Generators
Generators
NEC, NFPA 70, NFPA 70E and National Electrical Code are registered trademarks of the National Fire Protection Association.
1.11.13
Introduction
This small booklet contains a small sample of the 2011 NEC rules related to generators. As a continued service to the
industry, we are making this available at no charge. If you have any suggestions on how it can be improved, please
let me know by emailing me at Mike@MikeHolt.com.
God bless,
Mike Holt
ARTICLE
220
Branch-Circuit, Feeder,
and Service Calculations
ARTICLE
445
Generators
ductors from the generator to distribution devices containing overcurrent protection must not be less than 115 percent of the nameplate
current rating of the generator. Figure 4451
445.11 Marking. Each generator must be provided with a nameplate indicating the manufacturers name, rated frequency, power
factor, number of phases, rating in kilowatts or kilovolt amperes, volts
and amperes corresponding to the rating, RPM, insulation class and
rated ambient temperature or rated temperature rise, and time rating.
Figure 4451
Figure 4454
Figure 4452
Carry the maximum unbalanced current as determined by
220.61.
Serve as the low-impedance fault current path.
Separately derived system generators must have the neutral conductor sized not less than required to carry the maximum unbalanced
current as determined by 220.61.
Authors Comment: If the feeder conductors from the generator terminate in a transfer switch that doesnt open the neutral
conductor, the generator isnt considered a separately derived
system [250.30 Note 1]. Figure 4453. A neutral-to-case bond
isnt permitted at the generator. Under this condition, the neutral
conductor from the normal power to the transfer switch, and the
neutral conductor from the generator to the transfer switch, are
required to provide the low-impedance fault current path back to
the power source. Figure 4454
Authors Comment: If the feeder conductors from the generator terminate in a transfer switch that opens the neutral
conductor, the generator is considered a separately derived
system [Article100]. Figure 4455. A neutral-to-case connection (system bonding jumper) is required at the generator
[250.30(A)(1)] to provide a low-impedance fault current path
back to the power source. Figure 4456
Figure 4455
Figure 4453
Figure 4457
Figure 4456
(1) The driving means for the generator can be readily shut down,
and
Caution: If one generator is used to supply emergency, legally required, as well as optional standby
power, then there must be at least two transfer
switches; one for emergency power and another for legally
required as well as optional stand-by power [700.6(D)].
ARTICLE
700
Emergency Systems
Part I. General
700.1 Scope. Article 700 applies to the installation, operation,
and maintenance of emergency systems. These consist of circuits and
equipment intended to supply illumination or power within 10 seconds [700.12] when the normal electrical supply is interrupted. Figure
7001
Note 3: Emergency systems are generally installed where artificial illumination is required for safe exiting and for panic control in
buildings subject to occupancy by large numbers of persons, such
as hotels, theaters, sports arenas, health care facilities, and similar institutions.
Figure 7001
700.2 Definitions.
Emergency Systems. Emergency systems are those systems legally
required and classed as emergency by a governmental agency having
jurisdiction. These systems are intended to automatically supply illumination and/or power essential for safety to human life. Figure
7002
Figure 7002
Figure 7004
Authors Comment: Multiple transfer switches are required
where a single generator is used to supply both emergency
loads and other loads.
700.7 Signs.
(A) Emergency Sources. A sign must be placed at the serviceentrance equipment indicating the type and location of on-site emergency power sources. Figure 7005
Figure 7006
(B) Wiring. To ensure that a fault on the normal wiring circuits wont
affect the performance of emergency wiring or equipment, all wiring
to emergency loads must be kept entirely independent of all other
wiring, except:
(1) Wiring in transfer equipment. Figure 7007
(2) Luminaires supplied from two sources of power.
(3) A junction box attached to luminaires supplied from two sources
of power.
(4) Wiring within a common junction box attached to unit equipment,
containing only the branch circuit supplying the unit equipment
and the emergency circuit supplied by the unit equipment.
(5) Wiring from an emergency source is permitted to supply any
combination of emergency, legally required, or optional standby
loads in accordance with (a), (b), and (c).
a. From separate vertical switchboard sections or from individual
disconnects mounted in separate enclosures.
Figure 7005
Figure 7007
Ex to (5)(b): Overcurrent protection is permitted at the source or for
the equipment, provided the overcurrent protection is selectively
coordinated with the downstream overcurrent protection.
c. Legally required and optional standby circuits dont originate
from the same vertical switchboard section, panelboard enclosure, or individual disconnect enclosure as emergency circuits.
Authors Comment: Separation of the circuits served by a
generator source for emergency, legally required, and optional
standby circuits may be accomplished by running feeders
from a single generator to individual overcurrent devices or to
a distribution switchboard that separates emergency circuits in
different vertical sections from other loads.
(C) Wiring Design and Location. Emergency wiring circuits must be
designed and located to minimize the hazards that might cause failure
due to flooding, fire, icing, vandalism, and other adverse conditions.
Figure 7008
Figure 7009
(C) Uninterruptible Power Supplies. Uninterruptible power supplies
serving as the emergency power source must comply with the applicable requirements of 700.12(A) and (B).
(F) Unit Equipment. Individual unit equipment (an emergency lighting
battery pack) must consist of the following: Figure 70010
Figure 70011
Authors Comment: There are two reasons why the emergency
lighting battery packs must be connected ahead of the switch
controlling the normal area lighting: (1) in the event of a power
loss to the lighting circuit, the emergency battery lighting packs
will activate and provide emergency lighting for people to exit
the building, and (2) the emergency lighting battery packs wont
turn on when the switch controlling normal lighting is turned off.
Figure 70010
10
700.16 Emergency Illumination. Emergency lighting systems must be designed and installed so that the failure of any individual lighting element, such as the burning out of a lamp, wont leave in
total darkness any space that requires emergency illumination.
Authors Comment: This means that a single remote head is
never sufficient for an area. A minimum of two lighting heads is
always required. This is why individual unit equipment (sometimes called lunchboxes in the field) always has two lighting
heads.
700.27 Coordination. Overcurrent devices for emergency systems must be selectively coordinated with all supply-side overcurrent
devices.
Authors Comment: Selective coordination means the overcurrent protection scheme confines the interruption to a particular
area rather than to the whole system. For example, if a short circuit or ground fault occurs with selective coordination, the only
breaker/fuse that will open is the one protecting just that branch
circuit. Without selective coordination, an entire floor of a building can go dark. See Article 100 for the definition of the term
Coordination, Selective.
11
ARTICLE
701
Legally Required
Standby Systems
Part I. General
701.1 Scope. The provisions of Article 701 apply to the installation, operation, and maintenance of legally required standby systems
consisting of circuits and equipment intended to supply illumination
or power when the normal electrical supply or system is interrupted.
Authors Comment: Legally required standby systems provide
electric power to aid in firefighting, rescue operations, control of
health hazards, and similar operations.
701.2 Definitions.
Legally Required Standby Systems. Legally required standby systems are those systems classified as legally required by any governmental agency having jurisdiction. These systems are intended
to automatically supply power to selected loads (other than those
classed as emergency loads) in the event of failure of the normal
power source.
Note: Legally required standby systems typically supply loads such
as heating and refrigeration systems, communications systems,
ventilation and smoke removal systems, sewage disposal, lighting
systems, and industrial processes that, when stopped, could create
hazards, or hamper rescue or firefighting operations.
(C) Battery Systems Maintenance. If batteries are used, the authority having jurisdiction must require periodic maintenance.
(D) Written Record. A written record must be kept of all required
tests and maintenance.
Authors Comment: The NEC doesnt specify the required
record retention period.
12
Figure 7012
Figure 7011
701.7 Signs.
(A) Mandated Standby. A sign must be placed at the serviceentrance equipment indicating type and location of on-site legally
required standby power sources. Figure 7012
(2) Internal Combustion Engines as Prime Movers. If internal combustion engines are used as the prime mover, an on-site fuel supply
must be provided for not less than 2 hours of full-demand operation
of the system. Figure 7013
(5) Outdoor Generator Sets. If a generator located outdoors is
equipped with a readily accessible disconnecting means located
within sight of the building/structure, an additional disconnecting
means isnt required on or at the building/structure for the generator feeder conductors that serve or pass through the building/structure. Figure 7014
ted to occupy the same raceways, cables, boxes, and cabinets with
other general wiring.
13
Figure 7013
Figure 7015
To minimize the possibility of simultaneous interruption of the legally
required standby supply, a separate service drop or lateral must be
electrically and physically separated from all other service conductors.
(E) Connection Ahead of Service Disconnecting Means. If
approved by the authority having jurisdiction, connection ahead of, but
not within, the same cabinet, enclosure, or vertical switchboard section as the service disconnecting means is permitted. Figure 7016
Figure 7014
Authors Comment: According to Article 100, within sight
means that its visible and not more than 50 ft from one to the
other.
(C) Uninterruptible Power Supplies. Uninterruptible power supplies
serving as the legally required standby power source must comply
with 701.12(A) and (B).
(D) Separate Service. If approved by the authority having jurisdiction,
an additional service installed in accordance with Article 230 is permitted to serve as a legally required source of power. Figure 7015
Figure 7016
14
15
ARTICLE
702
Part I. General
702.1 Scope. The systems covered by Article 702 consist of those
permanently installed, including prime movers, and those arranged
for a connection to a premises wiring system from a portable alternate power supply. Figure 7021
Authors Comment: A portable generator that provides temporary power, like those used on construction sites, doesnt fall
within the scope of Article 702 unless the generator is permanently connected to the premises wiring. Figure 7022
Figure 7022
Figure 7021
16
Figure 7023
Figure 7024
17
(A) Standby Power Sources. A sign that indicates the type and location of on-site optional standby power sources must be placed at the
service-entrance equipment. Figure 7025
Figure 7025
Figure 7026
18
Practice Questions
Please use the 2011 Code book to answer the
following questions.
2.
ARTICLE 445Generators
1.
2.
3.
4
Separately derived system generators must have the _____
conductor sized not smaller than required to carry the
maximum unbalanced current as determined by 220.61.
5.
(a) neutral
(b) grounding
(c) a and b
(d) none of these
1.
6.
A written record shall be kept of required tests and maintenance on emergency systems.
(a) True
(b) False
19
(a) True
(b) False
8
9.
14. A sign shall be placed at the service-entrance equipment indicating the type and location of on-site emergency power sources.
(a) True
(b) False
15. Wiring from an emergency source or emergency source distribution overcurrent protection to emergency loads shall be kept
independent of all other wiring and equipment except in ______.
(a) transfer equipment enclosures
(b) exit or emergency luminaires supplied from two sources
(c) load control relay supplying emergency or exit luminaires or
a common junction box attached to exit or emergency luminaires supplied from two sources
(d) all of these
17.
(a) flooding
(b) fire
(c) icing
(d) all of these
Emergency circuit wiring shall be designed and located to minimize the hazards that might cause failure because of ______.
18.
In the event of failure of the normal supply to the building/structure, emergency power shall be available within ______ seconds.
(a) 5
(b) 10
(c) 30
(d) 60
20
(a) flooding
(b) fires
(c) icing, and vandalism
(d) all of these
20. A storage battery supplying emergency lighting and power
shall maintain not less than 87 percent of normal voltage at
total load for a period of at least ______ hour(s).
(a) 1
(b) 1
(c) 2
(d) 2
21. Where an internal-combustion engine is used as the prime
mover for an emergency system, an on-site fuel supply shall be
provided for not less than ______ hours of full-demand operation of the system.
(a) 2
(b) 3
(c) 4
(d) 5
Manual switches controlling emergency circuits shall be convenient to authorized persons responsible for their ______.
(a) maintenance
(b) actuation
(c) inspection
(d) evaluation
(a) True
(b) False
21
5.
(a) True
(b) False
6.
7.
Legally required standby systems that are tested upon installation and found to be acceptable to the authority having
jurisdiction shall not be required to undergo any future tests
unless the equipment is modified.
(a) True
(b) False
4.
8.
A written record shall be kept of required tests and maintenance on legally required standby systems.
9.
22
16. Where acceptable to the authority having jurisdiction, connections ahead of and not within the same cabinet, enclosure,
or vertical switchboard section as the service disconnecting
means shall be permitted for ______ standby service.
(a) emergency
(b) legally required
(c) optional
(d) all of these
17. Individual unit equipment for legally required standby illumination shall be permanently fixed in place. Flexible cord-and-plug
connection shall be permitted, provided the cord does not
exceed ______ in length.
(a) 12 in.
(b) 18 in.
(c) 3 ft
(d) 6 ft
18. The branch-circuit overcurrent devices for legally required
standby systems shall be accessible only to ______.
14. Legally required standby system wiring can occupy the same
raceways, cables, boxes, and cabinets with other generalpurpose wiring.
(a) True
(b) False
15. A generator set for a legally required standby system shall
______.
(a) have means for automatically starting the prime mover
(b) have 2 hours of fuel supply for full demand operation available on-site if the prime mover is an internal combustion
engine
(c)
not be solely dependent on a public utility gas system
unless acceptable to the AHJ
(d) all of these
(a) True
(b) False
20. Overcurrent devices for legally required standby systems shall
be ______ with all supply-side overcurrent devices.
(a) series rated
(b) selectively coordinated
(c) installed in parallel
(d) any of these
23
2.
4.
(a) True
(b) False
5.
8.
Optional standby systems utilizing automatic transfer equipment shall have adequate capacity and rating for the supply of
______.
A sign shall be placed at the service-entrance equipment indicating the ______ of on-site optional standby power sources.
(a) type
(b) location
(c) manufacturer
(d) a and b
7.
6.
9.
24
(b) 701.2
(b) 701.3(A)
(b) 701.3(B)
(c) 701.3(C)
(a) 701.3(D)
(b) 701.3(E)
(a) 701.4
(a) 701.4
(d) 701.5(A)
(b) 701.5(B)
(b) 701.5(C)
(d) 701.6(A),(B), and (C)
(d) 701.7(A)
(a) 701.1
(d) 701.12(B)(1),(2), (3), and (3)Ex
(b) 701.12(E)
(c) 701.12(G)
(b) 701.25
(a) 701.26
(b) 701.27 Coordination
25