The document outlines standard operating procedures to follow during load restriction at the Sekurit substation. Key points include:
1. Confirm the allowed load limit from the dispatch center and the load restriction time frame in advance.
2. Inform the dispatch center 30 minutes before load shedding starts and only start after their confirmation.
3. Inform plant staff to clear lines and put equipment in standby mode, and monitor the load energy meter to coordinate with production and dispatch.
4. During restrictions, keep the load below 1.5MW by shedding excess loads to avoid tripping the main breaker. Inform dispatch after lowering the load.
Download as DOC, PDF, TXT or read online on Scribd
0 ratings0% found this document useful (0 votes)
43 views
SOP For Load Restriction
The document outlines standard operating procedures to follow during load restriction at the Sekurit substation. Key points include:
1. Confirm the allowed load limit from the dispatch center and the load restriction time frame in advance.
2. Inform the dispatch center 30 minutes before load shedding starts and only start after their confirmation.
3. Inform plant staff to clear lines and put equipment in standby mode, and monitor the load energy meter to coordinate with production and dispatch.
4. During restrictions, keep the load below 1.5MW by shedding excess loads to avoid tripping the main breaker. Inform dispatch after lowering the load.
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 2
000/SGSC/SS/LR11
SOP TO BE FOLLOWED DURING LOAD RESTRICTION IN
SEKURIT SUB STATION 1. KNOW & CHECK THE ACTUAL LOAD ALLOWED FOR SEKURIT PLANT FROM DESPATCH CENTRE ( FLOAT SUB STATION) CONTACT PERSON MR. RAMESH VELAYUDAM (9!09"#$) OR MR.SARAVANAN (9%00009%) OR FROM THE COMMUNICATION EMAILS WHICHEVER IS AVAILABLE AND CONFIRM THE SAME. &. THEN KNOW THE ACTUAL LOAD RESTRICTION TIME FRAME BY EN'UIRING WITH THE LOAD DESPATCH CENTRE ( FLOAT SUB STATION) CONTACT PERSON MR. RAMESH VELAYUDAM (9!09"#$) OR MR.SARAVANAN (9%00009%) OR FROM THE COMMUNICATION EMAILS WHICHEVER IS AVAILABLE AND CONFIRM THE SAME. $. THE LOAD DESPATCH CENTRE (FLOAT SUBSTATION) PERSON COORDINATING THE (OB HAS TO BE INFORMED THAT THE CONFIRMATION FOR LOAD SHEDDING HAS TO BE TOLD OR RECEIVED HALF AN HOUR BEFORE THE ACTUAL LOAD SHEDDING HAS TO START !. START THE LOAD SHEDDING ONLY AFTER GETTING THE CONFIRMATION CALL OR INTIMATION FROM THE LOAD DESPATCH CENTRE OVER PHONE. #. AFTER CONFIRMATION INFORM THE PLANT PRODUCTION SHIFT INCHARGES/METHODS ENGINEERS ABOUT THE LOAD SHEDDING AND RE'UEST THEM TO CLEAR THE LINES AND TO PUT THE LINE IN STANDBY OR STOP MODE )TO BE COORDINATED BY THE MAINTENANCE SHIFT TEAM/MAC LELAN TEAM. %. THE MAINTENANCE ELECTRICAL SHIFT TEAM HAS TO KEEP A CONSTANT WATCH ON THE LOAD ENERGYMETER (KW) AVAILABLE IN THE 11KV INCOMER PANEL AND COORDINATE THE LOAD WITH THE PRODUCTION AS WELL AS THE LOAD DESPTACH CENTRE (FLOAT SUBSTATION). ". USUALLY THE ALLOWED LOAD FOR THE SEKURIT PLANT DURING LOAD SHEDDING IS 1.! MW FOLLOWING ARE THE WORK CENTRES THAT CAN BE RUN ALLOWED LOADS TO OPERATE SPB #0 FURNACE * 0.% MW PPL 1)&)LAMINATED PPL & FI * 0.! MW COMPRESSOR " BAR (10#0 CFM) * 0.& MW OTHER UTILITY LOADS (LIGHTING/AC/WATER PUMPS/PC...+,-) * 0.& MW TOTAL LOAD . 1.! MW (APPRO/) 1 000/SGSC/SS/LR11 LOADS TO BE KEPT IN OFF CONDITION/ OR NO LOAD ACGP FEEDER * 0 MW (PRIOR INFO TO BE GIVEN TOCONCERNED PERSON) MF100 FURNACE * 0 MW (STOP MODE) BT FURNACE * 0 MW (STOP MODE) KT FURNACE * 0 MW (STOP MODE AND HEATING BREAKER TO BE TRIPPED) ASSY) CHILLERS & AHU * 0 MW PPL $ AND NEW '/L LINE * 0 MW (STOP MODE)
. DURING ANYTIME OF THE RESTIRCTION PERIOD THE LOAD SHOULD NOT GO BEYOND THE ALLOWED LOAD, FAILING WHICH THE WHOLE INCOMER BREAKER COULD TRIP, SO THE ELECTRICAL SHIFT PERSON HAS TO KEEP A CONSTANT WATCH ON THE LOAD AT THE INCOMING FEEDER AND HAS TO TRIP ANY EXCESS LOADS ACCORDINGLY. 9. AFTER THE LOAD HAS BEEN DECREASED THE SAME HAS TO BE INFORMED TO THE LOAD DESPATCH CENTRE (FLOAT SUBSTATION). 10. AFTER GETTING THE CONFIRMATION CALL FROM THE LOAD DESPATCH CENTRE (FLOAT SUBSTATION) COORDINATOR THAT THE RESTRICTION PERIOD IS OVER THE LOADS CAN BE SMOOTHLY RAMPED UP DEPENDING ON THE CRITICALITY..0.+. 1,020,3 405+) 61789-+ BT) MF100) :,$ +,-..) N.B ; P24 8<,+ ,=+ A22<>+5 2<954 -98 ?+ 7+4,70-,+5 <7 4>0,-=+5 <66 5+@+8508A <8 ,=+ 2<95 40,19,0<8 985 06 6<185 8+-+44973 51708A 983,0B+ <6 ,=+ 2<95 7+4,70-,0<8. CREATED BY; CHECKED BY; &