Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Developing A Project Schedule (Cont'd) : - Calendars

Download as pptx, pdf, or txt
Download as pptx, pdf, or txt
You are on page 1of 6

Developing a Project Schedule

(Contd)
Calendars
Is the project going to be scheduled in
hours or days?
Will there be work activities that are
outside the normal work periods of the
project?
Will the project include week-ends and
holidays?

Developing a Project Schedule


(Contd)
Durations
Does the duration of each activity seem
practical and achievable?
Nature of the task critical to the project
or fill-in work?
Durations should be no less than 2-3
days nor longer than 15 days

Developing a Project Schedule


(Contd)
Resources
What resources should be
incorporated?
Tie resources to the level of the
activities
A good place to begin assigning
resources is from the budget or cost
estimate

Advanced Scheduling Topics

Resource Allocation
Constraints
Baselining the Plan
Updating / Reporting Progress
Controlling Change

Resource Allocation

Team Building
Matching Skills to Activities
Estimating Hours
Assigning to Activities
Over allocated?

Resource Histogram
ber
11/17 11/24

12/1

December
12/8 12/15 12/22 12/29

1/5

January
1/12 1/19

1/26

2/2

170

200

235

268.1 88.81

50

96.85

February
2/9
2/16

2/23

3/2

March
3/9
3/16

3/23

300%

250%

200%

150%

100%

50%

30

100

Graphics Support

224.96
Ov erallocated:

6.29

Allocated:

Shows the group and/or individual workload


against available resources
Helps assess if the work can be done based on
people involved

You might also like