Inspectation Test Plan
Inspectation Test Plan
Inspectation Test Plan
Customer : TOYO ENGINEERING & CONSTRUCTION SDN BHD Project : EPCC for Plant Rejuventation & Revamp 4 (PRR4) Project Item : Gate Valves ITP No : PFCSO2013110033-ITP R0 Customer Reference No: AYHB202A [JB-0255] Our Reference : TNSQ130522-01AL-R4
Panaflo VERIFYING DOCUMENTS Action Sign Action Sign Action Sign TOYO Qty : 3 nos Date : Rev.: Page 1 of 1 20-Nov-13 0
SL.NO.
ACTIVITIES
REFERENCE DOCUMENT
CHARACTERISTIC TO BE VERIFIED
CONTROLLING DOCUMENTS
Body and Adaptor Heat No , Material Grade, Chemical & Mechanical test results
Material Certificates
Test Results * Please note that equipment cannot detect carbon % and low temp carbon%
- PMI report
Test Results
GA Drawing
Dimension
Approved Drawings
- GA Drawing
ED-PRR4-COMM-TRS-PEP003
ED-PRR4-COMM-TRS-PEP003
Abbrevations R - Review of documents / drawings W - Witnessing activities H - Hold for next stage until approved / clearance given A - Documents for Approval by Client TPI - Third Party Inspection Agency PREPARED BY REVIEWED AND APPROVED BY APPROVED BY WR - Witnessed random M - Monitor P - Perform I - For Information