Project Execution Plan Example
Project Execution Plan Example
Contents
Acronyms/Abbreviations .............................................................................................................................. v
1.0
Introduction ......................................................................................................................................... 1
1.1 Overview ................................................................................................................................... 1
1.2 Purpose ...................................................................................................................................... 3
1.3 Approval and Revisions ............................................................................................................ 4
2.0
3.0
4.0
5.0
6.0
7.0
ii
8.0
Risk Management.............................................................................................................................. 25
9.0
iii
Figures
1.
2
3
4
5
6
7
Tables
1
2
3
4
5
6
iv
Acronyms/Abbreviations
325 Building
3410 Building
3420 Building
3425 Building
3430 Building
Shielded Operations
Materials Science & Technology
Radiation Detection
Ultra-low Background/Deep Lab
Ultra-Trace
AE
A/E
acquisition executive
architectural/engineering
BA
BCP
BO
BSF
Budget Authority
Baseline Change Proposal
Budget Obligation
Biological Sciences Facility
CCB
CD
CPD
CRL
CSF
DHS
DOE
DOE-RL
DSA
EA
EIR
EM
EPHA
ESAAB
ES&H
EVMS
Environmental Assessment
External Independent Review
DOE Office of Environmental Management
Emergency Preparedness Hazards Assessment
Energy Systems Acquisition Advisory Board
Environmental, Safety and Health
Earned Value Management System
FPD
HAR
HRT
HVAC
IES&H
IOPS
IPR
IPT
LEED
M&O
NEPA
NNSA
OECM
PARS
PEP
PIP
PMB
PMP
PNNL
PNSO
PSF
QAP
QAPD
RMP
RPL
SAE
SBMS
SC
SCC
TEC
TPC
VE
values engineering
WBS
vi
1.0 Introduction
1.1 Overview
The U.S. Department of Energy (DOE) is required under the Tri-Party Agreement with its regulators to
complete surplus facility disposition and remedial action clean-up of the Hanford Site 300 Area by 2015.
With about half of the space used by Pacific Northwest National Laboratory (PNNL) in the 300 Area
supporting their research programs, the DOE Office of Science (SC), the National Nuclear Security
Administration (NNSA), and the Department of Homeland Security (DHS) have undertaken the
Capability Replacement Laboratory Projects (CRL). The CRL projects will ensure the long-term viability
of the PNNL and preserve the following vital research capabilities:
Systems Biology
Environmental Science/Biomarkers
Subsurface Science
Materials Science & Technology
Chemistry (Radio, Actinide, Analytical) and Processing
Shielded Operations (Category 3)
Radiation Detection
Ultra-trace/Signature Detection
Information Analysis
Certification and Dosimetry.
The CRL projects will preserve these capabilities by constructing new facilities, renovating existing
facilities, installing new utility infrastructure and relocating staff and existing research equipment. A
federally funded line item project, the Physical Sciences Facility (PSF), will construct several new
buildings, collectively referred to as the Physical Sciences Facility (PSF-HRT), and perform life
extension modifications to the existing 325 Building. A developer will construct two privately financed
facilities, the Computational Sciences Facility (CSF) and the Biological Sciences Facility (BSF). Minor
renovations will be performed on the 318, 331 and 350 Buildings. This Project Execution Plan (PEP) will
focus exclusively on the PSF. The scope of the other CRL projects are described in the CRL project
Implementation Plan (PIP) (CRL-PLAN-PM-005) as a reference document to this PEP. The PIP
describes how each of the projects relates to the others and defines interface points. The CRL projects are
shown in Figure 1. The CRL Work Breakdown Structure (WBS) is shown in Figure 2. The PSF new
construction is shown in Figure 3.
1 of 46
PSF-325
318
350
331
PSF-HRT
BSF
CSF
PSF - HRT
Ultra-trace
Radiation Detection
PSF - 325
Shielded Operations
Radiation Detection
Systems Biology
BSF
3rd Party
CSF
Environmental Biomarkers
Figure 1.
Facilities Included in the CRL Projects Scope of Work. The PSF new construction and
325 Building Life Extension efforts are captured as the PSF Line Item scope in this PEP.
2 of 46
1.2 Purpose
This PEP defines the PSF project and describes planning, assumptions, constraints, roles, responsibilities,
authorities, management interactions, and interface management necessary to successfully execute the
PSF project. This PEP was prepared in accordance with the DOE Order 413.3A Program and Project
Management for the Acquisition of Capital Assets. The Deputy Secretary has previously designated the
PSF project as a Major System Project because it is jointly funded by SC, NNSA and DHS. The DOE
Deputy Secretary is the Acquisition Executive (AE) for the PSF project. As part of Critical Decision-2
(CD-2) approval, delegation of AE authority to the Under Secretary for Science will be requested and the
PSF Line Item project will be designated a Non-MSA Project. This PEP is written with the assumption
that after CD-2, the AE for the PSF project will be the Under Secretary for Science.
3 of 46
4 of 46
5 of 46
Among the applications of these capabilities are to provide advanced detection and analysis systems to
prevent nuclear proliferation and terrorism; radiochemistry and radiochemical processing for attribution
and mitigation of potential radiological dispersion devices and development of proliferation-resistant fuel
cycles; and materials science to increase nuclear plant life and to develop advanced materials for future
fission and fusion reactor applications and other advanced energy systems. More information on each
capability can be found in the Mission Needs Validation Report dated February 25, 2005.
6 of 46
7 of 46
8 of 46
Authority and responsibility for managing DOE programs and facilities resides with the Secretary of
Energy. Although the TPC of the PSF project is $224 million, because of the complexities of the project
including funding provided by various sources (SC, NNSA, and DHS), the Deputy Secretary is currently
designated as the AE for the project. Specific responsibilities of the AE for the PSF project include:
Chairs the ESAAB Equivalent Board
Approves CDs and project change controls as specified in Table 7.
Approves the PEP
Delegates approval authority for Level-2 baseline changes and future CDs.
4.1.2
SC has been delegated responsibility for comprehensive, long-range, basic energy-related research,
including state-of-the-art research facilities crucial to achieving goals described in the DOE Strategic
Plan.
The Under Secretary for Science, who is also the Director for SC provides overall program policy and
guidance, technical oversight, and budgets for implementing its assigned role. The DOE Deputy
Secretary is the Acquisition Executive for the PSF project, but has delegated overall management of the
Project to the Under Secretary for Science. Under this delegation, the Under Secretary for Science has
full responsibility for project planning and execution and for establishing broad policies and requirements
for achieving project goals.
4.1.3
Program management responsibility for the CRL mission, including the PSF, has been assigned to the
CRL Program Manager within the DOE Office of Biological and Environmental Research (SC-23). In
addition to SC-23, the Program Manager is supported by other SC organizations in the planning,
budgeting and execution of this mission. With regard to this project, the Program Manager reports
directly to the Under Secretary for Science.
The Program Managers role and responsibilities are summarized as follows:
Communicates direction from the Acquisition Executive to the project
Oversees development of project definition, scope and budget
Defines programmatic mission requirements and objectives
Establishes programmatic requirements for nuclear safety and recommends operational readiness to
the SC nuclear safety authorization authority
Prepares, defends and provides project budget with support from the field and SC headquarters
organizations
Reviews and provides recommendations to the Acquisition Executive on Level-0 and Level-1
baseline changes
9 of 46
Functions as the primary point-of-contact at DOE headquarters for project matters to all parties
external to the project team and SC
Develops project performance measures, and monitors and evaluates project performance throughout
the life cycle of the project
Organizes reviews as necessary
Ensures that environment, safety and health (ES&H) requirements are implemented by the project
Coordinates with other SC offices, project sponsors and the DOE Office of Engineering and
Construction Management as needed to execute the project
Controls changes to project baselines in accordance with the PSF PEP.
4.1.4
The PNSO reports to SC and administers the M&O contract with Battelle Memorial Institute, which
includes day-to-day oversight of PNNL. In carrying out its oversight responsibilities, PNSO obtains
matrix support in various technical disciplines from the SC Integrated Support Centers. In addition to the
site office, the DOE Richland Operations Office (DOE-RL) has assigned a senior executive to coordinate
and resolve conflicted activities of the CRL mission that cross DOE organizational boundaries with EM
and RL.
The execution of the PSF project is the responsibility of the FPD. The PNSO Manager will ensure that
the FPD has priority access to PNSO resources and, when necessary, resources at the SC Integrated
Support Center, for that purpose. The FPDs responsibilities and authorities include the following:
Provides day-to-day oversight of the project and direction to ensure timely execution
Monitors, reviews, evaluates and reports on the performance of the project against established
technical, cost, and schedule performance baselines
Ensures ES&H is integrated into the project
Leads the Integrated Project Team (IPT)
Controls changes to project baselines in accordance with the PEP
Participates in Quarterly Project Reviews, ESAAB Equivalent Board meetings, and project reviews
conducted by the PSF project and DOE headquarters
Maintains project data in the DOE Project Assessment and Reporting System (PARS)
Issues Project Directive Authorizations for disbursement of funds and work authorizations
Prepares project documents
Coordinates matrix support from the SC Integrated Support Centers
Prepares and submits budget and funding documents to the Office of Biological and Environmental
Research Program Manager (e.g., Congressional Project Data Sheet and Exhibit 300).
10 of 46
PNNL Director
The PNNL Director is responsible for managing all activities at the PNNL site, including ensuring that all
laboratory programs meet the requirements of DOE Contract DE-AC05-76RL01830 between Battelle
Memorial Institute and DOE. Having delegated the authority to manage and execute the PSF project to
the CPD, the PNNL Director will ensure that the CPD has priority access to PNNLs resources to achieve
project goals. Key PNNL project staff and their roles and responsibilities are depicted in Figure 5.
4.2.2
The CPD has overall implementation responsibility for the full scope of project activities, which include
the PSF Line Item. In this role, the CPD is a member of the PNNL Directors Office and reports directly
to the PNNL Director. The CPD is responsible for the project staff selection at PNNL and at other
institutions collaborating in the project. Specific responsibilities of the CPD include:
Manages day-to-day execution of the project at PNNL and any other collaborating institutions
Establishes technical and administrative controls to ensure project is executed within approved cost,
schedule and technical scope
Ensures that project activities are conducted in a safe and environmentally sound manner
Ensures ES&H responsibilities and requirements are integrated into the project
Directs overall project planning
11 of 46
Ensures integration of the existing 300 Area research and development programs with the design,
fabrication, installation, construction and commissioning of the project
Represents the project in interactions with DOE; participates in management meetings with DOE and
communicates project status and issues
Chairs the Change Control Board (CCB)
Approves Level-3 change control proposals; prepares and provides recommendations to the FPD for
Levels-0, -1 and -2 change control proposals
Identifies and manages project risks.
The CPD is responsible for implementing the PSF project baseline. The CPD will report directly to the
FPD and will serve as the technical and contracting integrator on the PSF project. The CPD has
established a project organization to accomplish the PSF project. The project team includes staff who
report directly to the CPD and matrix staff. For the purposes of accomplishing PSF project activities,
both direct and matrix members of the team provide management and support services to the project and
take project direction from the CPD director.
PNNL will provide project management, integration, contracting, procurement services, technical and
engineering support, and other services as needed for the project. The PNNL technical team also is
responsible for oversight of the design, construction, facility operational component procurement,
equipment installation and testing and startup. In carrying out these responsibilities, PNNL will
Perform technical reviews of the deliverables
Integrate future facility operational components into existing PNNL facility management systems
Implement an Earned Value Management System (EVMS) to track performance against an approved
Performance Measurement Baseline (PMB)
Develop an annual work plan for each sub-project
Comply with the requirements of the PNNL Performance Evaluation and Management Plan as
conveyed via contract
Be responsible for implementing the facility capability replacement, including design, permitting,
material and equipment procurement, infrastructure development, facility construction, equipment
installation and component testing and startup
Be responsible for overall project management and integration, technical and engineering support,
and other services as needed.
Contractor Deputy Project Director
The Contractor Deputy Project Director provides senior technical oversight; assists in mitigating project
risks and has delegated approval authority from the CPD.
HRT New Construction Project Manager
The HRT New Construction Project Manager is responsible for the design, construction, startup and
turnover to operations of the new facilities in the HRT, including 3410 Building Materials Science &
12 of 46
Technology, 3420 Building Radiation Detection, 3425 Building Ultra-low Background/Deep Lab and
3430 Building Ultra-Trace.
325 Building Project Manager
The 325 Building Project Manager is responsible for the 325 Building life-extension upgrades for retained
radiological and nuclear facilities and provides project oversight of the design, construction and readiness
activities.
Internal/External Interfaces
The PSF project has internal and external interfaces that will be managed by the FPD, members of the
IPT and the CPD. External interfaces are with organizations or individuals outside the oversight
responsibility of PNSO and/or PNNL (i.e., NNSA, DHS, EM, State of Washington, City of Richland).
Internal interfaces are between PNSO and PNNL, the FPD and the CPD, members of the IPT and the
various organizations and contractors involved in the project. Interfaces also exist among the contractors
providing services to the PSF project and Hanford (i.e., A/E, commissioning, other project support
activities). Interface issues are anticipated to be technical, as well as associated with communications and
decision-making.
13 of 46
OPCa
($million)
$5.8
$$1.5
$4.3
$2.2
$.011
$14.0
PEDb
($million)
$23.8
$4.8
$$$$$28.5
PSF
Construction
($million)
$2.0
$15.1
$58.8
$77.1
$19.3
$9.9
$181.5
BA (Funds)
($million)
$31.6
$19.9
$60.4
$81.5
$21.6
$9.0
$224.0
Table 2 shows the estimated contributions from the PSF funding agenciesSC, NNSA and DHS.
Table 2. Total Project Annual Funding Requirements
$18,470
$10,896
$2,250
$31,616
FY 2007
$7,920
$10,000
$2,000
$19,920
FY 2008
$0
$35,379
$25,000
$60,379
FY 2009
$37,919
$30,549
$13,000
$81,468
FY 2010
$3,625
$7,977
$10,000
$21,602
FY 2011
Total
$1,689 $69,623
$3,643 $98,444
$3,684 $55,934
$9,016 $224,000
Note: SC committed to funding mission critical requirements above $224 M (e.g., $2M Large Detector Laboratory)
without any additional costs to NNSA and DHS.
As a result of the conceptual design process to-date, it has become evident that significant cost savings
and research efficiency gains can be achieved if replacement facilities are constructed to maximize
capability synergies. Doing so, however, means that funding from multiple sponsors will need to be
aggregated and applied to the overall effort.
A Memorandum of Understanding agreeing to pursue these funding shares to support the project was
signed on November 7, 2006, by the principals from each agency (see Attachment A).
14 of 46
1.1.02 HRT
Facilities
1.1.01.01 Project
Mgmt & Business
Systems Integration
1.1.02.01 HRT
Facilities Integration
1.1.01.02
Environmental Safety
& Health
1.1.02.02
Engineering, Design
& Inspection
1.1.01.03 Quality
Assurance
1.1.02.03 Safety
Basis
1.1.01.04 R&D
Liaison
1.1.02.04 Facility
Construction
1.1.02.05
Operational Startup
& Readiness
1.1.02.06 Site
Permitting
15 of 46
Work Authorization
Work by project participants will be authorized using processes consistent with DOE O 412.1,
Work Authorization System. Funding will be distributed to PNNL using the Financial Plan
Authorization process. Critical Decision approval authority is reflected in Table 3.
Table 3. Critical Decision Approval Authority
Critical Decision Milestone
Approval Authority
Deputy Secretary
Deputy Secretary
Deputy Secretary
Under Secretary for
Science
Under Secretary for
Science
Under Secretary for
Science
Under Secretary for
Science
16 of 46
6.1.1
Physical Boundaries. The physical boundaries of this WBS element are consistent with Battelle
management, regulatory and administrative services provided in support of developing the HRT site and
within the physical perimeters of the 325 Building site within the 300 Area.
Completion. This WBS element will be considered complete when the Acquisition Executive or his
designee approves CD-4b, PSF Project Closeout.
Work Scope Description. This WBS element will deliver resources for general management, project
integration and support services for the retention and relocation of PNNL capabilities in accordance with
the PSF project objectives. This includes establishing and maintaining effective working relationships
between the FPD, the IPT and the PNNL Director. The resources within this task will direct and support
efforts required to successfully support design, modifications, commissioning, startup and occupancy of
the PNNL facilities and associated infrastructure related to WBS elements 1.1.02, HRT Facilities, and
1.1.03, 325 Building Life Extension Improvements. This scope includes identifying and assessing all
vulnerabilities and ensuring managerial action is taken to prevent adverse consequences to the PSF
project.
6.1.2
Physical Boundaries. The PSF new construction includes all new facilities and supporting infrastructure
on the HRT.
Completion. This WBS element will be considered complete when all facilities are complete, the
transition to operation requirements in PEP Section 11.0 have been met, and the AE or his designee
approves CD-4b, Project Closeout.
Work Scope Description. This WBS element will provide the necessary infrastructure and facilities to
relocate the following capabilities from the 300 Area to the HRT: materials science and technology,
radiation detection, ultra-trace, and chemistry and processing (non-nuclear). Design, construction,
commissioning, readiness assessment, and turnover to operations of the following key project deliverables
are included. The following are included in this WBS element:
17 of 46
Facility engineering, design, inspection and commissioning will be performed by a subcontracted A/E.
6.1.3
Physical Boundaries. The 325 Building life extension includes all modifications to the existing facility
in the 300 Area.
Completion. This WBS element will be complete when the approval authority has transitioned from EM
to SC and all physical verifications are complete and operationally accepted.
Work Scope Description. This WBS element will perform necessary modifications and upgrades to
extend the useful life of the existing 325 Building (also known as the Radiochemical Processing
Laboratory [RPL]) for a minimum of 20 years. This work includes definitive design, engineering and
inspection services, and authorization basis updates required to modify the facility and extend the
facilitys operating life. This includes preparation of drawings, specifications and acceptance test
procedures to support site work, building alterations and support equipment, furnishings, and
authorization or regulatory document revisions. Facility engineering, design and inspection, safety basis
technical document preparation and natural phenomena analysis will be performed by a subcontracted
A/E. PNNL will provide nuclear safety expertise, processes and procedures as well as design,
construction and construction management services required to modify the 325 Building.
To support increased heating, ventilation, and air conditioning (HVAC) capacity requirements,
modernization of the 325 Building will include removal of fume hoods, design, fabrication and
installation of new hot cells and glove boxes. In addition, roof repairs, replacement of personnel
contamination monitoring systems and various HVAC components , design and construction of new
second-floor access and structural seismic upgrades recommended by the 10-year update of the natural
phenomena hazards assessment will be performed.
6.2 Cost
The TPC is $224 million. The PSF project cost estimate by WBS is shown in Figure 7.
Project Cost Estimate by Client Reporting Level
WBS
Description
1.1.1
1.1.2
1.1.3
(multiple)
Budget ($M)
CD-2 Baseline
16.7
123.9
32.9
11.8
185.3
38.7
224.0
24%
18 of 46
6.3 Schedule
The master schedule is consistent with the WBS and is coordinated with interfacing projects to ensure
PNNL transition from the 300 Area supports cleanup objectives and results in minimal impact to research
operations. The integrated master schedule is developed and maintained by PNNL in the Primavera P3
Cost and Scheduling software. The Projects critical path runs through the HRT new construction.
The PSF project Level 1 milestones are shown in Table 4, and Level 2 milestones are shown in Table 5.
Table 4. PSF Project Level 1 Milestones
Level and
Number
Milestone Description
1-1
CD-0 Approve Mission Need
Revalidated
1-2
CD-1 Approve Preliminary Baseline Range
Revised
1-3
CD-2 Approve Performance Baseline
1-4
CD-3a Approve Start of Construction site work, foundation and structural steel
for the HRT Facilities
1-5
CD-3b Approve Start of Construction Balance of construction
1-5
CD-4a Completion of readiness activities for the first Horn Rapids Triangle facility
(Ultra-Trace) and subsequent declaration of readiness to operate. Approval
authorizes the start of operations of the first HRT facility (3430 Ultra-Trace).
1-6
CD-4b Completion of readiness activities and subsequent declaration of readiness
of the last HRT facility (3420-Radiation Detection) and 325 Building. Completion
marks the transition to operations of the final HRT facility and the start of PSF
project closeout activities.
Completion Date
September 2004 (A)
February 2005 (A)
December 2005 (A)
December 2006 (A)
June 2007
July 2007
February 2008
January 2010
February 2011
Activity
Number
SM1007
SM1080
SM1131
SM1012
SM1058
SM1024
SM1107
SM1239
SM1149
SM1031
SM1133
SM1032
SM1034
SM1094
SM1030
SM1035
SM1074
SM1105
SM1195
Description
Award Early Sitework Contract PSF
Complete Final Design
Award Steel Contract
Submit CD-3B Package
Award Balance of Construction Contract
Complete Structural Steel Contract
Submit 325 Building Modernized DSA for DOE Approval
325 Bldg Infrastructure Upgrade Complete
325 Bldg Construction Complete
3420-Ultra-trace Facility Construction Complete
Authorization to Operate 3420-Ultra-trace
3410-MS&T Facility Construction Complete
3420-Rad Detection Facility Construction Complete
3425- Ultra-low Background/Deep Lab Construction Complete
Central Utility Plant Facility Construction Complete
PSF Facility Construction Complete
Authorization to Operate 3410-MS&T
Authorization to Operate 3420-Rad Detection
Authorization to Operate 3425 Ultra-low Background/Deep Lab
19 of 46
Completion
Date
18-Jul-07
26-Sep-07
8-Nov-07
9-Jan-08
5-May-08
7-Nov-08
20-Mar-09
6-Mar-09
9-Mar-10
15-Jan-10
26-Apr-10
17-May-10
22-Jun-10
22-Jun-10
29-Jun-10
21-Jul-10
2-Aug-10
21-Sep-10
21-Sep-10
The PSF project has implemented a project management control system. This system provides the
essential earned value information needed for management control of the project and maintains the
database for progress reporting. The system integrates the cost and schedule baselines and provides the
tools to monitor project performance. The data from the control system is the basis for information
entered into PARS.
The PSF project controls changes in functional and physical requirements and evaluates the impact of
changes on cost and schedule through a baseline change control process. The process promotes orderly
evolution from the baseline design, and ensures that the effect of changes on cost, schedule and technical
scope performance are properly evaluated and documented by project management. A Baseline Change
Proposal (BCP) must be initiated when there will be an impact on any of the cost, schedule or scope
baselines. Thresholds for determining the BCP approval level during project execution, per
DOE O 413.3A, are delineated in Table 6.
The CPD has established a change control process in accordance with EVMS criteria to address changes
at Level 3 and below. A CCB has been established for Level 2 and above changes requiring DOE
approval. The board includes the Chairman (the CPD), a change control manager and board members as
defined by the Change Board Charter. At a minimum, the CCB consists of the CPD, the FPD and the SC
Program Manager. The board members review the technical, cost and schedule impacts of changes and
advise the Chairman. All BCP actions are maintained in a change control log.
Congressional notification is required when a project change results in a 25 percent increase in the total
estimated cost (TEC). Project changes caused by Congressional action, such as a funding shortfall or the
addition of new requirements, will be called directed changes. Directed changes will follow the change
control process and will be approved by the appropriate authority.
Several key milestones have been selected as performance measurement control points by the FPD.
These milestones are listed in Table 5, are defined to be Level 2 milestones, and will be controlled as
described in Table 6.
20 of 46
Scope
Schedule
Cost
Approval
authority only
required in case
of Deviation as
Defined below
for the SAE.
PNNL Contractor
Project Director
Any change in scope that
does not alter the overall
project scope as defined
in Section 6.1 of this PEP.
Performance Baseline Deviations: Project changes which DO modify the Performance Baseline.
Performance Baseline Change Authority1
Secretarial Acquisition Executive
A change in scope that affects the ability to satisfy the
mission need, an inability to meet a Key Performance
Parameter, or nonconformance with the current approved
Project Execution Plan, which must be reflected in the
Project Data Sheet.
A delay of 6 months or greater (cumulative) from the
original project completion date.
An increase in excess of the lesser of $25M or 25%
(cumulative) of the original CD-2 cost baseline.
Under Secretary
(Program Secretarial Officer, if delegated)
A change in scope that 1) does not affects the ability to
satisfy the mission need; 2) still meet a Key
Performance Parameter; or 3) maintains conformance
with the current approved Project Execution Plan
baseline, which must be reflected in the Project Data
Sheet.
A delay of less than 6 months cumulative from the
original project completion date, CD-4b.
An increase that is less than $25M or 25%
(cumulative) of the original CD-2 cost baseline.
Cost and schedule variance analysis will be performed for variances at the DOE reporting level (one level
higher than the control account) against any element of the project baseline that exceeds the following
variance thresholds:
Current Period: 15% and $50,000
Cumulative: 10% and $100,000
A formal review of the project will be conducted quarterly following approval of CD-0 or as requested by
the AE.. This activity is consistent with the performance review requirement in DOE O 413.3A. This
review will involve a detailed evaluation of each replacement facility and 325 Building to determine the
cost of work completed, milestones accomplished, cost of work yet to be performed, determination of an
appropriate contingency factor for the remaining work, and a reassessment of all work schedules to
reaffirm the specific facility completion date.
Quarterly reviews are held to communicate accomplishments and issues to the FPD, the IPT and
stakeholders as appropriate to maintain project momentum. These reviews can be held in
Washington, D.C., or in Richland, Washington, depending on logistical preferences. Maximum use of
teleconferencing, when practical, will be pursued to control travel costs.
As part of the quarterly review, the team will verify that all known budget and schedule changes approved
since the last review have been incorporated in the approved baseline. A check also will be made to
assure that the remaining construction work can be completed within the approved construction
schedules.
Emphasis will be placed on identifying PSF project interface questions and concerns to allow for timely
SC, NNSA, DHS, EM and PNNL management involvement in resolving issues to maintain project scope,
schedule and budget objectives.
7.3.2
Independent Reviews
Peer and independent reviews are an important project management tool and serve to verify the PSF
project's mission, organization, development, processes, baseline and progress. Reviews may be initiated
internally by the project team or may be independently initiated and conducted by an external
organization. Reviews may be scheduled or unscheduled to meet a specific objective or need, such as a
budget validation or a CD request.
The following reviews have been performed or are expected for the PSF project:
Mission NeedIndependent Project Review (IPR). This was a limited review of the project
following CD-0. It refined and validated the mission need. This review was conducted in
November 2004, and is documented in the Mission Need Validation Report.
PMB IPR. This was a review of the performance measurement baseline by an independent team led
by the Office of Project Assessment (SC-1.3). The purpose of the reviews are to evaluate the
projects readiness to proceed.
22 of 46
PMB External Independent Review (EIR). This is a detailed review of the entire project, including
an Independent Cost Review, prior to CD-2. The EIR verifies the proposed technical scope, schedule
and cost baselines and will assess the overall status of the project management and control system.
Executability IPR. This is a general review of the project prior to each of the phased CD-3 decisions
that may range from an abridged review of specific areas within a project to a comprehensive review
of the entire project. As a minimum, it will verify the readiness of the project to proceed into
construction. This review is expected to be completed prior to the formal CD-3 review meeting and
again, as required, as project conditions warrant.
7.3.3
The design effort is subdivided into preliminary and detailed engineering. Information produced at the
completion of a design phase is verified by an independent review. The independent review validates and
certifies that the design is in accordance with all applicable local, regional and national engineering codes
and regulations and complies with the project specifications. Guidelines for independent verification can
be found in DOE-STD-1036-93, Guide to Good Practices for Independent Verification. PNNL will
coordinate and manage the review process for all engineering drawings and documents in each of the
design phases. Rework of the design documents will be carried out until requirements are met.
To attain uniformity in preparing designs and design implementation where such uniformity will
contribute to safety, quality and economy, PNNL will use nationally recognized codes and standards. The
PNNL lead design engineer will identify and apply the appropriate codes, standards and requirements
needed to satisfactorily prepare the design.
The technical objectives for this project will also be implemented by conforming to PNNL design
standards. These standards will provide the basis for the design and implementation of this project.
Design and constructability reviews will be conducted to verify the design meets the technical and
functional requirements. Constructability reviews will include both internal and external reviewers to
ensure the design can be efficiently implemented.
Design reviews will be conducted to ensure that current codes and standards are incorporated into
specifications, drawings and other related reports (e.g., the energy conservation report) that pertain to the
facility functional requirements. The purpose of the review is to verify that the design complies with
customer and agency requirements and accepted standards. As the owner of the design contract, PNNL
will perform design reviews throughout the development of the design. The PNNL design subcontractor
for A/E contracted work or the PNNL Lead Designer for self-performed work will present and defend the
design during the review. The formal review will include:
Assessing technical adequacy and conformance with agency and customer requirements, codes,
standards and other criteria such as budgetary constraints
Identifying consistent problems and errors as lessons learned to pass on to future projects
Managing reviewer participation and providing a process for conflict resolution.
23 of 46
PNNL will coordinate the review by providing the design documents to qualified participants in the fields
of ES&H; all applicable disciplines of engineering, architecture, controls, communications, security,
maintenance, fire protection, energy conservation and other areas as necessary and deemed appropriate.
The eventual programmatic user of the facility also will participate or be represented in the review to
ensure research requirements are achieved.
24 of 46
25 of 46
26 of 46
limitations occurs. At that point, the management systems and facility and organizational structures will
be responsible for costs associated with maintaining, modifying or updating permits.
The Hazard Analysis Report (HAR) satisfies the hazard analysis documentation requirements associated
with CD-2 of the DOE acquisition process defined in DOE O 413.3A, Program and Project Management
for the Acquisition of Capital Assets. The HAR also 1) meets the optional documentation requirements
for a radiological facility specified in Table 2-2 of PNL-MA-440, Safety Analysis, Section 2.0, Facility
Hazard Classification, and 2) supports the Radiological Facility determination of PSF-TECH-ESH-002,
Hazard Category Determination for the Physical Science Facility.
9.3.2
325 Building is a Hazard Category-2 nuclear facility, currently operating with a EM-approved
Documented Safety Analysis (DSA). Activities supporting the 325 Building life extension include
evaluations of existing 325 Building structures, systems and components (SSC) and administrative
programs that are important to safe operation. These activities include reviews of recent applicable DOE
directives and guidance for new projects and long-term operational facilities and implementation of
Defense Nuclear Facility Safety Board recommendations. The PSF project approach is documented in
the Capability Replacement Laboratory Project Plan CRL-PLAN-ESH-001, Radiochemical Processing
Laboratory (RPL) Life Extension Safety Design Strategy. Development and approval of this strategy has
been coordinated with the DOE Safety Basis Review Team.
9.3.3
In assuring the appropriate level of emergency preparedness is provided, an understanding of the hazards
associated with each facility will occur by preparing a Hazard Survey and, if necessary, based on the
results of the Hazard Survey, an Emergency Preparedness Hazards Assessment (EPHA). The Hazard
Survey and, if required, the EPHA will be prepared in accordance with DOE O 151.1C, Comprehensive
Emergency Management System, and PNNL-MA-110, PNNL Emergency Management Plan. Building
Emergency Procedures, emergency preparedness drills and exercises and the level of required training for
staff will all be based on the results of the Hazard Survey and any EPHA.
27 of 46
Reducing the use of potable water for landscape irrigation and maximizing potable water efficiency
Selecting building materials with the lowest reasonable life cycle cost and environmental impact
(e.g., greenhouse gas emissions, recycled content, water and air pollution)
Minimizing the waste generated from the construction process
Achieving LEED certification.
29 of 46
30 of 46
assessment needed to confirm the adequacy of a facilitys overall conduct of operations, including
procedures, facility staff training and emergency preparedness.
The PSF Readiness Review Plan will define the startup authorization authority, processes for
preparation and conduct of readiness activities and reviews to confirm a satisfactory state of
operations for the PSF.
PNNLs Integrated Operations System (IOPS) structure will be deployed in PSF. PSF facility
workspaces will be identified and configured in IOPS following the standard process outlined in PNNLs
SBMS, Establishing and Maintaining IOPS in a Facility. Work practices and other facility-related
content will be developed to reflect the new facility characteristics with relocated staff being trained to the
new or upgraded Hazard Awareness Summaries, Work Practices and permits.
Operational readiness is achieved when facility, personnel, equipment and procedures are in a condition
that will allow routine operations to be started. The PNNL Management System description identifies the
basic set of facility and operational permits and processes needed for supporting routine operations. A
Facility Core Team will deploy work processes to manage the building operational boundary through
implementation of Facility Use Agreements using the Establishing a Facility Use Agreement subject area
in PNNLs SBMS. Emergency management functions, including Off-Normal Reporting coordination,
will be integrated into the existing PNNL process. Normal maintenance is established by a Facility Core
Team after beneficial occupancy has been accomplished.
The 325 Building is a Hazard Category-2 nuclear facility that currently operates under an EM-approved
DSA. The transition of authorization authority for the safety basis from EM to SC will occur as a
prerequisite for CD-4b. This is further discussed in Section 9.3 Safety Assessment Documentation. As
part of this transition, readiness review activities are anticipated. The level of readiness review will be
identified in the Readiness Review Plan described above. 325 Building transition of authorization basis
and operational acceptance is performed in accordance with CRL-INC-07-0011.
31 of 46
32 of 46
33 of 46
34 of 46
35 of 46
36 of 46
37 of 46
Project Objectives
Provide facilities to enable relocation of PNNL research capabilities from the majority of Hanford
300 Area facilities which they currently occupy. Design and construct new replacement facilities and
facility modifications to extend the life of 325 Building in the Hanford 300 Area. Do so in a manner that
Minimizes the impact to the PNNL programmatic research missions.
Minimizes delays to the demolition and cleanup of the Hanford 300 Area.
Provides the necessary infrastructure for PNNL staff to fulfill the research requirements necessary to
meet mission needs.
Maximizes research efficiencies/synergies across the entire PNNL research complex.
Optimizes space usage.
Optimizes the safety envelope of the replacement facilities with appropriate hazard categorization.
Expedites the DOE project management process in support of the projects critical-path schedule.
Completes the technical objectives in accordance with the cost and schedule baselines approved by
the Acquisition Executive.
Designs and constructs new facilities and modifies existing facilities within the fixed Total Project
Cost (TPC) of $224 million.
Project Organization
This project will be managed by the DOE-SC Federal Project Director (FPD) located at PNSO. The FPD
will be responsible and accountable for project execution to the HQ Program Manager. The FPD has
chartered an IPT which will assist the FPD as necessary to accomplish the project objectives.
38 of 46
IPT Members *
Discipline
Federal Project Director -PSF
Program Manager (Office of Science)
Portfolio Project Director (Richland Operations Office) EM
Federal Project Director - 325 Building Sub-Project
Facility Transition Manager
Safety Basis Review Team Lead/Nuclear Safety Analyst (Oak Ridge Operations)
Contractor Project Director (Battelle)
Member
Chad Henderson
Marcus Jones
Dave Brockman
Russell Warren
Julie Turner
Randy Persinger
James McClusky
39 of 46
Homeland Security (DHS). In addition to this role, the Program Manager will be responsible for the
following tasks:
Oversees development of project definition, technical scope and budget
Defines programmatic mission requirements and objectives
Establishes programmatic requirements and recommends operational readiness to the authorization
authority
Prepares, defends and provides project budget with support from the field organizations
Reviews and provides recommendations to the Acquisition Executive on Level-0 and Level-1
baseline changes
Functions as the primary point-of-contact at DOE headquarters for project matters
Develops project performance measures, and monitors and evaluates project performance throughout
the life cycle of the project
Organizes reviews as necessary
Ensures that environment, safety and health (ES&H) requirements are implemented by the project
Coordinates with other SC offices, project sponsors and the DOE Office of Engineering and
Construction Management as needed to execute the project
Controls changes to project baselines in accordance with the PSF PEP.
Portfolio Project Director
Due to the inter-relationship of the PSF with the Hanford 300 Area cleanup activities managed by the
Richland Operations Office (RL), a Portfolio Project Director (PPD) at RL has been assigned half-time to
the project. The PPD is an experienced SES level manager who will assist the FPD by providing
guidance and advice on management of the project and facilitate communication and coordination
between PNSO and RL for the new utility infrastructure that will be funded and installed by RL for the
retained 300 Area facilities and the ultimate transfer of full operational responsibility from RL to SC.
Federal Project Director 325 Building Sub-Project
The FPD for the 325 Building Sub-Project reports to the PSF FPD and will:
Define project objectives and technical, schedule, and cost scopes.
Ensure timely completion and quality of required project documentation.
Assess contractor project performance versus contract requirements.
Proactively identify and resolve critical issues within Federal control.
Integrate and manage the timely delivery of government reviews, approvals, property, services, and
information.
Ensure the design, construction, environmental, safety, health, and quality efforts performed are in
accordance with the contract, public law, regulations, and Executive Orders
40 of 46
Approves changes within authority threshold in accordance with change control process defined in
the PEP.
Manages project contingency funds.
Subject Matter Expert Support
Additional support in specific disciplines will be necessary to execute the project on a periodic and
intermittent task basis and will be obtained as required, on a matrix basis, from PNSO and SC Support
Center staff. The disciplines required and anticipated sources are listed below.
PNSO: Contracting Officer, safety, health, quality, environmental permitting, security
Oak Ridge Support Center: CFO, budget, procurement, legal
42 of 46
Applicability to Documentation
PSF
for Applicable
Requirement
NA
2.
A
A
CD-1
CD-2a/3a
CD-2b/3b
CD-4
Environmental
restoration (ER) &
Facility Disposition
(FD) Project CDs
Baseline Change
Control
Baseline Change
Control Approval
Authority (A2 &A5)
NA
Memorandum from
Deputy Secretary
Memorandum from
Deputy Secretary
Memorandum from
Acquisition
Executive
Memorandum from Acquisition Executive authority currently resides
Acquisition
with the DOE Deputy Secretary.
Executive
NA
Not an ER or FD Project.
A
A
A
Justification of
Mission Need
3.
Chapter II
1.
2.
3.
4.
Thresholds (A3)
Variances
Programmatic
Baseline Changes
Chapter III Acquisition Process
1.
Pre-conceptual
Planning
1.1
Mission Needs
Statement (A4)
1.2
1.3
Integrated Project
A
Team
Pre-conceptual Design A
(IM)
Memorandum from
Deputy Secretary
Mission Need
Statement and 300
Area Capability
Transition Plan
43 of 46
2.1
2.2
3.
3.1
Acquisition Process
Conceptual Design
Report
3.2
3.4
Configuration
Management Plan
(IM)
AT
3.5
System Engineering
Plan (IM)
QA Program
Description
AT
Work Breakdown
Structure (IM)
Design Baseline
3.3
3.6
3.7
3.8
3.9
Earned Value
Management System
(IM)
AT
3.10
Preliminary Project
Baseline Range
4.
4.1
Acquisition Planning
Acquisition Strategy
A
(IM)
CDR
PDSA Is Not
Required
CDR
44 of 46
A
AT
A
Preliminary Design
A
(IM)
Final Design &
AT
Review (A4)
Operational Readiness AT
Review & Acceptance
Report (A4)
Project Transition to
Operations Report
(A4)
AT
Final Documented
Safety Analysis
(FDSA)
Project Closeout
Report (A4)
NA
A
1.
1.1
Lessons Learned
A
Report (IM)
Project Execution Plan
Preliminary PEP
A
1.2
Final PEP
Preliminary PEP,
6/30/2005
PEP
1.3
PEP
2.
AT
3.
Business Clearances
NA
Acquisition
Strategy
NA
AT
Energy Systems
Acquisition Advisory
Board
Chapter VI Performance
Reviews & Reporting
1.
Performance Reviews
1.1
Contractor PM System A
Review (A4)
Chapter V
45 of 46
Applicability to Documentation
PSF
for Applicable
Requirement
A
PEP Section 5.10.2
2.2
AT
2.3
2.4
2.5
3.
AT
AT
AT
AT
AT
Chapter
VII
1.
Additional
Requirements
Chief Operating
AT
Officer Watch List and
A7
2.
Project Manager
Development
Contractor Project
Management System
Per McSlarrow
CD-0 approval
PNNL PMP
4.
Value Engineering
AT
5.
Integrated Safety
Management
AT
PEP Section 6
6.
Sustainable Building
Design
AT
NA
3.
46 of 46