuts
are
Unit equipment
Sa y valve, by %I strument
e
Engineer
Engineer
.
by Instrument \
Bolts
and nuts,
Gasket; by Piping
Engineer
by Mechanical
Stud bolts
(Pipe
or instrument)
Mating
b.
In cases,
only
gasket
is nonstandard.
by Piping
Mating
and nuts,
3402G
-48-
c.
In cases,
only
connecting
flange
is nonstandard.
Unit equipment
$5
of combination attached flange
bolts
Engineer
and nuts
and gasket,
(Pipe
or
instrument)
d. (3)
of directly
a.b.c.,
to be consistent
with
the
above
to the
flange,
nozzle bolts
of
unit
Blind
and nuts
by Mechanical
Engineer
(4) Notes
a. Though above mentioned scope of work is a standard practice, cofirmation of the scope should always be made by Piping Engineer. b. In cases of rotating equipment or aluminum carefully for flanges which art officially in R-103 or flanges having larger thickness or strength requirements.
When welded
heat exchanger etc., check standard but not covered because of manufacturing
c.
joints are used, attention should be paid to the dimensions of inside and outside diameter of pipes, their tolerances and end preparation etc. connection of two pieces of equipment who is the originator of bolts and nuts design is required for reformer the originator of such equipment is made, and
t.
3402G
-49-
instrument between instrument of work for piping vendor's piping engineer and piping materialsg, which engineer is agreed should be by them . .I'. : ;,_ .-. : . :. ,.
general, matching joints art made by welding. Attention should paid to the dimension of inside and outside diameter of pipes, ir tolerances and end preparation etc. Mction or confirmation should be made without fail ts, support points, displacement etc. in relation ss. I with customer'6 equipment and piping made by welding. Attention should and outside diameter of pipes etc. Special fittings shduli be : _.I, : .:. I ,I: - _ .:. ,. ,.,..:.. :.: ..::'.-- .. :.,g:-. ,__ .. ., : I :.: .:. :. ..- . ... .. ..:. .: :.....' ... of anchor to thermal
neral, matching of pipes are id to the dimension of inside tolerances and end preparation ed where required.
?r Supply equipment, when connected with TEC's piping should >fully checked for flanges and pipes not covered in Hll.03. ges not covered in R-103 are used, Buyer should be request& Ly their mating flanges. The confirmation of the above !d should be made without fail. : .-. :..
2.1
Scope
of
,rpplicat
ic+l 800{: or
;tfot. insul,\tion shou..lj be appllc!d for equipment/piping of nigher terclberature, exlcuding chere heat loss is fzjrorable. lh->t insulat .iOn should be appliec for lr*ter temperature, whtzn necessai*,y. Equipment an: its part:, shown below equil,ment/pipil\T of
(2)
800~ or
.,. .. _; \ ..-.
(3)
should
ilot
be inntllated.
a. Boti\?r,
b.
Expl,?sion mechanical
witL calculi\
the tion
case of of
ot JIS
A 95111.
general, :ign
operati.?g
tem\h?rature,
rotec
rsulatici\ should bc applied tor equipm?nt/piping emperatXlre, exclutling where .Yeat absori)tion
is
ulation should be applied for equipmel\t/piping ai: 50~ or !mperatr\re but uncttr ambient temperatul,e, in ordr?r to :ondensat:ion of moisture on the surfact? when : \sation sation \rould caust electric damage danger. tcl the equicllent.
\+Duld caustl
:ection If application nt/PiPin9 of 65C or higher temperature, liable to be rd by operators during their work, should be hot-insulated iolated by protective means, in order to prevent ~1s burn , when the equipment/piping is located: 800 mm above 00 mm from grade the edges or floor. of platform or
walkway.
.: -.-:: . . . :.:
; I .,: :.r.-
..
application
rack fed.
columns within hazardous area should The extent should be up to the first intermediate transverse beams -should .'.
be
transverse not
be
al or ed.
ure ures should be fire-proofed, where the structures are .L. of a process unit handing flammable liquid, or Elapse of the structure can cause severe damage to Init. The fire-proofing should be for columns only, ting from foundation to 2nd floor.
: . .
: : _.
..
.,
:-.
.-
Support
structure
for
furnaces
furnaces should be fire-proofed, unless Support structure d s for the furnace handles-only non-combustible fluid or there is only hydrocarbon vapor in the tubes. Even when the furnace handles only non-combustible fluid or there is only hydrocarbon gas in the tubes, the support structure should be fire-proofed, if the structure is within 6 m from a. furnace whose structure is fire-proofed. The fire-proofing should be for columns only, the extent being from the foundation to bottom of the furnace. Horizontal beams should not be fire-proofed.
:..
.: : ;. :
.2 (1)
Design
:
:,
. _: :.: ._.
.. .
Fire-proofing
Structural steel
lining
and
should .
vessels be covered
50
protection Scope of application for noise protection should be applied pipk,ng of compressors or other similar valve and its downstream piping). the of
job.
. .- . :. .
._ ,.
(2)
scope
of
application
should
be
decided
on at
-53-
:,
5.6.2
Design (1) Noise Glass protection wool, rock material wool, hard *. cement, etc.
6. Noise 6.1
and vibration Noise 6.1.1 (1) General Purpose Noise of control noise control be made for the purpose of:
should
safety,
distraction to noise.
of operator's
attention.
protection
at
the
Select
b.
Layout should be such that equipment/apparatus producing large noise is located away from areas where regulative restriction severe, or located behind a building. Under certain circumstances, it may be necessary to: 1) attach 2) wrap 3) provide
a muffler
to
the of
source with
of
up the
source
sound
protection of
around
source
with
shielding
of
building
done,
l L
3402G
-54-
(2)
When customer's
done,
observing
is non-existent, as a rule in
design general.
should
be
Location Area work Inside of B.L. Walkway, and Area where maintenance done frequently during operation Operation maintenence operation. Control Outside of B.LOn the boundary line of complex 1 (In view work area, and Area where work is done constantly room, and Office the plant concerned) the whole 1 , work is visited is done occasionally, occasionally. and Area where
during
of only
1 60dBA j 65dBA II
34026
-55-
..
sources of noise Kinds of major sources of noise are as follows. Specifically, measures should be decided on, at the stage of job. Kinds of source of noise
I
Classification ,l. r 2.
1.
I Cycle(*l)
I -
LIX?diUIp-
hxqh high
-
Machine proper
3.
A 1.
,
Blower
PM1 uw&a.raJ i n tnwar cs*
5. 6. 7.
Driving
F=t
1.
2.
Exhaust to
G-8.
1.
2. 3.
1.
2.
Piping system
medium I1 arae medium I medium low large medium medium large hiqh mediumme-urn high lame I 1 high large high small high medium mediumhigh large high large
low
(*2)
high
"
large
PipiqJ
2.
parts
Piping
3. 4.
c 3. 4. 5. 1. 2.
3.
Butterfly valva 1+3) Restriction orifice (*2)(*3) Ejector . Steam desuperheater Noise from rotating machine Noise from piping parts
I Combustion
3ther s : (*l)
High speed flow friction noise 1. Furnace 2. Boiler 3. Flare stack I 1: Transformer 2. Vessel 3. Air compressor suction port
medyy x large mediurpmedium xrh high I large high large med umhigh i arae high large hign medium iOge-aum I med=s low-- medium I medium low large low small high small high large
Note
Values of cycle and noise energy shown in the table apply only in general. They are subject to change according to the size of equipment, etc. (*2) Noise is produced when shock wave emerges. (*3) Noise is produced when cavitation occurs.
3402~
-56-
6.2
Vibration 6.2.1 (1) General Purpose Vibration a. b. c. d. (2) preventing preventing vibration. establishing without any preventing Vibration For the supports a. b. c. d. e. Isnt of vibration countermeasures should stress of due be provided to vibration. performance operators vibration. can due run to the plant for the purpose of:
countermeasures excessive deterioration circumstances anxiety. public prevention purpose should there any nuisance design
of start-up) possible to
vibration,
by one with lesser vibration any need to provide straight any need to increase thickness?
any vibration?
f.
g. h. . i.
Isnt it possible thermal stress is Isnt Isnt there the any piping
absorber,
in
the
case
where
fear liable
34026
-5-f-
6.2.2 (1)
Vibration
of piping requires consideration of vibration countermeasures of vibration which should be taken into in the piping design and the causes of such as shown below. refer to '6. Loading Condition and Allowable Stress' load.
Piping which Major sources consideration vibration are Furthermore, for vibration
Fluid
Source
of vibration rg pump
vibration i ! ! I 1 (*5) ! ,f I t jL 1
Gas, Steam
Lntrifugal pump Restriction orifice -Butterfly valve, Gate valve Centrifugal pump Gas/liquid mixed flow Others Reciprocating compressor Roots type blower Centrifugal compressor Blower Restriction orifice Pressure reducing valve Safety valve Steam line IOthers Wind
(*6)
Discharge counterforce Water-hammer Wind pressure, Karman vortex, Vibration of fixing point Vibration of fixing point
natural ; phenomennon I
Note: (*3) (*I) (*5) (*6) For pumps which are liable to surge at start-up, vibration prevention measures should be planned in advance. This is liable at high speed liquid flow. Two-phase flow lines are indicated specifically by Process Engineer. Shock wave emerges when downstream pressure is lower than l/2 of upstream pressure.
34026
-58:
.
(2)
Pipings
which
require
attention
with
regard
to resonance in
Major sources of vibration which should be taken into account the piping design in order to prevent resonance and conditions for occurrence to such resonance are as shown below. Fluid
Source
Conditions
for
resonance
] t I
Reciprocating Roots Liquid Roots type meter Thermowell Reciprocating compressor Gas,
Roots
type
1. Coincidence of frequency of pressure / pulsation and natural frequency of liquid column--pipeline (liquid column resonance) 2. Coincidence of frequency of pressure pulsation and natural frequency of piping
system
type
blower
steam
I Thermowell
I
(3) Vibration
1. Coincidence of frequency of Karman vortex i natural frequency of thermowell 1. Coincidence of frequency of pressure pulsation and natural frequency of gas column--pipeline (gas column resonance) 2. Coincidence of frequency of pressure pulsation and natural frequency of piping I system Il. Coincidence of frequency of Karman vortex natural frequency of thermowell * I caused
by
and 1 ;
i
I( 1 and, I
of equipment
Equipment shown below is liable to vibrate designed properly. This requires particular the piping design.
Equipment Centrifugal Pump Centrifugal compressor Turbine 7. Cathodic 7.1 Ascertain accordance ascertain
' Causes
at piping
1 Causes
at equipment of shaft coupling ; I of of rotating protection shaft shaft coupling coupling shaft I 1 I
Excessive nozzle cunterforce Mixing-in of air Insufficiency of EPSH (incl. unbalanced flow) Excessive nozzle counterforce Excessive nozzle counterforce Mixing-in of drain protection and grounding for static
Cathodic
protection
7.1.1 Object of its application and related laws and regulations whether cathodic protection should be adopted or not, by ITB or in with the customer's requirements. When it is to be adopted, about any related laws and regulations. 7.1.2 Consideratins Major Spec. points H-119. required in design should based pH of
be as
of consideration
follows.
values
For
details,
refer
to Eng'g (1)
Detail design should be made, specific resistivity of soil, obtained by site survey, etc.
which
of are to be
3402G
-59-
(2)
It should be decided on in early stage, which of the impressed current system and galvanic anode system is to be adopted. extent about of cathodic any place of protection electrical current should discontinuity. system and galvanic anode
be
shown clearly.
between
table
impressed
the
shown below.
A COMPARISON OF GALVANIC ANODE SYSTEM AND IMPRESSED CURRENT SYSTEM IMPRESSED CURElNT SYSTEM In this system, the negative pole of the external D.C power source is connected to the structure to be protected and the positSve pole to the electrode immersed in the electrolyte 1. Can be applied to a wide range of structures including, if necessary, large, uncoated structure. 2. Use is less restricted by the resistivity of the soil or water. 3. Requires relatively simple controls and can be made automatic to maintain potentials within close limits despite wide variations of conditions. 4. Requires generally a small total number of anode and long life. 1. Requires a main supply other source of electric power. 2. requires structures
DEMERITS groundbed
GALVANIC ANODE SYSTEM In this system, anode metal of lower potential than that of structure to be protected, is connected directly or with lead-wire to the structure
OF
OUTLINE SYSTEM
i ! !
MERITS
of any power.
2. Their usefullness is generally restricted to the provision of local protection. 3. They are less likely to affect any nearby structures because the output at any one point is low. 4. They are relatively to install. simple
to
structures
to be assessed.
1. Their use may be impracticable except with soils or waters with low resistivity. 2. Their output can not be controlled but there is a tendency for their current to be selfadjusting. 3. They maybe required at a large number of positions. Their life varies with conditions so that fill up the anode may be required.
; * I f
3402G
-6O-
7.2
Grounding (1)
for
static of
Grounding
piping
any flange connection of the made of insulating material, with bonding wire (conductor)..
is connected by bolts or the flanges should be provided bonding should be made be made at the place which are welded to
b. When bolts are not made of insulating material, for each 30 m length pipe and grounding should of the bonding. c. d. Bonding flanges. wires should be connected to lug plates They are not to be connected to bolts.
If length of piping connected to equipment is 30 m or shorter, such piping should be deemed as a part of the equipment and, therefore, bonding and grounding are not required. reference) Dangerous electricity. 1) Petroleum products 2) Ether, Formic fluid which Class Class
Class
(For
a.
are
liable
Carbon esters,
disulfide, Pyridine,
Collodion, Chlor-bensol,
etc.
3) Powder which can cause disaster non-conductive powder (systhetic contained in pneumatic conveyor b. Notes - Safe about flow electric velocity flow pipe charge
for charge
(API) dia. is
charge
is
when velocity
340X
-61-
(2)
a.
Standard Bonding
practice between
of pipes
installing
lugs
Lug for
bonding _._ -.
and
b.
Bonding
between
valve
and pipe
SW terminal
I V8mm2
Lugs' to installed c.
be
fabricated
Rack piping should be connected to grounding main, length of pipe. Rack columns should be treated in the piping.
30 m way as
IV14mm2
External damage protection pii= Not required when there is no fear of external damage.
Grounding
main
34026
-62-
pipe(L=30+thickness
of insUlation)
To fit Dimension of Lug 2) -Material When pipe material is alloyed be the same as ipe material. P design details Piping 8.1.1 around tower and vertical Layout arrangement around tower
t?
to tolt
size
SUS terminal
steel
.:
8. Piping 8.1
tank
(1) Typical
Location
,.L
\-
P 'iping
(Conde
to
' to eqti
3402G
-63-
(2)
Considerations
required
with
regard
to maintenance
are:
of filling work for reboiler of valve and tower enough area should
(using
pipe
davitl
of above, height
on grade.
can be affected
for with
reboiler flow-down (gravity flow line) tower valve, when reboiler of other neighboring
nozzle
refer
to
'Par.
3 Nozzle
Orientation'
8.1.3 (1)
Piping Height
around of
nozzles
of
tower
Elevations of bottom draw-off nozzle (X17) and drain nozzle (131) They are rather affected by the cannot be fixed uniformly. But, as far height of skirt, NPSH of pump and other conditions. the followings should be observed in order to have as possible, uniformity in each plant area.
In (*)
case
of
leg
To be decided on case by case, where considerations are required for NPSH of pump, headroom for operators (min.2100), and height of the destination point to which the piping is connected. of bottom draw-off line to pump, have least piping. of number of bends and
b. No pocket
C.
made in the
Location of supports and shape of the piping should be given careful attention, so that any undue force caused by expansion the piping will not be effected to the pump.
3402G
-64-
(2,
Installation
In principle, valves should be installed directly, so that drain cannot accumulate is shut. Drain here.
Cal-l
accumulate
tit
Qood
g-a
(3)
Flexibility
of piping by to
'. : ..
Attention.should be paid to the thermal expansion of piping When 'the piping is such that the feed positi& can be alterid changeover operation of valves which are connected respectively. -some number ,sf. Feed nozzles located at different elevations.
Loop
should
be avoided
as far as possible.
Supports and piping route should be planned with attention to any difference of expansion between the tower and the _piping, . caused by temperature gradient within the tower or dissimilar materials used for the tower and me piping.
Support
* G 4:5-
Piping connected to equipment should be of them due to wind etc., the procedure
11. Displacement due to force 1 extermal (wind pressure, / earthquake) ! :2. Displacement ; due to heat I
(2
alculation
\1
I Use
OUT
Iplanning
(Note)
Use of bellows
should
be avoided
3402G
-66-
(4)
Clearance
to
.
(5) Roundabout of piping
to have ring.
contact
In general, rising piping should pass vertical But, nozzle to which the piping is connected. the piping may be as follows:
the
Kin 4z
Min. Flexibility
Min.
BV should be provided at a place near to the nozzle possible. This applies even when there is &&&out piping. Supports should be provided in the vertical piping. (6) Reboiler
a. Outlet piping of reboiler should have least number of bends and shortest length, because pressure drop is critical in there. Furthermore, in case of thermosiphon type reboiler, attention is required because there are some restrictions with regard to the position of nozzle and the installation height of the equipment, in order to have proper circulation of the liquid. b. Because the piping around reboiler is generally of large diameter, careful attention is required to the thermal stress and the load effected to nozzle. Especially in case where there is stand-by equipment, spring supports may be used to support the reboiler, in order to cope with temperature difference between the operating equipment and spring support should not the stand-by equipment. (In general, be used, however.) 3402G -67-
(7)
Sampling
piping
Sampling nozzles should preferably be located adjacent to the platform. If sample nozzles are inevitably located at a higher level, the sample piping should be extended downward to the platform or grade, as shown in the Fig. shown below.
Sample Platform
connection
of
sampling small
piping dia. piping PDI, fire-fighting, in a group as far accordingly. platform 20 that
and other
Pipings for hose station, etc. should be extended so that tower possible,
as
it
b.
Hose station should be located at the does not interfere with manhole.
C. In case of especially tall tower, attention is required temperature difference between the tower and the piping, provide flexibility of the piping accordingly. d. Attention is tower top. required to possible movement of pipe davit
to any and to
at
the
3402G
-68-
8.2
Piping 8.2.1
heat heat
alphabetical
Steel
types
'4 e? pbe sheet k&'A stationary One pass Channel and remo+Sble--c&er Fixed Lii"B" tube sheet stqtiontiy shell
-------
Wo pass shell #ith longitudinal saffle F$xe$ sube sheet Fe2 C stationary Bonnet (integral cover)
------1 T
Split
flow
Outside floatinu
packed head
T 1
Divided flow
U-tube
bundle
*I ! LL;
&ecial pressure 3402G -69hi h cP osure
I UJCII
Kettle reboiler type
Considerations
required
for
arrangement
Where heat exchangers are installed side by side, coolant pipings and valve-operation positions should be placed at the same side of the heat exchanger. Space should be provided so that removal cover and tube bundle can be made easily. of channel cover, shell
(3)
(4)
In case of heat exchagers installed within a building structure where trolley beam or the like is provided, be avoided to have any piping running just above the of the heat exchanger. Piping should be as short as possible, unnecessary loop or pocket. without having
(5) (6)
Piping, when connected with a nozzle located far from the should be arranged under' fixed-side saddle of heat exchanger, movement due to thermal consideration of the heat ex de #ger*e expansion. Usually, the saddle at the channel side is fixed. .' t ..
. . . ..
Fixed
side
Sliding
side
(7)
valves,
blinds,
etc.
should
be installed
against
(8)
Consideration is required to have the shape of the which no excessive force is effected to the nozzle weight or thermal expansion of the piping, together consideration to have supports accordingly. Alteration of flow direction be done process nozzle, made by
in by the
(9)
When necessary, it can design, maintenance or direction, position of rating design has been
from the view points of piping requirement, etc., to alter flow for which etc. of a heat exchanger Process Engineer. a study alteration in can
However, such alteration should be made only after close cooperation with Process Engineer, since the affect the rating of the heat exchanger. Flow directions should be in principle such that:
3402G
-7O-
a. b.
flows
whereas
high
temperature
temperature
fluid
flows
are
c.
if the fluids passing through the heat exchanger are liquid non-condensable gas, and tube-.@ide is of multi-pass configuration, inlet and outlet' can be exchanged each other, shell side and also at tube side. If tube side is of single pass configuration, can be exchanged each other, provided that at both of shell side and tube side. Alteration of nozzle type
Or at
d.
this
(10)
Floor sxc
h
t Y&c
(B)
a.
b.
should
be used. of
it may require that heat exchangers is iarge, If there is any restriction height be increased. height, (B)-type should be used. example: installation height same as the
for
- When heat exchanger is to be installed underneath and any increase in the heat excha%er's installation would require unnecessarily high structure. - When heat - When heat c. exchanger exchangers is mounted are on a horizontal
the
structure height
vessel.
When (B)-type is used, this should be informed So this should be decided Mechanical Engineer. stage of piping study. - Dimension a should be decided on by Piping
- Dimension 'h' should be checked in accordance with the table of 'Drain piping dimensions for each type', which is included in 'Par. 9.14 Drain, vent'.
34026
-71-
8.2.3 (Example
Example 1)
of piping
around
horizontal
type
'heat
exchanger
..
:.. No p&icular
consideratio ration
of W.N. 2)
flange,.
this
s-hould
be make-up
size.
consideration operation
Piping to be removable (determined case by case) These lines valve to be symmetric when there is i~o in the lines
/7
34026
-72-
- Supply general,
operated
in parallel
should
be,
in
is
required
for
operation
of
Cavitation is likely to happen due to pressure reduction in the neighborhood of the valve outlet. Low insta we ferred llati .on level is
(Example
. by case)
Support should be removable (If not, inconvenience is incountered when putting blind or removing pipe) To allow of drain installation valve flanges In this support. rehoiler of reboiler's leg reboiler This pipe length (i.e. forces no changeover reboiler to operation) slide for the purpose case, attention of maintenance should be paid should be also for
Determination there
a. .Where
is no stand-by
.
3402G -73-
have
of of
of
vessel
31 Reboiler should be slidable in such a way that it can move sufficiently by the expansion force exerted onto the nozzle. We Teflon sliding plate.) ' 4) Check should - When r&oiler piping. be done for strength of the to absorb nozzle. the elongation of
is made slidable
plates sliding
Bolt
hole de .-.
Clearance of sliding - When there is no need to make reboiler need to have bolt holes slotted).
absorbed
Clearance
3402G -74of liner
required
(2Oumd
for
provision
L
In general, alleviating
to have
bellows
for
b.
is stand-by
reboiler
(i.e.
there
is changeover
height of leg, so that the elongation of +AL3 is equal to that of vessel ALl, stresses of piping and nozzle neck which the reboiler is shut down.
are
2) If the result of this check is 'out', increase the flexibility of the piping by altering the size or type of the reboiler after a study in cooperation with Mechanical Engineer, and recheck the stresses. the reboiler should be supported by If this is not possible, springs. In this case, check of the stress produced by load change (due to deflection) of the spring is required. (In general, spring should not be used, however.)
3) Arrangement symmetrical.
of
reboilers
and pipings
in
parallel
should
be
4) Route of the piping should be simple as far After that there will occur only small AP. been fixed, AP should be checked by Process 34026 -75-
(2)
Considerations of
in view
of maintenance
a. Removal
Provide
space
for
lifting
up
Here,
flanges
are needed
In case where one reboiler 'is put out of operation for maintenance while the other reboiler is under operation, consideration should be given for positions of valves and flanges (to enable removal of rehoiler's cover).
Area
for
removal
of
cover
Position *Provision
bf valve of flanges
(3) a.
Check
of
thermal of the
stresses elongation
around of
Calculation 1) Temperature
2) Calculate
when installed
= -5C
at max. nozzles,
the difference of elongations of vessel and operating. temperature, and check the stresses. see Par.b)
3402G
-76-
a. This is a kind of heat exchanger composed of a combination of elements, each being made up of two aluminum sheets and a wave-shaped fin brazed to the sheets ,. so that each fluid passes through respective space along the wave-shaped fin, and heat exchange accurs through the fin and the sheet.
b.
Merits
1) Compared with,shell and tube type heat exchabger, several to about 10 times larger heat transfer area can be obtained with the volume being the same. Therefore, it is very compact and of light weight. 2) Efficiency 3) It is of heat exchange is good .and loss .,
A^---
is
small.
because
low-temperature
service,
4) Various
5) When shape of heat transfer c. Demerits 1) Cleaning is free of dirt nearby. 2) Material
Therefore, it is used only for fluid purified by use of filter etc. installed is almost limited to aluminum.
of construction
34026
-78-
d.
Some number of heat exchangers in combination are housed and The space between the cold-insulated within a box (shelter). heat exchabngers and the box wall is filled with pearlite etc. for the cold-insulation and N2-purged constantly to remove moisture in there.
N2 inlet'
(2)
:..i..
of nozzle
ai
Access
area
Rack piping
1) If any equipment to which the heat exchanger is connected is consideration is required to installed in the neighborhood, have some nozzles at the side opposite to the rack, in view of thermal stress and allowable load of nozzles.
direction manifold
of
within
nozzle the
box,
of
.~Rack piping
b.
_..-. :: i
In general, platform and side. However, platform also so as to facilitate nozzles and retightening required
ladder should be installed at access should be installed at the rack side access to strainers installed at inlet of nozzle flanges. for piping .-
.43). Considerations a.
Because the allowable load of nozzle is generally very small, this load should be ascertained by reply from the vendor and consideration is required for arrangement of supports, accordingly. In addition to the above, because thermal expansion is unexpectedly differs from one heat exchanger to also be ascertained by reply from Because any welding avoid trouble, clips prior to shipment. displacement of nozzles due to large, and the fixing point another, these matters should the vendor.
b.
C.
on the box should not be done in order to for support should be provided by vendor to galvanic corrosion due to contact of
is
of
should
thick,
by should
is generally
Flange gaskets should be sheet'gasket, so that the flanges. (Check them against H-103.) h. Because, in many cases, filters consideration is required for
not
mar
3402G
-8O-
8.2.6 (1)
Piping
around
air
cooler for piping of piping for the around air cooler, followings which are to is
Considerations
required
In many cases, several number of air coolers are combined In this case, consideration become one item as equipmant. required for uniform distribution of fluid flow. In the above case, header becomes very long and, inevitably, problem of thermal expansion becomes more apparent, requiring careful study in this respect.
b.
the
c.
Arrangement of piping should be designed in such a way that no excessive force or moment will be effected to the nozzles of air cooler. This is because, if excessive force or moment is effected, tube bundle would tend to warp, to cause trouble such The allowable force or as leak at the tube-to-tube sheet joints. moment is limited to very low value and these values are presented by vendor of the air cooler. Therefore, arrangement of piping should be designed, based upon so that requirements given calculations of thermal stress, etc., by vendor are sufficiently met. Vendor/purchaser should be clearly
around rotating around
together
with
scope
of
supply,
Piping General
pump
The followings are intended to supplement or revise the customer's requirements regarding pump piping and the manual TM-3074 (pump piping), and also to stipulate about the items ear-marked in the manual to be defined at the job stage. Therefore, matters other than the folllowings should be in accordance with TEM-3074.
t
be as shown below.
(See line-up
of
f402G
-al-
b. Height In case
of pump's
of pumps for
: ... .:
as a standard should
be
pump's
foundation
defined
for
each
Piping 1) Piping
around
pump should
be
as
shown below.
piping, an Suction line to have large dia. short length. {If small dia. long length, cavitation can occur.) , Provision of space for removal of 'rotor Adjustable support
,.
Not to use chain valve, in general. Valve to be at 1.8m or less from operating floor. (If higher than 1.8, Operation stage is needed.) PG to be seen fran the place of vlave Operation Spare for removal of rotor. No spare required depending on pump model
This foundation, if uneven settlement is likely, to be onebody with pump's foundation as far as possible
for
should without
be designed
shifting
impeller
34026
-82-
(2)
Fundamental
and discharge
pipings
a. End-top type 1). Arrangement with discharge valves in vertical when discharge pipe size is 2-6B). run (in general,
Y-type
strainer
At pump's main line, height of valve handle should b@ 1800 mm If it is higher than 1880 am, operation stage should or less. be provided. 2) Arrangement with discharge valves in horizontal run (in general, when discharge pipe size is 8B or larger). Increase this length when thermal stress is severe. Increase this length when thermal stress
is severe.
e . . .._.
T-type strainer
3402G
-%4-
d.
Considerations
required
for
2)
dia.
be installed
in
can stay
here.
tit
good
Not
good
good
3)
gate
stem
valve
posture.
should
preferably
be installed
in
its
can stay
here.
Large-sized Dia. (12B 1501: as a standard). Provide support so that no bending moment is effected to the valve body.
Not good
FJood
34026
-87-
pipe
(a) Approaching velocity Vm,, 50.3 m/s . fb) Pit width should be B2 &2D k) Distance between pumps should be B3 &2D
3402G -813-
Nominal
dia.
I
I
- --__ _
200 I 320-370 I
. _ -----I i ! I ! ; I I I ! I I 500 550 600 700 800 850 900 1300 1200 1000 i 1 ! i I I
i
_- _.._.__
300 350 400 500 550 600 650
1 1 I!
10 1
/
I --700 600 500 BOO 900 1000 ,1 17nf-l 1150 1020 92 - I [
200 220 250 300 350 350 400 600 550 500 750 700 800 900 1000
*.a
1 I I
i !
1 I 1 I
1Arif-l - _.v"
1650
1700
1
1
(1100)
1800 1 2000 1 .220 0 I 1 2400 I I 2600 1 2800 .. . - - 1 mm aeposltlon of sludge to cope with this should clearance.
1600 1500 1800 2100 2300 2400 1100 i --~. 1200 2600 1300 i 2800 j 1950 1400 3000 2100 1 I on the pit floor is anticipated, be added to the dimension of pit
i I : 1 1 i !
i allowal floor
ace
Item Bellomouth dia Pit floor clearance Immersion depth Back wall clearance Pit width Distance between pumps D C s Bl B2 B3
(Note)
1.43 - 1.33d 1.5 - l.Od 21.5d sl.5d __.-I I z3d I z3d I Where two figures are shown for the ratio, to small dia. and the rigth to large dia.' suction bellmouth is provided.
I ;
Ratio
to nominal
dia.
I f I f
i
the
left
I corresponds
When inclined
3402G
-89-
When suction -v
pipe is horizontal.
c SZZ3d b I4 \ I, (1
C2 ll.Sd t
D-1.43-1.33d
(3) Suction
strainer
for pump
Because there are two kinds of strainers - one necessary in view of process (permanent) and one necessary when the plant is not under normal operation (temporary) - the kind of strainer should be ascertained by reply from Process Engineer. a. Permanent :. 1) !&eof-.such strainer is shown on P&I dia. '- .. ; .. 2) When' size is 3B or smaller, Y-type should be used, and when 4B or larger, T-type. b. Temporary When size is IB or smaller, 6B or larger, T-type.
P&I -
conical .
desianation
.
Type
-b
TR
34026 -9O-
(4) Method
of
attaching
pressure
gauge
In case
of one pump
In case
In
case
of
three
pumps
be adopted
be
at
the
c.
If pressure gauge contacts with any above-located piping, direction of PG take-out boss should be turned 45O toward valve operation side {so that the pressure gauge is still visible). Pressure the
gauges
d.
should
of
be located valve
within
the
range
of
vision
position s1.1/2B
discharge
operation 2B--3B
and also
from
size
should
be
specified
to have
-91-
(5) Cooling
water
and drain
pipings
for
Pump-bed drain (Material by Piping Dept) I When to be discharged to outside - Base drain should be led to oily dictated by the kind of fluid. - Casing liquid drain drain sewer
Casing Drip
drain funnel
or chemical
sewer,
as
should be led to oily sewer, chemical line (as indicated in P&I dia.).
sewer
or
34026
-92-
(6) a-
Examples
of piping
for BEW
pump
around
(for
pump referance)
piping
III
It
bmass
Ylkintenance
area
rl-
at
trt! gic
easily Maintenance
accessib
area
. t
cl-
b.
Piping
fo r turbine-driven
BEW pump
(for
reference)
Turbin
H
Steam exhaus t Pipe Oil rkf piping
34026
-94-
c. Oil piping
for
Drip
funnel
.J$pQy
'
(Notes) 1. FQ~ high pressure pump, oil cooling unit as shown above is provided. i. When the pump is turbine-driven, gland condenser is provided in addition. 3. In such-cases as this, although many small dia. pipings are attached, maintenance or operation work ehould not be inconvenienced by these pipings. Consideration is required in this respect. 4. Oil piping belongs to the scope of vendor's supply as a unit piping. Because, in most cases , the vendor's piping drawing is made without consideration for actual condition of gurroundings, check the vendors drawing and ask revision, if necessary, in order to allow convenient operation and maintenance. 8.3.2
a.
Piping Piping
driving
Exhaust pipe
/ (During -
k
f%ee to five drain pipes \ (3/4B or the like) come from turbine. w
steam' is
large quantity
warming
UP,
0:.
exhausted.)
\
c
~'U~yqTiJ \ I L \)
PUMP
1 ,fl';-.xr+taln
valve
2G
-95-
Spring./-support
Trap
b.
of
piping
around
the
3) Determine the counterforce and moment through calculation of thermal stress hot). 4) If the counterforce carry out design of for
and moment are within the allowable springs and place order of them. design of support structure and
drain
water
pipings.
material
drawing drawing.
and material
take-off.
Piping around .compressor :: .Design standard for piping around compressor is as shown in iiere, matters not coverd in TEM-3069 will be explained. TEM-3069. (1) a. Considerations required for piping design instrument should be at
On the suction line, position of pressure downstream side of suction strainer. On the suction side of suction If drain fail. pocket line, position strainer. can be produced, of therasowell
b.
should
be at
upstream
c.
provide
drain
valves,
without
d.
Piping above the compressor floor should preferably be once brought to under the floor, so that operation and maintenance flange connection should be works are facilitated. In this case, provided in the piping, ao that compressor casing can be removed easily. In the space under the compressor floor, the process piping, oil piping, trace piping etc. are to be placed, tending to become congested. It is recommended to design routing of the whole piping by allocating.different elevations to different kind of piping respectively. It should be avoided to have oil or other high temperature line. occur. ) Vent
not
e.
f.
line /If
g.
line of oil system should be free from pocket, and should have configuration such that gas cannot be vented due to piping weight or thermal expansion. When this is feared, the support span should be shortened or, if it is convenient, the line should be provided with slope. It should compressor be avoided
room.
h.
to have
exhaust
from
trap
etc.
in
the
3402G
-96-
i.
Selection of material and study of strength for the strainer should be done so that it has sufficient durability for 100% load. Furthermore, the strainer composed of perforated plate and wire mesh screen should be installed in such manner that the perforated plate comes to downstream side in view of gas flow. The wire mesh screen should be of 8 - 10 mesh as a standard. Considerations required for making civil information around the etc. should be will not be
(2) a.
Floor of compressor room and maintenance platform compressor should be separated, or rubber cushion employed, so that any vibration of the compressor transferred to the floor. Maintenance platform should removable. When penetrated into two or three parts.
b.
c.
In order that maintenance work on large valves located below the floor can be done by use of overhead crane of the compressor room, provision of hole with removable cover in the floor should be made. around furnace required in general in the used when
8.4
Considerations
It should be avoided to have any obstructing piping neighborhoods of walkway and peep holes, which are operating the furnace. Enough space should be provided for removal of
(2) (3)
burners. consideratin
Piping around the furnace should be planned for its relation with heater tubes. Relation Relation removed. between between (Space outlet/inlet port of heater
under
a. b. c. d.
tube
heater tubes and the piping when for removal should be provided.) between heater heater tubes tubes and the
by each flange
and piping
8.4.2 (1)
Outlet piping of heater is, in most cases, made of alloyed steel because of its high temperature, this requiring that the length be short as far as possible. Consideration is required for flexibility of the piping and also for proper supporting of it.
34026
-97-
(2) Arrangement
of
transfer
line
(for
8.4.3
piping gas piping of fuel gas feed piping so that uniform header, in should be made at the top of distribution can be obtained. fuel gas piping for iso-flow
ad&
drain
fixed to Header is installed at outside of heater , on brackets valves to be operated at the heater's legs. In this arrangement, the time of ignition are not in the range of operator's vision. But, good flow condition can be obtained and construction is inexpensive. Because the valves operated at the time of ignition not used for the purpose of control, but are are, in general, used in either full open or full shut condition, it is not so much of problem, even though they are not within the operator's vision.
34026
-98-
Control
valve
drain
Gas manifold
A header box, which is used as drain pot at the same time, is installed at underneath heater , and each piping from there is connected with burner. In this arrangement, because the header box is at the center area, enough space is left in around the heater. This is advantageous because of its ease of operation. On the other hand, however, in this arrangement, operator must stay for a long duration of time beneath the heater at the time of ignition or shut-down.
der
drain
A header is installed around the heater at a height just above peepholes and each branch piping goes down vertically in the vicinity of the peephole, to be connected with burner. This arrangement is especially advantageous, because these valves can be operated well within the reach of operator's vision. However, this arrangement is expensive in view of construction material and work required. * Header drain should in order to prevent (2) a. Fuel oil piping piping coming if necessary, from the tank should be made so that excess oil circulates not fire be opened hazard. in the vicinity of the heater,
34026
-99-
b.
Example
of
fuel
oil
piping steam
around
burner
(for
reference).
Atomizing
Fuel Peep ho le
Regulation valves for fuel oil and atomizing installed at places where operator can oprate valves while looking at peephole. (3) Installation of block valves and regulation
a. Block valves on the main fuel oil and fuel gas piping leading the furnace should be located at a place 15 m away from the furnace so that rapid operation can be done in an emergency. (except where EmV is provided) b. Regulatioh valves for piping leading to the below. fuel oil, fuel furnace should
gas and atomizing steam be installed at places shown in in the the vicinity vicinity of burner, of burner.
- In case of wall burner type furnace, where peephole is conveniently seen. - In case of floor burner type furnace,
8.4.4
Snuffing
steam
piping for combustion chamber space of furnace arch. these can be operated
(1) Snuffing steam piping should be provided of furnace, for header box and for upper (2) Arrangement at a place (3) Example of of valves away from snuffing should be such the furnace. steam piping. that
.I .I 1
line
Steam trap
3402G
-lOO-
8.5
Rack piping 8.5.1 General In general, followings. a. Lines apart lines which are run of side by side on the pipe rack or more
include
the
equipment
located
6 meters unit
going out to storage tanks or other heat exchangers, pumps etc.. of raw material (Flare lines). ducts. lines. plant air and instrument or other feeds.
plants
Instrument duct
Cable duct
e. Instrument f.
ducts/Cable
or more
feed water, city water, water other than those and gases, and others.
pure
of pipe
When heat exchangers are installed underneath the below, the height of the rack should be determined heighest portion of exchangers and their connected
(2) (3)
When double-rack is used, the distance racks should be 2000 mm, as a standard. In general, racks and plant-north-south heights determined in
between
the
tops
of
the
each unit, which are run in plant-east-west directions should have their respective with a combination of 4n/6d8m and 5m/7m/9m.
3426G
-lOl-
8.5.3
of pipes of pipes should be as follows: should be located to reduce bendi$ng as close to moments of
Large-sized pipes (14B and larger) the sides of the rack as possible the rack beams.
In
(2)
of
(3)
utility piping In case of double-rack, located on the upper rack and process But, large-sized pipes may be located of space. of location on single-rack
should generally be piping on the lower rack. on the upper rack in view
a. Example
Process Utilities I I
Process
Large SiFd . I
c x/d c
----I
Instrument
,b.
Example
of
location
on double-rack
Instrument
m-generally
for
u&it
piping
Lower
rack---
generally
for
proces
c: i. Ping
34266
of
the
pipe's
location
should
be as shown
in
the
Upper Side
rack Middle 1
i I
Lower Side
rack Middle I
Piping (Flare) feed feed product procuct lines lines lines 12B and larger 10B and smaller 128 and larger 10B and smaller and lines 0 I
l
I 0
1 0
1
I
0
I
!
lines lines
:01 :I 1 , 0
jo , I ,
Overheads of tower and drum connected to pump or heat exchanger Delivery Lines lines subject of pump
1
equipment and
ispecial A i I i i I i i t !
o I I
0
f I 1 !
o I 0
lo 0 I 1 10;
i" ; ; I I
Condensate Boiler Lines (water, Plant-air Headers Fuel oil of feed for
!O i
I I
Instrument
i i
I I 1 j
u u a
E
l
Instrument
ducts
IO
to I
is required
on the
Lines containing corrosive or cable ducts. instrument, Delivery valves, located vibration
34266
-103-
lines of reciprocating compressors, large-sized return water lines etc., should be given special on the rack, prevention.
of pipes and the position and type of anchor lines at B.L, should be clearly defined by with parties concerned. for the valve located and maintenance. on the
points
rack
the ends of utility headers should be blind-flanged, large-sized pipes (14B or larger, as a guide) should But, use of dead ends should be minimum, considering
(10)
When a loop is provided in condensate line it should be bent horizontally to prevent waterhammer. If it is impracticable bend horizontally, bend it as shown in the drawings below. (Example 1)
to
(Example
2)
8.:
(11)
Loops other than for condensate lines for good appearance as shown below.
should
be grouped
together
Lines should be laid on the rack in a sequence so that larger sized pipe or pipe having larger expansion and contraction comes closer to the side of the rack. (12) Piping should which is long have horizontal in length, loops. such as yard piping or pipe line,
34266
-104-
(13)
Dimensions
of
down-pipes insulation Be careful not to attach a shoe close to the weld line.
(In
general)
-Pot insulation a. In general, the location of down-pipes is indicated by the dimension of beam-center-to-pipe-center. But, the dimension be beam-center-to-pipe-surface, if required to facilitate supporting the pipes. I
may
b.
In general, the beam-center-to-pipe-center dimension is 500 mm, except for large-sized pipes in which the distance between outside surface of the insulation and the beam flange could be less than 100 mm or the weld line would come on the rack beam. Elevation of pipes pipes should be determined considering the height of
Insulation Th'k (mm) 25- 75 80-'125 130-175 180-225 25- 50 55-100 105-150 155-200
Height of shoe, cradlt;nmgaddle 100 150 200 250 50 100 150 200 100
Remarks Do not use shoe etc., for pipes with personnel protection insulation.
Cold-insulated pipe
Bare
pipe
Only for special design such as lines exceeding allowable span in Pipe List, or lines requiring vibration prevention.
8.6
Critical 8.6.1
lines Critical Attention lines should such in view be given line surface in such as: condencer. lines as: of pipe to the strength. following.
(1)
Vacuum of Piping
(2)
Thermal
a. Piping
steam
desuperheater
b. Condensate
34266
-105-
(3) Vibration
due to shock
waves
in such
line
The line downstream of pressure flow bypass line of compressor. (4) Erosion Decoking (5) Cavitation of such lines lines erosion of such line as:
reducing
The line downstream of restriction bypass line of boiler feed water (6) Two-phase Line flow in such line as: Engineer.
indicated
by Process
(7) Vibration Effluent (8) 8.6.2 Others Critical Attention (1) (2) (3) (4) (5) (6)
(7)
or earthquake
in such to the
lines
as:
header.
lines should
in view
be given
Pump NPSH Thermosiphon Lines Gravity Lines Lines Lines Lines requiring flow which subject for
urea
of reboiler water
or sloped
exchanger.
pressure or slurry
drop. etc.
which
solidify.
requiring
Lines subject to special design conditions in the pressure or temperature , or repetition Lines for selection
for which the piping material caustic soda wr the like, is strictly dependent on its operating temperature.
34266
-106-
(11)
Lines
in which of
flow
is allowed.
a. Examples 1) Branch
such
lines
valves.
(Fuel
feed
line)
2) Heat
exchanger
piping
without
valves.
Flow
is
not
regulated
with
ow is
regulated
with
valves
3) Piping
around
three
heat
exchangers
without
valves.
symmetrical
piping
3426G
-107-
4) Piping
around
reboiler
usually
by vendor)
Main
stop
valve
3426~
-108-
b. Branch
lines
in which
uneven
flow
is prevented.
Type
Type
'B'
Type
'C'
Type
'D'
I 3
Type E
(t
\
Type F
8.6.3 (1)
Critical Large-sized
lines
in view
of cost.
piping
(2) Piping which is high in cost, such as for high temperature and pressure service, SUS pipes and pipes of special specification. Cost comparison of higher cost should be made for should have priority these pipings and the in piping arrangement. piping
34266
-109-
8.7
Piping 8.7.1
around General
safety
valve
Safety valves act automatically so as to prevent a predetermined thus internal pressure is maintained and pressure pressure being exceeded, vessel is protected. Safety valves are classified depending on fluids to which they are applied. (1) Safety For (2) Relief Mainly (3) valve and vapors including air and steam.
gases
valve for liquids. valve vapors and liquids. the term 'safety valves. safety valve should be installed in the piping close safety valves connected to the flare close to the rack as shown below.
valve'
is used
for
all
of
the
8.7.2 (1)
Inlet
piping
of
safety valves In general, to the top of tower, but system should be installed
to
rack
valve
I
34266 -llO-
Pressure drops between equipment and safety valve 0.6 kg/c& or less 3 % or less of safety valve set-pressure
inlet line to safety valve should be equal to of the size of inlet flange of the safety vlave. lines, drop consult is larger Process than Engineer the allowable to check limit, for try as
(3)
should should
so that
they
are of
for
a. Ample body.
dismantling
I+- Clearance
for
adjusting
Lock
bolts
c. When difficult to have access, used. But the platform is not pipe rack, which are accessible. (4)
ladder or platform should be required for places such as on the at a place where a
34266
-ill-
(5)
valves should not have Inlet lines to safety off them, except when the branch line is for
taken
(6)
to safety valves should be taken off the as colse to the anchor point as possible, vibration or thermal, movement is small. point
portion where
Of
Support
Welded pipe-to-pipe connections between valves and main lines should be provided after determining the pad, if required, discharge.
(9) TEM-3058 should be referred to for checking the inlet piping reaction stresses at the header nozzle portion and the safety valve portion.
for
3426G
-112-
8.7.3
line
of
safety
valve
of discharge lines of safety valves should than that of the valve outlet flanges. to be used into in the the discharge line should
be
be
equal
to
Elbows
of
long
radius.
(2) Discharging
atmosphere
a. Safety valves, which discharge poisonous fluids (including N2) or flammable gases to the atmosphere through vent piping, should have the pipe extended at least 3 meters above any platform or roof within a 12 meter radius of the point of discharge. Safety valves, which discharge steam to the atmosphere, should have the pipe extended at least 3 meters above any platform within a 7.5 meter radius of the point of discharge. 12oC0, 7500 ,
Top of platform
b.
Relief valves, which discharge poisonous liquids directly atmosphere, should have discharge piping provided with a protective device in order not to drop the liquids directly the ground. of discharge pipe
to the on
c. Cut angle
In general,
this
type
should
be used.
To be used only when the direction of Because the discharge is limited. direction of reaction force changes, the nozzle and support to be carefully Not to be used checked for strength. high pressure of 100 kg/cm2 or higher, in general.
for
3426G
-1l3-
two or more discharge lines of safety d. In general, not be joined to the header close to each other. But, if required, they may be joined as shown in below.
valves the
should
drawing
Cross-sectional area of the header should nat be less than the sun-of cross-sectional area of the pipes to be joined.
(3) a.
Plare
system piping in flare system and should be drained should be routed into the headers. so as not
b.
Vert.
c.
Discharge lines of safety valves should be connected header at the point as close to its anchor points as If this is impracticable, the discharge lines should sufficient flexibility to absorb the movement of the
34266
-114-
d.
Discharge lines should be connected to the header as follows: Liquid or drain lines are on the top of the header. The angles of intersection are 45O for 2B and larger and 90' for l.l/2B and smaller. All branched connections on the top or side of the header should have provision for flexibility.
1.1/2B-and
smaller
safety
valve
Steam piping Discharge I Support (To be supportedseparateiy from the valve body) l
pipe
3m or more above workng area
Safety
valve
w el bow
(Only 1 20K steam. T' Y Notes: 1. The pan should be separated from the discharge pipe. 2. Material of the pan should be equal to that of safety valve outlet pipe. 3. When the piping between safety valve and pipe support such type as shown below may has sufficient flexibity, be used instead of the above type.
3426G
-115-
I
A 2.1/2B 38 48 5B 6B 188 1OB I~ I 128 48 48 6B 88 88 1 10B I 12B
' 1 14B
Table
of dimensions C(PIPE)
h/m)
B (PIPE)
D 200 220 250 300 350 420 I 500 I 580 540 1 580 610 . 690 640 720 1 350 1 210 400 400 500 560 250 280 360 440
650 1 520
Method
of
supporting
.er
than
To be slidable
(2)
Piping
for
other
than
steam
out
of
po=g,i,o h
discharging rll Reaction force of discharging Check
far
nttenath\
nozzle
increases increase)
To be slidable
($)..;
L<4D
To be piped to the grade, in case of poisonous gases or liquids. (TO be piped to flare system, in case of flammable substances.) Only a hole, in case of innoxious substances.
34266
-116-
8.8
Pipi*
wound
instruahAB
8.8.1 (1)
Instruments should be installed in places operation and maintenance. Platform or ladder should be provided, if (3) Size of instrument Sizes 3/4B PIG I 3/4B 3/4B
1.428
which required.
permit
ease
of
Remarks Piping, I Places Dirty Ditto free places vessel and H.X of dirt vessel and .B.X
I l.l/ZB 3/4B
2B
I1
I Piping,
In general Fluids
2B LI, LIC 4B
Gate
Float
Analyzer 3/4B
S.sC I
I Gate I Gate
lines
8.8.2 (1) a. b.
for (Except
general for
valve
use type)
to be 3/4B
valve
diaphragm
to be glove
34266
-ii7-
c. Installation
Connections should be taken off of vertical pipes. For vessels, connections should unless otherwise specified.
be located
siphon
tube
Lines
generally
used
Steam
line
(2) PdI a. Sise 3/4B l.l/2B b. Block Gate c. valve valve criteria Services Services free with of dirt dirt
of block valves at vessels may be made from ladder. Platform is required for transmitters because, in general, they are located adjacent to the block valve , in services on liquids or mist. However, the information, whether or not the platform is required, should be obtained from Instrument Engineer. ndzzleo for WI In general, 'should b+ located On vesse&s, but,'. &en they.-are 'taken off
the :'.
:-. .:. ::
l- I -%I
3426G -118-
Conform
8.8.3
instrument
Flanged type
1.1/28
flange
type
should
te :mper ,ature .t
Fl=qd
tyl?=
Boss-welded
type
(2)
and insertion
a/d ) 10 (Refer
Note:
34266
-11%
(3)
of
should aginst
6~ and larger
t a
3/4B-44B
1 -- ---q+p. L \
I CON
. . . . Vertical
line
34266
-120-
(4)
Location
of
temperature
The bottom end of thermowell should not come to the higher than the terminal portion, wherever possible.
Thermowell should preferably be located vertical line rather than the horizontal and should be accessible for maintenance.
Do not locate the thermowell Scale or the like is here'. liable to deposit in the gap between nozzle and thermowell.
here,
(Vertical
section)
Clearance
for
I 3 1200 -1300
/I/
////////f
1 / /
.. .
.: :: ._ .,:
TemperatiAinstrument
rU
at a junct.i&~'of
TIC
two flows
(Example)
in
P&I
point
of
34266
-321-
P
180~
8.8.4 (1)
Flow Orifice
instrument :
a.
Installation
practice
of
orifices should be installed In general, located 600 mm or more above the grade of inspection. Orifices may be installed in vertical dry gas or liquid if it is guaranteed completely filled with the liquid. the approval of Instrument Engineer. b. Type of orifice 1) Flange taps I type I (2B-14B)
ease
2)
Throat
taps
type
Upstream
.eam
tap
10
3) Corner
taps
type
34266
-122-
4) Flow
the
feed
for
high
pressure
steam
lines,
boiler
L----r 1.1 4 t 2,
-,----L--eL
By Instrument Engineer Dimension (For
II
b
aJ 0
reference)
5)
-LOSS
For
tube
of straight the
tube
pipe, for
refer
maintenance
used where I
pressure
drop
is critical.
34266
-123-
c.
Required
length
of
straight
pipe
for
orifice
The length should be determined depending on the configurations of piping and the diameter ratio given in JIS 2 8762. (Diameter ratio of 0.7 should be used as a standard, but, Confirm it by asking assigned engineer.) Minimum various required fitting length installed of straight pipe between orifice and upstream or down stream of orifice. _. _ --
:: ._I. .,
or
ratio 0.5 or larger whose diameter is smaller whose diameter is 1. When the'straight length is larger than that shown the expected additional error outside of parenthesis, is zero. 2. When the straight length is larger than that in parenthesis and less than that outside of parenthesis, the expected error in flow measurement is equal to the expected error for the len-gth shown outside of parenthesis plus 0.5%. The addition should be made as follows: )x100+0.5)% A( (m3/
Notes:
3426G
-124-
6. Dioection
of BC:ifice taps
1) Orifice taps should preferably be located on the horizontal centerline in horizontal pipe runs. (To be applied for all services)
2) For dry or wet gases, and where there are space limitations.
3) For dry gases and liquids , and where there are space limitaions.
sufficient side 4) When the condense pot etc. is installed, clearance should be provided between the pot and neighboring piping. Be careful,
Steam
-..
-.L" l,
\\\7.
at
34266
-12%
e. Location
of differential
pressure
transmitter center
In general, differential pressure transmitters should be installed on the horizontal plane which includes the pipe line, and located adjacent to the orifice. 1) For wet gases
Upward
slope
2) For
dry
gases
or
liquids
on the grade
or platform,
To be installed
::. : :_
To be installed
Location of differential pressure transmitters should be determined by Instrument Engineer. When operation stage is required, Piping Engineer should be informed of it by Instrument Engineer.
34266
-126-
(ECC or CON)
(Turbihe
meter)
(3)
Magnetic
flow
meter should be installed in vertical in horizontal lines, provided with the liquids.
In general, magnetic flow meters But, they may be installed lines. that the line is completely filled
(4)
Variable
area
flow
meter
...
Variable area flow meters should be installed in vertical lines. The installation error should be within 2 8 as against the vertical line. The indicator should be located at 1,500 mm or less above the grade or platform.
34266
-127-
a. Plow
meter
(Local Type.
indicaton
type) Type
2
Indicator
ff I7I-r 1
Indi
ator
b.
Flow
meter
(With
local
indicatipn
and
transmitter)
c.
Flow Install
meter it
(Tapered so as not
glass
to be affected
34266
-128-
(5) Positive
Install
support
displacement
flow
. f!!F
. . l . .I l I
8.8.5
Restriction
orifice
Type
type
a. Plate
b,
Socket
weld
TObe
used mainly
c.
Butt
weld
To be used mainly
34266
-129-
8.6.6
Liquid
level
instrument criteria
L/A)
level
normal
b. Location
of nozzles
1
Permissible of installation range
A baffle plate should be provided , if the liquid level is installed outside the permissible range because of construction work or other reasons. (2) Displacement
a. Side-side
instrument
tower, tank
type)
-. _..--
;; $3 II
Vindicator A
34266
-l30-
; :
b. Side-bottom
type
(3)
type
(Inside
cylinder
type)
this type should be installed on the top of vessels. be considered for reading and maintenance of the
,
for
removal
I. . ~
Guide pipe / Ample space for opening should be provided the cover.
34266
-131P
(4) Differential
a.
type
liquid
level
instrument Type)
Differential
transmitter
(bp/CELL
This
pipe
tobe
horizontal.
Engineer.)
(5)
.
Float
type
liquid
level
instrument
1.
::
Wire
hook
34266
-132-
float
body
tym
(Xn general,
be supported
not
to be used)
securely.
should
1/2B vent
1/2B
drain
.
Con&o1 general,
should ~
f
be provided/when z ~s~~cted
4-6B
(8)
Electrode
type
level
instrument
+ Clearance PI I
,fO?f
removal
34266
-133-
-IL
t B T
i
use) 0C or lower) (Caustic soda-solution) is required, and with the ladder or at ____
a. Reflex Reflex
type type
3/4B 2B type
b. Through-vision
For low temperature services, non-frost type care should be taken not to have interference platform. 8.8.7 (1) Control Installation valve criteria
Control valves should be installed on the grade, floor or platform so as to facilitate the inspection and maintenance any time, andw stages should be provided, if required.
Side handle, in preference to positioner, should be oriented toward maintenance side. . Contact Instrument Engineer when the valve with bottom for confirmation, flange is used.
Min.800 Min.900
For
be installed position.
(2)
Sizes
of
bypass
and block
valves
for
control
valve
Line
sizes
Bypass Valve sizes C.v C.v body body size size size as gate
size
should
control valves should be globe valve, for bypass valves 6B and larger. valve control piping valve.
(3)
a.
Arrangement
Standard
450 bypass
valve
position.
34266
-135-
c. Manifold
laid
on a horizontal
plane.
(Example)
L Easy to remove
d. Manifold (Example) In general, not to be used on the pipe rack.
e. Manifold
in which
the
line
goes
up from
lower
level
to higher.
(Example)
f.
Insertion
of
flanges,
is
joined
by welding.
34266
-136-
Valve
welded
Insertion
flanges
8.9
Control
valve
a. All the
from
steam
headers
should.be
taken
off
the
top
of to
should
be provided
in each branch,
adjacently valve
Lines injecting steam into process lines should have a block and a check valve, adjacently to the point of injection. Criteria for installation of steam drain
(2)
The following positions valve and pipe to the with steam trap. a. Ends of b. Drain C. Every headers of
of piping should be provided with drain sewers, where requiked, or should be provided
of control
valves
side of control valves (To be shown in P&I) draining steam lines operated
(3) Methods
of
a. Superheated
at
100 kg/cm2
or higher.
34266
-137-
b. Saturated
rteaa liner
or smaller.
2B-2.1/2B
l.l/2B
and smaller
(Sewer)
(Header)
34266
-138-
b.
Recovw
ing
type
valves
1) When recovering directly into the condensate header, block on the upstream and downstream sides of the trap, and a block-valved bypass should of provided. (Any check valve on the downstreamside of the trap should shown in P&I.)' To condensate
be as
2) When recovering upstream side (5) a. Steam drain Steam lines line
only a block valve on the into the sub-header, and a block-valved bypass should be provided. I
operated
at
100 kg/cm2
or higher.
Desuperheater
Turbine
Vent
stack
3426G
-139-
b.
0th~
steam
lines
Desugerheater
Vent
stack
installation
of
vent stack.
(6) Vent stack a. Installation The vent stack criteria is required for the following.
or
higher.
3)
Drains, when exhausted in the room. (But, not required, when the drain line Other portions conditions. requiring the vent stack
4)
34266
-140-
b. VS.9
(Vent
stack
where.H
Insulation
12x6~
Reducer
1.1/2B
C.
(vent
stack
large)
protection
Inlet from
of steam traps
Drain
l.l/2B
Note:
For
bolts, Detail
(7) Desuperheater
a. =YW
piping
1) Variable
area
type
Because.of high cost, this type should be used for import steam where there is a change of steam balance.
2) Atomizing
Steam
type
Because of low cost, this type should be used for general service, but not t6 be used where there is change of steam balance. is not especially required, b. Support because regerded as a part of piping. Desuperheaters type should be installed on the rack.
C.
desuperheater of atomizing
is steam
of straight pipes, bending radius, should conform to PC1 OK instructions shown drawing) Min.13m (Straight pipe) in the drawing below are
standard.
Notes:
so that thickness.
the
pipe
is sealed
with
water
at
3426G
-142-
(8)
Steam
ilencec
piping
of
When difficuty is found in the piping flexibility, the manufacturer should be requested to supply the silencer with a sliding nozzle.
Pipe should be sloped so as not to allow accumulation of condensate condensate. (Calculate elongation, and provide ,+ sufficient slope to cope with Attention should be paid to the elongation.) the vibration of outlet pipi of P.C.V. (Provision of supports or diverging nozzle should be considered.)
:-. :.. ._ .:
. . .:. .f ,, : .-
:.
,. -
34266
-143-
entpiping (Air is vented, when the is hydrostatic-tested.) Air is vented by.this bypass valve, when hydrostatic testino. + Attention of this shou Id line.
Never allow a down slope toward the drum. (Attention should .be paid to the upward eloncjation o riser pipes.)
Attention should be paid to vibration caused by two phas flovi. (Provide direction stoppers)
-Down
Note:
For
drum , reaction
forces
due to
calculated,
-.
Installation
Positions
Internal
Drains
Vents
pockets
fluids
Liquids For operation
All drain
Required (with valve)
Gas pockets
2.l/ZB or
in
larger
lines
Requir ed
Gases
34266
(with valve) or not required, refer to note. For Required hydrostatic Gases (Plug or blind test flange) Drains are not required where condensate Notes: operating or ambient temperatures. -144-
flange)
will not
be
produced ..
at
should
be
3) Drain and vent together with valve should be equipment not automatically drained or vented. should be located on the equipment, wherever located in connecting line, provided that no valve is installed between the equipment and b. Sizes of drains and vents not indicated line in P&I. size
provided for all Connections possible, but may be restriction such as the connection.
or smaller
I Drains Main line size Min.3/4B I I 3/4B Min.lB Same with connections
Abrasive fluids and fluids having high viscosity when operated at lw temperatures. Equipment c. Locations connect of drains
ions
3/4B 1B or larger
discharging
3) Drain valves should be located so as not passage ways or access to other equipment. 4) Drains and vents discharging to atmosphere, the direction not to endanger personnel. 5) Heights of drains above the grade
or
to interfere should
floor.
Note:
should
be min.
200 mm
1.
..
.,
..-
34266
-145-
of
valve
block valves
b. ANSI 900# and higher class.es Single globe valves (Note 3), lubricated double seated valves or two gate valves.
C.
plug valves,
resilient
abs. or
d. Corrosive Single
globe
b,c,e.
(Note 2) In general, gate valves. (Note 3) Only for Vents. 8.11 Utility piping
8.11.1 Hose station (1) Arrangements should be as shown in the drawing below. (2) Connection minimum. sizes for hoses and fittings
OK
34266
-146-
(4) Length
of h 088 should
be 15 m.
in
d adjacen e connections)
..
ffose banQ
&
150
(Detail
of hoseconnection)
34266
- 147-
(Detail Notes:
of hose
rat
be
1. The location of hose racks should consultation in the field. 2. All joints should be by welding. and shower
determined
after
8.11.2
Eye washer
(1) Water for eye washers and showers should be taken from drinking water sys'tem. Nozzles should be manufacturer's proprietary divices suitable outdoor installation. (2) Pedal-operated 'For reference' valves should
be
for
provided.
Typical drawings of the eye washer and shower are shown in the following. Shapes and sizes shown here should be used only for reference in planning, and detail design should conform to manufacturer's drawings. The dimensions shown below are of NIKXI Company. There are cases in which the eye washer and shower are installed being combined into single units. 280~300~ a4
Eye washer
(3) There are cases in which component parts are procured than two manufacturers for minimizing cost. (4)
In cold districts, provisions of winterizing should be considered. (steam tracing should be avoided. Apply insulation, and provide bypasses or blow valves to prevent staying of water from occurring.)
34266
-148-
8.11.3
Ejector
piping Elevation of ejector and related piping should be checked by Process Engineer in view of the function of the ejector.
or
Suction (Straight
lines pipe
should
have
minimum
is preferable.)
8.11.4
Cooling
water
for
pump,
turbine the
Installation
a. Sample located
be a
1) Lines connected to equipment equipment connections. 2) Connections having high 1B. taken off viscosity
should
be equal
to
the
sizes
of '- :. of
the lines for abrasive fluids or fluidsat low temperature, should be a minimum analyzers should be provided. be 3/4B, and a block
c. Connections for process of the same size should d. Sample connections should be located Sample connections whenever possible.
valve
taken off product lines connected to tanks, upstream of the control valve. should be located adjacently to the sewer, for high Single temperature cooler may
e. Sample connections taken off pipes or equipment service should be provided with sampling cooler. be used for two or more sample connections. f. For fluids having high viscosity should be made to clean the line media.
34266
-149-
,'
valve
connections
should classes
be
valved
as follows:
classes valve, having of double vapor pressure gate of valves 4.5 kg/cm2
abs. or
globe
valves
valve
or lubricated
plug
valve
piping and safe distance ---To conform to attached "Standard for layout of outdoor storage tank yard.. To conform to attached "Design manual for tank' yard in conformity with NFPA CODE 301".
Regulations
When regulations in Japan are applied. When NFPA CODE is applied. 8.13.2 (1) Tank yard Piping piping oil
outside
(liquid)
dike 6 n in
Piping should be run on pipe racks or sleepers. The height of pipe racks should generally be a maximum of view of loss prevention. There is no limitation for sleeper's height. (2) Piping inside oil (liquid) dike on tank laying
In general, piping should be run on sleepers. The height of sleepers should be determined based height, pump nozzle height, dike height and pipe's sequence and branches etc..
nozzle
34260.
-150-
piping
In general, piping should be grouped on the same sleepers, pump suction lines being routed to have the shortest possible run. Therefore, two or more groups of piping are required where there are many of tanks.
b.
Pump suction
piping
Piping should not have air pockets, tank nozzles being located the highest elevation. (Drain pockets may be allowed.) c. Flexibility of piping and flexible
tube ..
at
To cope with settlement of tank (Settlement when full-watertested, uneven settlement, settlement due to;earthquake)-; displacement of nozzle when full of oil, thermal expansion .etc., the pipe loops, expansion joints, flexible tubes may be used. However, in general, flexible tubes should be used for tank feed nozzles (other than for spherical tanks) and for pump suction In this case, piping should be designed with a nozzles. displacement of 100 mm.
:I. .:
._
34266
-El-
Dimensions
of
flexible
tubes
are as follows:
llni Y...hb t
.
mm .-
Nominal diameters ND 40 50 65 a0 100 125 150 200 250 300 350 400 Note: d. Piping
Maximum displacements 50 Actual 500 600 600 700 700 800 800
900
in 200
vertical 250 300 metal 1000 1100 I.200 ~00 1400 1500 1700 la00 2100 2300 2400 2700
direction 350 hoses 1100 1200 I.300 1400 l500 1600 1800 1900 2200 2500 2600 2900 1200 I300 1400 1500 1600 1800 1900 2100 2300 2600 2800 3200 400
150 (L) 700 800 900 loo0 1100 I.200 I.300 1400 1500 1700 1800 2000
of
flexible 900 1000 1100 1200 I.300 1400 1600 1700 2000 2200 2200 2500
800 900 1000 1100 I.200 I.300 1500 1500 1700 1900 2000 2200 the
manufacturer,
be careful
I not
tank tank
shutoff nozzles.
valves
should
be installed
directly
shutoff valves and header changeover installed in a group, and a stage, which walkway crossing over the grouped piping, for operation of such valves.
valves should be also serves as a should be provided should be installed on foundation to the
valve is heavy, the tank nozzles 3) When the shutoff reinforced (consult vessel engineer) or a support the tank shell. When the valve is supported on a foundation, such should be integral with the tank foundation. \ shutoff 4) Emergency tanks as possible. valves should be located as clash
valve for safety valve is of gate valve, such 5) Where shutoff gate valves should be installed in vertical line so that the valves are kept open even when the disc is disconnectd due to corrosion.
6)
not
be taken
off
of
pipes sewer
inside the dike should not 7) Lines lines. (Attention should be paid to the
extinguishing.)
by drip funnels, and led to 8) Tank drain should be received ditches or sump boxes inside the dike through underground pipes. (Do not allow tank drain to flow directly to the outside of the dike.) 9) In general, 34266 -152pipes should not penetrate the dike.
8.3.3.3
Drainage Refer
system to "8.14.4 Sewer lines" system Fire extinguishing facilities" in this design in this Design instruction.
8.13.4
Fire
extinguishing
Refer to "8.15 instruction. 8.14 Underground 8.14.1 (1) Lines Sewer piping
to be installed lines
underground
a. Oily b. Non-oily c. Chemical (2) Water a. Cooling b. Drinking c. Seawater ial water d.Industr (3) Fir@ a. Foam lines
extinguishing extinguishing
b. Firefighting (4) Trench a. For b. Lines (5) 8.14.2 Sanitary Design cable required
water
by process
(1) Priority
when planning
Priority should be given to cooling water main l.ines of large size, and oily sewer lines or chemical sewer lines having a slope. (2) Limitation for trench line should generally be limited to insulated inspection and repairing during connection to the
Trench lines in the unit lines and lines requiring operation. (3) Limitation for
use of flanged
Use of flanged connection should generally be limited connections to valve, equipment and machine.
34266
-153-
::
.. I,.,
_y;
(4)
Minimum
depth
of
than
underground freezing
(This should not be applied to USSR job, which by USSR regulation for electrical equipment.)
should
be covered
Min.
50
For
dimensions of pipe
Civil
Engineer.
(6)
underground
be indicated
by
top
a%~\
...
Top.
EL'indication
:_ : .i:..
a-IN,.,,. I
(Invert ele.vation)
.1:_
3426G
-154-
(7)
Jointing
to aboveground
piping
Underground piping is installed prior to aboveground piping works, and the ends of pipes should generally be capped as shown below until1 they become ready to joint.
Cap
or
plate
L 45'
is preferable
(8)
for
underground
(9)
Consideration
Displacements due to thermal expansion of high underground pipes should be limited to 40 mm. such pipes should be back-filled with sand. 8.14.3 (1)
a.
of
Cooling Design
water
piping
requirements especially be designed piping materials. as far as possible. inspection of pipe inside. to have simple
b.
should
be
avoided,
c.
Manholes Installation
1) Where main size is 248 or larger, is a pocket. : and ,there 2) Pipes adjacent to B, L etc., where
run
length
is 200 m or more
there
is
a block
valve. one
above
3) For large plant area such as ethylene plant, approximately manhole for each area is a standard in consideration of 1) and 2). (For example, one for quench and one for compressor ---.) 4) Manhole should be installed inside the valve with main block valve, instrument connection, mentioned below, as far as possible.
3426G
-155-
-: >
5) Detail8
of
the
manhole water)
are
as
follows: c . \
Manhole
(Cooling
d.
should criteria
be
draining
mud in
the
pipes.
1) Where main size is 24B or larger and there is a pocket. (When the pipe dia. is reduced the pocket is produced, the reducer being top flat.) 2) Other 3) Details Dr&n places
of
accumulation nozzle
are
of
as
mud is follows:
expected.
(Cooling
water) I
(2)
Piping
materials
(Fittings)
a. For jobs where JIS G3451 (Coated steel pipes for city water) is applicable, 90 bend class-l, 45' bend class-l, and tee class-l from among JIS 3451 (see attached tables below) may be used. However, these piping materials should be ANSI base, if, in a particular job, the thickness of the pipe is different from that of attached and the quantity of such materials is small, which would result in high cost.
34266
-156-
b.
miter
bend
(short)
with
: _.
n ww
UU
D*
!D R a
I-_
L 1
14
16 18 20 22 24 26 1 I / ! I I 1 1 I 1
,
1 1 1 1 i 1 i1 ! t i I i 1 1 \
355.6 406.4 457.2 508.0 558.8 609.6 660.4 711.2 762.0 812.8 663.6 914.4 lnlc n 1117.6 1219.2 1371.6 1524.0
.L.L.
i
i
700 750 800 850 900 ,nnn 1100 1200 1350 1 1500
A
28 30 32 34 36 Ah 44 48 54 60
1
---
.-
i 1524.0
! / .! I 1 I 'i 1 1
762.0 -7 8.12'.8 -i 963.6 T914.4 1016.0 ' .-mm - 1 1111.6 ---J.4J.Y.I 1371.6 1524.0 I
7119
34266
-157-
JIS
G3451 Coated
90
steel
piIJes
for
city
water
Bend Class-l
Unit:
Nomihal
mm
Dia. (A)
Inside Dia. 60.7 105.3 130.8 155.2 204.7 254.2 304.7 343.6 394.4 445.2. 496.0 597.6 699.2 798.6 898.6 998.6 1097.0
Dimensions R 230 230 230 250 310 360 410 460 510 530 5Go 660 790 790 860 910 J12 L 170 170 170 200 400 ii: 450 500 550 600 600 650 700 700 850 950 950 1050
1
lE6 15.9
26.5 40.7 55.1 52.8 65.0 79.6 87.7 128 165 224 312 398 518 635 798 984
1: t:
200
139.8 165.2
216.3 267.4 318.5 355.6 406.4 457.2
4.5 5.0
5.8 6.6 6.9 6.0 6.0 6.0 6.0 6.0 6.0
123.2 123.2 123.2 134.0 166.2 193.0 219.8 246.6 273.4 284.0 iii:: 423.4 423.4 460.8 487.6 487.6 519.8 546.6 573.4 569.5 616.3 643.1
709.6
709.6 709.6
802.0
878.6 959.01039.4 1019.8 1100.2
190
t:
290.1
366.8 371.7 371.7 420.4 433.8
140 190 160 160 190 19O 190 180 180 180
150
433.8
439.9 453.3 466.7
1.50
150
1200
471.5
1150 1540
2000 line
3426G
-X58-
mm
-I-
OutsideThic Dia. D2
Dimensions
T
P3 L 350 350 350 450 450 450 450 500 500 500 196.7 196.7 196.7 271.9 247.0 222.2 197.3 218.3 193.5 168.6
Izl 147.2 147.2 147.2 171.o 195.0 218.8 242.6 270.6 294.4 318.2 342.2 389.8 465.4 465.4 513.2 537.0 537.0 560.8 564.8 608.6
Reference Weight *1
(kg)
1
.:....:
89.1 114.3 139.8 165.2 216.3 267.4 318.5 355.6 406.4 457.2 508.0 609.6 711.2 812.8 .914.4
4.2 4.5 4.5 5.0 5.8 6.6 6.9 6.0 6.0 6.0 6.0 6.0 6.0 7.1 7.9
80.7 105.3 130.8 155.2 204.7 254.2 304.7 343.6 394.4 445.2
370 270.3 370 270.3 370 270.3 430 357.4 430 344.5 550 331.6 610 318.6 680 3S3.6 740 340.7 800 327.7
687.8 687.8 687.8 885.8 884.0 882.0 879.8 977.8 975.8 973.6 972.0 1467.8 1461.6 1961.6 1357.8 1955.6 1955.6 1953.6 1951.8 1943.8 1944.9 1944.9 1941.1
6.05 8.39 10.3 17.5 26.6 37.4 46.6 50.6 57.8 65.0 7i.2 131 152 277 347 422 550 647 779 922 1080 1390 1740
line
496.0 8Go 314.9 597.6 980 539.0 639.2 1170 438.1 798.6 1170 748.0 898.6 1290 722.4 998.6 1097.0 1197.0 1347.8 1350 1350 1410 1470 709.3 709.3 696.4 683.5 670.6
143.8 : 500 344.1 750 265.4 750 515.4 1000 465.7 1000 440.8 440.8 416.0 391.1 366.3 1000 1000 1000 1000 1000
34266
-159-
04ominal
Dia.
600X600A
and smaller)
I (Nominal Note: Dia. 7OOX25OA and larger) ,for R are f Sam. Allowances
:__::. -..: : ..
.: ..
34266
-160-
Outside 02
Dia d2
Thickness
4.2
4.2
2so
250
250 250 250 250 250
89.1 114.3 139.8 89.1 114.3 139.8 165.2 114.3 139.8 165.2 216.3 114.3 139.8 165.2 216.3
267.4 114.3 139.8 165.2 216.3 267.4 318.5 165.2 216.3 267.4 318.5 355.6 6:O 6.0 86:: 6.0 6.6' 6.6 i:t 6.6 4.5 2: 5.8 6.6 4.5 ;:i
150 X 125
150 x 150 200 200 200 200
250 x loo 267.4 250 x 125 267.4 250 x 150 267.4 250X200 267.4
250 x 250 267.4 318.5 318.5 316.5 318.5 318.5 318.5
300 x 100 300 x 125 300 x 150 300x 200 300x 250 300X300
iit 6.9
Zi:o"
ii:;
950x 150 355.6 550X200 355.6 150x 250 355.6 so x 300 355.6
HIx350 355.6 406.4 406.4 406.4 :Ei 40614 457.2 457.2 457.2 457.2 457.2 457.2 457.2 508.0 508.0 506.0 503.0 508.0 508.0 508.0
6:0
55:: :-ii
165.2 216.3
267.4 318.5 355.6 406.5 165.2 216.3 267.4 318.5 355.6 406.4 457.2 216.3 267.4 318.5 355.6 406.4 457.2 508.0
ii:8 ii:: ii:8
::
.I_ . . . . :.
..-
91.7
80.3 82.7
84.8
83.7 84.8 85.9
101
outside
Dia.
Thickness
Reinforcement
Length
Reference
D2 609.6 609.6 609.6 609.6 609.6 609.6 609.6 609.6 711.2 711.2 711.2 711.2 711.2 711.2 711.2 711.2 812.8 812.8 812.8 812.8 812.8 812.8 812.8 914.4 914.4 914.4 914.4 914.4 1016.0 1016.0 1016.0 1016.0 1016.0. 1016.0 1016.0 1016.0
d2 216.3 267.4 318.5 355.6 406.4 457.2 508.0 609.6 267.4 318.5 355.6 406.4 457.2 508.0 609.6 711.2 318.5 355.6 451.2 406.4 508.0 609.6 711.2 812.8 355.6 318.5 406.4 457.2 609.6 508.0 711.2 812.8 814.4
T 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.9 6.0 6.0 6.0 6.0 6.0 7.1 7.1 7.1 7.1 7.1 7.1 7.1 7.9 7.9 7.9 7.9 7.9
t 5.8 6.6 6.9 6.0 6.0 6.0 6.0 6.0 6.6 6.9 6.0 6.0 6.0 6.0 6.0 6.0 6.9 6iO 6.0 6.0 6.0 6.0 7.1 6.0 6.9 6.0 6.0 7.1 6.0 7.9 6.0 6.0 6.0 6.0 6.0 6.0 7.1 7.9 6.0 6.0 6.0 6.0 7.1 7.9 a.7
t1 6G:: i:: i:: i:: 2 t :: X:8 6.0 6.0 ii:8 t :t 6.0 t.8 6:0 28 X:i ,. 6.0 El 6.0 28 ii:8 2: 6.0 6.0
8 ;i ;i 70 70 3: 70 70 70 70 70 70 70 70 70 70 70 70 70 70 70 70 70 70 70 70 70 70 70 70 70 70 70
Ii 750 750 750 750 z! 750 750 3: s: 750 750 750 750 1000 1000 1000 1000 1000 1000 1oOO 1000 1000 loo0 1000 1000 loo0 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000
I 500 500 500 500 to 500 500 600 600 600 600 600 600 ii: 700 700 ;ii zii ;t
Height
(kg)
600 X 200 600 X 250 600 X 300 600 X 350 600 X 400 600 X 450 600 X 500 600 X 600 700 X 250 700 X 300 700 X 350 700 X 400 700 X 450 700 X 500 700 X 600 700 X 700 800 X 300 BOO X 350 800 X 450 400 800 X 500 800 X 600 800 X 700 800 X 800 900 X 350 300 400 900 X 450 900 X 600 500 900 X 800 700 900 X 900 1000X350 1000X400 1000X450 1000X500 1000X600 1000X700 1000X800 1000X900
138 140 142 141 141 142 142 164 168 171 170 171 173 174 177 203 298 297 ii 301 304 306 355 if: i: iii ;!t 438 446 447 zi 449 449 4sT 465 E 572 570 568 572 575 530
355.6 8.7 406.4 8.7 457.2 8.7 508.0 8.7 609.6 8.7 711..2 : 8.7 812.8 8.7 914.4 8.7 451.2 406.4 508.0 609.6 711.2 812.8 914.4 1016.0 10.3 10.3 10.3 10.3 10.3 10.3 10.3
1100X450 400. 1117.6 1100X500 1117.6 1100X600 1117.6 1100X700 1117.6 1100X800 1117.6 1100X900 1117.6 1100X1000 1117.6
34266
-162-
Outside 02
Dia. a
Thickness
Reinforcement
Length
Reference
t1
B 70 70 70 70 70 70 70 70 70 70 70 70 70
If
Weight
(kg)
1200x 400
1000
1000
900
900
ii;
700
1200X11001219.2 1117.6
1350X 450 1350X 500 1371.6 1371.6 457.2 508.0
1350X600 1371.6 609.6 1350X 700 1371.6 711.2 1350X800 1371.6 812.8
1350X 900 1350X1000 1371.6 1371.6 914.4 1016.0
1350X11001371.6 1117.6 1350X12001371.6. 1219,2 1500X500 1524.0 1500X600 1524.0 1500X 700 1524.0 1500X~8001524.0 1500X900 1524.0 1500X10001524.0 1500X11001524.0 1500X12001524.0 1500X13501524.0 1600X 600 1628.0 1600X 700 1623.0 1600X 800 1628.0 1600X 900 1628.0 1600X10001628.0 1600X11001628.0
1800X 700 1800X 800 1800X 900 1800X1000 1800X1200 !OOOX800 !OOOX900 1832.0 1832.0 1832.0 1832.0 1832.0 2036.0 2036.0
11.9 11.9 11.9 12.7 12.7 12.7 -12.7 12.7 12.7 12.7 12.7 12.7 14.0 14.0 14.0 14.0 14.0 14.0
16.0 16.0 16.0 16.0
8.7 10.3 11.I 6.0 6.0 6.0 7.1 7.9 8.7 10.3 11.1 11.9 6.0 6.0 7.1 7.9 8.7 10.3
6.0 7.1 7.9 8.7
6.0 2 ;:i ;:: 9.0 9.0 1f:i 12.0 12.0 12.0 12.0 12.0 12.0 12.0
12.0 12.0 12.0 12.0
100 100 100 100 100 100 100 100 100 100 loo 100 100
1250 1250 1250 1250 1250 1250 1250 1250 1250 1250 12!% 1250 KEO
1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 Ei 1200 1200 1200 1200 1400
1400 1400 1400
1020 1040 lOS0 1190 1190 1190 1190 1190 1190 1200 1220 . 1230 1710 1710 1720 1730 1730 1750 2190
2200 2210 2220 2240 2250 2750 2750 2760 2780 2790 2800
508.0 609.6 711.2 812.8 914.4 1016.0 1117.6 1219.2 1.371.6 609.6 711.2 812.8 914.4 1016.0 1117.6
711.2 812.8 914.4 1016.0 1219.2 812.8 914.4 1219.2
155 1500 150 1500 150 1500 150 1500 150 1500 150 1500 150
150 150 150
1500
1500 i 1500 1500
1800X11001832.0. 1117.6
16.0
t6.0:. 18.0 18.0
1409 1400
1500
lSO0
1500 1500 1500
1500
1500
18.0 18.0
18.0
18.0
1500
1500
1500
1500
34266
-163-
8.14.4
Sewer piping
(1) Type Applications 1. Drainage from equipment handling oil. 2. Drainage of rain water from oily paving areas. 3. Waste water produced by decoking of cracking furnace etc. 4. Drainage from the inside of oil dike. 5. Others indicated in P&I. 1. Drainage from equipment handling chemicals. 2. Drainage of rain water from chemical paving areas. 3. Chemical drainage from control room, laboratory and analyzers. 4. Others indicated in PSI. 1. Drainage equipment. 2. Drainage oily or 3. Drainage other than those from oily or chemical from 1 i I I
l I
Oily
sewer
Chemical
sewer
of rain water other than those chemical paving areas. of drinking water from buildings. 4, Drainage of firefighting water. 5. Neutralized waste water from neutralization tank.
Type
Oily
sewer
1. Carbon steel pipe with outside anticorrosion tapes. 2. Concrete pipe should be used for and larger when long distance. Consult Civil Engineer.
16B
_
.. . .: ..-: ,I .;...
Chemical
sewer
1. Carbon steel pipe with-outside anticorrosion tapes; (Careful study should be made on possible corrosion of steel due to acid and alkali.) 2. Cast-iron pipe 3. Ceramic pipe 4. PVC pipe 1. Carbon steel pipe
Non-oily
sewer
34266
-164-
(3) Design
of oily
and chemical
a. In general, underground,
In general, oily and chemical sewers within planned with a slope of l/300, and finally, between each catch basin or manhole should and civil Engineers.
Flow quantity should be based on rain water plus process water. me quantity should be determined by Civil Engineer based on process data, amount of rainfall, area of pavements, coefficient of discharge etc. c. Design Design d. Sizing flow flow velocity velocity sewer should line based on be 0.3-2.1 m/s.
of main
1) The'sizes should be determined by Civil Engineer, design flow quantity and design flow velocity. (For other than main line, by Piping Engineer.) 2) Minimum size of main of catch lines basin should area with for concrete each catch be 6B.
basin areas should be paved periphery spill-walled. -. basin basin of l/150 should area be provided should
etc., basin
and area.
..
400 m2.
in
the
drawing
Max.22.sn i-
100 I It" EL 0
34266
-165-
f.
Determination
of
paving
area
After receiving the information of equipment requiring paving from Process Engineer, Piping Engineer should determine the dimensions of paving area in cosideration of equipment maintenance, dismantling of piping, limitations of catch basin area etc.. g. The catch basin, sump box and manhole pit should generally installed in the main lines at intervals of 25 to 30 m. Type of oily sewers should be such that water seal can be provided for prevention of spreading of the fire. h. Drip funnel located to-permit direct discharge from and connected to the main line, catch size of drip funnel should be as shown size and number of discharge lines. be
Drip funnels should be equipement and piping, basin or sump box. The below, depending on the
Drip
funnel
(Type 11
non-pving
,'
or
trenches,
where
floor
is
Drip
funnel.
(Typ6
2:) te 1
34266
-166-
i.
Cleanout
A sub-header
should be provided for two OK more drip funnels. should be provided with a cleanout at its end. (Each drip funnel serves as a cleanout, because its perforated plate is removable.)
It
(Type
1)'
nChekered
plate
Clean
out
~o~~
X6 St Checkered (M&T'L SS4u plate Detail Polyethylene used when "J" which were may be used. ELO) caps, shipping, plate Clean out
'X6
Detail
"G"
34266
-167-
j.
For catch basins or sump boxes which flammable gases, water sealed covers gases should be discharged to a safe Type and purpose basin --types of pit This is a pit for
the
k.
1) Catch
catch
basin
area.
(A) Typical
Gratincf
Type
"A"
Type
Gratins
Type (Seal
YzH type)
Type (Seal
D type)
34266
-168-
(B)Sleeve Connections of pipes to pits which vary depending on construction method or time schedule, should be determined after consulting with Civil Engineer, and the scope of works should be made clear. sleeves are shown in the Here, dimensions for flanged following.
a I? 7
Id(B) 112 ii 14
2) Sump box Sump box is the intermediate pit which is installed intervals between catch basins or between a catch manhole pit exceed 25-30 m. (A)Typical types
..:: .:
* When non-paving,' the height of 50 mm fr& paving should be revised to read EL 150.
each (where
GL=EM)
34266
-169-
I Type
(Seal
G type) EL.3000
Type ,II" (-Seal type) , (B)For sleeves, refer to those for catch
(Seal
type)
basin.
3426G
-170-
3) Manhole
pit are installed for the purpose of cleaning of long main lines , and provided with water by internal partition wall. should therefore be located adjacently to B.L Or of unit or area.
Manhole pits and inspection seal effected Manhole pits the boundary
"SO"
should'be
(B)Por I. Details
sleeves,
of
refer cover
to those
for
catch
basin.
pit
Type
Type
A*
"Bm Detail "B"
.. .:
T_vDe "C"
, 34266
-171-
Detail
"C"
S't Checkered'plate
t----hi I w
u5Ox5Ox6 Detail Type "D" 71"
Type Type
Type
34266
-172-
MAT'L
SS41)
Detail
"F"
Detail
"G"
D&tail
"H"
I _. A I I
I L 90x56x6
Tvoe
El
Type
"I"
34266
-173-
m. Drainage
from
inside
the oil
(liquid)
dike
Tank
be
provided
for
both
oily
and non-oily
will
n. For catch basins located in the area of heaters is used, provisions should be made to keep the to allow accumulation of water in the pits.
o. When structures or two or more story buildings require flocr drainage, the floor drainage pipes should be provided and connected to the main sewer line. funnels In this case, the drip should generally be in the scope of Civil Engineer. (Consult Civil Engineer.) p. Sump Boxes should be provided at the corners of main lines. Inlet and outlet pipes of pits should be installed at right to the pit wall. 34266 -174angle
q. The angle of intersection ot 415. should be used for branch lines except for the start points of drip funnels. The branch lines should be buried as close to the ground surface as possible.
and main line are in different and they constitute threep.tpFng. should be as shown below, for each area. (Oily
(Oily
Catch Manhole
basin
(Oily
(Chemical (Chemical
(Chemical
sewer)
Drip
funnel
fu~el
(Oily
sewer) sewer)
--cz \ Y cc
(Chemical (Oily
out out of
sewer) sewer)
(Chemical indication
Manhole 800X1600 800 Sump box Catch basin 800 Drip funnel 2.54 Clean out 2.5Q 8. Preparation of General Drawing
make
It is recommended to information such as cover details of the valves at oil dikes number. (The General Drawing plants having large 34266 -175-
General Drawing, which includes the sizes elevations, directions, and drip funnels , cleanouts and changeover all together with each identification generally items.) be made for congested
of
t.
Preparation
P&I or Utility
of Plow sheet
Plow sheets of the sewer system are usually not included in other F.D, and it is recomendable to make the flow sheets for transmission OK confirmation of information, and for convenience of field construction and operation. are examples. -extraction unit
The followings
--
Butadiene
3rd n
I
6" 6 6"
drain drain .
area of pLd
8" Pumps .washing)
(Only
--
--
r-------
Product
tank
area
--_. :.
t1
:;.
34266
-176-
ggs 2 :;a
(4) Design
of
sewer sewers should should should be designed on rain by Civil water in of Engineer.
flow
be based
Design
velocities
be 0.6
flow. brick of
trough,
concrete
building drainage, f.
should be provided on both sides of road, periphery with roof, and in a place where there is non-oily etc.. considerations should be paid in the
sewer
The following
design.
1) Interference of non-oily sewers with other underground piping. (When the amount of rainfall is larger, or the length of sewer is longer, the bottom of the sewer is likely to become deeper;) 2) Isolation of paving area (Do not allow rainwater of oily enter into the non-oily sewer.) 3) Interference 8.14.5 (1) Trench piping with passage ways or chemical paving areas to
Scope of application required by process. such as for steam curtains, water below . .._. curtains the grade
a. Piping
b. Water-spray etc..
C.
piping
Gravity flow lines whose main lines are located (G.L) and are liable to clog. (Example : Drain lines to underground tanks.) interferes cosuaonly with used 150 the passage for
operation
and
_. ._ . . .:1..
Construction
Notes:
a. Inside of trenches should be filled with sand, if for safety. b. Top covers may be of checkered plates or gratings. Sometimes, the cover is not required.
required
34266
-178-
c. In gener81, piping for steam curtains or water curtain8 should not be covered. But, when the trench interrupts a passage-way, the . interrupted portion should be covered with a light cover. d. For above mentioned(l)C gravity flow lines, 45O bends and 45O branches should be used, and nozzles for cleaning should be provided at cirtical points. (Example of installatin 450 of the cleaning nozzle)
Cover
8.15 Firefighting
piping
(When requlations
system
Hydrant system b. Water-spray and deluge systems c. Sprinkler system d, Water curtain (Including steam curtain)
Air-Form sys
(2)
tea hydrant ] system ..: .. ..: _. .-. system system should not be used for any permanent for firefighting purposes.
a. Outdoor air-foam extinguishing b. Air-foam chamber system. (3) (2% system 8.15.2 Water extingushing 1. Water for firefighting facilities other than
2. Lines going to each yard should generally be underground, but the lines inside the tank-yard-dike should be aboveground. (1) Hydrant system
a.
Location
of hydrant
Hydrants should be installed so that all equipment and buildings are included within a 40 meter radius of the point of the hydrants, 34266 -179-
b;L Hose box Hose boxes should be located within 5 meter distance. c. Piping i) Main plant planning lines for firefighting to contribute looped water piping. should be routed around each
on the right
side
of
the
hydrants
so as to permit
the
(Example 1
expansion
is
expected,
the
firefighting
water
line
Firefighting
water
line
(2)
a.
1) Spherical tanks should be provided with topnozzle-type deluge system, which covers all of the upper half surface, and bottom-spray-system, which covers all of the lower half surface of the tank.
34266
-180-
2) Top-nozzle-deluge or drencher system should be provided on the roop of cone roof tanks for liquefied petroleum gases. For tank shells, the drencher system should be used.
I
Deluge
b.
I
system Drencher svsteo
:
Piping
2) Distribution valves and main valves should be installed in a safe place outside of dike. (15 m apart from the outside surface of tanks) 3) A strainer distribution Galvanized
stq+irl$E.:
should
header.
be
installed
between
4) Piping inside the dike should be above ground and provided with drain valves. The piping should not penetrate the dike. 5) Winterizing should
be
provided
in cold districts.
:.
._I..
.: 1:
-::
_.
1 .:
3426G
-181-
around
tanks
should
be sloped
to prevent
staying
of
of
piping
at distrubution
valves)
(Example
of
piping
at
spherical
tank)
6FF AU EL.1000
3426G
-182-
(3)
Sprinkler
a. Sprinkler This
etc.. b.
system
Piping 1) Main
planning valves should should pipes be manually operated. piping. down-stream piping of the
a. Water
Water curtain is used for shielding curtain for dilution of gases leaked. b. Steam headers should of steam and pressure c. Piping planning
be designed,
account
the
amount
drops
etc..
2) When the length of header for steam curtain is longer than 15 m (TEC standard), the steam should be supplied to the header from two or more lines. Inlet of steam
Control
steam
control
to access the
valves should be used and when gas leakage occurs. curtain headers
installed
steam
34266
-183-
header should
in the trench as
expansion
-one) -
Air-foam system should be used for fire extingushing of nowwater-soluble and flammable substance such as naphtha, oil etc.. a. Air-foam system includes two systems shown below. hydrant.
light
1) Tanks whose liquid surfaces are 40 m2 (tank diameter of approximately 7.2 m) or more, or heights are 6 m or more. .
oirer
3426G
-184-
d. Air-foam 6y6tam6 should bc designed to allow fteding of foam liquid to the air-foam hydrant or the air-foam chamber6 from both the pressure balance tank and the air-foam firefighting truck.
fyq Foam liquid
Strainer
Bt
To foam chamber
Connection (Connection
place
to the
e. Air-foam extinguishing hydrant6 should be located so that concerned hazardous material6 are covered within a 40 10radius the hydrant. f. Hazardous materials within a 15 m radius of the hydrant coverd also by other air-foam extinguishing hydrants. (2) Number of air-foam Tank diameter i Le66 than l3 II! 13 1 to le66 than 19 a-to less than 24 a to le66 than 35 m to less than 42 m to le66 than 46 m to less than 53 m to less than 60 m to less than 67 m to less than 73 m to less than 79 m to les6 than 85 m to less than chamber6 Cone roof 19 1 24 m 35 m
42 m
of
should be
tank
Floating
roof 2 3; 4' 5 6 7 8
tank
1 1 I; 2
3 4 6 8'
.. .
46 53 60 67 73 79 85 90
IQ m m m m m m m
10
12 14 16 18
10 10 l2 12
14 14
34266
-185-
(3) Piping
a.
When two of more foam chambers are following should be complied with. 1) Foam chambers should at uniform intervals. 2) The piping distribution
be
located
should be planned so as to obtain of the foam from each chamber. piping is not required to be a loop of
b.
C.
Foam liquid
Foam liquid piping inside the oil-dike be underground, and should not penetrate
d.
Foam liquid piping should be sloped(1/250) and be provided valves at the lowest points so that the foam liquid in the can be drained completely. When the lowest points are underground, pits should be provided for the drain valves. water strainers. lines to the foam liquid
tanks
piping
e. Feed
should control
be provided valves
with
f.
The foan liquid tanks and manual be located outside the dikes. Block valves in the lines to extinguishing system should as far as grouped together, They should be located 15 m
tanks.
operated
should
be used for the hydrants of foam be located outside the oil dikes and possible. apart from the outside surfaces of
should
be located
in
a place
adjacent
to
Foam chamber
Foam liquid
tank
8.15.4
system system should be provided rooms, computer rooms etc.. for the switch
8.15.5
Cases
where
yards
in
conformity
with
34266
-186-
MALONEY
PROTEK ENGINEERS MALONEY FILE: CQ91-207 PAGE 2
STEEh LTb
l*O
1.1
DESIGN BASIS PRCCESS DESCRIPTION Our offer Is based on the use of triethylae glycol as the dehydrating medium. The reasons fox the choice of a glycol drying system and for the use of TEC are outlined in section 3.10 and 3.11 of this quotation, The glycol contactor lower consists of a gas/liquid knock-out sections The liquids are where entrained liquids are removed from the gas, discharged under level control and the gas passes up through the vessel counter current with lean TEG, Mass transfer of water into the glycol from the gas takes place over the length of the coatactor before the gas leavesthe top of the tower as dry gas. The tower is fitted with a chimney tray between the knock-out and contacting sections in order to collect the rich glycol and from where it is discharged under level control. The tower has a mist extractor above the knock-out section to prevent entrainment of liquids entering theoontactor section and contacting the glycol and a second mist extractor below the gas outlet,to prevent entrainment of glycol in the dry gas, The contactor section has been designed using valve trays which However a design using we believe gives the most economical design. a structured packing would result In a more compact tower with consequent reduction in weight which would be a bonus on an offshore installation. We would be pleased to consider such a design if this basic offer is of interest. A glycol dehydration unit can de designed with a large number of variation of glycol flowrate and concentration, number of stages The design and degree of heat recovery on the regeneration package. to provide the most cost effective offered has been computer rjptimized design. The water rich glycol discharged from the chimney tray is piped to the regeneration package where it firstly, passes through a still reflux coil where it is preheated to approxLmately 162F. Then the rich glycol is piped to a vessel operating at about 4 barg (60 psig) which serves as a flash drum and a hydro-carbon liquid skimmer. This vessel is a vertical three-phase separator sized to provide thus assuring complete degassing 15 minutes glycol retention time, of the rich glycol and removal of any liquid hydrocarbons which may have been entrained in the glycol solution. The degaeeed rich glycol is discharged from the flash drum through firstly a glycol sock filter which removes solids and then through a carbon filter which removes any remaining hydrocarbons, well treating chemicals or any other trouble-some impurities and then through a rich-lean glycol heat exchanger where it is further preheated to 350Q F. &.Jd filtered, the rich glycol is Having been preheated, degassed ed to a feed point near the centre of the packed still. reflux
l ,
column
where
the water
and glycol
are
separated
by
fractiona
I al st
at I on.
,:,
1. .::
PROTEK ENGINEERS MALONEY FILE: CQ91-207 PAGE 3 1.1 PROCESS, DESCRIPTION The still column reflux condenser is cooled by the rich glycal leaving the contactor tower. The sole purpose of the dietillation or still column is to vent water vapour and to recover all glycol vapours generated by heat in the reboiler, This method is so effective that glycol losses in the still overhead are small. As the rich glycol passes from the bottom of the still column downward into the reboiler, the temperature is further increased to the reboiler temperature of 204C (4OOF.f with heat being supplied Normal reboiler temperature is 204*C. Alternatively by a gas fired heater. the reboiler could be electrically heated at additional cost. Even though TEG begins to degrade at slightly above 204C, glycol degradation ie not a problem when air is excluded from the system and when heater flux rates are reasonable. The lean glycol from the reboiler then passes through the glycol/glycol heat exchanger where it is cooled while preheating the rich glycol before passing to the gl.ycol accumulator. Before re-entering the contactor tower at the completion of the regeneration cycle further cooling is required which may be by sea water, process gas or ambient air. This offer is based on the use of sea water cooling using a litanium plate and frame heater exchanger. After final cooling the glycol is pumped into the top of the contactor tower using an electric driven positive displacement pump. This offer includes the supply of 2 x 100% duty pumps, 1.2 DESI.Gp DATA Each dehydration unit ie designed to dry 165 MMSCFD of gas water saturated at 850 psig and 14OF. to an outlet dewpoint of 57*F(14*C). Gas supplied at 980 psig contains less water and hence the equipment will handle gas from 850 to 980 pslg, The tower offered has sufficient contactor stages to maintain the 14C dew point if the gas inlet temperature is increased to 155*F but gas throughput is then limited by the capacity of the regeneration package, and hence gas throughput must be reduced. If the system is operated with gas at 400 psig an extra stage must be added to the contactor tower in order to maintain the 14C dew point and also the gas throughout must be reduced.
'HI
WlALONEY
PR0TEK ENGINEERS MALONEYFILE: CQ91-207 PAGE 4 1,2 DESIGN DATA Maximum gas throughputs INLET TEMPERATURES &F 140 145 150 ,': 155 NB. 1.3 Extra stage required JJESIGNBASIS
STEEL Mb
are listed
INLET PRESSURE 850 - 980 psi& 165 151 138 128 for operation
Gas flow rate 165 MMSCFU Gas inlet pressure 850-980 psig Gas inlet temperature 1406F. Mechanical design pressure 1700 psig Gas molecular weight 21.3 Gas saturated with water at above inlet conditions. Gas outlet dewpoiat 57F (14'C), Water removal rate 1220 lb/h. Lean glycol concentration 99.1% TEG Lean glycol circulation 27,785 lb/h, Rich $1~~01 circulation 29,005 lb/l Glycol circulation 2.5 USG/lb water removed Glycol contactor ID 81" height s/s 21'6" for 850 psig 23'6 for 400 psig Contactor design pressure 1700 psig Contactor design code ASME VIII Div. 2 Reboiler operating temp. 400'F pressure atmospheric Reboiler heat load Heat load recovered by reflux coil. Heat load recovered by glycol/glycol exchanger Total regeneration heat load Reboiler capacity filLed 2.5 x lo6 BTU/h 0.3 x lo6 BTU/h 3.5 x lo6 BTU/h 6.3 x lo6 BTU/h 3.0 x 106 BTU/h
--
--
__,
Wm.--(
WUONEV
PROTEKENGINEERS MALONEYFILE: CQ91-207 PAGE 5 1.3 DESIGN BASIS
OTEEL LTD
Gas consumptions if reboiler gas fired Power consumption if electr1caU.y heated Gas consumption based on gas with GCV Glycol cooler sea watersupply Sea water consumption Sea water return
4?
SO00 SCFH 900 kw 1000 BTII/SCF Assumed 9O*F 34,710 lb/h lllF 34 hp (25 kw) 40 hp (30 kw)
pump
Pump power based on max pressure casing designed for 1700 psig,
Pumps
Regeneration skid dimensiona (apprax.) Height to top of still column 1.4 INSTRUMENTATION AND CONTROL
This offer is baaed on the minimum controls required for safe operations of the unit, We would be pleased to consider controls in more detail once your control philosophy is determined, For example we would need to know whether controls should be electric or pneumatic and whether controllers are to be local or provided by a remote DCS syatem, CONTROLS INCLUDEDARE: 4) Contactor Tower: Level. controLler and control valve for knock-out section Level controller and control valve for chimney tray Level contwoller and control valve for glycol level High and low level ewitches for knock-out level section High and low level switches for chimney tray glycol Level gauge for knock-out section Level gauge for chimney tray glycol level.. Pressure gauge Temperature indicator REBOILER: Temperature controller Fuel gas valve train consisting of fuel gas shut down valve, control/shut down valve, pilot valves , manual isolating valve, main,gas regulator, pilot gas regulator:. Flame f allure sensor Low level switch High temperature switch Level gauge
MALQNEY
PROTEKENGINEERS MALONEYFILE: CQgl-207
PAGE 6 1.4 CONTROLS LNCLUDEU: GLYCOL PUMPS Pressure gauge8 Relief valve6
STEEL Ltll
FLASH TANK Level controller and control valve for glycol Manual valve for manual skim of hydrocarbon condensate ReguLaror and relief valves for gas blanket Level gauge High and low liquid level ewitches Pressure gauge Relief valve.
FILTERS
fsolating valve8 Pressure gauges Differential pressure gauges Manual bypass valve for charcoal Thermal relief valves 2.0 EXLUSI,ON All instrumentation controls and valves far process gas* All instrumentatlcn, controls and valves for sea water. Any instruments , controls or valves not listed in section Relief valves on contactcr tower, ESD valves or blowdown valves Accees platforms and ladders on contactor tower, Brackets fitting of ladders/platforms are included. HIC and SSC testing We would would be pleased to advise prices for any of the once your final requirements are known. 3.0 3.1 REPLY TO ATTACHMENT 2 OF YOUR RF-Q Reboiler BTU/SCF, Electrical Nl3, This fuel gas demafid 5000 SCFH based on gas with GCV of 1000
filter
1.4 above
far
above
3.2
power requirement for electric reboiler offer is based on the use of a gas fired
3.3
The rsboiler offered is deeigned for uce with sweet gas. However controls, firetube, burner and exhaust be specified for use with aour gas at extra cost if
MALONEY
PROTEKENGXNEERS MALONEYFILE: cp9 l-207
PAGE 7
3.4
STEEL LTD
Choice between electric heating or gas firing ie an economic trade off depending upon capital cost and relative costs of gas as opposed to electricity, An electric reboiler will take up less space which can be at a premium for offshore applications.. Thyristor control is recommended for electric heaters with the control panel mounted Indoors in a non-hazordous area. However the thytistor control panel cost is significant. The dehydration unit may be turned down to 30% of design flow, i.e. to 50 MMSCFD at 850.-980 psig or to 30 MMSCFD at 400 p&g. The unit offered is constructed from carbon requirements fo NACE MR-01-75, Vessels are and pipework will be heat treated to ensure also complies with NACE MR-01-75, steel. conforming to A-516-70. Vessels that weld hardness
.+a Tb
3.5
3.6
3.7
Maloney dehydration systems are designed to minimize Details of maintenance requirements and recommended can be discussed when controlphilosophy is decided See section See section 1.2 1.2
The alternative to a glycol dehydration system is a dry bed system. Dry bed systems are capable of dehydrating to lower dewpoints rhan glycol systems but equipment costs and energy costs are higher. The required dewpoint far this application is 14C. which is relatively high and easily obtainable using a glycol system. There is thus no advantage in using a dry bed system in this case and economic disadvantages. vapour pressure than DEG or MEG. Consequently in the gas outlet stream are lower if TEG is used, especially when gas temperatures are high as in this case. DEG is normally only used when gas temperature is below 2O*C (68F) and MEG only when gas is refrigerated. Also because of its lower vapour pressure the fractional distillation of the rich glycol is easier with TEG with lower Losses in the water vapour stream from the still column, A further advantage of TEG 1s its higher thermal stability enables the use of higher reboiler temperatures leading to higher concentrations of lean glycol without the use of gas stripping to increase glycol concentration, TEG has a lower
losses of glycol
3.11
4.0
P .a .
OFFSHORE GLYCOL DEHYDRATION UNITS AND REGENERATORS LOC&CION North Sea North Sea Gulf Thailand North Sea North Sea CAPACITY MMSCFD 375 100 75 47 116 use OR floating under condftions production of severe
commissioning building
The last two references above are for platforms and are designed CO operate roll, heave and pitch.
. Wilter
. Lean
removed glycvl
per
train
: $.%G5 LB/HR
(050
PSIG,
140F)
ioed
: 99.1 X weight : 33 000 LB/HR : 2.75 Gall/LB KW (4.4 KV (5.1 MMBTUIH) MMBTU/H)
Reboilcr
: 1300 i : 1500 I
FbR PACH
3,
DESCRlPTfON .------v---.
OF
S1JPPI.Y
TRAIN
gackake
housj.nA
ba.cksd 1:ypc, including an integrated inlet. , 5r.G m height; ! - Ona caslglycol heat excha$ger, t.ubular BEM type, mounted along the , absorber. I I hcces+jories and i,nst-rumtnts, associated CO - Including piping, valves, ccntactot and heat exchanger; Skid s1.7.ing : II = 11 m
w = 3.5 m
I
I
I I : 50 i.ona
- Two full glycol flow c:arjridg:e filters, able tr) remove all solids particles of 5 microns diamc!Rnr and ahow. I - 1)ne side flow glyr:vl c:haIjc:oal filter, able t,o handle 20 X of rich I glycol flow rate. i - OI~F! gly~~~.~l/glycvl heater ekc:hangcr, plate type of tubular type. !
bundlel;
(3)
: 2,3
m diameter TL / TL
per
per
3 m
column,
surge
packed drum,
34
inches rk?r:t?ive
diameter
4 m height:
to
the
glycol
c:ontained
in
reboiler
- Twn gJ.yr..ol recirculation frumps, with. their electrical muters: f Including at:c(~s~;nries .
!
interc:onncr:t.~TIS
piping,
inStrumant.3
still
:ons
column
installed.
Estimated
empty
wright.
: 70
fired ~lycul reboile:: : Futrl gas consumpr.i.on ,it 7 case of direct a Net heating value of 1005 p e r c Ka 1.n , based on a fue, I. I gas hav !ng BTU./SCF, fuel gas con+:;umpt.. ii ,n will be : 7050 SCF/HR and per train.
4.1.
power : 1305
rdql KW
in
case
of
elac:trically dehydrated R. of
heated gas
as
heated
heat.er :
a vis
elec:trically
- smaller - smaller
associated
cnnt.rnl
panel
1 1 sizing
investmen
- lower
t-1cost I i i , I 1 i I j I
6.6.
r'~~on'uW~lded
Metallurgy
ttr
r:las
thr
first
hundred
::0Llr recommerlddtion due t0 the 1owek part ut the contac:rlor mil limrrter~ of strut:t.ured packing.
Rich g!.ycol piping up to f;lash vessel, flash vrs$el. flash out.ler, gas piping should satrsfy recommenciations of NACE, Still and internals shall be l)rc>vj $ctd in stainless steal. 4.7 Wlml thrnufihput. st.rigl>ing operating at 400 shall be reducef gas shall be uticd. at : 145/l. PSIG : down 4 Oll55F
vc+ssel cc~1um.n
instead of 850 PSIG t,hc inlt?t gas lo 7 +4 MMSCFD and 1 SCPT/GALL or the inlet gas t.hroughput shall be
4.0 W?len uperating reduced as fc~llows 145F 0 150F 3 55F : 10.5 MNSCFD : 127 MMSCFD : 112 MMSCFD
5. --
BUDGET PRIcrf pri~:e for d.ehydration the desii n and sul)ply of trains is : 38 000 000 FF
four
Hutiget. ~,lyc:ol
identical
gas
and
j?ii.- DELXVERY
TIME
Delivery
time
gf LIST of
those
unit.:;
will
be between
12 to
14 months.
refercxes disposal
is fol ;
added
hert!
your
any other
l/j i