Gas Turbine Maintenence Aspects
Gas Turbine Maintenence Aspects
Gas Turbine Maintenence Aspects
HYDERABAD
GT INSPECTIONS
HDGT.PPT/ 2
HYDERABAD
Speed Load Fired Starts Fired Hours Site Barometric Reading Temperatures Inlet Ambient Compressor Discharge Turbine Exhaust Turbine Wheelspace Lube Oil Header Lube Oil Tank Bearing Drains Exhaust Spread
Pressures Compressor Discharge Lube Pump(s) Bearing Header Cooling Water Fuel Filters (Fuel, Lube, Inlet Air) Vibration Data for Power Train Generator Output Voltage Field Voltage Phase Current Field Current VARS Stator Temp. Load Vibration Start-Up Time Coast-Down Time
RUNNING INSPECTIONS
HYDERABAD
OPERATIONAL DIAGNOSTICS
Start up
Increased Startup time Jaw clutch disengagement at a lower speed Higher vibrations during critical speeds
HYDERABAD
First critical 1900 rpm Second critical 3250 rpm Third critical 5200 to 5600 rpm
HDGT.PPT/ 5
HYDERABAD
First critical 980 rpm Second critical 1300 rpm Third critical 2300 rpm
HDGT.PPT/ 6
RUNNING INSPECTIONS
HYDERABAD
OPERATIONAL DIAGNOSTICS
- Indicative of clogged hydraulic filters and / or damaged fuel pump and / or relief valve
HDGT.PPT/ 7
RUNNING INSPECTIONS
HYDERABAD
OPERATIONAL DIAGNOSTICS
RUNNING INSPECTIONS
HYDERABAD
OPERATIONAL DIAGNOSTICS
Lower Loads under similar conditions Higher Exhaust Temperature under similar
HDGT.PPT/ 9
HYDERABAD
STANDBY INSPECTION
Inspections carried out during Off-peak periods when Unit is not running for a long duration
Check Battery system, Oil levels, instrument calibrations, replacement of various filters & servicing of accessory systems etc. Put the unit on ratcheting / barring gear for atleast 30 min daily Crank the Turbine once in a Fortnight to drive away Moisture Run the Gas Turbine FSNL once every month to avoid corrosion to turbine wheel dovetails
HDGT.PPT/ 10
HYDERABAD
HYDERABAD
Design Features
Duty Cycle
Cost of Downtime
Diagnostics
Type of Fuel
Maintenance Program
Availability Need On-Site Maintenance Capability Expert Systems
Utilization Need
Environment
Reserve Requirements
HYDERABAD
Because not all customers operate their gas turbines the similarly
Case 2
1,000 Hrs/Yr 400 Starts/Yr HGP at 3 years, not 24 years
HYDERABAD
Maintenance Cost and Equipment Life Are Influenced by Key Service Factors
Fuel Firing Temperature Steam/Water Injection Cyclic Effects (Start-up rate, number of trips) Air Quality
Service Factors Different From the Reference Condition* Can Increase Maintenance Cost & Reduce Maintenance Intervals
HYDERABAD
HYDERABAD
Maintenance Factors
Typical Max Inspection Intervals (MS6B/Ms7EA) Hot Gas Inspection 24,000 hrs or 1200 Starts Major Inspection 48,000 hrs or 2400 Starts
Criterion is Hours or Starts (Whichever Occurs First)
Starts Factors
Trip From Full Load 8 Fast Load 2 Fast Start 20
1 1.5 2 to 3 3 to 4
Peak Load 6 Water/Steam Injection Dry Control 1 (GTD-222) Wet Control 1.9 (5% H20)
HYDERABAD
Operation of Gas Turbine in Extended lean-lean base mode in DLN-1 units has a maintenance factor of 10
HDGT.PPT/ 17
HYDERABAD
HYDERABAD
Maintenance Requirements are Based on an Independent Count of Hours and Starts Certain Operating Factors Reduce Maintenance Intervals Peak Load Steam/Water Injection >2.2% Liquid Fuel Trips From Load Fast Starts Exceeding BHEL Specification Limits can Significantly Increase Maintenance Factors and Reduce Component Life Equations for Establishing Application Specific Hot Gas Path Maintenance Intervals are Available
HYDERABAD
Residual
Maintenance Factor
Distillates
Heavy
7 8 9 10 11 12 13 14 15
20
HYDERABAD
540 Deg C
Acceleration Light-off
Unload Ramp
Exh. Temp.
Warm-up
Fired Shutdown
Start-up
Time
Shutdown
HYDERABAD
Base
FSNL
20
HYDERABAD
Shutdown Inspections
Combustion Hot-Gas-Path Major
Special Inspections
Borescope IGV Bushing insp.
HYDERABAD
Base Line Recommended Inspection Intervals Base Load - Gas Fuel - Dry
Type of Inspection Combustion Hot-Gas Path Major MS32/52/51 Upgrade (Standard)
Hours/Starts MS6B MS6FA & 9FA Standard DLN2 & DLN1 12000/1200
24000/1200 48000/2400
12000/800
Eliminated/1200 48000/2400
8000/450
24000/900
48000/2400
Factors That Can Reduce Maintenance Intervals Trips from Load Fuel Start Cycle Load Cycle HGP Hardware Design Steam/Water Injection Peak Load Operation
HYDERABAD
WORK SCOPE:
Criteria:
Inspection Methods:
Visual LP Borescope
HYDERABAD
Buckets (1,2,3)
Stator Shrouds IGVs & Bushings
Foreign Objects Damage Repair/Refurbishment Nozzles Oxidation/Corrosion/Erosion Weld Repair Cracking Reposition Cooling Hole Plugging Recoat Remaining Coating Life Buckets Nozzle Deflection/Distortion Strip & Recoat Weld Repair Abnormal Deflection/Distortion Blend Abnormal Wear Missing Hardware Clearance Limits
Criteria:
Inspection Methods:
Visual LP Borescope
HYDERABAD
WORK SCOPE: Combustion Inspection Work Scope + HotGas Path Inspection Work Scope +
Key Hardware
Compressor Blading Turbine Wheels Dovetails Journal and Seal Surfaces
Inspect for:
Foreign Objects Damage Oxidation/Corrosion/Erosion Cracking Leaks Abnormal Wear Missing Hardware Clearance Limits
Potential Actions:
Repair/Refurbishment Stator Shrouds Oxidation/Corrosion/Erosion Buckets Coating Deterioration FOD/Rubs/Cracking Tip Shroud Deflection Creep Life Limit Nozzles Deterioration IGV Bushings Wear Bearings/Seals Boring/Wear Compressor Blades Corrosion/Erosion Rubs/FOD
Availability of On Site Spares Is Key to Minimizing Downtime
Bearing Seals
Inlet System Exhaust System
Criteria:
Op. & Instr. Manual Inspection Visual Methods: LP TILs Service Engineers Borescope
HYDERABAD
Shroud#2,3
HGPI
4HGPI
3HPGI
HYDERABAD
New Nozzle
Nozzle Condition
First repair
10,000 20,000 30,000 40,000 50,000 60,000 70,000 80,000 Operating Hours FIRST STAGE NOZZLE WEAR - PREVENTIVE MAINTENANCE LIFE EXTENSION
HDGT.PPT/ 29
Acceptance Standard
HYDERABAD
Cost Procurement cycle time Repair cycle time Vs. Inspection down time Shelf life Storage facilities Environment Transport facilities
HDGT.PPT/ 30
HYDERABAD
Borescope Inspection
BORESCOPE INSPECTION CRITERIA
Corrosion
Tip Erosion Trailing Edge thinning
HYDERABAD
Borescope Inspection
BORESCOPE INSPECTION CRITERIA
Cracking
Bulging Wear
HYDERABAD
Borescope Inspection
BORESCOPE INSPECTION CRITERIA
Erosion
Burning
HDGT.PPT/ 33
HYDERABAD
Borescope Inspection
BORESCOPE INSPECTION CRITERIA
ACCESS AREA
Turbine buckets
INSPECT FOR
Foreign object damage Corrosion
Blisters
Erosion Cracks Tip clearance Missing metal
HDGT.PPT/ 34
HYDERABAD
Borescope Inspection
RIGID BORESCOPE
BORESCOPE
FLEXIBLE BORESCOPE
HDGT.PPT/ 35
HYDERABAD
Airflow Direction
2. Set up dial indicator to measure motion normal to the vane chord. Position the indicator to read as close to the vane inner button as possible 3. Deflect vane in a tangential direction (perpendicular to the air flow direction) to both sides of the bushing clearance and record full dial indicator reading.
HDGT.PPT/ 36
VIGV
Dial Indicator
HYDERABAD
HDGT.PPT/ 37
HYDERABAD
With upper half of casings removed, it is possible to remove nozzles and inspect buckets without removing rotor
All bearing housings are horizontally split and bearings can be replaced without removing the rotor. Large blades are moment weighed and sequenced to avoid rebalancing of rotor after site replacement. Components like governing components, fuel nozzles, combustion components are mounted type for easy maintenance. All major accessories are separate assemblies and are accessible for inspection and maintenance.
HDGT.PPT/ 38