Float in Cofferdam Concept
Float in Cofferdam Concept
Float in Cofferdam Concept
Robert B. Bittner, P.E., President, Ben C. Gerwick, Inc. San Francisco, CA, USA
Large diameter piles (2 to 3-m diameter, both driven and drilled) are being used
more frequently by designers of bridge foundations. The use of these large
piles allows the pile cap to be positioned off the bottom but usually still below
water. Conventional cofferdams as shown in Figure 1 below are not suited to
this type of pile cap. However, float-in cofferdams offer a viable alternative.
This paper describes the float-in cofferdam system, its initial development for
use on the Bath-Woolwich Bridge in Maine and its most recent application on
the new Carquinez Bridge in California.
Introduction
Cofferdams are temporary structures used in the
construction of bridge piers and other marine
structures. Their primary purpose is to hold out
water and unstable soil from the construction
area, and thereby, allow in-the-dry construction
of the permanent structure below the water line
and quite often below the mud line. Typically,
cofferdams consist of long interlocking steel
sheet piles driven through water into the bottom
of the waterway.
The sheet piles form
temporary exterior walls which are typically
braced internally with wales and struts. The
bottom of the cofferdam is typically sealed with
tremie concrete or an impervious clay layer if
one exists. This type of cofferdam is typically
used for structures positioned at or below the
mud line.
Fig. 1
2.
3.
4.
5.
6.
7.
8.
Fig. 2
Fig. 4
Fig. 6
Fig. 5
Fig. 7
Fig. 8
3)
4)
obtained.
Additionally, selection of the
fabrication site should take into consideration
the method of launching.
(See launch
method below for specific details.)
Temporary
bulkheads
Temporary
bulkheads are typically steel ribbed elements
used to close off openings in the shell
structure, making the shell water tight and
allowing it to float after launch.
These
bulkheads are typically salvaged and re-used
on following caps.
The bulkheads are
typically bolted in place and use
compressible neoprene or rubber seals at the
mating surfaces to maintain water tightness.
(See Figs. 23 and 24 for a view of the
temporary bulkheads used on the Carquinez
Bridge float-in cofferdams.)
Pile-top bulkheads Pile-top bulkheads can
be classified as a special type of temporary
bulkhead. They are inverted open-bottomed
cans that are centered directly over the top
of the circular openings in the bottom of the
pre-fabricated shells.
They allow the
foundation piles to penetrate up into the
interior of the shell while maintaining the
watertight integrity of the float-in cofferdam.
(See Figs. 10 and 22 for examples of pile-top
bulkheads used on the Bath-Woolwich and
Carquinez bridges respectively.)
These
blockouts are of course watertight except for
the open bottom and can act as individual
ballast compartments if compressed air
hoses are attached to each compartment.
By regulating the air pressure in each pile-top
blockout, it is possible to level or trim the
float-in cofferdam during launch and
transport. (See Fig. 12 for a view of the air
piping used on the Bath-Woolwich Bridge.)
Follower steel cofferdams Follower
cofferdams are required for pile-top
structures that are positioned completely
under water. Follower cofferdams extend the
height of the prefabricated shell walls
sufficiently to allow the pile cap to be lowered
to final grade without allowing water to
overtop the cofferdam. These are typically
stripped at completion of the pier and re-used
on following piers. (See Figs. 14, 15 and 18
for pictures of the follower cofferdam used on
the Bath-Woolwich Bridge.) These follower
cofferdams are very similar to conventional
sheet pile cofferdams. They have the same
Examples
Bath-Woolwich Bridge
Ben C. Gerwick, Inc. (BCG) of San Francisco
working for Flatiron Structures Company of
Longmont, Colorado designed the floating
cofferdam system used on the Bath-Woolwich
Bridge across the Kennebec River at Bath,
Maine.
The
Maine
Department
of
Transportation awarded the design-construct
contract for the 1,000m long four lane bridge to
Flatiron Structures Company (FSC) and Figg
Engineers in August of 1997, and shortly
thereafter, FSC contracted with BCG to design a
cofferdam system for the six main river piers.
Figgs design for the six main river piers called
for two size footings: 10.9m by 9.9m by 3.6m
deep supported by four 2.44m diameter steel
cylinder piles socketed into rock and 9.6m by
9.6m by 3.6m deep supported by three piles of
the same size. The typical footings had a 2.7m
deep tremie seal and was located in 13m of
water with the top of the footing about 1.4m
below mean tide. This cap design significantly
reduced the water depth at which the footing
were to be constructed, however, it created the
problem of how to construct an underwater
footing suspended 6m above the river bottom.
In order to address this problem and reduce the
amount of work in the river, BCG proposed the
use of a floating cofferdam system (See plan
view in Fig. 2 and sequence of construction
shown in Figs. 3 through 8):
Pre-install the drilled shafts using a two stage
template.
Construct a precast pile-cap shell on shore and
attach a reusable temporary steel follower
cofferdam.
Launch the cofferdam and tow it to the bridge
site.
Position the cofferdam over the drilled shafts
and fix it in position with four spud piles.
Lower the cofferdam down over the preinstalled drilled shafts with jacks located on top
of the spud piles.
Lock the pile-cap shell to the drilled shafts by
placing a 1.3m deep tremie seal.
Fig. 9
10
11
12
13
14
Bibliography
1. Anderson, H. V.: Underwater
Construction Using Cofferdams,
2. Bittner, R. B.: Tapping Technology,
BRIDGE design & engineering, Issue
No. 14, First Quarter 1999, pp. 40-41.
3. Bittner, R. B. : Fast-track float-in,
BRIDGE design & engineering, Issue No.
24, Third Quarter 2001, pp. 38-40.
4. Ratay, R. T.: Handbook of Temporary
Structures in Construction , Chapter 7, by
Ben C. Gerwick, Jr.
5. Stubb, F. W., Jr.: Handbook of Heavy
Construction, 3rd Edition, Chapter 23,
Cofferdams and Caissons, by Ben C.
Gerwick, Jr.