Operations Management
Operations Management
intentionally left
blank
Copyright © 2009, New Age International (P) Ltd., Publishers
Published by New Age International (P) Ltd., Publishers
Operations management has been recognised as an important factor in a country’s economic growth.
The traditional view of manufacturing management is the concept of Production Management
with the focus on economic efficiency in manufacturing. Later the new name Operations
Management was identified, as service sector became more prominent. Rapid changes in technology
have posed numerous opportunities and challenges, which have resulted in enhancement of
manufacturing capabilities through new materials, facilities, techniques and procedures. Hence,
managing a service system has become a major challenge in the global competitive environment.
Operations Management has been a key element in the improvement and productivity in business
around the world. Operations Management leads the way for the organisations to achieve its goals
with minimum effort. Hence, the study of the subject at undergraduate and postgraduate level has
more significance.
This book on ‘Operations Management’ covers the complete syllabus of Bachelor of Engineering
of Visvesvaraya Technical University, Karnataka, however the coverage is wide enough to include
the requirements of Bachelor and Master Degree courses of other Indian universities and professional
courses like MBA, PGDCA, BBA.
Being student friendly is the unique feature of this book. The subject matter has been presented
systematically in ten chapters, which can enable the reader master the topics covered without any
additional guidance.
Complete care has been taken to make the book error free. However, mistakes might have
crept inadvertently. Readers finding any error are requested to bring it to our notice, for enabling us
to rectify them in our future editions.
We are grateful to Mr. Saumya Gupta, Managing Director and Mr. Sudarshan of New Age
International (P) Limited Publishers for their commitment and encouragement in bringing out this
book in time with good quality and for providing us the opportunity to share our knowledge with you.
vi
vi Contents
Preface
The authors wish to express their sincere thanks to Principals and Managements of respective
colleges. Our acknowledgements are also due to Dr. Poornima Anil Kumar and Mrs. Bharathi
Suresh without whose support and sacrifice this work would not have been completed by the
deadline.
Finally, our acknowledgement is due to the Almighty who has blessed us with the knowledge,
required for writing this book.
S. Anil Kumar
N. Suresh
Contents vii
CONTENTS
Preface v
1. OPERATIONS MANAGEMENT CONCEPTS 1–26
1.1 Introduction 1
1.2 Historical Development 1
1.3 Concept of Production 3
1.4 Production System 3
1.5 Classification of Production System 4
1.5.1 Job-Shop Production 4
1.5.2 Batch Production 5
1.5.3 Mass Production 5
1.5.4 Continuous Production 6
1.6 Production Management 7
1.6.1 Objectives of Production Management 7
1.7 Operations System 7
1.7.1 A Framework of Managing Operations 8
1.8 Operations Management 9
1.9 Operations Management Objectives 11
1.10 The Strategic Role of Operations 13
1.11 Strategic Planning 15
1.11.1 Strategic Planning for Production and Operations 15
1.11.2 Strategic Planning Approaches for Production/Operations 15
1.11.3 Strategic Planning—Forced Choice Model 15
1.11.4 A Strategic Planning Operations Model 16
1.12 The Trend: Information and Non Manufacturing Systems 17
1.13 Productivity 18
1.13.1 Modern Dynamic Concept of Productivity 18
1.13.2 Factor Productivity and Total Productivity 18
1.13.3 Productivity Analysis 19
viii Contents
1
OPERATIONS MANAGEMENT CONCEPTS
CHAPTER OUTLINE
1.1 Introduction 1.11 Strategic Planning
1.2 Historical Development 1.12 The Trend: Information and Non Manufactur-
1.3 Concept of Production ing System
1.4 Production System 1.13 Productivity
1.5 Classification of Production System 1.14 Factors Affecting Productivity
1.6 Production Management 1.15 International Dimensions of Productivity
1.7 Operations System 1.16 The Environment of Operations
1.8 Operations Management 1.17 Scope of Operations Management
1.9 Operations Management Objectives • Exercise
1.10 The Strategic Role of Operations • References
1.1 INTRODUCTION
Operation is that part of as organization, which is concerned with the transformation of a range of
inputs into the required output (services) having the requisite quality level. Management is the process,
which combines and transforms various resources used in the operations subsystem of the organization
into value added services in a controlled manner as per the policies of the organization.
The set of interrelated management activities, which are involved in manufacturing certain products,
is called as production management. If the same concept is extended to services management, then
the corresponding set of management activities is called as operations management.
and developed scientific management. From then till 1930, many techniques were developed prevailing
the traditional view. Brief information about the contributions to manufacturing management is shown
in the Table 1.1.
Production Management becomes the acceptable term from 1930s to 1950s. As F.W. Taylor’s
works become more widely known, managers developed techniques that focused on economic
efficiency in manufacturing. Workers were studied in great detail to eliminate wasteful efforts and
achieve greater efficiency. At the same time, psychologists, socialists and other social scientists
began to study people and human behaviour in the working environment. In addition, economists,
mathematicians, and computer socialists contributed newer, more sophisticated analytical approaches.
With the 1970s emerge two distinct changes in our views. The most obvious of these, reflected in
the new name Operations Management was a shift in the service and manufacturing sectors of the
economy. As service sector became more prominent, the change from ‘production’ to ‘operations’
emphasized the broadening of our field to service organizations. The second, more suitable change
was the beginning of an emphasis on synthesis, rather than just analysis, in management practices.
Table 1.1 Historical summary of operations management
Limitations
Following are the limitations of Job-shop Production:
1. Higher cost due to frequent set up changes.
2. Higher level of inventory at all levels and hence higher inventory cost.
3. Production planning is complicated.
4. Larger space requirements.
Operations system converts inputs in order to provide outputs, which are required by a customer.
It converts physical resources into outputs, the function of which is to satisfy customer wants.
Everett E. Adam & Ronald J. Ebert defines as ‘An operating system is the part of an
organisation that produces the organistion’s physical goods and services’.
Ray Wild defines operations system as ‘a configuration of resources combined for the provision
of goods or services’.
In some of the organisation the product is a physical good (breakfast in hotels) while in others it
is a service (treatment in hospitals). Bus and taxi services, tailors, hospital and builders are the
examples of an operations system. The basic elements of an operation system show in Figure 1.3
with reference to departmental stores.
A departmental store's has an input like land upon which the building is located, labour as a stock
clerk, capital in the form of building, equipment and merchandise, management skills in the form of
the stores manager. Output will be serviced customer with desired merchandise. Random fluctuations
will be from external or internal sources, monitored through a feedback system.
Late delivery
Labour tumover
manager must exercise control by measuring actual outputs and comparing them to planned operations
management. Controlling costs, quality, and schedules are the important functions here.
1. Behaviour: Operations managers are concerned with the activities, which affect human
behaviour through models. They want to know the behaviour of subordinates, which affects managerial
activities. Their main interest lies in the decision-making behaviour.
2. Models: Models represents schematic representation of the situation, which will be used
as a tool for decision-making. Following are some of the models used.
Aggregate planning models for examining how best to use existing capacity in short term,
break-even analysis to identify break-even volumes, Linear programming and computer simulation
for capacity utilisation, Decision tree analysis for long-term capacity problem of facility expansion,
simple median model for determining best locations of facilities, etc.
The operations managers have the prime responsibility for processing inputs into outputs. They
must bring together under production plan that effectively uses the materials, capacity and knowledge
available in the production facility. Given a demand on the system work must be scheduled and
controlled to produce goods and/or services required. Control must be exercised over such parameters
such as costs, quality and inventory levels.
The definition of the operations Management contains following keywords: Resources, Systems,
transformation and Value addition Activities.
RESOURCES
Resources are the human, material and capital inputs to the production process. Human resources
are the key assets of an organisation. As the technology advances, a large proportion of human input
is in planning and controlling activities. By using the intellectual capabilities of people, managers can
multiply the value of their employees into by many times. Material resources are the physical facilities
and materials such as plant equipment, inventories and supplies. These are the major assets of an
organisation. Capital in the form of stock, bonds, and/or taxes and contributions is a vital asset.
Capital is a store of value, which is used to regulate the flow of the other resources.
SYSTEMS
Systems are the arrangement of components designed to achieve objectives according to the plan.
The business systems are subsystem of large social systems. In turn, it contains subsystem such as
personnel, engineering, finance and operations, which will function for the good of the organisation.
A systems approach to operations management recognises the hierarchical management
responsibilities. If subsystems goals are pursued independently, it will results in sub-optimization. A
consistent and integrative approach will lead to optimization of overall system goals.
The system approach to specific problems requires that the problem first be identified and
isolated from the maze of the less relevant data that constitute the environment. The problem abstracted
from the overall (macro) environment. Then it can be broken into manageable (micro) parts and
analysed and solutions proposed. Doing this analysis is advantageous before making any changes. If
the solution appears to solve the problem in a satisfactory way, changes can be made to the real
system in an orderly and predictable way.
The ability of any system to achieve its objective depends on its design and its control. System
design is a predetermined arrangement of components. It establishes the relationships that must
exist between inputs, transformation activities and outputs in order to achieve the system objectives.
With the most structured design, there will be less planning and decision-making in the operations of
the system. System control consists of all actions necessary to ensure that activities conform to
preconceived plans or goals. It involves following four essential elements:
1. Measurement by an accurate sensory device.
2. Feedback of information in a timely manner.
3. Comparison with standards such as time and cost standards.
4. Corrective actions by someone with the authority and ability to correct.
Operations Management Concepts 11
A closed loop control system can automatically function on the basis of data from within its own
system.
TRANSFORMATION AND VALUE ADDING ACTIVITIES
The objective of combining resources under controlled conditions is to transform them into goods
and services having a higher value than the original inputs. The transformation process applied will
be in the form of technology to the inputs. The effectiveness of the production factors in the
transformation process is known as productivity.
The productivity refers to the ratio between values of output per work hour to the cost of inputs.
The firms overall ratio must be greater than 1, then we can say value is added to the product.
Operations manager should concentrate improving the transformation efficiency and to increase the
ratio.
These aspects of customer service – specification, cost and timing – are described for four
functions in Table 1.1. They are the principal sources of customer satisfaction and must therefore
be the principal dimension of the customer service objective for operations managers.
Generally, an organisation will aim reliably and consistently to achieve certain standards and
operations manager will be influential in attempting to achieve these standards. Hence, this objective
will influence the operations manager’s decisions to achieve the required customer service.
Table 1.2 Aspects of customer service
Manufacture Goods of a given, requested Cost, i.e. purchase price or cost of obtaining
or acceptable specification goods. Timing, i.e. delivery delay from order or
request to receipt of goods.
Supply Goods of a given, requested or Cost, i.e. purchase price or cost of obtaining
acceptable specification goods. Timing, i.e. delivery delay from order or
request to receipt of goods.
Service Treatment of a given, requested Cost, i.e. cost of movements. Timing, i.e.
or acceptable specification 1. Duration or time required for treatment.
2. Wait or delay from requesting treatment to its
commencement.
RESOURCE UTILISATION
Another major objective of operating systems is to utilize resources for the satisfaction of customer
wants effectively. Customer service must be provided with the achievement of effective operations
through efficient use of resources. Inefficient use of resources or inadequate customer service
leads to commercial failure of an operating system.
Operations management is concerned essentially with the utilisation of resources, i.e. obtaining
maximum effect from resources or minimising their loss, under utilisation or waste. The extent of
the utilisation of the resources’ potential might be expressed in terms of the proportion of available
time used or occupied, space utilisation, levels of activity, etc. Each measure indicates the extent to
which the potential or capacity of such resources is utilised. This is referred as the objective of
resource utilisation.
Operations management is concerned with the achievement of both satisfactory customer service
and resource utilisation. An improvement in one will often give rise to deterioration in the other.
Often both cannot be maximized, and hence a satisfactory performance must be achieved on both
objectives. All the activities of operations management must be tackled with these two objectives in
Operations Management Concepts 13
mind, and because of this conflict, operations managers’ will face many of the problems. Hence,
operations managers must attempt to balance these basic objectives.
The Table 1.3 summarizes the twin objectives of operations management. The type of balance
established both between and within these basic objectives will be influenced by market considerations,
competitions, the strengths and weaknesses of the organization, etc. Hence, the operations managers
should make a contribution when these objectives are set.
Table 1.3 The twin objectives of operations management
competitive advantage is defined by the total time required to produce a product or service. Firms
able to respond quickly have reported growth rates over three times the industry average and double
the profitability. Thus the pay-off for quick response is market dominance. These basic strategic
choices set the tone for the shape and content of the operations functions.
OPERATIONS OBJECTIVES
The overall objective of the operations subsystem is to provide conversion capabilities for meeting the
organization’s goals and strategy. The sub-goals of the operations subsystem, must specify the following:
1. Product/service characteristics.
2. Process characteristics.
3. Product/service quality.
4. Efficiency
z Effective employee relations and cost control of labour.
Quality reflects the ‘goodness’ of the product or services to the customer. Flexibility is the adoptability,
the capability to change as business conditions change.
1.13 PRODUCTIVITY
Productivity is defined in terms of utilization of resources, like material and labour. In simple terms,
productivity is the ratio of output to input. For example, productivity of labour can be measured as units
produced per labour hour worked. Productivity is closely inked with quality, technology and profitability.
Hence, there is a strong stress on productivity improvement in competitive business environment.
Productivity can be improved by (a) controlling inputs, (b) improving process so that the same
input yields higher output, and (c) by improvement of technology. These aspects are discussed in
more detail in the lesson on Productivity Management.
Productivity can be measured at firm level, at industry level, at national level and at international level.
Generally factor productivity calculations are required at firm level and industry level, whereas
total factor productivity calculations are made for measuring productivity at national and international
level.
Productivity of materials can be measured as output units per unit material consumed. It can
also be measured in terms of value generated per unit expenditure in materials.
For measuring productivity of different groups of operatives, different ratios can be used, which
are indicative of output/input relationship. For example, the productivity of assembly line work can
be measured as output units per man-hour or alternatively, the value of good produced per cost of
labour on assembly line.
It evolves from the religious and cultural norms of society, from childhood training, education, and
reflection on the purpose of life and the value of one’s self and of others. The preferred values of
the society reflect purpose, integrity and a respect for the life and humanity of others.
Every facet of our economic and social environment regulated and controlled by law designed
to protect general public. The figure illustrates some of the laws impact on the productivity of the
firms.
LOCATION OF FACILITIES
Location of facilities for operations is a long-term capacity decision, which involves a long-term
commitment about the geographically static factors that affect a business organisation. It is an
important strategic level decision-making for an organisation. It deals with the questions such as
‘where our main operations should be based?’
The selection of location is a key-decision as large investment is made in building plant and
machinery. An improper location of plant may lead to waste of all the investments made in plant and
machinery equipments. Hence, location of plant should be based on the company’s expansion plan
and policy, diversification plan for the products, changing sources of raw materials and many other
factors. The purpose of the location study is to find the optimal location that will results in the
greatest advantage to the organization.
PLANT LAYOUT AND MATERIAL HANDLING
Plant layout refers to the physical arrangement of facilities. It is the configuration of departments,
work centres and equipment in the conversion process. The overall objective of the plant layout is to
design a physical arrangement that meets the required output quality and quantity most economically.
According to James More ‘Plant layout is a plan of an optimum arrangement of facilities including
personnel, operating equipment, storage space, material handling equipments and all other supporting
services along with the design of best structure to contain all these facilities’.
Operations Management Concepts 23
‘Material Handling’ refers to the ‘moving of materials from the store room to the machine and
from one machine to the next during the process of manufacture’. It is also defined as the ‘art and
science of moving, packing and storing of products in any form’. It is a specialized activity for a
modern manufacturing concern, with 50 to 75% of the cost of production. This cost can be reduced
by proper section, operation and maintenance of material handling devices. Material handling devices
increases the output, improves quality, speeds up the deliveries and decreases the cost of production.
Hence, material handling is a prime consideration in the designing new plant and several existing
plants.
PRODUCT DESIGN
Product design deals with conversion of ideas into reality. Every business organisation have to
design, develop and introduce new products as a survival and growth strategy. Developing the new
products and launching them in the market is the biggest challenge faced by the organizations. The
entire process of need identification to physical manufactures of product involves three functions—
Design and Marketing, Product, Development, and manufacturing. Product Development translates
the needs of customers given by marketing into technical specifications and designing the various
features into the product to these specifications. Manufacturing has the responsibility of selecting
the processes by which the product can be manufactured. Product design and development provides
link between marketing, customer needs and expectations and the activities required to manufacture
the product.
PROCESS DESIGN
Process design is a macroscopic decision-making of an overall process route for converting the raw
material into finished goods. These decisions encompass the selection of a process, choice of
technology, process flow analysis and layout of the facilities. Hence, the important decisions in
process design are to analyse the workflow for converting raw material into finished product and to
select the workstation for each included in the workflow.
PRODUCTION PLANNING AND CONTROL
Production planning and control can be defined as the process of planning the production in advance,
setting the exact route of each item, fixing the starting and finishing dates for each item, to give
production orders to shops and to follow-up the progress of products according to orders.
The principle of production planning and control lies in the statement ‘First Plan Your Work and
then Work on Your Plan’. Main functions of production planning and control include Planning, Routing,
Scheduling, Dispatching and Follow-up.
Planning is deciding in advance what to do, how to do it, when to do it and who is to do it.
Planning bridges the gap from where we are, to where we want to go. It makes it possible for things
to occur which would not otherwise happen.
Routing may be defined as the selection of path, which each part of the product will follow,
which being transformed from raw material to finished products. Routing determines the most
advantageous path to be followed for department to department and machine to machine till raw
material gets its final shape.
24 Operations Management
Scheduling determines the programme for the operations. Scheduling may be defined as 'the
fixation of time and date for each operation' as well as it determines the sequence of operations to
be followed.
Dispatching is concerned with the starting the processes. It gives necessary authority so as to
start a particular work, which has been already been planned under ‘Routing’ and ‘Scheduling’.
Therefore, dispatching is ‘Release of orders and instruction for the starting of production for any
item in acceptance with the Route sheet and Schedule Charts’.
The function of Follow-up is to report daily the progress of work in each shop in a prescribed
proforma and to investigate the causes of deviations from the planned performance.
QUALITY CONTROL (QC)
Quality Control may be defined as ‘a system that is used to maintain a desired level of quality in a
product or service’. It is a systematic control of various factors that affect the quality of the product.
Quality Control aims at prevention of defects at the source, relies on effective feedback system and
corrective action procedure.
Quality Control can also be defined as ‘that Industrial Management technique by means of
which product of uniform acceptable quality is manufactured’. It is the entire collection of activities,
which ensures that the operation will produce the optimum quality products at minimum cost.
The main objectives of Quality Control are:
1. To improve the companies income by making the production more acceptable to the customers
i.e. by providing longlife, greater usefulness, maintainability, etc.
2. To reduce companies cost through reduction of losses due to defects.
3. To achieve interchangeability of manufacture in large-scale production.
4. To produce optimal quality at reduced price.
5. To ensure satisfaction of customers with productions or services or high quality level, to build
customer good will, confidence and reputation of manufacturer.
6. To make inspection prompt to ensure quality control.
7. To check the variation during manufacturing.
MATERIALS MANAGEMENT
Materials Management is that aspect of management function, which is primarily concerned with
the acquisition, control, and use of materials needed and flow of goods and services connected with
the production process having some predetermined objectives in view.
The main objectives of Material Management are:
1. To minimise material cost.
2. To purchase, receive, transport and store materials efficiently and to reduce the related cost.
3. To cut down costs through simplification, standardisation, value analysis, import substitution,
etc.
4. To trace new sources of supply and to develop cordial relations with them in order to ensure
continuous supply at reasonable rates.
5. To reduce investment tied in the inventories for use in other productive purposes and to
develop high inventory turnover ratios.
Operations Management Concepts 25
MAINTENANCE MANAGEMENT
In modern industry, equipment and machinery are a very important part of the total productive
effort. Therefore their idleness or downtime becomes are very expensive. Hence, it is very important
that the plant machinery should be properly maintained.
The main objectives of Maintenance Management are:
1. To achieve minimum breakdown and to keep the plant in good working condition at the
lowest possible cost.
2. To keep the machines and other facilities in such a condition that permits them to be used at
their optimal capacity without interruption.
3. To ensure the availability of the machines, buildings and services required by other sections
of the factory for the performance of their functions at optimal return on investment.
EXERCISE
1. Define Operations management. Explain the key concepts of Operations management with a schematic
diagram.
2. Distinguish between manufacturing and service operation with example.
3. What is strategic planning? Explain the role of models in strategic planning.
4. Define the term operations management. Briefly explain the strategic role of operations.
5. Write a note on system view of operations.
6. Explain, how the considerations of environtnenta1 assessment and organisational position provide a
modeling framework for the strategic planning of operations.
7. Briefly explain how service producers differ from goods producers in important aspects of their
operations.
8. State the important objectives of production management.
9. Define the term productive system.
10. Give two examples for the productive systems concerned to service and manufacturing respectively.
11. “Operations strategy”—A key element in corporate strategy. Briefly explain.
12. Explain what do you understand by product-focused systems and process-focused systems.
13. Differentiate between Production Management and Operations Management.
14. Explain the historical evaluation of production function up to 21st century.
15. What are the various decisions and their applications made by operations manager in a POM system?
16. Briefly explain the importance of operations management in the corporate management.
17. Explain the concept of productivity.
26 Operations Management
REFERENCES
1. Everett, E. Adam, Jr.Ronald J.Ebert, Production and Operations Management, Prentice-Hall
of India Private Limited, 5th Edition, 1994.
2. R. Pannerselvam, Production and Operations Management, Prentice-Hall of India Private
Limited, 9th print, 2004.
3. Joseph, G. Monks, Theory and Problems of Operations Management, Tata McGraw-Hill
Publishing Company Limited, 2nd Edition, 2004.
4. Joseph, G. Monks, Operations Management, McGraw-Hill International Edition, 3rd Edition.
5. S. Anil Kumar, N. Suresh, Production and Operations Management, New Age International
(P) Limited Publishers, 2nd Edition, 2008.
Operations Decision-Making 27
2
OPERATIONS DECISION-MAKING
CHAPTER OUTLINE
2.1 Introduction 2.7 Economic Models
2.2 Management as a Science 2.8 Statistical Models
2.3 Characteristics of Decisions 2.9 Decision Tree
2.4 Framework for Decision-Making • Exercise
2.5 Decision Methodology • References
2.6 Decision Support System
2.1 INTRODUCTION
Thousand of business decisions are made everyday. Not all the decisions will make or break the
organisation. But each one adds a measure of success or failure to the operations. Hence decision-
making essentially involves choosing a particular course of action, after considering the possible
alternatives. This chapter examines management as a science and the characteristics of decisions.
The use of economic and statical models is discussed along with decision trees.
The significant or long lasting decisions deserve more considerations than routine ones.
Plant investment, which is a long-range decision, may deserve more thorough analysis. The time
availability and the cost of analysis also influence the amount of analysis. The degree of complexity
of the decision increases when many variables are involved, variables are highly independent and
the data describing the variables are uncertain.
Business decision-makers have always had to work with incomplete and uncertain data.
Fig. 2.1 below depicts the information environment of decisions. In some situations a decision-
maker has complete information about the decision variables; at the other extremes, no information
is available. Operations management decisions are made all along this continuum.
Complete certainty in decision-making requires data on all elements in the population. If such
data are not available, large samples lend more certainty than do small ones. Beyond this, subjective
information is likely to be better than no data at all.
z Formulation of a model.
z Generating alternatives .
Operations Decision-Making 29
With valid assumptions, algebra provides deterministic solutions such as break-even analysis and
benefit cost analysis.
z Calculus: The branch of mathematics provides a useful tool for determining optimal value where
making a product mix decisions; minimising transportation costs, planning and scheduling production
and other areas.
z Statistical analysis: Objective and subjective probabilities with the use of probability and
probability distribution, Estimation and tests of hypothesis, Bayesian statistics, Decision theory,
Correlation and regression technique for forecasting demand and Analysis of variance are some
of the techniques used for decision-making.
z Queuing theory: The analysis of queues in terms of waiting-time length and mean waiting time
is useful in analysing service systems, maintenance activities, and shop floor control activities.
z Simulation: Simulation duplicates the essence of an activity. Computer simulations are valuable
tools for the analysis of investment outcomes, production processes, scheduling and maintenance
activities.
z Heuristic methods: Heuristic methods involve set of rules, which facilitate solutions of scheduling,
layout and distribution problems when applied in a consistent manner.
z Network analysis techniques: Network approaches include decision trees, CPM and PERT
methods. They are helpful in identifying alternative course of action and controlling the project
activities.
z Utility theory: Utility theory or preference theory allows decision-makers to incorporate their
own experience and values into a relatively formalized decision structure.
indifferent.
that has the “best worst.” The Maximin approach is essentially a pessimistic one because it takes
into account only the worst possible outcome for each alternative. The actual outcome may not
be as bad as that, but this approach establishes a “guaranteed minimum.”
z Maximax: Determine the best possible pay-off, and choose the alternative with that pay-off.
The Maximax approach is an optimistic, “go for it” strategy; it does not take into account any
pay-off other than the best.
z Laplace: Determine the average pay-off for each alternative, and choose the alternative with
the best average. The Laplace approach treats the states of nature as equally likely.
z Minimax regret: Determine the worst regret for each alternative, and choose the alternative
with the “best worst.” This approach seeks to minimize the difference between the pay-off that
is realized and the best pay-off for each state of nature.
32 Operations Management
SOLUTION
(a) Using Maximin, the worst pay-offs for the alternatives are:
Small facility: Rs.10 million
Medium facility: 7 million
Large facility: –4 million
Hence, since Rs.10 million is the best, choose to build the small facility using the maximum
strategy.
(b) Using Maximax, the best pay-offs are:
Small facility: Rs.10 million
Medium facility: 12 million
Large facility: 16 million
The best overall pay-off is the Rs.16 million in the third row. Hence, the Maximax criterion
leads to building a large facility.
(c) For the Laplace criterion, first find the row totals, and then divide each of those amounts by the
number of states of nature (three in this case). Thus, we have:
Because the medium facility has the highest average, it would be chosen under the Laplace
criterion.
ILLUSTRATION 2: Determine which alternative would be chosen using a Minimax regret
approach to the capacity-planning programme.
Operations Decision-Making 33
SOLUTION: The first step in this approach is to prepare a table of opportunity losses, or regrets.
To do this, subtract every pay-off in each column from the best pay-off in that column. For
instance, in the first column, the best pay-off is 10, so each of the three numbers in that column
must be subtracted from 10. Going down the column, the regrets will be 10 – 10 = 0, 10 – 7 = 3,
and 10 – (– 4) = 14. In the second column, the best pay-off is 12. Subtracting each pay-off from
12 yields 2, 0, and 10. In the third column, 16 is the best pay-off. The regrets are 6, 4, and 0. These
results are summarized in a regret table:
The second step is to identify the worst regret for each alternative. For the first alternative, the
worst is 6; for the second, the worst is 4; and for the third, the worst is 14. The best of these worst
regrets would be chosen using Minimax regret. The lowest regret is 4, which is for a medium
facility. Hence, that alternative would be chosen.
SOLUTION: For each state of nature by the pay-off for that state of nature and summing them:
EVsmall = 0.30 (Rs.10) + 0.50 (Rs.10) + 0.20 (Rs.10) = Rs.10
EVmedium = 0.30 (Rs.7) + 0.50 (Rs.12) + 0.20 (Rs.12) = Rs.10.5
EVlarge = 0.30 (–4) + 0.50 (Rs.2) + 0.20 (Rs.16) = Rs. 3
Hence, choose the medium facility because it has the highest expected value.
ILLUSTRATION 4: Global Telecom Corp. must choose one of three partnering firms (X
Co., Y Co., or Z Co.) with which to develop a personal communicator. The possible states of
nature are that future demand may be low, medium, or high. Estimated dollar pay-offs (in net
present value terms) for each alternative under each state of nature are shown in the
accompanying Table. Which partnering firm should be chosen under the criterion of (a)
maximax, (b) Maximin, and (c) Laplace?
SOLUTION
(a) Maximax: Choose the alternative that offers the best possible (highest) pay-off. The highest
pay-off is Rs.140 million with Z Co. Therefore choose Z Co.
(b) Maximin: For each alternative, locate the worst possible pay-off. Then choose the best of
these “worst” values. The best of the worst is X Co. with a minimum profit of Rs.10 million.
(c) Laplace: Find the average pay-off for each alternative, and choose the alternative with the
best. The highest average is Z Co. [(0 + 20 + 140)/3 = Rs.0.53.3 m]. Choose Z Co.
Pay-off Table
X Co. partner 10 50 70
When probability values, P(X), are assigned to the states of nature of a pay-off table, two
additional decision criteria can be considered: maximum probability and expected monetary value.
The expected monetary value approach utilizes the highest average, or expected value, E (X).
E(X) = Σ [X.P(X)].
ILLUSTRATION 5: For the data in illustration 8, assume probabilities of:
P (low demand) = 0.3 P(medium demand) = 0.5P (high demand) = 0.2
Which partnering firm should be chosen under the criterion of (a) maximum probability
and (b) Expected Monetary Value (EMY)?
Operations Decision-Making 35
SOLUTION
(a) Maximum probability: Find the most likely state of nature, and choose the best alternative within
that state. Most likely is [P(medium demand) = 0.5]. Choose X Co., where pay-off is Rs.50 m.
(b) Expected monetary value: For each alternative, multiply the value of each possible outcome
(X) by its probability of occurrence, P (X). Then sum across all outcomes, i.e., L [X. P(X)] to
get the expected value, E(X), of each alternative. The alternative with the highest expected
outcome is designated the expected monetary value, EMV*.
E(X Co.) = 10(0.3) + 50(0.5) + 70(0.2) = 42
E(Y Co.) = –10(0.3) + 44(0.5) + 120(0.2) = 43
EMY* = Rs. 43 m
E(Z Co.) = 0(0.3) + 20(0.5) + 140(0.2) = 38
z Margin of safety: It is excess of budgeted or actual sales over the break-even sales volume i.e.
margin of safety = (actual sales minus sales at BEP)/actual sales. A high margin of safety would
mean that even with a lean period, where sales go down, the company would not come in loss
area. A small margin of safety means a small reduction in sale would take company to cross BEP
and come in red zone.
CALCULATION OF BEP
Relationship between costs and activity level (AL) is also assumed to be linear. For every elemental
cost, actual cost figures at different activity levels are plotted, and by ‘least square analysis’ a ‘line
of best fit’ is obtained. This would give a fixed cost component and a variable cost component for
the elemental cost.
This analysis is carried out for all elemental costs. The total cost function would give total fixed
cost and total variable cost for the company. The Break-even Point is that volume where the fixed
and variable costs are covered. But no profit exists. Thus at BEP, the total revenues equal to the
total costs.
If F – Fixed Costs, which are independent on quantity produced
a – Variable Cost per unit
b – Selling Price per unit
Q – Quantity (Volume of output)
The total costs are given by
Total Cost (TC) = Fixed Cost + Variable Cost
TC = (F + a⋅ Q)
Sales Revenue (SR) = Selling price per unit × Quantity
SR = b.Q
The point of Intersection of Total Cost line and the sales revenue is the Break-even Point
i.e. at Break-even Point, Total Cost (TC) = Sales Revenue (SR)
F+a⋅Q = b⋅Q
F = Q (b – a)
F
Q = in units ...(1)
(b – a )
In terms of the number of units sold the break-even point is given by :
F
Unit
QBEP = (b – 1)
Profit volume ratio (PVR) is defined as the ratio between Contribution Margin and Sales Revenue.
Contribution ⋅ Margin
i.e. Profit Volume Ratio (f) =
Sales. Revenue
Sales. Revenue – Total×Variable× Cost
=
Sales. Re venue
Operations Decision-Making 37
(b ⋅ Q – a ⋅ Q )Q (b – a )
φ = = (2)
b⋅Q b⋅Q
From Equation 1, F = Q ⋅ (b – a), Hence Equation 2 can be written as
Q ⋅ (b – a ) F
φ = =
b ⋅Q b⋅Q
F
i.e. b ⋅ Q =
Q
So BEP can also be given by
F F
QBEP = = (3)
PV ⋅ Ratio φ
Fig. 2.3
Margin of safety (MOS) is defined as the ratio between Operating Profit and Contribution
Margin. It signifies the fractional reduction in the current activity level required to reach the break-
even point.
Sales turnover (STO) is defined as ratio between Sales Revenue and the Capital Employed. It
represents the number of times capital employed is turned over to reach the sales revenue level that
is called Operating management performance [OMP].
IMPROVING OMP
A company interested in improving its OMP will have to improve its operating profit. Following any
of the strategies given below or a combination of them can do this:
(a) By reducing variable costs
(b) By reducing fixed costs
38 Operations Management
Fig. 2.4
(b) A reductin in fixed costs will bring down BEP and increase margin of safety. It will have no
effect on PV ratio. To achieve a required TP by controlling fixed cost alone, the fixed cost
would have to be controlled as
F=(SR – V) – Z
Fig. 2.5
Operations Decision-Making 39
(c) An increase in selling price will bring BEP down, it will increase PV ratio and it will also
increase the margin of safety. To get the targeted profit level the increase required in selling
price is given by
(F + Z )
b ' = (b − a ) × b
Fig. 2.6
(d) An increase in activity level will of course have no effect on BEP, it will not change PV
ratio, but will increase the margin of safety. The new activity level required to achieve the
desired TP is given by
(F + Z ) or
(F + Z ) × SR
NewSR =
PV Ratio ( SR – V )
If now is the existing activity level, the activity level required in terms of number of units Nnew to
achieve a targeted profit is given by
( F + Z ) or ( F + Z ) × N
N New =
CM (SR – V ) New
With the help of this analysis, discreet decisions regarding control of variable costs, fixed costs,
fixing sales price and activity level can be taken to achieve the desired targeted profit.
ILLUSTRATION 6: The owner of shop is contemplating adding a new product, which will
require additional monthly payment of Rs. 6,000. Variable costs would be Rs. 2.00 per new
product, and its selling price is Rs. 7.00 each.
40 Operations Management
ILLUSTRATION 7: A manager has the option of purchasing one, two, or three machines.
Fixed costs and potential volumes are as follows:
Variable cost is Rs.10 per unit, and revenue is Rs.40 per unit.
(a) Determine the break-even point for each range.
(b) If projected annual demand is between 580 and 660 units, how many machines should
the manager purchase?
SOLUTION
(a) Compute the break-even point for each range using the formula
F
QBEP =
(b − a )
F 9600
For one machine QBEP = = = 320 units
(b − a ) (40 − 10)
[Not in range, so there is no BEP]
F 15000
For two machines QBEP = = = 500 units
(b − a ) (40 − 10)
F 20000
For three machines QBEP = = = 666.67 units
(b − a ) (40 − 10)
Operations Decision-Making 41
(b) Comparing the projected range of demand to the two ranges for which a break-even point
occurs, we can see that the break-even point is 500, which is in the range 301 to 600.
This means that even if demand were at the low end of the range, it would be above the break-
even point and thus yield a profit. That is not true of range 601 to 900. At the top end of
projected demand, the volume would still be less than the break-even point for that range, so
there would be no profit. Hence, the manager should choose two machines.
ILLUSTRATION 8: For an existing product that sells for SP = Rs.650 per unit, FC = Rs.82,000
and VC = Rs. 240 per unit. (a) What is the BEP? (b) What volume is needed to generate a
profit of Rs.10,250?
SOLUTION
F 82000
(a) QBEP = = = 200units
(b − a) (650 − 240)
(b) The volume needed for a specific profit can be computed as:
Z + F 10250 + 82000
QBEP = = = 225 units
b−a (650 − 240)
Note: For volumes > BEP, all contribution of (Rs.650 – 240 = Rs.410/unit) goes into profit. Thus
the additional volume needed is Rs.10,250 ÷ Rs.410/unit = 25 units.
ILLUSTRATION 9: Process X has fixed costs of Rs. 20,000 per year and variable costs of
Rs. 12 per unit, whereas process Y has fixed costs of Rs. 8,000 per year and variable costs of
Rs. 22 per unit. At what production quantity (Q) are the total costs of X and Y equal?
SOLUTION
X = Y
Fx + Vx.Q = F y + V y⋅ Q
Rs. 20,000 + Rs. 12Q = Rs. 8,000 + Rs. 22Q
Rs. 10Q = Rs. 12,000
Q = 1,200 units.
ILLUSTRATION 10: Cover-the-Globe Paint Co. produces 9,000 paint sprayers per year
and obtains Rs. 675, 000 revenue from them. Fixed costs are Rs. 210,000 per year, and total
costs are Rs. 354,000 per year. How much does each sprayer contribute to fixed costs and
profit?
SOLUTION
Contribution Margin(CM) = SP – VC
675000 Total Variable Cost
Where Sales × Price = = Rs. 75 per unit and VC =
9000 Quantity
Where TVC = Total Cost – Fixed Cost = Rs. 354,000 – Rs. 210,000 = Rs. 144,000
42 Operations Management
144000
= = Rs. 16 per unit
9000
Therefore, C = Rs. 75 – Rs.16 = Rs. 59/unit
ILLUSTRATION 11: A firm has annual fixed costs of Rs.3.2 million and variable costs of
Rs.7 per unit. It is considering an additional investment of Rs. 800,000, which will increase
the fixed costs by Rs. 150,000 per year and will increase the contribution by Rs. 2 per unit.
No change is anticipated in the sales volume or the sales price of Rs.15 per unit. What is the
break-even quantity if the new investment is made?
SOLUTION: The Rs. 2 increase in contribution will decrease variable cost to Rs.7 – Rs.2 = Rs. 5
per unit. The addition to fixed cost makes them Rs. 3.2 million + Rs.150,000 = Rs. 3,350,000.
F 3350000
QBEP = = = 335000 units.
b − a (15 − 5)
ILLUSTRATION 12: A producer of air conditioners sells the industrial model for Rs. 175
each. The production costs at volumes of 2,000 and 4,000 units are as shown in Table. The
company does not know the fixed cost at zero volume and realizes that some of its costs are
“semivariable.” Nevertheless, it wishes to prepare a break-even chart and determine the BEP.
SOLUTION: This is a more realistic situation, because the fixed cost and variable cost are determined
from actual production volumes. Plot the total cost at both volumes as seen in Fig. 2.7. The slope of
the total cost line (∆Y / ∆X) is the estimated variable cost per unit.
5,00,000
BEP
3,50,000
Costs
Fig. 2.7
ILLUSTRATION 13: A professional sports promoter leases a 40,000 seat stadium for soccer
games. Tickets sell for an average of Rs.14 each. If fixed costs per season (four games) are
Rs.1720,000 and variable costs are Rs. 2 per spectator, what is the break-even point in number
of seats filled per game?
SOLUTION
F 720000
QBEP = = = 60000 seats/season
b−a (14 − 2)
60000 seats
QBEP = =15000 seats/games
4 games
ILLUSTRATION 14: Market research data on a company’s product has shown that during
the first 3 years of use, 10 per cent of the products had a mechanical difficulty and 40 per
cent had an electrical problem. The probability of an electrical problem, given some mechanical
difficulty, is 0.6. What is the probability that a product will have either a mechanical difficulty
or an electrical problem, or both?
SOLUTION
Probability of Mechanical defect is P (M) = 0.10
Probability of Electrical defect is P (E) = 0.40
Probability of an electrical problem, with mechanical defect P(E/M) = 0.60
Probability that a product will have either a mechanical difficulty or an electrical problem is
given by P (M or E) = P (M) + p (E) – P (M and E)
Where P (M and E) = P (M) P (E/M) = (0.10)(0.60) = 0.06
P (M or E) = 0.10 + 0.40 – 0.06 = 0.44.
ILLUSTRATION 15: Three molding machines (X, Y and Z) are used to produce 600 computer
terminal keys that are rushed (without inspection) to a customer. The number of good (G) and
defective (0) keys from each machine is as shown in Table.
When customer receives the keys, they are randomly selected for installation at the probability
that a key selected (a) is defective, (b) was produced by machine Z and good, (c) was either
produced by machine Z or is good? (d) Is the probability of selecting a good key independent of the
machine from which the key was made?
Operations Decision-Making 45
SOLUTION: Given the data, we can estimate the empirical probabilities as follows:
Number of good 540
P (G ) = = = 0.900
Total number keys 600
Number from Z 300
P(Z ) = = = 0.500
Total number keys 600
P(G l Z), which is read “Good, given it is from Z,” is found as follows:
Number from Z that are good 270
P (G / Z ) = = = 0.900
Total number from Z 300
Now, using the rules of probability we have:
(a) P (G) =1– P (g) =1 – 0.90 = 0.10
(b) P (Z and G)=P (Z) P (G/Z) = (0.50)(0.90) = 0.45
(c) P (Z or G) = P (Z) + P (G) – P (Z and G) = 0.50 + 0.90 – 0.45 = 0.95
(d) The P (G) does not depend on whether the key is from machine X, Y, or Z:
P (G) = P (G/X) = P (G/Y) = P (G/Z) = 540/600 = 225/250 = 0.90
Discrete Continuous
(countable: attributes data) (measurable: variables data)
Population
Sample
S = pq
Standard deviation
S=
∑ ( X − X )2
n −1
Where q = 1 – p
Sampling distribution
pq S
Sp = SX =
Standard error n n
ILLUSTRATION 16: In 400 observations of a computer operator, an analyst found him idle
32 times. Find (a) the sample proportion and (b) the standard error of proportion.
SOLUTION
no.idle 32
(a) = = = 0.08
P total no. 400
pq (0.08)(0.92)
(b) Sp = = = 0.014 .
n 400
ILLUSTRATION 17: In a study to find the time to service customers, a bank teller worked
60 minutes and served 36 customers. A record of the individual service times showed Σ (X – X)2
= (0.79 minutes)2. Find (a) the sample mean time and (b) the standard error of the mean.
60
(a) Mean X = = 1.67 min/customer
36
(b) SX =
S
where S =
∑ ( X − X )2 =
79
= 0.15 min
n n −1 36 − 1
S 0.15
Therefore, SX = = = 0.025 min .
n 36
After the tree has been drawn, it is analyzed from right to left; that is, starting with the last
decision that might be made. For each decision, choose the alternative that will yield the greatest
return (or the lowest cost). If chance events follow a decision, choose the alternative that has the
highest expected monetary value (or lowest expected cost).
Fig. 2.8 A schematic representation of the available alternatives and their possible consequences
ILLUSTRATION 18: A manager must decide on the size of a video arcade to construct. The
manager has narrowed the choices to two: large or small. Information has been collected on
pay-offs, and a decision tree has been constructed. Analyze the decision tree and determine
which initial alternative (build small or build large) should be chosen in order to maximize
expected monetary value.
Hence, the choice should be to build the large facility because it has a larger expected value than
the small facility.
ILLUSTRATION 19: A manufacturer of small power tools is faced with foreign competition,
which necessitates that it either modify (automate) its existing product or abandon it and
market a new product. Regardless of which course of action it follows, it will have the
opportunity to drop or raise prices if it experiences a low initial demand.
Pay-off and probability values associated with the alternative courses of action are shown
in Fig. 2.10. Analyze the decision tree, and determine which course of action should be
chosen to maximize the expected monetary value. (Assume monetary amounts are present-
value profits.)
SOLUTION: Analyze the tree from right to left by calculating the expected values for all possible
courses of action and choosing the branch with the highest expected value. Begin with the top
(modify product) branch.
At chance event 2
Drop price branch: E(X) = Rs. 20,000(0.2) + Rs.150,000(0.8) = Rs.124,000
Raise price branch: E(X) = Rs. 40,000(0.9) + Rs. 200,000(0.1) = Rs.56,000
Therefore, choose to drop price and use Rs.124,000 as the value of this branch at Decision 2.
Note: The Rs.124,000 is an expected monetary value (EMV) and can be entered above the square
box under Decision 2. Place slash marks through the other (non-usable) alternative.
Operations Decision-Making 49
At chance event 1
If low demand: Rs. 124, 000 (0.3) = Rs. 37,200
If high demand: 400,000 (0.7) = Rs. 280, 000
E (X) = Rs. 317, 200
Therefore, use Rs. 317,200 as the value of this branch at Decision 1. Similarly, for the bottom
(new product) branch, the values are Rs. 86,000 at Decision 2 and [Rs. 86,000 (0.5) + Rs. 600,000
(0.5) ] Rs. 343,000 at Decision 1. The new product branch thus has a higher expected value and is
selected as the best course of action under the expected value criteria.
EXERCISE
1. List the steps in a systematic decision-making process.
2. Identify some major advantages of using models.
3. What types of models are most useful for operations management decision-making?
4. How do the characteristics of the decision situation affect the choice of a technique to use in decision
analysis?
5. What factors contribute most to the complexity of a decision situation?
6. What is break-even analysis?
7. What is contribution?
8. What is a decision tree?
9. What kinds of decision situations are particularly well suited to analysis by the use of decision
analysis?
50 Operations Management
10. Distinguish between (a) classical, (b) empirical, and (c) subjective probabilities.
11. Explain the two concepts underlying statistical inference of (a) sampling distribution and (b) the
central limit theorem.
12. What is the difference between the standard error of proportion and standard error of mean?
13. Ten observations taken of the time required to assemble a sofa frame in a furniture plant were as
shown below (min). Find the (a) mean time, (b) standard deviation, and (c) standard error of the mean.
Observation 4.7 4.2 5.1 4.8 5.5 5.4 5.8 4.8 5.0 4.7 50.0
(X – X) – 0.3 – 0.8 0.1 –0.2 0.5 0.4 0.8 – 0.2 0.0 –0.3
(X – X) 2 0.09 0.64 0.01 0.04 0.25 0.16 0.64 0.04 0.00 0.09 1.96
14. Fixed costs are Rs. 40,000 per year, variable costs are Rs. 50 per unit, and the selling price is Rs. 90
each. Find the BEP. [Ans. 1,000 units]
15. Florida Citrus produced 40,000 boxes of fruit that sold for Rs. 3 per box. The total variable costs for
the 40,000 boxes were Rs. 60,000, and the fixed costs were Rs.75,000. (a) What was the break-even
quantity? (b) How much profit (or loss) resulted?
[Ans. (a) 50,000 boxes and (b) Rs.15, 000 loss]
16. A travel agency has an excursion package that sells for Rs. 125. Fixed costs are Rs. 80,000; and at the
present volume of 1,000 customers, variable costs are Rs. 25,000 and profits are
Rs. 20,000. (a) What is the break-even point volume? (b) Assuming that fixed costs remain constant,
how many additional customers will be required for the agency to increase profit by Rs.1000?
[Ans. (a) 800 units (b) 10 customers]
17. Last year, Dever Furniture Co. produced 200 maple dressers (pattern 427) that sold for Rs. 210 each.
The company included labour costs of Rs. 42 per unit and material costs of Rs.18 per unit, and it
allocated Rs. 80 per unit of overhead costs to each dresser. Cost records reveal that overhead costs are
60 per cent fixed and 40 per cent variable. What was the total annual contribution from pattern 427?
[Ans. Rs.118 per unit, or Rs. 23, 600 total]
18. Given the pay-off table below showing the profit (present value Rs.in lakhs), a firm might expect in a
foreign country for three alternative factory investments (X, Y, and Z) under different levels of
inflation. Economists have assigned probabilities of 0.2, 0.3, 0.4, and 0.1 to the possible inflation
levels A, B, C and D, respectively. Find the preferred investment alternative using criteria of
(a) Maximax, (b) Maximin, (c) Laplace, (d) Maximum probability, and (e) Expected monetary value.
Finally, (f) use your “judgment.”
A = 2% B = 5% C =10% D =15%
Build factory Y 40 50 60 70
Lease plant Z 10 40 80 10
19. Frozen Pizza Co. is considering whether it should allocate funds for research on an instant freeze-dry
process for home use. If the research is successful (and the R&D manager feels there is a 75 per cent
chance it will be), the firm could market the product at a Rs.4 million profit. However, if the research
Operations Decision-Making 51
is unsuccessful, the, firm will incur a Rs.6 million loss. What is the expected monetary value (EMV)
of proceeding with the research? [Ans. Rs.1.5 million]
20. The operations manager of a large airport is concerned with the problem of having adequate personnel
to offer individual assistance to handicapped passengers during rush hours. Data were collected on
the number of requests for assistance during 20 randomly selected rush hours and revealed the
information shown in Table.
Hour no. 1 2 3 4 5 6 7 8 9 10
No. of requests 40 42 42 30 38 48 42 44 37 38
Hour no. 11 12 13 14 15 16 17 18 19 20
No. of requests 49 47 34 57 42 52 56 44 50 48
Determine (a) Mean, (b) Standard Deviation, and (c) Standard Error of the mean.
Ans. (a) 44 requests per hour (b) 7 requests per hour (c) 1.57
REFERENCES
1. Joseph, G. Monks, Theory and Problems of Operations Management, Tata McGraw-Hill
Publishing Company Limited, 2nd Edition, 2004.
2. Joseph, G. Monks, Operations Management, McGraw-Hill International Edition, 3rd Edition.
3. S.Anil Kumar, N. Suresh, Production and Operations Management, New Age International
(P) Limited Publishers, 2nd Edition, 2008.
This page
intentionally left
blank
Systems Design and Capacity 53
3
SYSTEMS DESIGN AND CAPACITY
CHAPTER OUTLINE
3.1 Introduction 3.5 Process of Capacity Planning
3.2 Manufacturing and Service Systems 3.6 Importance of Capacity Decisions
3.3 Design and Systems Capacity • Exercise
3.4 Capacity Planning • References
3.1 INTRODUCTION
Before products can flow into a market, someone must design and invest in the facilities and
organisation to produce them. This chapter concerns the planning of the systems needed to produce
goods and services. Capacity Planning for manufacturing and service systems are different. Both
must be designed with capacity limitations in mind. The approaches for long-term and short-term
capacity planning will help the managers to make best use of resources.
DESIGN CAPACITY
Designed capacity of a facility is the planned or engineered rate of output of goods or services under
normal or full scale operating conditions. For example, the designed capacity of the cement plant is 100
TPD (Tonnes per day). Capacity of the sugar factory is 150 tonnes of sugarcane crushing per day.
The uncertainty of future demand is one of the most perplexing problems faced by new facility planners.
Organisation does not plan for enough regular capacity to satisfy all their immediate demands.
Design for a minimum demand would result in high utilisation of facilities but results in inferior
service and dissatisfaction of customers because of inadequate capacity. The design capacity should
reflect management’s strategy for meeting the demand. The best approach is to plan for some
in-between level of capacity.
System/effective capacity: System capacity is the maximum output of the specific product or
product mix the system of workers and machines is capable of producing as an integrated whole.
System capacity is less than design capacity or at the most equal it because of the limitation of product
mix, quality specification, and breakdowns. The actual is even less because of many factors affecting
the output such as actual demand, downtime due to machine/equipment failure, unauthorized absenteeism.
The system capacity is less than design capacity because of long-range uncontrollable factors.
The actual output is still reduced because of short-term effects such as breakdown of equipment,
Systems Design and Capacity 55
inefficiency of labour. The system efficiency is expressed as ratio of actual measured output to the
system capacity.
These different measures of capacity are useful in defining two measures of system effectiveness:
efficiency and utilization. Efficiency is the ratio of actual output to effective capacity. Utilization is
the ratio of actual output to design capacity.
Actual output
Efficiency =
Effective capacity
Actual output
Utilization =
Design capacity
It is common for managers to focus exclusively on efficiency, but in many instances, this emphasis
can be misleading. This happens when effective capacity is low compared with design capacity. In
those cases, high efficiency would seem to indicate effective use of resources when it does not.
Capacity planning is the first step when an organisation decides to produce more or new products.
into the future is more risky and difficult. Even sometimes company’s today’s products may not be
existing in the future. Long-range capacity requirements are dependent on marketing plans, product
development and life-cycle of the product. Long-term capacity planning is concerned with accommodating
major changes that affect overall level of the output in long-term. Marketing environmental assessment
and implementing the long-term capacity plans in a systematic manner are the major responsibilities of
management. Following parameters will affect long-range capacity decisions.
z Multiple products: Company’s produce more than one product using the same facilities
in order to increase the profit. The manufacturing of multiple products will reduce the risk
of failure. Having more than on product helps the capacity planners to do a better job.
Because products are in different stages of their life cycles, it is easy to schedule them to
get maximum capacity utilisation.
z Phasing in capacity: In high technology industries, and in industries where technology
developments are very fast, the rate of obsolescence is high. The products should be
brought into the market quickly. The time to construct the facilities will be long and there
is no much time, as the products should be introduced into the market quickly. Here the
solution is phase in capacity on modular basis. Some commitment is made for building
funds and men towards facilities over a period of 3-5 years. This is an effective way of
capitalizing on technological breakthrough.
z Phasing out capacity: The outdated manufacturing facilities cause excessive plant
closures and down time. The impact of closures is not limited to only fixed costs of plant
and machinery. Thus, the phasing out here is done with humanistic way without affecting
the community. The phasing out options makes alternative arrangements for men like
shifting them to other jobs or to other locations, compensating the employees, etc.
2. Short-term capacity strategies: Managers often use forecasts of product demand to
estimate the short-term workload the facility must handle. Managers looking ahead up to 12 months,
anticipate output requirements for different products, and services. Managers then compare
requirements with existing capacity and then take decisions as to when the capacity adjustments are
needed.
For short-term periods of up to one year, fundamental capacity is fixed. Major facilities will not
be changed. Many short-term adjustments for increasing or decreasing capacity are possible. The
adjustments to be required depend upon the conversion process like whether it is capital intensive or
labour intensive or whether product can be stored as inventory.
Capital-intensive processes depend on physical facilities, plant and equipment. Short-term capacity
can be modified by operating these facilities more or less intensively than normal. In labour intensive
processes short-term capacity can be changed by laying off or hiring people or by giving overtime to
workers. The strategies for changing capacity also depend upon how long the product can be stored
as inventory.
The short-term capacity strategies are:
1. Inventories: Stock finished goods during slack periods to meet the demand during peak
period.
2. Backlog: During peak periods, the willing customers are requested to wait and their orders
are fulfilled after a peak demand period.
3. Employment level (hiring or firing): Hire additional employees during peak demand
period and layoff employees as demand decreases.
Systems Design and Capacity 57
4. Employee training: Develop multi skilled employees through training so that they can be
rotated among different jobs. The multi skilling helps as an alternative to hiring employees.
5. Subcontracting: During peak periods, hire the capacity of other firms temporarily to make
the component parts or products.
6. Process design: Change job contents by redesigning the job.
ILLUSTRATION 2: The design capacity for engine repair in our company is 80 trucks per
day. The effective capacity is 40 engines per day and the actual output is 36 engines per day.
Calculate the utilization and efficiency of the operation. If the efficiency for next month is
expected to be 82%, what is the expected output?
58 Operations Management
SOLUTION
Actual output 36
Utilization = = = 45%
Design capacity 40
Actual output 36
Efficiency = = = 90%
Effective capacity 40
Expected output = (Effective capacity)(Efficiency)
= (40)(0.82) = 32.8 engines per day
ILLUSTRATION 3: Given: F = Fixed Cost = Rs. 1000, V = Variable cost = Rs. 2 per unit
and P = Selling price = Rs. 4 per unit, Find the break-even point in Rs. and in units. Develop
the break-even chart.
SOLUTION
F 1000 1000
Break-even point($) = BEP($) = = = = $2,000
V 2 0.5
1− 1−
P 4
F 1000
Break-even point( x ) = BEP( x ) = = = 500
P −V 4 − 2
Fig. 3.2
ILLUSTRATION 4: Jack’s Grocery is manufacturing a “store brand” item that has a variable
cost of Rs. 0.75 per unit and a selling price of Rs. 1.25 per unit. Fixed costs are Rs. 12,000.
Current volume is 50,000 units. The Grocery can substantially improve the product quality by
adding a new piece of equipment at an additional fixed cost of Rs. 5,000. Variable cost would
increase to Rs. 1.00, but their volume should increase to 70,000 units due to the higher
quality product. Should the company buy the new equipment? What are the break-even points
(Rs. and units) for the two processes? Develop a break-even chart.
Systems Design and Capacity 59
SOLUTION
Profit = TR – TC
Option A: Current Equipment
BEP Sales in value (Rs.)
BEP Sales in Quantity (Units)
Option B: Adding New Equipment
BEP Sales in value (Rs.)
BEP Sales in Quantity (Units)
Profit = 50000 * (1.25 – 0.75) –12000 = Rs.13000.
Option B: Add equipment:
Profit = 70000 * (1.25 – 1.00) – 17000 = Rs.500.
Therefore, the company should continue as is with the present equipment as this returns a
higher profit.
Using current equipment:
Fig. 3.3
60 Operations Management
EXERCISE
1. What is meant by ‘phasing in’ capacity?
2. Distinguish between design capacity and system capacity.
3. How the following organizations adjust to the daily fluctuations in demand?
(a) Airlines, (b) Restaurants, (c) Dentists.
4. A manufacturer of TV watches uses three TRS7 electronic chips in each TV watches produced.
Demand estimates for the number of TV watches that could be sold next year are shown
Demand X 20000 40000 50000
REFERENCES
1. Joseph, G. Monks, Theory and Problems of Operations Management, Tata McGraw-Hill
Publishing Company Limited, 2nd Edition, 2004.
2. Joseph, G. Monks, Operations Management, McGraw-Hill International Edition, 3rd Edition.
3. S. Anil Kumar, N. Suresh, Production and Operations Management, New Age International
(P) Limited Publishers, 2nd Edition, 2008.
Facility Location and Layout 61
4
FACILITY LOCATION AND LAYOUT
CHAPTER OUTLINE
4.1 Introduction and Meaning 4.8 Classification of Layout
4.2 Need for Selecting a Suitable Location 4.9 Design of Product Layout
4.3 Factors Influencing Plant/Facility Location 4.10 Design of Process Layout
4.4 Location Theories 4.11 Service Layout
4.5 Location Models 4.12 Organisation of Physical Facilities
4.6 Locational Economics • Exercise
4.7 Plant Layout
I. When starting a new organisation, i.e., location choice for the first time.
II. In case of existing organisation.
III. In case of Global Location.
I. In Case of Location Choice for the First Time or New Organisations
Cost economies are always important while selecting a location for the first time, but should
keep in mind the cost of long-term business/organisational objectives. The following are the
factors to be considered while selecting the location for the new organisations:
1. Identification of region: The organisational objectives along with the various long-term
considerations about marketing, technology, internal organisational strengths and weaknesses, region-
specific resources and business environment, legal-governmental environment, social environment
and geographical environment suggest a suitable region for locating the operations facility.
2. Choice of a site within a region: Once the suitable region is identified, the next step
is choosing the best site from an available set. Choice of a site is less dependent on the
organisation’s long-term strategies. Evaluation of alternative sites for their tangible and intangible
costs will resolve facilities-location problem.
The problem of location of a site within the region can be approached with the following
cost-oriented non-interactive model, i.e., dimensional analysis.
3. Dimensional analysis: If all the costs were tangible and quantifiable, the comparison and
selection of a site is easy. The location with the least cost is selected. In most of the cases
intangible costs which are expressed in relative terms than in absolute terms. Their relative merits
and demerits of sites can also be compared easily. Since both tangible and intangible costs need
to be considered for a selection of a site, dimensional analysis is used.
Dimensional analysis consists in computing the relative merits (cost ratio) for each of the
cost items for two alternative sites. For each of the ratios an appropriate weightage by means
of power is given and multiplying these weighted ratios to come up with a comprehensive figure
on the relative merit of two alternative sites, i.e.,
C1M, C2M, …, CzM are the different costs associated with a site M on the ‘z’ different cost
items.
C1N, C2N, …, CzN are the different costs associated with a site N and W1, W2, W3, …, Wz
are the weightage given to these cost items, then relative merit of the M and site N is given by:
(C ) ( ) ( )
W1 W2 Wz
M
1 /C1N × C M2 /C 2N ,...,C Mz /C zN
If this is > 1, site N is superior and vice-versa.
When starting a new factory, plant location decisions are very important because they have
direct bearing on factors like, financial, employment and distribution patterns. In the long run,
relocation of plant may even benefit the organization. But, the relocation of the plant involves
stoppage of production, and also cost for shifting the facilities to a new location. In addition to
these things, it will introduce some inconvenience in the normal functioning of the business.
Hence, at the time of starting any industry, one should generate several alternate sites for locating
the plant. After a critical analysis, the best site is to be selected for commissioning the plant.
Location of warehouses and other facilities are also having direct bearing on the operational
performance of organizations.
Facility Location and Layout 63
The existing firms will seek new locations in order to expand the capacity or to place the
existing facilities. When the demand for product increases, it will give rise to following decisions:
O Whether to expand the existing capacity and facilities.
O Whether to close down existing facilities to take advantage of some new locations.
For an established organization in order to add on to the capacity, following are the ways:
(a) Expansion of the facilities at the existing site: This is acceptable when it does not
violate the basic business and managerial outlines, i.e., philosophies, purposes, strategies and
capabilities. For example, expansion should not compromise quality, delivery, or customer service.
(b) Relocation of the facilities (closing down the existing ones): This is a drastic step
which can be called as ‘Uprooting and Transplanting’. Unless there are very compelling reasons,
relocation is not done. The reasons will be either bringing radical changes in technology, resource
availability or other destabilization.
All these factors are applicable to service organizations, whose objectives, priorities and
strategies may differ from those of hardcore manufacturing organizations.
III. In Case of Global Location
Because of globalisation, multinational corporations are setting up their organizations in India
and Indian companies are extending their operations in other countries. In case of global locations
there is scope for virtual proximity and virtual factory.
VIRTUAL PROXIMITY
With the advance in telecommunications technology, a firm can be in virtual proximity to its
customers. For a software services firm much of its logistics is through the information/
communication pathway. Many firms use the communications highway for conducting a large
portion of their business transactions. Logistics is certainly an important factor in deciding on a
location—whether in the home country or abroad. Markets have to be reached. Customers have
to be contacted. Hence, a market presence in the country of the customers is quite necessary.
VIRTUAL FACTORY
Many firms based in USA and UK in the service sector and in the manufacturing sector often out
sources part of their business processes to foreign locations such as India. Thus, instead of one’s
own operations, a firm could use its business associates’ operations facilities. The Indian BPO firm
is a foreign-based company’s ‘virtual service factory’. So a location could be one’s own or one’s
business associates. The location decision need not always necessarily pertain to own operations.
REASONS FOR A GLOBAL/FOREIGN LOCATION
A. Tangible Reasons
The tangible reasons for setting up an operations facility abroad could be as follows:
Reaching the customer: One obvious reason for locating a facility abroad is that of
capturing a share of the market expanding worldwide. The phenomenal growth of the GDP of
India is a big reason for the multinationals to have their operations facilities in our country. An
important reason is that of providing service to the customer promptly and economically which
is logistics-dependent. Therefore, cost and case of logistics is a reason for setting up manufacturing
facilities abroad. By logistics set of activities closes the gap between production of goods/services
and reaching of these intended goods/services to the customer to his satisfaction. Reaching the
customer is thus the main objective. The tangible and intangible gains and costs depend upon the
company defining for itself as to what that ‘reaching’ means. The tangible costs could be the
logistics related costs; the intangible costs may be the risk of operating is a foreign country. The
tangible gains are the immediate gains; the intangible gains are an outcome of what the company
defines the concepts of reaching and customer for itself.
Facility Location and Layout 65
(d) The firm could hunt for human capital in different countries by having operations in
those countries. Thus, the firm can gather the best of people from across the globe.
(e) Foreign locations in addition to the domestic locations would lower the market risks
for the firm. If one market goes slow the other may be doing well, thus lowering the
overall risk.
67
68 Operations Management
6. External economies
7. Capital.
UNCONTROLLABLE FACTORS
8. Government policy
9. Climate conditions
10. Supporting industries and services
11. Community and labour attitudes
12. Community Infrastructure.
CONTROLLABLE FACTORS
1. Proximity to markets: Every company is expected to serve its customers by providing
goods and services at the time needed and at reasonable price organizations may choose to locate
facilities close to the market or away from the market depending upon the product. When the
buyers for the product are concentrated, it is advisable to locate the facilities close to the market.
Locating nearer to the market is preferred if
• The products are delicate and susceptible to spoilage.
• After sales services are promptly required very often.
• Transportation cost is high and increase the cost significantly.
• Shelf life of the product is low.
Nearness to the market ensures a consistent supply of goods to customers and reduces the
cost of transportation.
2. Supply of raw material: It is essential for the organization to get raw material in right
qualities and time in order to have an uninterrupted production. This factor becomes very important
if the materials are perishable and cost of transportation is very high.
General guidelines suggested by Yaseen regarding effects of raw materials on plant location
are:
• When a single raw material is used without loss of weight, locate the plant at the raw
material source, at the market or at any point in between.
• When weight loosing raw material is demanded, locate the plant at the raw material
source.
• When raw material is universally available, locate close to the market area.
• If the raw materials are processed from variety of locations, the plant may be situated
so as to minimize total transportation costs.
Nearness to raw material is important in case of industries such as sugar, cement, jute and
cotton textiles.
3. Transportation facilities: Speedy transport facilities ensure timely supply of raw materials
to the company and finished goods to the customers. The transport facility is a prerequisite for
Facility Location and Layout 69
the location of the plant. There are five basic modes of physical transportation, air, road, rail,
water and pipeline. Goods that are mainly intended for exports demand a location near to the port
or large airport. The choice of transport method and hence the location will depend on relative
costs, convenience, and suitability. Thus transportation cost to value added is one of the criteria
for plant location.
4. Infrastructure availability: The basic infrastructure facilities like power, water and
waste disposal, etc., become the prominent factors in deciding the location. Certain types of
industries are power hungry e.g., aluminum and steel and they should be located close to the
power station or location where uninterrupted power supply is assured throughout the year. The
non-availability of power may become a survival problem for such industries. Process industries
like paper, chemical, cement, etc., require continuous. Supply of water in large amount and good
quality, and mineral content of water becomes an important factor. A waste disposal facility for
process industries is an important factor, which influences the plant location.
5. Labour and wages: The problem of securing adequate number of labour and with skills
specific is a factor to be considered both at territorial as well as at community level during plant
location. Importing labour is usually costly and involve administrative problem. The history of
labour relations in a prospective community is to be studied. Prospective community is to be
studied. Productivity of labour is also an important factor to be considered. Prevailing wage
pattern, cost of living and industrial relation and bargaining power of the unions’ forms in
important considerations.
6. External economies of scale: External economies of scale can be described as
urbanization and locational economies of scale. It refers to advantages of a company by setting
up operations in a large city while the second one refers to the “settling down” among other
companies of related Industries. In the case of urbanization economies, firms derive from locating
in larger cities rather than in smaller ones in a search of having access to a large pool of labour,
transport facilities, and as well to increase their markets for selling their products and have
access to a much wider range of business services.
Location economies of scale in the manufacturing sector have evolved over time and have
mainly increased competition due to production facilities and lower production costs as a result
of lower transportation and logistical costs. This led to manufacturing districts where many
companies of related industries are located more or less in the same area. As large corporations
have realized that inventories and warehouses have become a major cost factor, they have tried
reducing inventory costs by launching “Just in Time” production system (the so called Kanban
System). This high efficient production system was one main factor in the Japanese car industry
for being so successful. Just in time ensures to get spare parts from suppliers within just a few
hours after ordering. To fulfill these criteria corporations have to be located in the same area
increasing their market and service for large corporations.
7. Capital: By looking at capital as a location condition, it is important to distinguish the
physiology of fixed capital in buildings and equipment from financial capital. Fixed capital costs
as building and construction costs vary from region to region. But on the other hand buildings can
also be rented and existing plants can be expanded. Financial capital is highly mobile and does
not very much influence decisions. For example, large Multinational Corporations such as Coca-
70 Operations Management
Cola operate in many different countries and can raise capital where interest rates are lowest
and conditions are most suitable.
Capital becomes a main factor when it comes to venture capital. In that case young, fast
growing (or not) high tech firms are concerned which usually have not many fixed assets. These
firms particularly need access to financial capital and also skilled educated employees.
UNCONTROLLABLE FACTORS
8. Government policy: The policies of the state governments and local bodies concerning
labour laws, building codes, safety, etc., are the factors that demand attention.
In order to have a balanced regional growth of industries, both central and state governments
in our country offer the package of incentives to entrepreneurs in particular locations. The
incentive package may be in the form of exemption from a safes tax and excise duties for a
specific period, soft loan from financial institutions, subsidy in electricity charges and investment
subsidy. Some of these incentives may tempt to locate the plant to avail these facilities offered.
9. Climatic conditions: The geology of the area needs to be considered together with
climatic conditions (humidity, temperature). Climates greatly influence human efficiency and
behaviour. Some industries require specific climatic conditions e.g., textile mill will require humidity.
10. Supporting industries and services: Now a day the manufacturing organisation will
not make all the components and parts by itself and it subcontracts the work to vendors. So,
the source of supply of component parts will be the one of the factors that influences the
location.
The various services like communications, banking services professional consultancy services
and other civil amenities services will play a vital role in selection of a location.
11. Community and labour attitudes: Community attitude towards their work and towards
the prospective industries can make or mar the industry. Community attitudes towards supporting
trade union activities are important criteria. Facility location in specific location is not desirable
even though all factors are favouring because of labour attitude towards management, which
brings very often the strikes and lockouts.
12. Community infrastructure and amenity: All manufacturing activities require access
to a community infrastructure, most notably economic overhead capital, such as roads, railways,
port facilities, power lines and service facilities and social overhead capital like schools, universities
and hospitals.
These factors are also needed to be considered by location decisions as infrastructure is
enormously expensive to build and for most manufacturing activities the existing stock of
infrastructure provides physical restrictions on location possibilities.
DOMINANT FACTORS
Factors dominating location decisions for new manufacturing plants can be broadly classified in
six groups. They are listed in the order of their importance as follows.
Facility Location and Layout 71
DOMINANT FACTORS
The factors considered for manufacturers are also applied to service providers, with one important
addition — the impact of location on sales and customer satisfaction. Customers usually look
about how close a service facility is, particularly if the process requires considerable customer
contact.
72 Operations Management
PROXIMITY TO CUSTOMERS
Location is a key factor in determining how conveniently customers can carry on business with
a firm. For example, few people would like to go to remotely located dry cleaner or supermarket
if another is more convenient. Thus the influence of location on revenues tends to be the
dominant factor.
TRANSPORTATION COSTS AND PROXIMITY TO MARKETS
For warehousing and distribution operations, transportation costs and proximity to markets are
extremely important. With a warehouse nearby, many firms can hold inventory closer to the
customer, thus reducing delivery time and promoting sales.
LOCATION OF COMPETITORS
One complication in estimating the sales potential at different location is the impact of competitors.
Management must not only consider the current location of competitors but also try to anticipate
their reaction to the firm’s new location. Avoiding areas where competitors are already well
established often pays. However, in some industries, such as new-car sales showrooms and fast-
food chains, locating near competitors is actually advantageous. The strategy is to create a
critical mass, whereby several competing firms clustered in one location attract more customers
than the total number who would shop at the same stores at scattered locations. Recognizing this
effect, some firms use a follow –the leader strategy when selecting new sites.
SECONDARY FACTORS
Retailers also must consider the level of retail activity, residential density, traffic flow, and site
visibility. Retail activity in the area is important, as shoppers often decide on impulse to go
shopping or to eat in a restaurant. Traffic flows and visibility are important because businesses
customers arrive in cars. Visibility involves distance from the street and size of nearby buildings
and signs. High residential density ensures night time and weekend business when the population
in the area fits the firm’s competitive priorities and target market segment.
1. Facility utilization 8 3 5
2. Total patient per month 5 4 3
3. Average time per emergency trip 6 4 5
4. Land and construction costs 3 1 2
5. Employee preferences 5 5 3
SOLUTION
Sl. No. Location Factor Location 1 Location 2
factor rating (Rating) Total= (Rating) Total
(1) (2) (1) . (2) (3) = (1) . (3)
1. Facility utilization 8 3 24 5 40
2. Total patient per 5 4 20 3 15
month
3. Average time per 6 4 24 5 30
emergency trip
4. Land and 3 1 3 2 6
construction costs
5. Employee 5 5 25 3 15
preferences
Total 96 Total 106
The total score for location 2 is higher than that of location 1. Hence location 2, is the best
choice.
Location 1 Location 2
1. Facility utilization 25 3 5
2. Total patient km per month 25 4 3
3. Average time per emergency trip 25 3 3
4. Land and construction costs 15 1 2
5. Employee preferences 10 5 3
Facility Location and Layout 75
SOLUTION: The weighted score for this particular site is calculated by multiplying each
factor’s weight by its score and adding the results:
Weighted score location 1 = 25 × 3 + 25 × 4 + 25 × 3 + 15 × 1 + 10 × 5
= 75 + 100 + 75 + 15 + 50 = 315
Weighted score location 2 = 25 × 5 + 25 × 3 + 25 × 3 + 15 × 2 + 10 × 3
= 125 + 75 + 75 + 30 + 30 = 335
Location 2 is the best site based on total weighted scores.
Rectilinear distance measures distance between two points with a series of 90° turns as city
blocks. Essentially, this distance is the sum of the two dashed lines representing the base and side
of the triangle in figure. The distance travelled in the x-direction is the absolute value of the
difference in x-coordinates. Adding this result to the absolute value of the difference in the
y-coordinates gives
DAB = |XA – XB| + |YA – YB|
CALCULATING A LOAD-DISTANCE SCORE
Suppose that a firm planning a new location wants to select a site that minimizes the distances
that loads, particularly the larger ones, must travel to and from the site. Depending on the
industry, a load may be shipments from suppliers, between plants, or to customers, or it may be
customers or employees travelling to or from the facility. The firm seeks to minimize its load-
distance, generally by choosing a location so that large loads go short distances.
To calculate a load-distance for any potential location, we use either of the distance measures
and simply multiply the loads flowing to and from the facility by the distances travelled. These
loads may be expressed as tones or number of trips per week.
This calls for a practical example to appreciate the relevance of the concept. Let us visit
a new Health-care facility, once again.
ILLUSTRATION 3: The new Health-care facility is targeted to serve seven census tracts
in Delhi. The table given below shows the coordinates for the centre of each census tract,
along with the projected populations, measured in thousands. Customers will travel from
the seven census tract centres to the new facility when they need health-care. Two locations
being considered for the new facility are at (5.5, 4.5) and (7, 2), which are the centres
of census tracts C and F. Details of seven census tract centres, co-ordinate distances along
with the population for each centre are given below. If we use the population as the loads
and use rectilinear distance, which location is better in terms of its total load-distance
score?
Sl. No. Census tract (x, y) Population (l)
1 A (2.5, 4.5) 2
2 B (2.5, 2.5) 5
3 C (5.5, 4.5) 10
4 D (5, 2) 7
5 E (8, 5) 10
6 F (7, 2) 20
7 G (9, 2.5) 14
SOLUTION: Calculate the load-distance score for each location. Using the coordinates from
the above table. Calculate the load-distance score for each tract.
Using the formula DAB = |XA – XB| + |YA – YB|
Facility Location and Layout 77
CX =
∑ D .W
ix i
CY =
∑ D .W iy i
∑W i ∑W i
1 A (2.5, 4.5) 2
2 B (2.5, 2.5) 5
3 C (5.5, 4.5) 10
4 D (5, 2) 7
5 E (8, 5) 10
6 F (7, 2) 20
7 G (9, 2.5) 14
SOLUTION: To calculate the centre of gravity, start with the following information, where
population is given in thousands.
Sl. No. Census tract (x, y) Population (l) Lx Ly
1 A (2.5, 4.5) 2 5 9
2 B (2.5, 2.5) 5 12.5 12.5
3 C (5.5, 4.5) 10 55 45
4 D (5, 2) 7 35 14
5 E (8, 5) 10 80 50
6 F (7, 2) 20 140 40
7 G (9, 2.5) 14 126 35
Total 68 453.50 205.50
Break-even
point
Advantages
1. In process layout machines are better utilized and fewer machines are required.
2. Flexibility of equipment and personnel is possible in process layout.
3. Lower investment on account of comparatively less number of machines and lower cost
of general purpose machines.
4. Higher utilisation of production facilities.
5. A high degree of flexibility with regards to work distribution to machineries and workers.
6. The diversity of tasks and variety of job makes the job challenging and interesting.
7. Supervisors will become highly knowledgeable about the functions under their department.
Limitations
1. Backtracking and long movements may occur in the handling of materials thus, reducing
material handling efficiency.
2. Material handling cannot be mechanised which adds to cost.
3. Process time is prolonged which reduce the inventory turnover and increases the in-
process inventory.
4. Lowered productivity due to number of set-ups.
5. Throughput (time gap between in and out in the process) time is longer.
6. Space and capital are tied up by work-in-process.
Advantages
1. The flow of product will be smooth and logical in flow lines.
2. In-process inventory is less.
3. Throughput time is less.
4. Minimum material handling cost.
5. Simplified production, planning and control systems are possible.
6. Less space is occupied by work transit and for temporary storage.
7. Reduced material handling cost due to mechanised handling systems and straight flow.
8. Perfect line balancing which eliminates bottlenecks and idle capacity.
9. Manufacturing cycle is short due to uninterrupted flow of materials.
10. Small amount of work-in-process inventory.
11. Unskilled workers can learn and manage the production.
Limitations
1. A breakdown of one machine in a product line may cause stoppages of machines in the
downstream of the line.
2. A change in product design may require major alterations in the layout.
3. The line output is decided by the bottleneck machine.
4. Comparatively high investment in equipments is required.
5. Lack of flexibility. A change in product may require the facility modification.
Fig. 4.7 Combination layout for making different types and sizes of gears
Facility Location and Layout 85
Advantages
The major advantages of this type of layout are:
1. Helps in job enlargement and upgrades the skills of the operators.
2. The workers identify themselves with a product in which they take interest and pride in
doing the job.
3. Greater flexibility with this type of layout.
4. Layout capital investment is lower.
number of machine-component cells (group) such that all the components assigned to a cell are
almost processed within that cell itself. Here, the objective is to minimize the intercell movements.
The basic aim of a group technology layout is to identify families of components that require
similar of satisfying all the requirements of the machines are grouped into cells. Each cell is
capable of satisfying all the requirements of the component family assigned to it.
The layout design process considers mostly a single objective while designing layouts. In
process layout, the objective is to minimize the total cost of materials handling. Because of the
nature of the layout, the cost of equipments will be the minimum in this type of layout. In product
layout, the cost of materials handling will be at the absolute minimum. But the cost of equipments
would not be at the minimum if the equipments are not fully utilized.
In-group technology layout, the objective is to minimize the sum of the cost of transportation
and the cost of equipments. So, this is called as multi-objective layout. A typical process layout
is shown in Fig. 4.9.
minute. This is also true for other two stations. Since the parts arrive at a rate of one per minute,
parts are also completed at this rate.
Assembly-line systems work well when there is a low variance in the times required to
perform the individual subassemblies. If the tasks are somewhat complex, thus resulting in a
higher assembly-time variance, operators down the line may not be able to keep up with the flow
of parts from the preceding workstation or may experience excessive idle time. An alternative
to a conveyor-paced assembly-line is a sequence of workstations linked by gravity conveyors,
which act as buffers between successive operations.
LINE BALANCING
Assembly-line balancing often has implications for layout. This would occur when, for balance
purposes, workstation size or the number used would have to be physically modified.
The most common assembly-line is a moving conveyor that passes a series of workstations
in a uniform time interval called the workstation cycle time (which is also the time between
successive units coming off the end of the line). At each workstation, work is performed on a
product either by adding parts or by completing assembly operations. The work performed at
each station is made up of many bits of work, termed tasks, elements, and work units. Such tasks
are described by motion-time analysis. Generally, they are grouping that cannot be subdivided on
the assembly-line without paying a penalty in extra motions.
The total work to be performed at a workstation is equal to the sum of the tasks assigned
to that workstation. The line-balancing problem is one of assigning all tasks to a series of
workstations so that each workstation has no more than can be done in the workstation cycle
time, and so that the unassigned (idle) time across all workstations is minimized.
The problem is complicated by the relationships among tasks imposed by product design and
process technologies. This is called the precedence relationship, which specifies the order in
which tasks must be performed in the assembly process.
The steps in balancing an assembly line are:
1. Specify the sequential relationships among tasks using a precedence diagram.
2. Determine the required workstation cycle time C, using the formula
Production time per day
C =
Required output per day (in units)
3. Determine the theoretical minimum number of workstations (Nt) required to satisfy the
workstation cycle time constraint using the formula
Sum of task times (T)
Nt =
Cycle time (C)
4. Select a primary rule by which tasks are to be assigned to workstations, and a secondary
rule to break ties.
5. Assign tasks, once at a time, to the first workstation until the sum of the task times is
equal to the workstation cycle time, or no other tasks are feasible because of time or
sequence restrictions. Repeat the process for workstation 2, workstation 3, and so on
until all tasks are assigned.
6. Evaluate the efficiency of the balance derived using the formula
Facility Location and Layout 89
SOLUTION
1. Draw a precedence diagram as follows:
2. Determine workstation cycle time. Here we have to convert production time to seconds
because our task times are in seconds
Production time per day
C =
Required output per day (in units)
420 min × 60 sec 25200
= = = 50.4 secs
500 cars 500
90 Operations Management
3. Determine the theoretical minimum number of workstations required (the actual number
may be greater)
T 195 seconds
Nt = = = 3.87 = 4 (rounded up)
C 50.4 seconds
4. Select assignment rules.
(a) Prioritize tasks in order of the largest number of following tasks:
Task Number of following tasks
A 6
B or D 5
C or E 4
F, G, H, or I 2
J 1
K 0
Our secondary rule, to be invoked where ties exist from our primary rule, is (b) Prioritize
tasks in order of longest task time. Note that D should be assigned before B, and E
assigned before C due to this tie-breaking rule.
5. Make task assignments to form workstation 1, workstation 2, and so forth until all tasks
are assigned. It is important to meet precedence and cycle time requirements as the
assignments are made.
Station Task Task time Remaining Feasible Task with Task with
(in sec) unassigned remaining most longest ope-
time (in sec) tasks followers ration time
Station 1 A 45 5.4 Idle None
Station 2 D 50 0.4 Idle None
Station 3 B 11 39.4 C, E C, E E
E 15 24.4 C, H, I C
C 9 15.4 F, G, H, I F, G, H, I F, G, H, I
F 12 3.4 idle None
Station 4 G 12 38.4 H, I H, I H, I
H 12 26.4 I
I 12 14.4 J
J 8 6.4 idle None
Station 5 K 9 41.4 idle None
T 195
Efficiency = = = .77 or 77%
N a C 5 ´ 50.4
7. Evaluate the solution. An efficiency of 77 per cent indicates an imbalance or idle time
of 23 per cent (1.0 – .77) across the entire line.
In addition to balancing a line for a given cycle time, managers must also consider four other
options: pacing, behavioural factors, number of models produced, and cycle times.
Pacing is the movement of product from one station to the next after the cycle time has
elapsed. Paced lines have no buffer inventory. Unpaced lines require inventory storage areas to
be placed between stations.
BEHAVIOURAL FACTORS
The most controversial aspect of product layout is behavioural response. Studies have shown that
paced production and high specialization lower job satisfaction. One study has shown that
productivity increased on unpaced lines. Many companies are exploring job enlargement and
rotation to increase job variety and reduce excessive specialization. For example, New York Life
has redesigned the jobs of workers who process and evaluate claims applications. Instead of
using a production line approach with several workers doing specialized tasks, New York Life
has made each worker solely responsible for an entire application. This approach increased
worker responsibility and raised morale. In manufacturing, at its plant in Kohda, Japan, Sony
Corporation dismantled the conveyor belts on which as many as 50 people assembled camcorders.
It set up tables for workers to assemble an entire camera themselves, doing everything from
soldering to testing. Output per worker is up 10 per cent, because the approach frees efficient
assemblers to make more products instead of limiting them to conveyor belt’s speed. And if
something goes wrong, only a small section of the plant is affected. This approach also allows the
line to match actual demand better and avoid frequent shutdown because of inventory buildups.
NUMBER OF MODELS PRODUCED
A mixed-model line produces several items belonging to the same family. A single-model line
produces one model with no variations. Mixed model production enables a plant to achieve both
high-volume production and product variety. However, it complicates scheduling and increases
the need for good communication about the specific parts to be produced at each station.
CYCLE TIMES
A line’s cycle time depends on the desired output rate (or sometimes on the maximum number
of workstations allowed). In turn, the maximum line efficiency varies considerably with the cycle
time selected. Thus, exploring a range of cycle times makes sense. A manager might go with
a particularly efficient solution even if it does not match the output rate. The manager can
compensate for the mismatch by varying the number of hours the line operates through overtime,
extending shifts, or adding shifts. Multiple lines might even be the answer.
For process layouts, the relative arrangement of departments and machines is the critical
factor because of the large amount of transportation and handling involved.
PROCEDURE FOR DESIGNING PROCESS LAYOUTS
Process layout design determines the best relative locations of functional work centres. Work
centres that interact frequently, with movement of material or people, should be located close
together, whereas those that have little interaction can be spatially separated. One approach of
designing an efficient functional layout is described below.
1. List and describe each functional work centre.
2. Obtain a drawing and description of the facility being designed.
3. Identify and estimate the amount of material and personnel flow among work centres
4. Use structured analytical methods to obtain a good general layout.
5. Evaluate and modify the layout, incorporating details such as machine orientation, storage
area location, and equipment access.
The first step in the layout process is to identify and describe each work centre. The
description should include the primary function of the work centre; drilling, new accounts, or
cashier; its major components, including equipment and number of personnel; and the space
required. The description should also include any special access needs (such as access to running
water or an elevator) or restrictions (it must be in a clean area or away from heat).
For a new facility, the spatial configuration of the work centres and the size and shape of
the facility are determined simultaneously. Determining the locations of special structures and
fixtures such as elevators, loading docks, and bathrooms becomes part of the layout process.
However, in many cases the facility and its characteristics are given. In these situations, it is
necessary to obtain a drawing of the facility being designed, including shape and dimensions,
locations of fixed structures, and restrictions on activities, such as weight limits on certain parts
of a floor or foundation.
To estimate the flows between work centres, it is helpful to begin by drawing relationship diagram
as shown in Fig. 4.11.
For manufacturing systems, material flows and transporting costs can be estimated reasonably
well using historical routings for products or through work sampling techniques applied to workers
or jobs. The flow of people, especially in a service system such as a business office or a
university administration building, may be difficult to estimate precisely, although work sampling
can be used to obtain rough estimates.
The amounts and/or costs of flows among work centres are usually presented using a flow
matrix, a flow-cost matrix, or a proximity chart.
1. Flow Matrix
A flow matrix is a matrix of the estimated amounts of flow between each pair of work
centres. The flow may be materials (expressed as the number of loads transported) or people
who move between centres. Each work centre corresponds to one row and one column, and the
element fij designates the amount of flow from work centre (row) I to work centre (column) j.
Normally, the direction of flow between work centres is not important, only the total amount, so
fij and fji can be combined and the flows represented using only the upper right half of a matrix.
Work centre
A B C D E F G H I
A - 25 32 0 80 0 30 5 15
B - - 20 10 30 75 0 7 10 Daily flows
C - - - 0 10 50 45 60 0 between
D - - - - 35 0 25 90 120 work
E - - - - - 20 80 0 70 centres
F - - - - - - 0 150 20
G - - - - - - - 50 45
H - - - - - - - - 80
I - - - - - - - - -
2. Flow-cost Matrix
A basic assumption of facility layout is that the cost of moving materials or people between
work centers is a function of distance travelled. Although more complicated cost functions can
be accommodated, often we assume that the per unit cost of material and personnel flows between
work centres is proportional to the distance between the centres. So for each type of flow
between each pair of departments, i and j, we estimate the cost per unit per unit distance, cij.
94 Operations Management
Work centre
A B C D E F G H I
A - 25 32 0 80 0 30 5 15
B - - 40 10 90 75 0 7 10 Daily cost
C - - - 0 10 50 45 60 0 for flows
D - - - - 35 0 50 90 240 between
E - - - - - 20 80 0 70 work centres
F - - - - - - 0 150 20 (Rs. per day
G - - - - - - - 150 45 per 100 ft)
H - - - - - - - - 80
I - - - - - - - - -
3. Proximity Chart
Proximity charts (relationship charts) are distinguished from flow and flow-cost matrices by
the fact that they describe qualitatively the desirability or need for work centres to be close
together, rather than providing quantitative measures of flow and cost. These charts are used
when it is difficult to measure or estimate precise amounts or costs of flow among work centres.
This is common when the primary flows involve people and do not have a direct cost but rather
an indirect cost, such as when employees in a corporate headquarters move among departments
(payroll, printing, information systems) to carry out their work.
or even the company’s secrets. It has to serve as a part of the production facilities and as a
factor to maximise economy and efficiency in plant operations. It should offer a pleasant and
comfortable working environment and project the management’s image and prestige. Factory
building is like skin and bones of a living body for an organisation. It is for these reasons that
the factory building acquires great importance.
Following factors are considered for an Industrial Building:
A. Design of the building.
B. Types of buildings.
A. Design of the Building
The building should designed so as to provide a number of facilities—such as lunch rooms,
cafeteria, locker rooms, crèches, libraries, first-aid and ambulance rooms, materials handling
facilities, heating, ventilation, air-conditioning, etc. Following factors are considerations in the
designing of a factory building:
1. Flexibility: Flexibility is one of the important considerations because the building is likely
to become obsolete and provides greater operating efficiency even when processes and technology
change. Flexibility is necessary because it is not always feasible and economical to build a new
plant, every time a new firm is organised or the layout is changed. With minor alternations, the
building should be able to accommodate different types of operations.
2. Product and equipment: The type of product that is to be manufactured, determines
column-spacing, type of floor, ceiling, heating and air-conditioning. A product of a temporary
nature may call for a less expensive building and that would be a product of a more permanent
nature. Similarly, a heavy product demands a far more different building than a product which
is light in weight.
3. Expansibility: Growth and expansion are natural to any manufacturing enterprises. They
are the indicators of the prosperity of a business. The following factors should be borne in mind
if the future expansion of the concern is to be provided for:
(i) The area of the land which is to be acquired should be large enough to provide for the
future expansion needs of the firm and accommodate current needs.
(ii) The design of the building should be in a rectangular shape. Rectangular shapes
facilitate expansion on any side.
(iii) If vertical expansion is expected, strong foundations, supporters and columns must be
provided.
(iv) If horizontal expansion is expected, the side walls must be made non-load-bearing to
provide for easy removal.
4. Employee facilities and service area: Employee facilities must find a proper place in
the building design because they profoundly affect the morale, comfort and productivity. The
building plan should include facilities for lunch rooms, cafeteria, water coolers, parking area and
the like. The provision of some of these facilities is a legal requirement. Others make good
working conditions possible. And a good working condition is good business.
Facility Location and Layout 97
Service areas, such as the tool room, the supervisor’s office, the maintenance room, receiving
and dispatching stations, the stock room and facilities for scrap disposal, should also be included
in the building design.
B. Types of Buildings
Industrial buildings may be grouped under two types:
1. Single-storey buildings,
2. Multi-storey buildings.
The decision on choosing a suitable type for a particular firm depends on the manufacturing
process and the area of land and the cost of construction.
1. SINGLE-STOREY BUILDINGS
Most of the industrial buildings manufacturing which are now designed and constructed are single
storeyed, particularly where lands are available at reasonable rates. Single-storey buildings offer
several operating advantages. A single-storey construction is preferable when materials handling
is difficult because the product is big or heavy, natural lighting is desired, heavy floor loads are
required and frequent changes in layout are anticipated.
Advantages
Advantages of single-storey building are:
1. There is a greater flexibility in layout and production routing.
2. The maintenance cost resulting from the vibration of machinery is reduced considerably
because of the housing of the machinery on the ground.
3. Expansion is easily ensured by the removal of walls.
4. The cost of transportation of materials is reduced because of the absence of materials
handling equipment between floors.
5. All the equipment is on the same level, making for an easier and more effective layout
supervision and control.
6. Greater floor load-bearing capacity for heavy equipment is ensured.
7. The danger of fire hazards is reduced because of the lateral spread of the building.
Limitations
Single-storey buildings suffer from some limitations. These are:
1. High cost of land, particularly in the city.
2. High cost of heating, ventilating and cleaning of windows.
3. High cost of transportation for moving men and materials to the factory which is generally
located far from the city.
2. MULTI-STOREY BUILDINGS
Schools, colleges, shopping complexes, and residences, and for service industries like Software,
BPO etc. multi-storey structures are generally popular, particularly in cities. Multi-storey buildings
are useful in manufacture of light products, when the acquisition of land becomes difficult and
expensive and when the floor load is less.
98 Operations Management
Advantages
When constructed for industrial use, multi-storey buildings offer the following advantages:
1. Maximum operating floor space (per sq. ft. of land). This is best suited in areas where
land is very costly.
2. Lower cost of heating and ventilation.
3. Reduced cost of materials handling because the advantage of the use of gravity for the
flow of materials.
Limitations
Following are the disadvantages of multi-storey building:
1. Materials handling becomes very complicated. A lot of time is wasted in moving them
between floors.
2. A lot of floor space is wasted on elevators, stairways and fire escapes.
3. Floor load-bearing capacity is limited, unless special construction is used, which is very
expensive.
4. Natural lighting is poor in the centres of the shop, particularly when the width of the
building is somewhat great.
5. Layout changes cannot be effected easily and quickly.
Generally speaking, textile mills, food industries, detergent plants, chemical industries and
software industry use these types of buildings.
II. LIGHTING
It is estimated that 80 per cent of the information required in doing job is perceived visually. Good
visibility of the equipment, the product and the data involved in the work process is an essential
factor in accelerating production, reducing the number of defective products, cutting down waste
and preventing visual fatigue and headaches among the workers. It may also be added that both
inadequate visibility and glare are frequently causes accidents.
In principle, lighting should be adapted to the type of work. However, the level of illumination,
measured in should be increased not only in relation to the degree of precision or miniaturization
of the work but also in relation to the worker’s age. The accumulation of dust and the wear of
the light sources cut down the level of illumination by 10–50 per cent of the original level. This
gradual drop in the level should therefore be compensated for when designing the lighting system.
Regular cleaning of lighting fixture is obviously essential.
Excessive contrasts in lighting levels between the worker’s task and the general surroundings
should also be avoided. The use of natural light should be encouraged. This can be achieved by
installing windows that open, which are recommended to have an area equal to the time of day,
the distance of workstations from the windows and the presence or absence of blinds. For this
reason it is essential to have artificial lighting, will enable people to maintain proper vision and
will ensure that the lighting intensity ratios between the task, the surrounding objects and the
general environment are maintained.
Facility Location and Layout 99
CONTROL OF LIGHTING
In order to make the best use of lighting in the work place, the following points should be taken
into account:
1. For uniform light distribution, install an independent switch for the row of lighting fixtures
closest to the windows. This allows the lights to be switched on and off depending on
whether or not natural light is sufficient.
2. To prevent glare, avoid using highly shiny, glossy work surfaces.
3. Use localized lighting in order to achieve the desired level for a particular fine job.
4. Clean light fixtures regularly and follow a maintenance schedule so as to prevent flickering
of old bulbs and electrical hazards due to worn out cables.
5. Avoid direct eye contact with the light sources. This is usually achieved by positioning
them properly. The use of diffusers is also quite effective.
III. CLIMATIC CONDITIONS
Control of the climatic conditions at the workplace is paramount importance to the workers health
and comfort and to the maintenance of higher productivity. With excess heat or cold, workers
may feel very uncomfortable, and their efficiency drops. In addition, this can lead to accidents.
This human body functions in such a way as to keep the central nervous system and the
internal organs at a constant temperature. It maintains the necessary thermal balance by continuous
heat exchange with the environment. It is essential to avoid excessive heat or cold, and wherever
possible to keep the climatic conditions optimal so that the body can maintain a thermal balance.
WORKING IN A HOT ENVIRONMENT
Hot working environments are found almost everywhere. Work premise in tropical countries may,
on account of general climatic conditions, be naturally hot. When source of heat such as furnaces,
kilns or hot processes are present, or when the physical workload is heavy, the human body may
also have to deal with excess heat. It should be noted that in such hot working environments
sweating is almost the only way in which the body can lose heat. As the sweat evaporates, the
body cools. There is a relationship between the amount and speed of evaporation and a feeling
of comfort. The more intense the evaporation, the quicker the body will cool and feel refreshed.
Evaporation increases with adequate ventilation.
WORKING IN A COLD ENVIRONMENT
Working in cold environments was once restricted to non-tropical or highly elevated regions. Now
as a result of modern refrigeration, various groups of workers, even in tropical countries, are
exposed to a cold environment.
Exposure to cold for short periods of time can produce serious effects, especially when
workers are exposed to temperatures below 10°C. The loss of body heat is uncomfortable and
quickly affects work efficiency. Workers in cold climates and refrigerated premises should be
well protected against the cold by wearing suitable clothes, including footwear, gloves and, most
importantly, a hat. Normally, dressing in layers traps dead air and serves as an insulation layer,
thus keeping the worker warmer.
100 Operations Management
Except for confined spaces, all working premises have some minimum ventilation. However,
to ensure the necessary air flow (which should not be lower than 50 cubic metres of air per hour
per worker), air usually needs to be changed between four to eight times per hour in offices or
for sedentary workers, between eight and 12 times per hour in workshops and as much as 15
to 30 or more times per hour for public premises and where there are high levels of atmospheric
pollution or humidity. The air speed used for workplace ventilation should be adapted to the air
temperature and the energy expenditure: for sedentary work it should exceed 0.2 metre per
second, but for a hot environment the optimum speed is between 0.5 and 1 metre per second.
For hazardous work it may be even higher. Certain types of hot work can be made tolerable by
directing a stream of cold air at the workers.
Natural ventilation, obtained by opening windows or wall or roof airvents, may produce
significant air flows but can normally be used only in relatively mild climates. The effectiveness
of this type of ventilation depends largely on external conditions. Where natural ventilation is
inadequate, artificial ventilation should be used. A choice may be made between a blown-air
system, an exhaust air system or a combination of both (‘push-pull’ ventilation). Only ‘push-pull’
ventilation systems allow for better regulation of air movement.
V. WORK-RELATED WELFARE FACILITIES
Work-related welfare facilities offered at or through the workplace can be important factors.
Some facilities are very basic, but often ignored, such as drinking-water and toilets. Others may
seem less necessary, but usually have an importance to workers far greater than their cost to
the enterprise.
1. DRINKING WATER
Safe, cool drinking water is essential for all types of work, especially in a hot environment.
Without it fatigue increases rapidly and productivity falls. Adequate drinking water should be
provided and maintained at convenient points, and clearly marked as “Safe drinking water”.
Where possible it should be kept in suitable vessels, renewed at least daily, and all practical steps
taken to preserve the water and the vessels from contamination.
2. SANITARY FACILITIES
Hygienic sanitary facilities should exist in all workplaces. They are particularly important where
chemicals or other dangerous substances are used. Sufficient toilet facilities, with separate
facilities for men and women workers, should be installed and conveniently located. Changing-
rooms and cloakrooms should be provided. Washing facilities, such as washbasins with soap and
towels, or showers, should be placed either within changing-rooms or close by.
3. FIRST-AID AND MEDICAL FACILITIES
Facilities for rendering first-aid and medical care at the workplace in case of accidents or
unforeseen sickness are directly related to the health and safety of the workers. First-aid boxes
should be clearly marked and conveniently located. They should contain only first-aid requisites
of a prescribed standard and should be in the charge of qualified person. Apart from first-aid
boxes, it is also desirable to have a stretcher and suitable means to transport injured persons to
a centre where medical care can be provided.
102 Operations Management
4. REST FACILITIES
Rest facilities can include seat, rest-rooms, waiting rooms and shelters. They help workers to
recover from fatigue and to get away from a noisy, polluted or isolated workstation. A sufficient
number of suitable chairs or benches with backrests should be provided and maintained, including
seats for occasional rest of workers who are obliged to work standing up. Rest-rooms enable
workers to recover during meal and rest breaks.
5. FEEDING FACILITIES
It is now well recognized that the health and work capacity of workers to have light refreshments
are needed. A full meal at the workplace in necessary when the workers live some distance away
and when the hours of work are so organized that the meal breaks are short. A snack bar, buffet
or mobile trolleys can provide tea, coffee and soft drinks, as well as light refreshments. Canteens
or a restaurant can allow workers to purchase a cheap, well-cooked and nutritious meal for a
reasonable price and eat in a clean, comfortable place, away from the workstation.
6. CHILD-CARE FACILITIES
Many employers find that working mothers are especially loyal and effective workers, but they
often face the special problems of carrying for children. It is for this reason that child-care
facilities, including crèches and day-care centres, should be provided. These should be in secure,
airy, clean and well lit premises. Children should be looked after properly by qualified staff and
offered food, drink education and play at very low cost.
7. RECREATIONAL FACILITIES
Recreational facilities offer workers the opportunity to spend their leisure time in activities likely
to increase physical and mental well-being. They may also help to improve social relations within
the enterprise. Such facilities can include halls for recreation and for indoor and outdoor sports,
reading-rooms and libraries, clubs for hobbies, picnics and cinemas. Special educational and
vocational training courses can also be organized.
EXERCISE
Section A
1. What do you mean by plant location?
2. What is virtual proximity?
3. What is virtual factory?
4. What is agglomeration?
5. What is degglomeration?
6. What is plant layout?
7. Mention any four objectives of plant layout.
Section B
1. Explain different operations strategies in case of location choice for existing organisation.
2. Explain the factors to be considered while selecting the location for the new organisation.
Facility Location and Layout 103
CHAPTER OUTLINE
5.1 Introduction 5.6 Regression and Correlation Methods
5.2 Forecasting Objectives and Uses 5.7 Applications and Control of Forecast
5.3 Forecasting Decision Variables • Exercise
5.4 Forecasting Methods • References
5.5 Exponential Smoothing
5.1 INTRODUCTION
Forecasts are essential for the smooth operations of business organizations. They provide information
that can assist managers in guiding future activities toward organizational goals.
Field sales and product-line management Estimates from regional sales people are reconciled MR M
with national projections from product-line managers
Historical analogy Forecast from comparison with similar product SR-LR L-M
previously introduced
Delphi Experts answer a series of questions (anonymously), LR M-H
receive feedback, and revise estimates
Market surveys Questionnaires/interviews for data to learn about MR-LR H
consumer behaviour
Time series (quantitative)
Naive Forecast equals latest value or latest plus or minus SR L
some percentage
Moving average Forecast is average of n most recent periods SR L
(can also be weighted)
Trend projection Forecast is linear, exponential, or other projection MR-LR L
of past trend
Decomposition Time series is divided into trend, seasonal, cyclical, SR-LR L
and random components
Exponential smoothing Forecast is an exponentially weighted moving average, SR L
where latest values carry most weight
Box-Jenkins A time-series-regression model is proposed, statistically MR-LR M-H
tested, modified, and retested until satisfactory
Associative (quantitative)
Regression and correlation Use one or more associate variables to forecast via SR-MR M-H
(and leading indicators) a least-squares equation (regression) or via a close
association (correlation) with an explanatory variable
Econometric Use simultaneous solution of multiple regression SR-LR H
equations that relate to broad range of economic activity
Time series (quantitative)
Naive Forecast equals latest value or latest plus or SR L
minus some percentage
Moving average Forecast is average of n most recent periods SR L
(can also be weighted)
Trend projection Forecast is linear, exponential, or other projection of MR-LR L
past trend
Decomposition Time series is divided into trend, seasonal, cyclical, SR-LR L
and random components
Exponential smoothing Forecast is an exponentially weighted moving SR L
average, where latest values carry most weight
Box-Jenkins A time-series-regression model is proposed, MR-LR M-H
statistically tested, modified, and retested until
satisfactory
Associative (quantitative)
Regression and correlation Use one or more associate variables to forecast via SR-MR M-H
(and leading indicators) a least-squares equation (regression) or via a close
association (correlation) with an explanatory variable
Econometric Use simultaneous solution of multiple regression SR-LR H
equations that relate to broad range of economic
activity
Key: L = low, M = medium, H = high, SR = short range, MR = medium range, LR = long range.
108 Operations Management
∑x
MA = Number of Period
A weighted moving average (MAw) allows some values to be emphasized by varying the weights
assigned to each component of the average. Weights can be either percentages or a real number.
∑ (Wt ) X
MA wt =
∑Wt
I LLUSTRATION 1: Shipments (in tons) of welded tube by an aluminum producer are shown
below:
Year 1 2 3 4 5 6 7 8 9 10 11
Tons 2 3 6 10 8 7 12 14 14 18 19
(a) Graph the data, and comment on the relationship. (b) Compute a 3-year moving average,
plot it as a dotted line, and use it to forecast shipments in year 12. (c) Using a weight of 3 for the
most recent data, 2 for the next, and 1 for the oldest, forecast shipments in year 12.
Forecasting Demand 109
Demand
20
18 19
18
16
14
13 14
12 14
10 10
Tons
8 8
7
6 6
4
3
2 2
0
1 2 3 4 5 6 7 8 9 10 11
Years
(a) The data points appear relatively linear. (b) See Table 5.1 for computations and Fig. 5.2 for plot
of the MA. The MA forecast for year 12 would be that of the latest average, 17.0 tons.
(c) MA wt =
∑ (Wt ) X =
(1) (14) + (2) (18) + (3) (19)
= 17.8 tons
∑Wt 1+ 2 + 3
2. HAND FITTING
A hand fit or freehand curve is simply a plot of a representative line that (subjectively) seems to best
fit the data points. For linear data, the forecasting equation will be of the form:
Yc = a + b (X) (signature)
where Yc is the trend value, a is the intercept (where line crosses the vertical axis), b is the slope
(the rise, ∆ y, divided by the run, ∆ x), and X is the time value (years, quarters, etc.). The “signature”
identifies the point in time when X = 0, as well as the X and Y units.
110 Operations Management
I LLUSTRATION 2: (a) Use a hand fit line to “develop a forecasting equation for the data
in Fig. 5.2. State the equation, complete with signature. (b) Use your equation to forecast tube
shipments for year 12.
(a) Select points some distance apart. A straight line connecting the values for years 3 and 8
might be a good
Free hand representation of the data. From this we can determine the slope and intercept:
∆Y Y −Y 14 − 6
Slope : b = = 2 1 = = 1.6 tons
∆X X 2 − X 1 8 − 3
Intercept: a = 0.5 tons (Note: This is the estimated Y value at X = 0 from graph.)
Equation: YC = 0.5 + 1.6X (Yr 0 = 0, X = yrs, Y = tons)
(b) For year 12: Yc =0.5 + 1.6(12) = 19.7 tons.
3. LEAST SQUARES
Least squares are a mathematical technique of fitting a trend to data points. The resulting line of
best fit has the following properties: (1) the summation of all vertical deviations about it is zero,
(2) the summation of all vertical deviations squared is a minimum, and (3) the line goes through the
means X and Y. For linear equations, the line of best fit is found by the simultaneous solution for a
and b of the following two normal equations:
∑Y = na + b∑ X
∑ XY = a ∑ X + b∑ X
2
The above equations can be used in the form shown above and are used in that form for
regression. However, with time series, the data can also be coded so that ∑ X = 0 . Two terms
then dropout, and the equations are simplified to:
∑Y = na a=
∑Y
n
∑ XY = b∑ X 2 b=
∑ XY .
∑X 2
To code the time series data, designate the center of the time span as X = 0 and let each
successive period be ±1 more unit away. (For an even number of periods, use values of ±0.5, 1.5,
2.5, etc.).
I LLUSTRATION 3: Use the least square method to develop a linear trend equation for the
data from illustration 1. State the equation and forecast a trend value for year 16.
Forecasting Demand 111
Table 5.2
we have:
a =
∑ Y = 113 = 10.30 b=
∑ XY =
181
= 1.6
n 11 ∑X 2
110
The forecasting equation is of the form Y = a + bX.
Y = 10.3 + 1.6 X (year 6 = 0, X = years, Y = tons).
Seasonal indexes: A seasonal index (SI) is a ratio that relates a recurring seasonal
variation to the corresponding trend value at the given time. In the ratio-to-moving average
method of calculation monthly (or quarterly) data are typically used to compute a 12-month (or
4-quarter) moving average.
(This dampens out all seasonal fluctuations.) Actual monthly (or quarterly) values are then
divided by the moving average value centered on the actual month. In the ratio-to-trend
method, the actual values are divided by the trend value centered on the actual month. The
ratios obtained for several of the same months (or quarters) are then averaged to obtain the
seasonal index values. The indexes can be used to obtain seasonalized forecast values, Ysz (or
to deseasonalize actual data). Ysz = (SI) Yc.
I LLUSTRATION 4: Snowsport International has experienced low snowboard sales in July,
as shown in Table 5.3. Using the ratio-to-trend values, calculate a seasonal index value for
July and explain its meaning.
112 Operations Management
Table 5.3
Yr 5 Yr 6 Yr 7 Yr 8 Yr 9 Yr 10 Yr 11 Yr l2
July actual sales 22 30 18 26 45 36 40
July trend value, Yc 170 190 210 230 250 270 290
Ratio (actual ÷ trend) 0.13 0.16 0.09 0.11 0.18 0.13 0.14
Total = 0.94.
(a) A third row has been added to Table 5.3 to show the ratio of actual to trend values for
July. Using a simple average, the July index is SIJuly = 0.94 ÷ 7 = 0.13. This means that July
is typically only 13 per cent of the trend value for July in any given year. Winter months are
likely quite high.
I LLUSTRATION 5: The forecasting equation for the previous example, centered in July of
year 4 with X units in months, was Yc = 1800 + 20X (July 15, Yr 4 = 0, X = mo, Y = units/yr).
* Use this equation and the July seasonal index of 0.13 to compute (a) the trend (deseasonalized)
value for July of year 12 and (b) the forecast of actual (seasonalized) snowboard sales in July
of year 12.
(a) July of year 12 is (8)(12) = 96 months away from July of year 4, so the/trend value is:
Yc = 1800 + 20(96) = 3,240 units/yr or 3,240 units/yr 12 mo/yr = 310 units/mo
(b) The actual (seasonalized) forecast is Ysz = (SI) Yc = (0.13)(310) = 40 units.
Table 5.4
Week Actual demand Old forecast Forecast error Correction New forecast
At – 1 Ft – 1 At – 1 – Ft – 1 α t–1 t–1
(A – F ) (F t
)F t–1
+ (At – 1– Ft –1)
Feb. 1 450 500 – 50 –5 495
8 505 495 10 1 496
15 516 496 20 2 498
22 488 498 – 10 –1 497
Mar. 1 467 497 – 30 –3 494
8 554 494 60 6 500
15 510 500 10 1 501
The smoothing constant, α, is a number between 0 and 1 that enters multiplicatively into each
forecast but whose influence declines exponentially as the data become older. Typical values range
from 0.01 to 0.40. An Ion α gives more weight to the past average and will effectively dampen high
random variation. High α values are more responsive to changes in demand (e.g., from new-product
introductions, promotional campaigns). An α of 1 would reflect total adjustment to recent demand,
and the forecast would be last period’s actual demand. A satisfactory α can generally be determined
by trial-and-error modeling (on computer) to see which value minimizes forecast error.
Simple exponential smoothing yields only an average. It does not extrapolate for trend effects.
No α value will fully compensate for a trend in the data. An α value that yields an approximately
equivalent degree of smoothing as a moving average of n periods is:
2
α =
n +1
(
Fˆt = α At −1 + (1 − α) Fˆt −1 + Tt −1 )
Tt = β( Fˆt − Fˆt −1 ) + (1 − β)Tt −1
A low β gives more smoothing of the trend and may be useful if the trend is not well-established.
A high β will emphasize the latest trend and be more responsive to recent changes in trend. The
initial trend adjustment Tt–1 is sometimes assumed to be zero.
114 Operations Management
5.6.1 Regression
The simple linear regression model takes the form Yc = a + bX, where Yc is the dependent variable
and X the independent variable. Values for the slope b and intercept α are obtained by using the
normal equations written in the convenient form:
∑ XY − nXY
b = (1)
∑ X 2 − nX 2
a = Y − bX (2)
In Equations. (1) and (2), X = (∑ X ) / n and Y = ( ∑ Y ) / n Y are the means of the independent
and dependent variables respectively, and n is the number of pairs of observations made.
Forecasting Demand 115
SOLUTION: (a)
Table 5.6
X Y XY X2 Y2
15 6 90 225 36
9 4 36 81 16
40 16 640 1,600 256
20 6 120 400 36
25 13 325 625 169
25 9 225 625 81
15 10 150 225 100
35 16 560 1,225 256
184 80 2,146 5,006 950
n = 8 pairs of observations X = (∑ X ) / n or X=
184
8
= 23
Y = (∑ Y / n) or Y=
80
8
= 10
∑ XY − nXY b=
2146 − 8(23)(10)
= 0.395
b = or
∑ X 2 − nX 2 5006 − 8(23)(23)
116 Operations Management
a = Y − bX or a = 10 − 0.395(23) = 0.91
(b) The regression equation is
Yc = 0.91 + 0.395 X (X = permits, Y = shipments)
Then, letting X = 30,
Yc = 0.91 + 0.395(30) = 12.76 ~ 13 shipments.
STANDARD DEVIATION OF REGRESSION
A regression line describes the relationship between a given value of the independent variable X and
µy – x the mean of the corresponding probability distribution of the dependent variable Y. We assume
the distribution of Y values is normal for any given X value. The point estimate, or forecast, is the
mean of that distribution for any given value of X.
The standard deviation of regression S y – x is a measure of the dispersion of data points around
the regression line. For simple regression, the computation of S y – x has n – 2 degrees of freedom.
S y− x = ∑ Y 2 − a ∑ Y − b∑ XY .
n−2
I LLUSTRATION 8: Using the data from illustration 7, compute the Standard Deviation of
Regression.
SOLUTION
S y− x = ∑ Y 2 − a ∑ Y − b ∑ XY
n−2
950 − (0.91)(80) − (0.396)(2146)
S y− x = = 2.2 shipments.
8−2
I LLUSTRATION 9: Using the data from illustrations 7 and 8,develop a 95 per cent prediction
interval estimate for the specific number of shipments to be made when 30 construction permits
were issued during the previous quarter.
Note: X = 23 for the n = 8 observations, and ∑ (X – X)2 = 774. Also, from Illustration 7,
Yc = 13 shipments, where X = 30; and from Illustration 8, Sy – x = 2.2 shipments.
SOLUTION
Prediction interval = Yc ± tSind (3)
where the t-value for n – 2 = 8 – 2 = 6 degrees of freedom = 2.45 and where
1 ( X − X )2
S ind S
= y− x 1 + +
n ∑ ( X − X )2
1 (30 − 23) 2
S ind = 2.2 1 + + = 2.4 shipments
8 774
∴ Production interval = 13 ± 2.45 (2.4) = 7.1 to 18.90 (use 7 to 19 shipments).
Forecasting Demand 117
For large samples (n ≥ 100), Equation 3 can be approximated by using the normal (Z) distribution
rather than the t, in the form of Yc ± ZSy–x (Note: For 95 per cent confidence, the Z value is the
same as t with ∞ df, which from Table 5.7 (given below) equals 1.96.) Also, the significance of the
regression line slope coefficient (b) can be tested using the expression:
b
tcalc = S
b
1
Sb = S y − x
where
∑ ( X − X )2
If the value of tcalc > tdf from the t-table, the relationship between the X and Y variables is
statistically significant.
Table 5.7 t-Distribution values (for 90 per cent and 95 per cent confidence)
df 5 6 7 8 9 10 12 15 20 30 00
t05 (90%) 2.02 1.94 1.90 1.86 1.83 1.81 1.78 1.75 1.73 1.70 1.65
t10 (95%) 2.57 2.45 2.37 2.31 2.26 2.23 2.17 2.13 2.08 2.04 1.96
5.6.2 Correlation
The simple linear correlation coefficient r is a number between –1 and + 1 that tells how well a
linear equation describes the relationship between two variables. As illustrated in Fig. 5.2 r is designated
as positive if Y increases as X increases, and negative if Y decreases as X increases. An r of zero
indicates an absence of any relationship between the two variables.
r2 =
∑ (YC − Y )2
∑ (Y − Y )2
The coefficient of correlation r is the square root of the coefficient of determination:
r =
∑ (YC − Y )2
∑ (Y − Y )2
When the sample size is sufficiently large (e.g., greater than 50), the value of r can be computed
more directly form:
n∑ XY − ∑ X .∑ Y
r =
( )
n∑ X 2 − ( ∑ X ) 2 n∑ Y 2 − (∑ Y ) 2
I LLUSTRATION 10: A study to determine the correlation between plasterboard shipments
X and construction permits Y revealed the following:
∑ X = 184 ∑Y = 80’ n=8
∑ X = 5,006 ∑Y = 950
2 2
∑ XY = 2,146
Compute the correlation coefficient.
n∑ XY − ∑ X .∑ Y
r =
( n∑ X )
− ( ∑ X ) 2 n∑ Y 2 − (∑ Y ) 2
2
The significance of any value of r can be statistically tested under a hypothesis of no correlation.
Forecasting Demand 119
To test, the computed value of r is compared with a tabled value of r for a given sample size and
significance level. If the computed value exceeds the tabled value, the correlation is significant.
MAD =
∑ Error
n
The estimate of the MAD can be continually updated by using an exponential smoothing technique.
Thus the current MADt is:
MADt = ∝ (actual – forecast) + (1 – ∝) MADt–1
where ∝ is a smoothing constant. Higher values of α will make the current MAD, more responsive
to current forecast errors.
When the average deviation (MAD) is divided into the cumulative deviation
[ ∑ (Actual − forecast) ], the result is a tracking signal:
Tracking signal =
∑ (Actual − forecast)
MAD
Tracking signals are one way of monitoring how well a forecast is predicting actual values.
They express the cumulative deviation (also called the running sum of forecast error, RSFE) in
terms of the number of average deviations (MADs). Action limits for tracking signals commonly
range from three to eight. When the signal goes beyond this range, corrective action may be required.
ILLUSTRATION 11: A high-valued item has a tracking-signal-action limit of 4 and has
been forecast as shown in Table 5.8. Compute the tracking signal, and indicate whether some
corrective action is appropriate.
Table 5.8
Error (Error)2
Period Actual Forecast |Error|
(A – F) (A– F)
1 80 78 2 2 A
2 92 79 13 13 169
3 71 83 –12 12 144
4 83 79 4 4 16
5 90 80 10 10 100
6 102 83 19 19 361
Totals 36 60 794
120 Operations Management
∑ Error =
60
= 10
MAD =
n 6
Tracking signal =
∑ (Actual − forecast) = 36 = 3.6
MAD 10
Action limit of 4 is not exceeded. Therefore, no action is necessary.
Control charts are a second way of monitoring forecast error. Variations of actual from forecast
(or average) values are quantified in terms of the estimated standard deviation of forecast SF .
SF =
∑ (Actual − Forecast )2
n −1
Control limits are then set, perhaps at two or three standard deviations away from the forecast
average X or the 2SF or 3SF limits are used as maximum acceptable limits for forecast error. Note
that the limits are based on individual forecast values, so you assume that the errors are normally
distributed around the forecast average.
I LLUSTRATION 12
(a) Compute the 2SF control limits for the data given in Illustration 11.
(b) Are all forecast errors within these limits?
(a) Control limits about the mean CL = X ± 2SF
Where
78 + 79 + 83 + 79 + 80 + 83
X = = 80
6
SF =
∑ (Actual − Forecast)2 =
794
= 196 = 14
n −1 6−2
Therefore, CL = 80 ± 2(14) = 52 to 108 (rounded to integer values).
(b) All forecast errors (as calculated in Illustration 5.11) are within the ::t:: 28 error limit.
Note: Since n is less than 30, this distribution of forecast errors does not wholly satisfy the normality
assumption.
FORECAST APPLICATION
Forecasts should be sufficiently accurate to plan for future activities. Low-accuracy methods may
suffice; higher accuracy usually costs more to design and implement. Long-term forecasts—used
for location, capacity, and new-product decisions-require techniques with long-term horizons.
Short-term forecasts— such as those for production-and-inventory control, labour levels, and cost
controls–can rely more on recent history.
I LLUSTRATION 13: A food processing company uses a moving average to forecast next
month’s demand. Past actual demand (in units) is as shown in Table 5.9.
Forecasting Demand 121
(a) Compute a simple 5-month moving average to forecast demand for month 52.
(b) Compute a weighted 3-month moving average, where the weights are highest for the
latest months and descend in order of 3, 2 and 1.
Table 5.9
SOLUTION
∑ ( wt ) X =
3 × 137 + 2 × 128 + 1 × 130 797
= = 133 units
MA wt =
(b)
∑Wt 6 6
I LLUSTRATION 14: For N = 7 years of (Coded) time series data, ∑ Y = 56, ∑ XY = 70,
and ∑X 2
= 28.
(a) Find the intercept and slope of the linear trend line.
(b) Forecast the Y-value for 6 years distant from the origin.
SOLUTION
Y 56 ∑ XY = 70 = 2.5
(a) Intercept = = = 8.0 Slope =
N 7 ∑ X 2 28
(b) Yc = a + b (X) = 8.0 + 2.5 (6) = 23.0.
I LLUSTRATION 15: The following forecasting equation has been derived by a least-squares
method to describe the shipments of welded aluminum tube.
Yc = 10.27 + 1.65X (1996 = O, X = years, Y = tons/yr)
122 Operations Management
Rewrite the equation by (a) shifting the origin to 2001; (b) expressing X units in months,
retaining Y in tons per year; (c) expressing X units in months, and Y in tons per month.
SOLUTION
(a) Yc = 10.27 + 1.65(X + 5)
= 18.52 + 1.65X (yr 2001 = 0, X = years, Y = tons per year)
1.65 X
(b) Yc = 10.27 +
12
= 10.27 + 0.14X (July 1, 1996 = 0, X = months, Y = tons per year)
10.27 + 0.14 X
(c) Yc =
12
= 0.86+0.01 X (July 1, 1996 = 0, X = months, Y = tons per month)
I LLUSTRATION 16: Quarterly trend values for units demanded have been computed as Ql
= 620, Q 2 = 655,Q3 = 690, and Q4 = 725. The corresponding seasonal indexes for the
quarters are 0.72, 1.33, 1.05, and 0.90, respectively. Forecast the actual (seasonalized) sales
for Q3 and Q4.
SOLUTION
For Q3: Ysz = (SI) Yc = (1.05)(690) =725 units
For Q4: Ysz = (SI) Yc = (0.90)(725)= 653 units.
I LLUSTRATION 17: A sportswear manufacturer wishes to use data from a 5-year period to
develop seasonal indexes. Trend values and ratios of actual A to trend T for most months have
already been computed as shown in Table 5.10. April and May actual and trend values are
shown in Tables 5.11 and 5.12.
Table 5.10
Month Jan. Feb. Mar. April May June July Aug. Sept. Oct. Nov. Dec.
Ratio AIT 0.72 0.58 0.85 1.43 1.21 1.05 0.98 0.92 0.88 1.12
Compute the seasonal relatives for April and May, correct the total to equal 12.00, and determine
the resulting seasonal indexes. See Tables 5.11 and 5.12.
Table 5.11 Table 5.12
Year 1 2 3 4 5 Year I 2 3 4 5
April actual 382 401 458 480 533 May actual 485 530 560 592 656
April trend 400 436 472 508 544 May trend 403 439 475 511 547
April A/T 0.96 0.92 0.97 0.94 0.98 May A/T 1.20 1.21 1.18 1.16 1.20
SOLUTION
April total = 4.77 May total = 5.95
April average = 4.77 ÷ 5 = 0.95 May average = 5.95 ÷ 5 = 1.19
Forecasting Demand 123
Month Jan. Feb. Mar. April May June July Aug. Sept. Oct. Nov. Dec. 12 month.
Ratio A/T 0.72 0.58 0.85 0.95 1.19 1.43 1.21 1.05 0.98 0.92 0.88 1.12 11.88
12
Correction factor = = 1.01
11.88
Multiplying each month’s ratio by the correction factors, we get
Month Jan. Feb. Mar. April May June July Aug. Sept. Oct. Nov. Dec. 12 month.
Ratio A/T 0.73 0.59 0.86 0.96 1.20 1.44 1.22 1.06 0.99 0.93 0.89 1.13 12.00
I LLUSTRATION 18: The production manager of the sportswear firm in the previous problem
has projected trend values for next summer (June, July, August) of 586, 589 and 592. Using
the seasonal indexes given (1.44, 1.22, 1.60), what actual seasonalized production should
the manager plan for?
SOLUTION
June: Ysz= SI Yc = (1.44)(586) = 844
July: Ysz = (1.22)(589) = 719
August: Ysz = (1.06)(592) = 628
I LLUSTRATION 19: Lakeside Hospital has used a 9-month, moving-average forecasting
method to predict drug and surgical dressing inventory requirements. The actual demand for
one item is as shown in Table 5.13 Using the previous moving-average data, convert to an
exponential smoothing forecast for month 33.
Table 5.13
Month 24 25 26 27 28 29 30 31 32
Demand 78 65 90 71 80 101 84 60 73
SOLUTION
∑X =
78 + 65 + …. + 73
= 78 units
MA =
Number of Period 9
Thus, assume the previous forecast was Ft–1 = 78.
2 2
Then estimate ∝ as α = = = 0.2
n + 2 9 +1
So, Ft = Ft–1+ ∝ (At–1 – Ft–1) = 78 + 0.2 (73 – 78) = 77 units.
I LLUSTRATION 20: A shoe manufacturer, using exponential smoothing with ∝ = 0.1, has
developed a January trend forecast of 400 units for a ladies’ shoe. This brand has seasonal
indexes of 0.80, 0.90, and 1.20, respectively, for the first 3 months of the year. Assuming that
124 Operations Management
actual sales were 344 units in January and 414 units in February, what would be the
seasonalized (adjusted) March forecast?
SOLUTION
(a) Deseasonalize actual January demand.
344
Demand = = 430 units
0.80
(b) Compute the deseasonalized forecast.
F t = Ft–1 + α ( A t–1
– Ft–1)
= 400 + 0.1 (430 – 400) = 403
(c) Seasonalized (adjusted) February forecast would be:
F t(sz) = 403 (0.90) = 363
Repeating for February, we have:
414
(a) Demand = = 460
0.90
(b) F t = 403 + 0.1(460 – 403) = 409
(c) F t(sz) = 409 (1.20) = 491
I LLUSTRATION 21: Develop an adjusted exponential forecast for the week of 5/14 for a
firm with the demand shown in Table 5.14. Let α = 0.1 and β = 0.2. Begin with a previous
average of Fˆt –1 = 650, and let the initial trend adjustment, Tt–1 = 0.
Table 5.14
SOLUTION
We have:
Week 3/19: F t = ∝At–1 + (1 – ∝) (Ft–1+ Tt–1)
= 0.1(700) + 0.9(650 + 0) = 655.00
T t = β (Ft – Ft–1) + (1 – β) Tt–1
F t+1 = Ft + Tt = 655 + 1 = 656.000
The 656.00 is the adjusted forecast for week 3/26.
Week 3/26: F t = 0.1(685) + 0.9(655 + 1.0) = 658.90
Forecasting Demand 125
EXERCISE
1. What are forecasts?
2. What are the costs associated with forecasting–or not forecasting?
3. Summarize the key features of the more commonly used forecasting method.
4. What is a time series, and what are the components of a time series?
5. Explain the (a) trend, (b) seasonal, (c) cyclical, and (d) random components of a series.
6. What steps are involved in using time series data to make a forecast?
7. What is exponential smoothing?
8. Distinguish between, (a) simple regression, and (b) simple correlation.
9. Forecast demand for March was 950 units, but actual demand turned out to be only 820. If the firm is
using a simple exponential smoothing technique with a = 0.2, what is the forecast for April?
[Ans. 924 units]
10. Using the results from Problem 1, assume the April demand was actually 980 units. Now what is the
forecast for May? [Ans. 935 units]
11. A forecaster is using an exponential smoothing model with a = 0.4 and wishes to convert to a moving
average. What length of moving average is approximately equivalent? [Ans. 4 periods]
126 Operations Management
12. A university registrar has adopted a simple exponential smoothing model ( a = 0.4) to forecast
enrollments during the three regular terms (excluding summer). The results are shown in Table 5.16
(a) Use the data to develop an enrollment forecast for the third quarter of year 2. (b) What would be the
effect of increasing the smoothing constant to 1.0?
Table 5.16
Week 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Demand 30 34 22 16 10 10 14 20 30 36 30 10 12 20 30
14. Find the regression equation resulting from the values ∑X = 70, ∑Y = 90, ∑ XY = 660,
∑ (Y – Y )
2
a = 25 c = 22,500
∑ (Y – Y )
2
b = 0.10 c = 45,000
Forecasting Demand 127
(a) Provide a point estimate of the number of vacuums sold per week when 80 inquiries were
received in the earlier week. (b) Estimate (at the 95.5 per cent level) the number of vacuums sold per
week when 80 inquiries were received the week earlier. (c) State the value of the coefficient of
determination. (d) Explain the meaning of your r2 value.
[Ans. (a) 33, (b) Using the
large-sample approximation, the interval is 3 to 63 because Sy–x=15 (c) 0.5 (d) 50 per cent of the
variation in number of vacuums sold is explained by the magazine advertisements.]
17. A recreation operations planner has had data collected on automobile traffic at a selected location Y
on an interstate highway in hopes that the information can be used to predict weekday demand for
state: operated camposites 200 miles away. Random samples of 32 weekdays during the camping
season resulted in data from which the following expression was developed:
Yc = 18 + 0.02X.
where X is the number of automobiles passing the location and Y is the number of camposites demanded
∑ (Y – Y )
2
that day. In addition, the unexplained variation is c = 1,470, and the total variation is
∑ (Y – Y )
2
= 4,080. (a). What is the value of the coefficient of determination?
(b) Explain, in words; the meaning of the coefficient of determination. (c) What is the value of the
coefficient of correlation?
[Ans.(a) 0.64 (b) It tells the
percentage of variation in camposites demanded that is associated with automobile traffic at the
selected site. (c) 0.80.]
18. Allan’s Underground Systems installs septic systems for new houses constructed outside the city
limits. To help forecast his demand, Mr. Allan has collected the data shown in Table on the number of
country building permits issued per month, along with the corresponding number of bid requests he
has received over a 15-month period.
Table 5.18
Month 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
No. Building permits 8 20 48 60 55 58 50 45 34 38 10 5 12 29 50
No. Bid requests 20 7 8 4 18 40 48 54 47 42 30 22 10 4 3
(a) Compute the simple correlation coefficient r between the number of building permits issued and the
number of bid requests received in that month. Use all 15 periods of data.
(b) Use the first 12 months of data for building permits, and compute r between the number of building
permits issued in a month and the number of bid requests received 2 months later (i.e., a 2-month lag).
(c) Repeat (b), but use a 3-month lag. (d) Which type of regression model would be best to forecast bid
requests: a same-month model, a 2-month lag model, or a 3-month lag model?
[Ans. (a) 0.08 (b) 0.84
(c) 0.96 (d) A 3-month lag model is best. It permits Allan to explain 93 per cent of the variation in
number of bid requests.]
19. Two experienced managers have resisted the introduction of a computerized exponential smoothing
system, claiming that there judgmental forecast are “much better than any impersonal computer
could do.” There past record of prediction is as shown in Table 5.19.
128 Operations Management
Table 5.19
1 4,000 4500
2 4,200 5,000
3 4,200 4,000
4 3,000 3,800
5 3,800 3,600
6 5,000 4,000
7 5,600 5,000
8 4,400 4,800
9 5,000 4,000
10 4,800 5,000
(a) Compute the MAD. (b) Compute the tracking signal. (c) On the basis of your calculations, is the
judgmental system performing satisfactorily?
[Ans. (a) 570 (b) 0.53 (c) yes]
REFERENCES
1. Joseph, G. Monks, Theory and Problems of Operations Management, Tata McGraw-Hill
Publishing Company Limited, 2nd Edition, 2004.
2. Joseph, G. Monks, Operations Management, McGraw-Hill International Edition, 3rd Edition.
3. S. Anil Kumar, N. Suresh, Production and Operations Management, New Age International
(P) Limited Publishers, 2nd Edition, 2008.
Product Development and Design 129
6
PRODUCT DEVELOPMENT AND DESIGN
CHAPTER OUTLINE
6.1 Introduction 6.5 Design for Manufacture (DFM)
6.2 Purpose of a Product Design 6.6 Design for Excellence
6.3 Product Analysis • Exercise
6.4 A Framework for Process Design • References
6.1 INTRODUCTION
Product design is the mother of all operations processes in an organisation. The processes for
manufacture, the planning of production, the processes and checks for quality depend upon the
nature of the product. One may say that it all starts with the design of the product. Even the logistics
or plain shipment of the product depends upon how or what the product has been designed for.
Design gives the blueprint. When the design engineer keys in the computer aided design or when a
product design artist draws lines on a sheet of paper, it starts a train of activities.
product like toothpaste which is also designed to act as a mouth freshner needs to be placed,
advertised, promoted and priced differently. Thus, marketing is also impacted by product design. A
product design reflects a company’s overall strategy.
Product development and design is primarily governed by management decisions with respect
to quality and pricing policy. A development programme and a market survey can provide information
as to market potentialities as well as functional, operational, dependability, and durability requirements
and possibilities. Selection of the functional scope and application of standardization, simplification,
and specialization principles are closely related to plant efficiency and to its net profit and must
therefore be an integral part of management policy. The economics of a proposed new product or
new model have to be analyzed in order to establish the market size that would justify production.
Aesthetic considerations come normally at an advanced stage, but may sometimes be a dominant
factor in design, especially with consumer goods. Finally, product development and design must be
carried out with close liaison with the production departments, in order to ensure that the right
materials and processes are utilized and that their implications are considered at a fairly early stage.
The demand for the product in the market may already exist, and its volume can then be assessed
by consumer research and sales figures for identical or similar commodities. Demand can also be
created with the introduction of a new product, either by filling in a gap in the market or by offering
new properties, such as novelty, appearance, or some other specific merits.
The volume of such a demand is more difficult to forecast. Market research is a useful tool in
these cases, but experience and sound judgment are required to evaluate and apply the results of
such research, and in some cases a certain amount of speculation is inevitable. We shall discuss
some problems connected with market research in the next chapter.
The volume of demand is a function of a multitude of factors, some of which are closely related
to local conditions and are sometimes difficult to define or measure. It is therefore essential for an
enterprise to keep in touch with the market and “feel” its trends, especially when this market is
remote and different in character from the local one. This is of particular importance to firms
depending on export markets for the distribution of their products.
If we analyze, for example, the case of an American manufacturer of automobiles, we shall find
that the percentage of output destined for export is rather small, and design policy would therefore
be mainly dictated by American tastes and preferences. A British manufacturer, however, who sells
a substantial proportion of automobiles outside Great Britain, has to watch carefully the trends in
export markets in order to try and amalgamate the requirements and tastes of the various foreign
and home markets in an acceptable design.
Another pertinent question related to product design is : Should the customer get what he wants
or should he be offered what he is supposed to want? Basically this is an economic question. If
management wants to achieve maximum satisfaction and sets itself as a target to supply the customer
with what he wants, it may be faced with the possibility of having to produce an infinite variety of
models to suit every taste. On the other hand, were management to ignore the customer’s wishes or
to maintain that he does not really know what he wants and should therefore be told what is good for
him, the designer’s task would become far simpler, but the sales department would have to face an
unpredictable market.
In practice, product design is a result of some sort of compromise between infinite variety on
one hand and the designer’s concept of the ideal design on the other. In order to try selling this
compromise to potential customers, management resorts to an advertising campaign the policy of
which is dependent on the characteristics of the “compromised design” and on how far it conforms
to, or differs from, the expressed desires of the market to which such a campaign is directed.
Generally, the main objective of advertising is to expand the market, this being achieved by:
Providing general information about the existence of the product.
Providing technical information about its functional characteristics or utilitarian purposes.
Drawing the customer’s attention to those attributes of the product which he wants.
Winning undecided customers by exhibiting possible attractions (such as colour, design, novelty,
and price) that may persuade him to prefer the product to one offered by competitors.
Creating demand among a passive population of customers.
Educating the customer, or telling him what he should want.
Product Development and Design 133
Apart from these direct techniques, management may have some additional aims, such as
increasing the prestige of the firm as a whole, banking on the popularity of one product to strengthen
or introduce another or to publicize one aspect of the firm’s activity for the purpose of raising money
or deviating attention from other activities, and so on. Once the design features of a product have
been ascertained, appropriate advertising methods can be selected.
FUNCTIONAL ASPECT
When the marketing possibilities have been explored, the functional scope of the product has to be
carefully analyzed and properly defined. The definition of the objective itself rarely tells us very
much about the functional scope envisaged. A washing machine, for example, has a clearly defined
objective: to wash clothing. This does not state, however, how the washing should be carried out,
whether the machine should be capable of heating the water prior to washing, whether rinsing or
drying, or both, are to be done by the machine, and if so by what method, and what should the
proportion be between automatic functioning and manual supervision. A functional analysis of this
kind obviously affects the design of the machine, its complexity, its appearance, and its price.
Sometimes functional aspects are detachable, and usage can be left to the customer’s decision.
A steam iron is a case in point. The additional function of dampening the cloth when required, prior
to or during ironing, is incorporated in the steam iron, the main duty of which is to iron the cloth. The
customer can decide whether and when to exploit this characteristic of the apparatus.
There is a trend to offer functional versatility of the product, thereby increasing the range of
applications and sometimes combining several tools in one. A food mixer, for example, allows for a
large number of attachments to be added for a variety of duties. Basically the mixer housing contains
a power unit and a speed regulator, but it has to be designed so as to serve all the attachments, and
the customer has to decide and define for himself the functional scope to be compatible with his
needs, his taste, and his pocket. Household power-tool sets are designed on very much the same
principle: The hand drill is the basic unit, and with attachments it can become a table drill, a lathe, a
polisher, a hedge cutter, etc. Versatility of production machinery may quite often result in substantial
savings in floor space and capital expenditure, and this may become one of the fundamental factors
affecting design policy. Another example of versatility in design is shown in Figure 6.2.
OPERATIONAL ASPECT
After determining the functional aspect, the operational aspect has then to be considered. Not only
must the product function properly, it must be easy to handle and simple to operate. Sometimes it has
to be adaptable to various operational conditions, and very often it is subjected to varying degrees of
skill of potential operators. The designer’s problem becomes all the more critical with the trend for
increased versatility because this characteristic implies using basic attachments as elements for
building suitable combinations for specific purposes. This requires a certain amount of operator
intelligence and skill, which increases with the complexity of the machine. The scarcity of skill is a
prohibitive limitation in this respect on the product designer.
134 Operations Management
Fig. 6.2 Desk combinations (simplification of design). Variety achieved through standardization: With a
limited number of components (one piece table to without joined corners or seams, legs made of seamless
steel tubes, and interchangeable drawers) the designer managed to offer 36 possible combinations while
exhibiting a pleasant style and functional simplicity
(Courtesy: N.V. Wed. J. Ahrend & Zoon—N.V. “Oda” Stallwerk–Amsterdam, Holland. Designer: Friso Kramer,
1958).
The ‘get ready’ stage before the operation proper and the ‘put away’ time (including cleaning)
should be carefully analyzed with respect to the excepted skill of the operator. Too often one finds
ingenious gadgets (for example, in the field of household equipment) that are capable of performing
an operation in a fraction of the time normally required but which involve such complicated
preparations or such lengthy cleaning and ‘put away’ subsequent operations, that the ratio of net
machine time to overall machine time becomes absurdly small. The beneficial features attributed to
the gadget in such cases are rather questionable.
Versatility of equipment should also be analyzed in this light. Especially when subsequent operations
are to be carried out with the aid of different attachments, the designer should always bear in mind
the time required for an operator to perform the change over and should make certain that this time
is in reasonable proportion to the operation time.
DURABILITY AND DEPENDABILITY
These are two factors closely related to the selection of materials and class of workmanship and
hence to the design of the product and the economical analysis of its cost. Quality is not always a
simple characteristic to define, but durability and dependability are two factors that often determine
quality and have to be carefully considered by the designer. Durability is defined mainly by the
length of the active life, or endurance, of the product under given working conditions, but a measure
of the product capability to idle or withstand storage is also often considered in assessing durability.
Durability need not always be associated with selection of good materials. The actual working life
of a match or a rocket motor may be rather limited, but that does not mean that materials for these
articles may be of low quality. An additional criterion, therefore, has to be considered, that of
Product Development and Design 135
dependability, or the capability of the product to function when called upon to do its job. Returning to
our matches, dependability may be related to the number of duds in a box, and while the manufacturer
is eager to reduce this number to a minimum, he need not choose the very best raw materials to
ensure that not even one match will fail. Dependability of rocket motors, however, may be more
rigidly defined, and first class materials are chosen in spite of the short active life that is envisaged
for them in some applications.
Another aspect of durability is that of maintenance and repair. The amount of repair and
preventative maintenance required for some products is closely related to quality and design policy.
This is of particular importance when the equipment is supposed to operate continuously and when
any repair involves a loss of running time.
Problems of convenience and accessibility in operating the equipment have already been discussed,
and the same remarks are valid for maintenance and repair. Easy accessibility is a fundamental
principle in a sound design, and thorough knowledge on the part of the operational durability,
dependability, and maintenance requirements of the product are absolutely essential to ensure a
well- balanced design within the policy outlined by higher management.
AESTHETIC ASPECT
In what way does the appearance of a product affect its design? In most cases, where the functional
scope, durability, and dependability have already been defined, the aesthetics are mainly concerned
with molding the final shape around the basic skeleton. This molding of shape may very often be
severely limited in scope, and what finally emerges is sometimes termed a ‘functional shape’. The
view that functional shape is necessarily divorced from aesthetics, especially where engineering
structures or equipment are concerned, is well-exemplified by bridges, locomotives, or machines of
the late nineteenth or early twentieth century (see, for example, Fig. 6.1. However, a study of the
gradual changes in shape of these objects in the past few decades would convince us that there has
been an increasing recognition of the role of aesthetics in design. This is perhaps partly due to man’s
aesthetic taste being reconciled to accepting these objects as an integral part of the landscape or
everyday life, thereby leading to a modification of the original attitude that these “Monstrosities” are
hopelessly ugly and should be left alone.
Functional shape is a concept in its own right among designers. Those who believe in functional
shape argue that compatibility of function with shape is logical and should therefore be accentuated
and exploited, rather than covered up. A standard lamp is first and foremost a lamp and not a flying
saucer, and there is nothing wrong with its looking like a lamp. This approach is referred to in
Fig. 6.2, where the aesthetic aspects are dealt with at the design stage, after all the other aspects of
the proposed product have been analyzed.
In some cases, however, molding of shape may have financial implications; for instance, when
special materials have to be used or added to those basically required from the functional point of
view or when additional processes are involved. Such cases will call for a careful cost analysis of
the aesthetic aspects.
In extreme cases, aesthetics are the governing factor in design and completely dominate it. This
is especially true for many consumer goods, such as automobiles and household equipment, or
fashion goods. The functional scope, though more or less defined and accepted, may also be widened
136 Operations Management
to accentuate the novelty of the new model. But the idea of the new design starts with the concept
of its shape, from which the idea evolves and grows. The technical considerations have to be
somehow fitted in at a later stage, this being in complete contrast to the conventional sequence
shown in Fig. 6.1.
When styling is a dominant factor in product design, it is often used as a means to create
demand. Changes in fashion and taste, evolution of form, and the introduction of new ideas quickly
outdate previous designs. If the market is psychologically receptive and eager to discard former
designs in favour of new ones, styling becomes a race against time, a race that determines the
salability of the product.
Many tools can be utilized by the designer to bring out aesthetic characteristics. Some of these are:
1. Use of the special materials, either for the parts of the housing or as additional decorations.
Notable is the use of chromium strips, plastics, wood, glass, and fabrics for the purpose.
2. Use of colour, either natural colour of the material concerned or by use of paints, plating,
spraying, or even lighting. Composition and contrast of colours is of great importance to the
industrial designer in facilitating convenient operation and attractive appearance.
3. Texture supplements colour, either by appropriate treatment of the given surfaces or coatings.
Surface finish and requirements of brightness as determined by styling may in turn affect
the production processes in the finishing stages.
4. Shape denoted by outer contours and similarity to familiar objects. Shape can be exploited
to accentuate particular features, to create a sense of spaciousness or illusions of size,
richness and dependability.
5. Line is used to break the form, also for the purpose of emphasizing parts of it, or to give a
sense of continuity, graciousness, and stability.
6. Scaling the product, either to a blown-up size or to a small size (modeling). This creates
novelty and a sense of completeness. The success of styling of some popular small
automobiles in Europe may be partly due to the designer’s talent in creating a feeling of still
having the full-size version, with all its features.
7. Packaging, especially for small items. Novelty and attractiveness of packaging is often
transferred in the mind of the customer, attributing perhaps non-existent values to the contents.
In extreme cases packaging may assume an appreciable portion of the total production
costs and become the center of the design project.
Aesthetic molding, especially when governed by the selection of material, colour, texture, and
sometimes even line, has great economic advantages, since great variety can be achieved at a
comparatively low cost. The basic product remains the same, and variety is obtained by finishing
processes alone. Henry Ford’s maxim that the customer may choose any colour he likes, provided it
is black, is no longer valid. Modern production control techniques allow for a vast number of
combinations of colours and textures to be offered with little difficulty.
Aesthetics have been fully recognized as an integral part of design, and no designer worth his
mettle can afford to ignore their implications, their tools, and their benefits.
on the one hand and a detailed study about the functional, operational, and quality aspects of the
proposed product on the other, the economic analysis can proceed by seeking an answer to the
following questions:
What capital expenditure is required for manufacturing the new product?
What total production costs per piece are envisaged?
What is the reasonable margin of profit that can be expected?
Do the price (= total costs + profit) and the features of the product render it competitive
in the market?
In what numbers is the product expected to be sold?
Here, again, the interdependence of variables should be strongly emphasized. Not one single
question in this list can be isolated and solved independently of the others. The economic analysis is
in fact a cyclic and repetitive procedure. Each question is weighted in the light of the answer and the
data provided by the previous question, and all the answers are checked when their turn comes
again to be re-evaluated in the following cycles, until a state of equilibrium is reached and no further
modifications to these answers are required.
PROFIT AND COMPETITIVENESS
The measure of competitiveness of the product corresponds to the portion of the market it succeeds
in capturing. This is largely dependent on the value the customer is prepared to put on the product,
and on the ratio of this value to the price. As customer assessment of value is not universally
uniform but subject to preference of features, performance, or taste, ratios of values to prices vary
with customers. A state of equilibrium is formed in which the market is divided between different
preferences. This equilibrium may change: If the ratio of value to price of the product becomes
more favourable, when compared with other products, the product increases its portion of the market
and becomes more competitive.
Such an equilibrium is shown in Fig. 6.3 where the total costs include set-up, materials, overheads,
storage, and distribution. The total profit is determined by the margin of profit per unit and by the sales
volume. If the organization seeks to increase its profit, it can try one of the following methods 6.3:
(a) Increase the margin of profit per unit, hence the sales price, but leave the total production
to costs unchanged. If such a course would not affect the sales volume, the total profit would be
proportional to the increase in the margin of profit per unit. Such an increase, however, can upset the
market equilibrium unfavourably, in that both the ratio of customers’ value of the product to its price
will deteriorate and the products of competitors will become more attractive. The market may
shrink, and the total profit, far from attaining the expected value, may in extreme cases fall below its
original level.
(b) Leave the total costs unchanged, but try to improve the ratio of value to price and thus
widen the market. This can be done (1) by producing a better or more attractive product at the same
cost, (2) by launching an intense advertising campaign in order to boost the customer’s assessment
of the product value, or (3) by reducing the sales price at the expense of the margin of profit per unit,
in the hope that the market will expand enough to increase total profit. Too marginal a profit per unit
is, however, undesirable, as it allows little protection from possible fluctuations in the market, and
even slight instabilities may turn a small profit into a sizeable loss.
138 Operations Management
basic labour and material costs and limited resources or credit hampering expenditure on new
equipment and machines. Minimum requirements of quality should also be studied and met, as a
reduction in price at the expense of quality is easy enough; customer’s assessment of the product
value, however, deteriorates accordingly. But reducing production costs and thereby expanding the
market, while sustaining accepted quality standards, offers a challenge to the production engineer.
Probably the most characteristic feature of this process is that it is both dynamic and continuous,
that each success is a further advance along the spiral of increasing productivity and standard of
living (see Figure 6.4).
The three processes are usually linked together and develop as a logical sequence. From a wide
range of requirements it is first necessary to sort out the essential features, define them, and then
work out in a scientific manner, the minimum variety required to meet these essentials. This is a
process of standardization, and it is mainly an engineering process. Within a given range, whether
covered by standards or not, a process of simplification can be carried out with the view of reducing
the variety of products or materials that are produced or purchased. This is both an economic and an
engineering process, and specialization is one of its natural outcomes.
STANDARDIZATION
Standardization covers a wide field of activity, which may be described by the following main categories:
Physical dimensions and tolerances of components within a defined range.
Rating of machines or equipment (in units of energy, temperature, current, speed, etc.).
Specification of physical and chemical properties of materials.
Methods of testing characteristics or performance.
Methods of installation to comply with minimum precautionary measures and convenience of
use.
The first three categories relate to limitation of the number of sizes or grades and some aspects
of quality, one of the important aims being interchangeability of components or assemblies. Adherence
to standards of raw materials is one of the fundamentals of product design, since any deviation from
the standards in this respect may cause a substantial increase in the cost of materials. Industry is
rich with examples in which designers specify “special” materials wheareas the standard grades
can do just as well.
Standardization and interchangeability impose certain limitations on the designer and demand
higher skill and effort in planning. It is easy enough when designing a new component to decide that
no standard really meets the special requirements of the case in hand and that a special part has to
be specified. What designers seem to forget is that one of the purposes of standards is to provide
solutions to relieve them of the task of having to solve afresh some basic problems, and thereby
allow them more time to concentrate on the broader aspects of the design.
Another prerequisite of interchangeability is the precision required of the manufacturing process
in order to obtain production within the specified tolerances. This implies that production control has
to be tightened so that any deviations from the given standards will be immediately noticed and
appropriate action can be taken to avoid the process getting out of control.
Standardization has, however, many advantages, some of which may be briefly listed below:
Reduction of material waste and obsolescence.
Concentration of effort in manufacturing; hence, simplification and specialization.
Reduction in inventories, both of materials, semifinished, and finished products.
Reduction in bookkeeping and other paper work.
Lowering the grades of skill required in manufacture and assembly.
Reduction in price; hence expansion of the market.
Reduction of repair and maintenance costs.
Product Development and Design 141
SIMPLIFICATION
Simplification is a constant source of disagreement between the sales department and the production
personnel. A production engineer prefers little variety, minimum set ups, and long runs (Figure 6.5).
Simplification enables the production department to improve planning, achieve higher
found nowadays in industry. From the customer’s point of view this is a very unsatisfactory state of
affairs. A flood of variety confuses the customer, who ceases in many cases to appreciate the fine
differences between similar products and has either to make a haphazard choice or to invest effort,
time, and study (and quite often money) to enable him to make an intelligent choice.
This is undesirable for the firm as well. Apart from missing all the advantages listed above when
simplification is applied, an analysis of the market sometimes shows that variety has long passed the
saturation point and that an increase in variety will not be even noticed in the market. Also, the division
of the market between too large a number of products makes each portion so small that prices have to
be kept at high levels to avoid losses.
Variable costs aQ, where a respresents the constant total costs per unit, including materials,
labour, and other direct costs that vary with the plant activity. The variable costs are
shown in Figure 6.7 by the straight line aQ.
where Z is the profit of the plant. The desirable level of the plant activity can be expressed in terms
of the safety margin or the profit as
Z
Q2 = Q1 (1 + ∆ ) = Q1 1 + (6.3)
F
A similar diagram to the break-even chart, called the profit-volume chart is shown in Figure
6.10, where the fixed costs are marked as a negative quantity on the ordinate. The BEP is given by
the intersection of the income line with the abscissa. Operation below the abscissa incurs a loss;
operations above it, a profit.
ϕ2 s
or ≥ 1 + D (6.7)
ϕ1 Z1 + F
where D stands for the ratio
ϕ1 P/V ratio of old design
D= = (6.8)
ϕ2 P/V ratio of new design
It is clear that unless the P/V ratio of the product can be greatly improved, the organization will
have to sell more in order to justify the capital investment required for the introduction of the new
design. If, for example, the P/V ratio of the new design remains at the same level as that of the old
one,
D=1
Q2 s
hence, ≥ +1
Q1 Z1 + F
or Q2 > Q1
This fact is illustrated in the profit-volume chart shown in Figure 6.11. Line circle represents the
existing product, yielding profit Z1 when Q1 units are sold.
148 Operations Management
Fig. 6.11 Effect of P/V ratio on the required market size of a new design
For a new design, the preparation costs are added to the fixed costs F. If the P/V ratio is 2
unchanged (line 2), it is necessary to sell Q2 units to obtain the same profit. From the similarity of
triangles it is easy to see that in this case
Q2 s + Z1 + F
= +1
Q1 Z1 + F
which is what we obtain from Eqn. 6.7 when D = 1. If an increase in the market is not envisaged, the
P/V ratio must be increased (line 3). It is possible to achieve the original profit at Q3 < Q1 if the
P/V ratio is steep enough (line 3). However, even when the number of pieces sold is to remain
unchanged (Q4 = Q1), it is necessary to have a higher P/V ratio than the existing one (line 4), while
a decrease in the P/V ratio will increase appreciably the required sales volume (line 5).
Example
The annual fixed costs of a product are known to be $200,000 and the annual net profit $40,000 the
average monthly sale being 820 units. A new design is contemplated, involving an expenditure for
preparations amounting to $ 80,000, to be returned in two years. It is expected that with new
production methods the P/V ratio may be increased by 5 per cent. What should the annual sales
figure for the new design be
(i) so that the same net profit will be realized;
(ii) so that in addition to this profit a yield of 10 per cent on the capital invested will be obtained?
SOLUTION
(i) The ratio D = 1.00/1.05 = 0.95. The additional expenditure per year s = 80,000/2 = $40,000.
Product Development and Design 149
Q2 s 40,000
≥ 1 + D = 1 + 0.95 = 1.11
Q1 Z1 + F 40,000 + 200,000
Annual Sales required:
Q ≥ 1.11Q1 = 1.11 × 12 × 820 = 10920 units.
(ii) In the first year 10 per cent of the investment (i.e., $8,000) has to be added to the profit, or
Z2 = $48,000. The following expression for Q2/Q1 can be obtained by use of Eqns.6.5a and 6.6.
Q2 S + Z2 + F
= ×D
Q1 Z1 + F
Q2 40.000 + 48.000 + 200.000
Hence, = 0.95 = 1.14
Q1 40.000 + 200.000
or Q2 ≥ 1.14 × 12 × 820 = 11,220 units.
Similarly, in the second year,
Z2 = 40,000 + 4,000 = $44,000
Q2 40,000 + 44,000 + 200,000
and = 0.95 = 1.12
Q1 40,000 + 200,000
or Q2 ≥ 1.12 × 12 × 820 = 11,020 units.
The case where the same profit should be realized by an unchanged volume of sales deserves
special attention. It is often very difficult to forecast, let alone ascertain, an increased market for a
new design, and considerations of “change-over” have to be based on the assumption that the sales
volume will remain constant, i.e., Q1 = Q2. As already mentioned, this will require an improvement in
the P/V ratio, which can be quantitatively determined by
s
1 + D=1
Z1 + F
This relation is shown in Figure 6.12. Any point on the curve refers to a resultant profit equal to
the existing one, while for any point below the curve, an increased profit is implied.
Fig. 6.12 Required improvement of the P/V ratio when Q1 – Q2 to yield a profit Z2 > Z1.
150 Operations Management
identified. If the process is service-oriented, thesee needs will be reflected in the proposed quality,
speed, cost, and reliability of the service. If, on the other hand, the process will be manufacturing-
oriented, then these needs will be reflected in the product’s proposed quality, cost, function, reliability
and appearance. When these service or product parameters are transformed into a product, design,
it is essential that a cross-functional alliance between product, planning and process design groups
be established in order to ensure that the product objectives can indeed be profitably met. Otherwise
only local goals may be pursued. For example, the marketing and engineering departments working
alone may design a product which is very costly to manufacture and very difficult to service. In
short, the transformation process should be considered well before the design is finalized. This can
usually be accomplished in the following way:
Information from the product development stage can be directed to those responsible for
process R&D. They in turn can determine if the process capability for this product now exists
within the firm, whether it exists outside the firm or whether research and development effort would
be necessary to meet the specified objectives. Rough cost estimates would also be made for each
alternative identified. In large firms a special process R&D department may be organized just for
this purpose. In smaller firms this function is less formalized and more reliance would be placed on
outside suppliers of processing equipment and company engineers.
Fig. 6.13 The process planning task. (From Howard L. Timma and Michael F. Pohlen, The Production
Function in Business, Richard D. Irwin, Inc., Homewood, (II., 1970, p. 302.)
152 Operations Management
As the process R&D phase progresses, information is feedback to the product development
group. If the R&D group will be able to comply with the product specifications, then the product
final design stage can begin. If there are problems, however, in complying with product specifications,
then modifications in the product development stage must occur.
Information from both product final design and process R&D are inputs to the process design
stage. The purpose of this stage is to generate alternative ways of meeting the objectives formalized
in the final design stage, determine the criteria by which they will be evaluated, and make the final
selection.
A good product design would be such that it makes many or all of the manufacturing related
functions to be done in less time, less effort, and with less cost. Such a product design would
facilitate the manufacturing function. The manufacturing related operation include:
Material procurement,
Material handling,
Product conversion (e.g. machining processes),
Changeovers and set-ups, and
Quality control procedures.
All of these, if not handled properly, could lead to increased lead times. A good product design
takes the facts or realities of these operations into consideration, incorporates them into the design
and thereby facilitated these operations.
WHAT IS DFM?
The idea behind a DFM effort is to modify the existing product’s (and/or its components’) design or
have a new product designed in such a way that the processes to manufacture the same are easier,
quicker and or less expensive. Reducing the manufacturing time is a major consideration. This, of
course, has to be achieved without compromising on quality.
DFM, as a concept, is not new although its huge importance has dawned on the manufacturers
only lately because of the intensity of competition in the present times. It was Eli Whitney (and Le
Blanc) in the Western part of the world, who developed system 200 years ago for manufacturing
muskets that incorporated the concept of interchangeable parts. Earlier, all muskets were handmade.
This was cumbersome in addition to being expensive. It was also terribly time consuming and made
the immediate availability in large number a difficult task. Whitney redesigned each part to a specific
dimension with a limited tolerance. This paved the way for mass manufacture of muskets. Thus, he
designed the musket (and its components) for large scale manufacturability.
Henry Ford seemed to have grasped the concept of DFM about 90 years ago. The following
statement by him, about Model T succinctly expresses the idea behind DFM.
“...It was up to me, the designer, to make the car so completely simple...The less complex the
article, the easier it is to make, the cheaper it may be sold...We start with the consumer, work back
through the design, and finally arrive at manufacturing.”*
Product design influences the efficiency of manufacturing. Thereby it influences the flexibility
of marketing strategies and the organisation’s success in a competing business world.
Cultural barrier: It is indeed surprising that despite the emphasis during the last several decades
on increasing efficiency in manufacturing, the importance of product design for manufacturing
efficiency has not been appreciated. A majority of the organisations have had the design department
and the manufacturing department hardly ever interacting. Product designers in some manufacturing
industries have been sitting in ivory towers. They are highly respected, as their job is perceived to be
creative like that of an accomplished artist, whereas, the manufacturing executive is seen as a
rough-and-tough person who has risen from the ranks, and therefore lacking in such finer abilities. A
cultural barrier seems to separate the designer of the product and the person manufacturing the
product.
Product Development and Design 155
‘Over the Wall’ syndrome: Product designer believe that their job is over once they release
their drawings. They, so to say, throw their designs ‘over the wall’, for the manufacturing person to
do the next job of producing it. Manufacturing engineers then struggle to produce the product that is
‘dumped into their laps’. At their best, design and development people have been more concerned
with how a particular feature requested by marketing may be translated into a physical parameter.
How it may be produced, what it may cost and in what time, have not been much of their concern.
As a result there are several engineering changes after the design has been released, because
the design gives multitudinous problems when taken up for manufacture. The solution of these
problems wastes precious time, and by the time the company has made the product it is too late as
the market has shifted. It would have been so much better if the two departments—design and
manufacturing—had sat together during the early stages of product design and exchanged notes.
With the heat of the global competition intensifying, companies have now started to seriously
think as to how their products could remain competitive in a dynamic market. The Japanese companies
such as Toyota, Honda, Mitsubishi and several others have been the forerunners in manufacturing
products that were of high quality, yet inexpensive and available at short notice. They have done this
consistently over the years, have been quite profitable all through and growing in the international
markets, notably in the Western markets. They achieved this despite the fact that it was the West
that had been the harbinger of computer technology and automation, While it was Whitney and
Henry Ford who had initiated the concept, their message was lost because of the preoccupation
with technological superiority. The Japanese have much automation in their factories too; however,
they seem to have grasped the value of simplicity in the plants—fewer parts, same or similar parts
and parts that are simpler to manufacture. Table 6.1 presents some DFM principles for assemblies.
Table 6.1 DFM Principles for Assemblies
Fig. 6.14 Facilitation of insertion of parts by the use of funnel-shaped openings and tapered ends,
Source : Bralla, J.G., Design for Excellence, McGraw-Hill, New York, 1996.
V. Use modules
This allows for more standardisation and speeds up the assembly process.
VI. Minimise ‘new’-ness
Minimise:
new parts
new processes
new suppliers
new machines
New things—particularly too many new things—introduce many imponderables and increase
uncertainty and, consequently, errors resulting in unacceptable quality and time delays in assembling.
VII. Use ‘Poka Yoke’ or fool-proofing
Design in such a way that the parts cannot be assembled incorrectly.
A key part of any product realization process is the robustness of the design. “Design for”
initiatives such as Design for Assembly, Design for Cost, Design for Manufacturing, Design for
Test, Design for Logistics, Design for Performance, and so on are now being referred to as Design
for Excellence (DFX). It was found that Japanese design emphasizes two key areas; the overall
development process and concurrent engineering. As shown in Figure 6.15 there is a strong customer
focus at the product-planning phase and in the product evaluation phase of the product development
process. The overall product development process is rooted in what Japanese firms call the “market-
in”. Market-in refers to having a clear set of customer-driven requirements as the basis for product
development. This is a fundamental requirement for DFX. Concurrent engineering of product design
and development activities provides the second main step in achieving DFX.
Fig. 6.15 Japan’s product development activities (Toyoda Machine Tool Co.)
“In order to effectively deploy a timely design, thorough testing of the design and process
training are considered a must. A successful DFX process requires carefully managed design of
new products. As shown in Figure 6.16 there are numerous activities that must be coordinated in
order to develop and implement a successful product realization effort. Information must be gathered
and analyzed from regions of the globe in which products will be introduced, and products must be
market-tested in those specific regions. An engine controller for use in an American version of a
Japanese automobile, would, by necessity, receive its reliability testing in the United States.
158 Operations Management
Products that are targeted globally also get tested in Japan in order to carefully control the
products’ globalization. Technology development activities must operate in parallel with product
technology planning and market development planning to assure timely development and introduction
of new products.
EXERCISE
REFERENCES
1. S.N. Chary, Production and Operation Management, 3rd Edition, Tata McGraw-Hill
Publishing Company Limited, 2004.
2. Eilon, Samuel, Elements of Production Planning and Control, Bombay Universal Book Co.
1985.
3. Barry Shore, Operations Management, McGraw-Hill Publication, 1973.
7
MATERIALS MANAGEMENT
CHAPTER OUTLINE
7.1 Introduction and Meaning 7.7 Standardization
7.2 Scope or Functions of Materials 7.8 Simplification
Mangement 7.9 Value Analysis
7.3 Material Planning and Control 7.10 Ergonomics (Human Engineering)
7.4 Purchasing 7.11 Just-in-Time (JIT) Manufacturing
7.5 Stores Management • Exercise
7.6 Inventory Control or Management
(b) Value analysis: Value analysis is concerned with the costs added due to inefficient or
unnecessary specifications and features. It makes its contribution in the last stage of product cycle,
namely, the maturity stage. At this stage research and development no longer make positive
contributions in terms of improving the efficiency of the functions of the product or adding new
functions to it.
(c) Ergonomics (Human Engineering): The human factors or human engineering is concerned
with man-machine system. Ergonomics is “the design of human tasks, man-machine system, and
effective accomplishment of the job, including displays for presenting information to human sensors,
controls for human operations and complex man-machine systems.” Each of the above functions
are dealt in detail.
The basis for material planning is the forecast demand for the end products. Forecasting techniques
such as weighted average method, exponential smoothening and time series models are used for the
same. Once the demand forecast is made, it is possible to go through the excerse of material
planning. Bill of materials is a document which shows list of materials required, unit consumption
location code for a given product. An explosive chart is a series of bill of material grouped in a
matrix form so that combined requirements for different components can be done requirements of
various materials are arrives at from the demand forecast, using bill of materials, through explosion
charts. Thus material requirement plan will lead to be the development of delivery schedule of the
materials and purchasing of those material requirements.
7.4 PURCHASING
Purchasing is an important function of materials management. In any industry purchase means
buying of equipments, materials, tools, parts etc. required for industry. The importance of the purchase
function varies with nature and size of industry. In small industry, this function is performed by
works manager and in large manufacturing concern; this function is done by a separate department.
The moment a buyer places an order he commits a substantial portion of the finance of the corporation
which affects the working capital and cash flow position. He is a highly responsible person who
meets various salesmen and thus can be considered to have been contributing to the public relations
efforts of the company. Thus, the buyer can make or mar the company’s image by his excellent or
poor relations with the vendors.
To achieve maximum integration with other department of the company: The purchase
function is related with production department for specifications and flow of material,
engineering department for the purchase of tools, equipments and machines, marketing
department for the forecasts of sales and its impact on procurement of materials, financial
department for the purpose of maintaining levels of materials and estimating the working
capital required, personnel department for the purpose of manning and developing the
personnel of purchase department and maintaining good vendor relationship.
To train and develop the personnel: Purchasing department is manned with varied types
of personnel. The company should try to build the imaginative employee force through training
and development.
Efficient record keeping and management reporting: Paper processing is inherent in
the purchase function. Such paper processing should be standardised so that record keeping
can be facilitated. Periodic reporting to the management about the purchase activities justifies
the independent existence of the department.
buyer has to consider emergency situations like floods, strikes, etc. He should have ‘contingency
plans’ when force major clauses become operative, for instance, the material is not available due to
strike, lock-out, floods, and earthquakes.
4. Right source: The source from which the material is procured should be dependable and
capable of supplying items of uniform quality. The buyer has to decide which item should be directly
obtained from the manufacturer. Source selection, source development and vendor rating play an
important role in buyer-seller relationships. In emergencies, open market purchases and bazaar
purchases are restored to.
5. Right quantity: The right quantity is the most important parameter in buying. Concepts,
such as, economic order quantity, economic purchase quantity, fixed period and fixed quantity systems,
will serve as broad guidelines. But the buyer has to use his knowledge, experience and common
sense to determine the quantity after considering factors such as price structure, discounts, availability
of the item, favourable reciprocal relations, and make or buy consideration.
The purchase manager should be innovative and his long-term objective should be to minimise the
cost of the ultimate product. He will be able to achieve this if he aims himself with techniques, such
as, value analysis, materials intelligence, purchases research, SWOT analysis, purchase budget lead
time analysis, etc.
7. Right contracts: The buyer has to adopt separate policies and procedures for capital and
consumer items. He should be able to distinguish between indigenous and international purchasing
procedures. He should be aware of the legal and contractual aspects in international practices.
8. Right material: Right type of material required for the production is an important parameter
in purchasing. Techniques, such as, value analysis will enable the buyer to locate the right material.
9. Right transportation: Right mode of transportation have to be identified as this forms a
critical segment in the cost profile of an item. It is an established fact that the cost of the shipping of
ore, gravel, sand, etc., is normally more than the cost of the item itself.
10. Right place of delivery: Specifying the right place of delivery, like head office or works,
would often minimize the handling and transportation cost.
by the purchase officer. Out these copies, one copy each is sent to store-keeper, supplier, accounts
section, inspection department and to the department placing the requisition and one copy is retained
by the purchase department for record.
6. Payment of the invoice: When the goods are received in satisfactory condition, the invoice
is checked before it is approved for the payment. The invoice is checked to see that the goods were
duly authorised to purchase, they were properly ordered, they are priced as per the agreed terms,
the quantity and quality confirm to the order, the calculations are arithmetically correct etc.
7. Maintenance of the records: Maintenance of the records is an important part and parcel
of the efficient purchase function. In the industrial firms, most of the purchases are repeat orders
and hence the past records serve as a good guide for the future action. They are very useful for
deciding the timings of the purchases and in selecting the best source of the supply.
8. Maintenance of vendor relations: The quantum and frequency of the transactions with
the same key suppliers provide a platform for the purchase department to establish and maintain
good relations with them. Good relations develop mutual trust and confidence in the course of the
time which is beneficial to both the parties. The efficiency of the purchase department can be
measured by the amount of the goodwill it has with its suppliers.
Aljian, it has been described that the following variables to be considered while evaluating the
quotations of the suppliers:
1. Cost factors: Price, transportation cost, installation cost if any, tooling and other operations
cost, incidence of sales tax and excise duty, terms of payment and cash discount are considered in
cost factor.
2. Delivery: Routing and F.O.B. terms are important in determining the point at which the title
to the goods passes from vendor to the buyer and the responsibility for the payment of the payment
charges.
3. Design and specification factors: Specification compliance, specification deviations,
specification advantages, important dimensions and weights are considered in line with the
demonstration of sample, experience of other users, after sale services etc.
4. Legal factors: Legal factors include warranty, cancellation provision, patent protection, public
liability, federal laws and reputation compliance.
5. Vendor rating: The evaluation of supplier or vendor rating provides valuable information
which help in improving the quality of the decision. In the vendor rating three basic aspects are
considered namely quality, service and price. How much weight should be given to each of these
factors is a matter of judgment and is decided according to the specific need of the organization.
Quality would be the main consideration in the manufacturing of the electrical equipments while
price would be the prime consideration in the product having a tense competitive market and for a
company procuring its requirements under the blanket contract with agreed price, the supplier rating
would be done on the basis of two variables namely quality and delivery.
The Development Project Committee of the National Association of Purchasing Agents
(U.S.A.) has suggested following methods for evaluating the performance of past suppliers.
(a) The categorical plan: Under this method the members of the buying staff related with
the supplier like receiving section, quality control department, manufacturing department etc., are
required to assess the performance of each supplier. The rating sheets are provided with the
record of the supplier, their product and the list of factors for the evaluation purposes. The
members of the buying staff are required to assign the plus or minus notations against each
factor. The periodic meetings, usually at the interval of one month, are held by senior man of the
buying staff to consider the individual rating of each section. The consolidation of the individual
rating is done on the basis of the net plus value and accordingly, the suppliers are assigned the
categories such as ‘preferred’, ‘neutral’ or ‘unsatisfactory’. Such ratings are used for the future
guidance.
This is a very simple and inexpensive method. However, it is not precise. Its quality heavily
depends on the experience and ability of the buyer to judge the situation. As compared to other
methods, the degree of subjective judgment is very high as rating is based on personal whim and
the vague impressions of the buyer. As the quantitative data supported by the profits do not exist,
it is not possible to institute any corrective action with the vendor. The rating is done on the basis
of memory, and thus it becomes only a routine exercise without any critical analysis.
(b) The weighted-point method: The weighted-point method provides the quantitative
data for each factor of evaluation. The weights are assigned to each factor of evaluation according
Materials Management 171
to the need of the organization, e.g., a company decides the three factors to be considered—
quality, price and timely delivery. It assigns the relative weight to each of these factors as under:
Quality ……… 50 points
Price ……… 30 points
Timely delivery ……… 20 points
The evaluation of each supplier is made in accordance with the aforesaid factors and weights
and the composite weighted-points are ascertained for each suppliers—A, B and C—are rated
under this method. First of all the specific rating under each factor will be made and then the
consolidation of all the factors will be made for the purpose of judgment.
(c) Quality rating: Percentage of quantity accepted among the total quantity is called
quality rating. In other words, the quality of the materials is judged on the basis of the degree of
acceptance and rejections. For the purpose of comparison, the percentage degree of acceptance
will be calculated in relation to the total lots received. Price rating is done on the basis of net
price charged by the supplier. Timely delivery rating will be done comparing with the average
delivery schedule of the supplier.
(d) The cost-ratio plan: Under this method, the vendor rating is done on the basis of
various costs incurred for procuring the materials from various suppliers. The cost-ratios are
ascertained delivery etc. The cost-ratios are ascertained for the different rating variables such as
quality, price, timely delivery etc. The cost-ratio is calculated in percentage on the basis of total
individual cost and total value of purchases. At the end, all such cost-ratios will be adjusted with
the quoted price per unit. The plus cost-ratio will increase the unit price while the minus cost-
ratio will decrease the unit price. The net adjusted unit price will indicate the vendor rating. The
vendor with the lowest net adjusted unit price will be the best supplier and so on. Certain quality
costs can be inspection cost, cost of defectives, reworking costs and manufacturing losses on
rejected items etc. Certain delivery costs can be postage and telegrams, telephones and extra
cost for quick delivery etc.
SOLUTION
Quality accepted
Quality performance (weightage 40%) = × 40
Total quantity supplied
172 Operations Management
DELIVERY PERFORMANCE
X, Adherence to time schedule (weightage 30%)
The factor weightage for quality, delivery and price are 40%, 35% and 25% as per the
decision of the mar. Rank the performance of the vendors on the QDP basis and interpret the
result.
SOLUTION
Formal mode:
No. of lots accepted
= × (weightage for quality)
No. of lots submitted
No. of accepted lots
+ × ( weightage for delivery )
No.of lots submitted with time
Lowest Price
+ × (weightage for price)
Price of lot
Materials Management 173
Total vendor rating = Quality performance + Delivery performance rating + Price rating
12 15
Vendor A = × 40 + 0. 94 × 35 + × 25 = 89.90
15 15
9 15
Vendor B = × 40 + 0. 98 × 35 + × 25 = 90.036
10 19
15
Vendor C = 1 × 40 + 0. 90 × 35 + × 25 = 89.357
21
Vendor B is selected with higher rating.
in the price. In this system, the buyer need not lock up the capital and so the purchasing routine is
reduced. This is also significantly reduces obsolescence of inventory, lead time and clerical efforts
in paper work. Thus, the seller can devote his marketing efforts to other customers and production
scheduling becomes easy.
5. Rate contract: The system of rate contract is prevalent in public sector organizations and
government departments. It is common for the suppliers to advertise that they are on ‘rate contract’
for the specific period. After negotiations, the seller and the buyer agree to the rates of items.
Application of rate contract has helped many organizations to cut down the internal administrative
lead time as individual firms need to go through the central purchasing departments and can place
orders directly with the suppliers. However, suppliers always demand higher prices for prompt
delivery, as rate difficulty has been avoided by ensuring the delivery of a minimum quantity at the
agreed rates. This procedure of fixing a minimum quantity is called the running contract and is being
practised by the railways. The buyer also has an option of increasing the quantity by 25% more than
the agreed quantity under this procedure.
6. Reciprocity: Reciprocal buying means purchasing from one’s customers in preference to
others. It is based on the principle “if you kill my cat, I will kill your dog”, and “Do unto your
customers as you would have them do unto you”. Other things, like soundness from the ethics and
economics point of view being equal, the principles of reciprocity can be practiced. However, a
purchasing executive should not indulge in reciprocity on his initiative when the terms and conditions
are not equal with other suppliers. It is often sound that less efficient manufacturers and distributors
gain by reciprocity what they are unable to gain by price and quality. Since this tends to discourage
competition and might lead to higher process and fewer suppliers, reciprocity should be practised on
a selective basis.
7. Systems contract: This is a procedure intender to help the buyer and the sellers to reduce
administrative expenses and at the same time ensure suitable controls. In this system, the original
indent, duly approved by competent authorities, is shipped back with the items and avoids the usual
documents like purchase orders, materials requisitions, expediting letters and acknowledgements,
delivery period price and invoicing procedure, Carborandum company in the US claims drastic
reduction in inventory and elimination of 40000 purchase orders by adopting the system contracting
procedure. It is suitable for low unit price items with high consumption.
3. To meet the demands of the consuming departments by proper issues and account for the
consumption.
4. To minimise obsolescence, surplus and scrap through proper codification, preservation and
handling.
5. To highlight stock accumulation, discrepancies and abnormal consumption and effect control
measures.
6. To ensure good house keeping so that material handling, material preservation, stocking,
receipt and issue can be done adequately.
7. To assist in verification and provide supporting information for effective purchase action.
7.5.1 Codification
It is one of the functions of stores management. Codification is a process of representing each item
by a number, the digit of which indicates the group, the sub-group, the type and the dimension of the
item. Many organizations in the public and private sectors, railways have their own system of
codification, varying from eight to thirteen digits. The first two digits represents the major groups,
such as raw materials, spare parts, sub-contracted items, hardware items, packing material, tools,
oil, stationery etc. The next two digits indicate the sub-groups, such as, ferrous, non-ferrous etc.
Dimensional characteristics of length, width, head diameter etc. constitute further three digits and
the last digit is reserved for minor variations.
Whatever may be the basis, each code should uniquely represent one item. It should be simple
and capable of being understood by all. Codification should be compact, concise, consistent and
flexible enough to accommodate new items. The groupings should be logical, holding similar parts
near to one another. Each digit must be significant enough to represent some characteristic of the
item.
OBJECTIVES OF CODIFICATION
The objectives of a rationalized material coding system are:
1. Bringing all items together.
2. To enable putting up of any future item in its proper place.
3. To classify an item according to its characteristics.
4. To give an unique code number to each item to avoid duplication and ambiguity.
5. To reveal excessive variety and promote standardization and variety reduction.
6. To establish a common language for the identification of an item.
7. To fix essential parameters for specifying an item.
8. To specify item as per national and international standards.
9. To enable data processing and analysis.
ADVANTAGES OF CODIFICATION
As a result of rationalized codification, many firms have reduced the number of items. It enables
systematic grouping of similar items and avoids confusion caused by long description of items since
standardization of names is achieved through codification, it serves as the starting point of simplification
and standardization. It helps in avoiding duplication of items and results in the minimisation of the
number of items, leading to accurate record. Codification enables easy recognition of an item in
stores, thereby reducing clerical efforts to the minimum. If items are coded according to the sources,
176 Operations Management
it is possible to bulk the items while ordering. To maximise the aforesaid advantages, it is necessary
to develop the codes as concerned, namely, personnel from design, production, engineering, inspection,
maintenance and materials.
These questions are answered by the use of inventory models. The scientific inventory control
system strikes the balance between the loss due to non-availability of an item and cost of carrying
the stock of an item. Scientific inventory control aims at maintaining optimum level of stock of goods
required by the company at minimum cost to the company.
Table 7.1
The classification of ABC analysis is shown by the graph given as follows (Fig. 7.5).
Once ABC classification has been achieved, the policy control can be formulated as follows:
(a) A-Item: Very tight control, the items being of high value. The control need be exercised at
higher level of authority.
(b) B-Item: Moderate control, the items being of moderate value. The control need be exercised
at middle level of authority.
(c) C-Item: The items being of low value, the control can be exercised at gross root level of
authority, i.e., by respective user department managers.
2. HML analysis: In this analysis, the classification of existing inventory is based on unit price
of the items. They are classified as high price, medium price and low cost items.
3. VED analysis: In this analysis, the classification of existing inventory is based on criticality
of the items. They are classified as vital, essential and desirable items. It is mainly used in spare
parts inventory.
4. FSN analysis: In this analysis, the classification of existing inventory is based consumption
of the items. They are classified as fast moving, slow moving and non-moving items.
Materials Management 179
5. SDE analysis: In this analysis, the classification of existing inventory is based on the items.
6. GOLF analysis: In this analysis, the classification of existing inventory is based sources of
the items. They are classified as Government supply, ordinarily available, local availability and foreign
source of supply items.
7. SOS analysis: In this analysis, the classification of existing inventory is based nature of
supply of items. They are classified as seasonal and off-seasonal items.
For effective inventory control, combination of the techniques of ABC with VED or ABC with
HML or VED with HML analysis is practically used.
(a) Determine the total ordering cost for the orders placed.
(b) Determine the total cost for each lot size chosen which is the summation of inventory
carrying cost and ordering cost.
(c) Select the ordering quantity, which minimizes the total cost.
The data calculated in a tabular column can plotted showing the nature of total cost, inventory
cost and ordering cost curve against the quantity ordered as in Fig. 7.6.
I LLUSTRATION 3: The XYZ Ltd. carries a wide assortment of items for its customers. One
of its popular items has annual demand of 8000 units. Ordering cost per order is found to be
Rs. 12.5. The carrying cost of average inventory is 20% per year and the cost per unit is Re.
1.00. Determine the optimal economic quantity and make your recommendations.
SOLUTION
The table and the graph indicates that an order size of 1000 units will gives the lowest total cost
among the different alternatives. It also shows that minimum total cost occurs when carrying cost is
equal to ordering cost.
Materials Management 181
Fig. 7.7
The most economic point in terms of total inventory cost exists where,
Inventory carrying cost = Annual ordering cost (set-up cost)
Average inventory = 1/2 (maximum level + minimum level)
= (Q + 0)/2 = Q/2
Total inventory carrying cost = Average inventory× Inventory carrying cost per unit
i.e., Total inventory carrying cost = Q/2 × C1 = QC1/2 …(1)
Total annual ordering costs = Number of orders per year × Ordering cost per order
i.e., Total annual ordering costs = (D/Q) × C3 = (D/Q)C3 …(2)
Now, summing up the total inventory cost and the total ordering cost, we get the total inventory cost
C(Q).
i.e., Total cost of production run = Total inventory carrying cost + Total annual
ordering costs
C(Q) = QC1/2 + (D/Q)C3 (cost equation) …(3)
But, the total cost is minimum when the inventory carrying costs becomes equal to the total
annual ordering costs. Therefore,
182 Operations Management
QC1/2 = (D/Q)C3
or QC 1 = (2D/Q)C3
or Q 2 = 2C 3D/C1
2C3 D
or Q=
C1
2C3 D
i.e., Optimal quantity (EOQ), Q0 = C1 ...(4)
D
Optimum number of orders, (N0) = Q ...(5)
0
365 1 Q0
Optimum order interval, (t0) = in days = N in years or (t0) = ...(6)
N0 0 D
SOLUTION
Given data are:
Number of lubricants to be purchased, D = 1800 per year
Procurement cost, C3 = Rs. 16 per order
Inventory carrying cost, CI = C1 = Rs. 42 × Re. 0.20 = Rs. 8.40 per year
2C3 D
Then, optimal quantity (EOQ), Q0 = C1
2 × 16 × 1800
Q 0= = 82.8 or 83 lubricants (approx).
8.4
I LLUSTRATION 5: A manufacturing company purchase 9000 parts of a machine for its
annual requirements ordering for month usage at a time, each part costs Rs. 20. The ordering
cost per order is Rs. 15 and carrying charges are 15% of the average inventory per year. You
have been assigned to suggest a more economical purchase policy for the company. What
advice you offer and how much would it save the company per year?
Materials Management 183
SOLUTION
Given data are:
Number of lubricants to be purchased, D = 9000 parts per year
Cost of part, Cs = Rs. 20
Procurement cost, C3 = Rs. 15 per order
Inventory carrying cost, CI = C1 = 15% of average inventory per year
= Rs. 20 × 0.15 = Rs. 3 per each part per year
2C3 D
Then, optimal quantity (EOQ), Q0 = C1
2 × 15 × 9000
Q0 = = 300 units
3
Q0 300 1
and Optimum order interval, (t0) = in years = = years
D 9000 30
1
= × 365 days = 122 Days
30
Minimum average cost = 2C3 DC1 = 2 × 3 ×15 × 9000 = Rs. 900
If the company follows the policy of ordering every month, then the annual ordering cost is
= Rs 12 × 15 = Rs. 180
Lot size of inventory each month = 9000/12 = 750
Q
Average inventory at any time = = 750/2 = 375
2
Therefore, storage cost at any time = 375 × C1 = 375 × 3 = Rs. 1125
Total annual cost = 1125 + 180 = Rs. 1305
Hence, the company should purchase 300 parts at time interval of 1/30 year instead of ordering
750 parts each month. The net saving of the company will be
= Rs. 1305 – Rs. 900 = Rs. 405 per year.
7.7 STANDARDIZATION
Standardization means producing maximum variety of products from the minimum variety of materials,
parts, tools and processes. It is the process of establishing standards or units of measure by which
extent, quality, quantity, value, performance etc., may be compared and measured.
(b) More time is available to develop new design or to improve established design.
(c) Better resource allocation.
(d) Less qualified personnel can handle routine design work.
2. Benefits to Manufacturing Department
(a) Lower unit cost.
(b) Better quality products.
(c) Better methods and tooling.
(d) Increased interchangeability of parts.
(e) Better utilization of manpower and equipment.
(f) Accurate delivery dates.
(g) Better services of production control, stock control, purchasing, etc.
(h) More effective training.
3. Benefits to Marketing Department
(a) Better quality products of proven design at reasonable cost leads to greater sales volume.
(b) Increased margin of profit.
(c) Better product delivery.
(d) Easy availability of sales part.
(e) Less sales pressure of after-sales services.
4. Benefits to Production Planning Department
(a) Scope for improved methods, processes and layouts.
(b) Opportunities for more efficient tool design.
(c) Better resource allocation.
(d) Reduction in pre-production activities.
5. Benefits to Production Control Department
(a) Well proven design and methods improve planning and control.
(b) Accurate delivery promises.
(c) Fewer delays arise from waiting for materials, tools, etc.
(d) Follow-up of small batches consumes less time.
6. Benefits to Purchase and Stock Control Department
(a) Holding of stock of standard items leads to less paper work and fewer requisitions and
orders.
(b) Storage and part location can be improved.
(c) Newer techniques can be used for better control of stocks.
(d) Because of large purchase quantities involved, favourable purchase contracts can be made.
7. Benefits to Quality Control Department
(a) Better inspection and quality control is possible.
(b) Quality standards can be defined more clearly.
(c) Operators become familiar with the work and produce jobs of consistent quality.
Materials Management 185
8. Other Benefits
(a) Work study section is benefited with efficient break down of operations and effective work
measurement.
(b) Costing can obtain better control by installing standard costing.
(c) More time is available to the supervisors to make useful records and preserve statistics.
(d) Reduced reductions and scrap.
(e) Helps supervisors to run his department efficiently and effectively.
7.8 SIMPLIFICATION
The concept of simplification is closely related to standardization. Simplification is the process of
reducing the variety of products manufactured. Simplification is concerned with the reduction of
product range, assemblies, parts, materials and design.
Value analysis is concerned with the costs added due to inefficient or unnecessary specifications
and features. It makes its contribution in the last stage of product cycle, namely, the maturity stage.
At this stage, research and development no longer make positive contributions in terms of improving
the efficiency of the functions of the product or adding new functions to it.
Value is not inherent in a product, it is a relative term, and value can change with time and place.
It can be measured only by comparison with other products which perform the same function. Value
is the relationship between what someone wants and what he is willing to pay for it. In fact, the
heart of value analysis technique is the functional approach. It relates to cost of function whereas
others relate cost to product. It is denoted by the ratio between function and cost.
Function .
Value =
Cost
about human behaviour. Abilities and limitations and other characteristics to the design of tools,
machines, systems, tasks, jobs and environment for productive, safe, comfortable and effective
human use. Ergonomics aims at providing comfort and improved working conditions so as to channelise
the energy, skills of the workers into constructive productive work. This accounts for increased
productivity, safety and reduces the fatigue. This helps to increase the plant utilisation.
Introduction
Just-in-Time (JIT) Manufacturing is a philosophy rather than a technique. By eliminating all waste
and seeking continuous improvement, it aims at creating manufacturing system that is response to
the market needs.
The phase just in time is used to because this system operates with low WIP (Work-In- Process)
inventory and often with very low finished goods inventory. Products are assembled just before they
are sold, subassemblies are made just before they are assembled and components are made and
fabricated just before subassemblies are made. This leads to lower WIP and reduced lead times. To
achieve this organizations have to be excellent in other areas e.g. quality.
According to Voss, JIT is viewed as a “Production methodology which aims to improve
overall productivity through elimination of waste and which leads to improved quality”. JIT
provides an efficient production in an organization and delivery of only the necessary parts in the
right quantity, at the right time and place while using the minimum facilities”.
EXERCISE
Section A
1. What do you mean by materials management?
2. What is material planning and budgeting?
3. What do you mean by purchasing?
4. What do you mean by ‘Inventory Management’?
5. What do you mean by ‘Inventory Control’?
6. What is codification?
7. What do you mean by ‘Standardisation’?
8. What do you mean by ‘Simplification’?
9. What is ‘Value Analysis’?
10. What do you mean by ‘Ergonomics’?
11. What is EOQ?
Section B
1. Explain the objectives of materials management.
2. What are the functions of stores?
3. Explain the reasons for keeping inventories.
4. What are the objectives of inventory control?
5. What are the benefits of inventory control?
6. What are the objectives of codification?
7. What are the advantages of simplification?
8. Explain the basic steps in value analysis.
9. Explain the objective of ‘Ergonomics’.
Section C
1. Discuss the scope of materials management.
2. Discuss the parameters of purchasing.
3. Discuss the ten ‘R’s’ of purchasing.
4. Discuss the purchasing procedure.
5. Discuss the selection of suppliers.
6. Discuss the benefits of standardisation.
Aggregate Planning and Master Scheduling 191
8
AGGREGATE PLANNING AND MASTER SCHEDULING
CHAPTER OUTLINE
8.1 Introduction 8.5 Mathematical Planning Models
8.2 Variables Used in Aggregate Planning 8.6 Master Scheduling
8.3 Aggregate Planning Strategies • Exercise
8.4 Mixed Strategies • References
8.1 INTRODUCTION
Aggregate planning is the process of planning the quantity and timing of output over the intermediate
range (often 3 to 18 months) by adjusting the production rate, employment, inventory, and other
controllable variables. Aggregate planning links long-range and short-range planning activities. It is
“aggregate” in the sense that the planning activities at this early stage are concerned with homogeneous
categories (families) such as gross volumes of products or number of customers served.
Master scheduling follows aggregate planning and expresses the overall plan in terms of the
amounts of specific end items to produce and dates to produce them. It uses information from both
forecasts and orders on hand, and it is the major control (driver) of all production activities. Figure
8.1 illustrates a simplified aggregate plan and master schedule.
Table 8.1 Aggregate plan and master schedule for electric motors
Aggregate Plan
Month J F M A M J J A S
Number of motors 40 25 55 30 30 50 30 60 40
Master Schedule
Month J F M A M J J A S
AC motors
5hp 15 – 30 – – 30 – – 10
25hp 20 25 25 15 15 15 20 30 20
DC motors
20hp – – – – – – 10 10 –
WR motors
10hp 5 – – 15 15 5 – 20 10
192 Operations Management
6. Changing the use of existing capacity 6. Delayed response and higher fixed costs
To best understand the effect of changes in these variables, it is useful to first focus upon the
impact of a change in only one variable at a time, with other variables held constant. The examples
that follow show the effect on production costs of (isolated) changes in the decision variables. They
are presented in a simplified format in order to best convey the underlying concept; more realistic
examples follow in later sections.
ILLUSTRATION 1: Paris Candy Company has estimated its quarterly demand (cases) as
shown in Table 8.3 and Figure 8.1. It expects the next demand cycle to be similar to this one
and wishes to restore ending inventory, employment, etc., to beginning levels accordingly.
Table 8.3
Demand
Quarter Units
1st 500
2nd 900
3rd 700
4th 300
Each quarterly change of 200 units output has an incremental labour cost of Rs. 2,000 and
ending levels must be restored to initial levels. What is the cost associated with changing the work
force size?
SOLUTION
Table 8.4
2 900 5 2 4000
3 700 4 1 2000
4 300 2 2 4000
Six changes of work force have to be made. Employment change cost = 6 (Rs.2,000)
= Rs.12,000.
ILLUSTRATION 2: (Overtime and idle time) Maintain a stable work force capable of
producing 600 units per quarter, and use OT (at Rs. 5 per unit) and IT (at Rs. 20 per unit).
SOLUTION
Table 8.5
Period Demand OT production Idle Time (IT) capacity Cost in Rs.
(units) (units)
As shown in Table 8.5, 400 units will be produced on overtime, and workers will be idle when
400 units could have been produced. Total cost is Rs.10000.
ILLUSTRATION 3: Vary inventories: Vary inventory levels, but maintain a stable work
force producing at an average requirement rate (of 2,400 units + 4 quarters = 600 units
per quarter) with no OT or IT. The carrying cost (based on average inventory) is Rs. 32 per
unit per year, and the firm can arrange to have whatever inventory level is required before
period I at no additional cost. Annual storage cost (based on maximum inventory) is Rs. 5
per unit.
194 Operations Management
SOLUTION
Table 8.6
Quarter Forecast Rate of Change in Cls. balance End balance
production inventory
1 500 600 100 100 400
As shown in Table 8.6, inventory is accumulated during quarters 1 and 4, and depleted in quarters
2 and 3. The preliminary inventory balance column shows a negative inventory of 300 in quarter 3,
so 300 must be on hand at the beginning of quarter 1 to prevent any shortage. The average inventory
on hand is the ending balance total of 800 units divided by 4 quarters = 200 units.
Carrying cost, Cc (on avg. inventory) = (Rs. 32 per unit-yr) (200 units) = Rs. 6,400
Storage cost,Cs (on max. inventory) = (Rs. 5 per unit) (400 units) = Rs. 2,000
Total inventory cost (Cc + Cs) = Rs. 8,400
ILLUSTRATION 4: Back orders: Produce at a steady rate of 500 units per period, and
accept a limited number of back orders when demand exceeds 500. The Stockout cost of lost
sales is Rs. 20 per unit.
SOLUTION: A back order is an arrangement to fill a current order during a later period. Stockout
costs occur when some sales (or customers) are lost because products are not immediately available.
In this example, 200 units of the excess demand in period 2 are placed on back order for delivery in
period 4. The other 200 units demanded in period 2 are lost, alongwith the 200 in period 3.
Stockout cost = (200 + 200) (Rs.20 per unit) = Rs. 8,000
ILLUSTRATION 5: Subcontract: Produce at a steady rate of 300 units per period, and
subcontract for excess requirements at a marginal cost of Rs. 8 per unit.
SOLUTION: The firm must subcontract 200 units in period 1, 600 in period 2, and 400 in period 3,
as shown in table.
Subcontract cost = (1200)(Rs. 8 per unit) = Rs.9,600
of the five decision variables considered above, accepting back orders results in the least cost
(Rs. 8,000).
Aggregate Planning and Master Scheduling 195
Month Jan. Feb. Mar. April May June July Aug. Sept. Total
Forecast 40 25 55 30 30 50 30 60 40 360
Cumulative 40 65 120 150 180 230 260 320 360
Demand
196 Operations Management
40
May
30
June
20
July
10
Aug.
0
1 Sept.
Months
Fig. 8.2
1. Chase Strategy: If the production planner designed a plan to exactly match the forecast of
demand shown in Figure 8.2, by adding or laying off employees to change the level of production, the
planner would be using a chase strategy. Some overtime or subcontracting might also be used, but
no inventories would be accumulated.
2. Level Production Strategy: The graph in Figure 8.2 shows (visually) that the demand
exceeds the average requirement in some months and is below average in others. A production plan
could be developed to produce at the constant rate of 40 motors per month, accumulating inventory
in months 2, 4, 5, and 7, and using that inventory to meet the above average demands in months 3, 6,
and 8. Table shows that the cumulative demand (forecast) never exceeds the cumulative averages
(production), so no initial inventory is needed to prevent shortages. However, if there were shortages,
some back orders could be allowed under a level production, or inventory strategy.
3. Stable Work-Force Strategy: Referring to Figure 8.2, suppose the firm has a stable work
force capable of producing 36 motors per month on regular time. Production might go as high as 60
motors per month by using overtime, but if demand falls to less than 36 motors per month, some
workers would be idle. Using overtime and idle time to meet demand would be employing a stable
work-force strategy. As part of this strategy, however, it seems likely that planners would build up
some inventory during what might otherwise be idle time periods.
ILLUSTRATION 6: An aggregate plan is to be developed for the forecast of demand covering
nine periods shown in Table 8.8. Other relevant production and cost information is also
provided. Find the cost associated with an aggregate plan that involves varying the size of
the work force in order to have a production rate that matches demand.
Note: Since this plan does not allow for any inventory build up, a decision has been made
to carry 10 units of safety stock, but no overtime or subcontract labour is used.
Table 8.8 Demand, production, and cost information
Month Jan. Feb. Mar. April May June July Aug. Sept. Total
Forecast 40 25 55 30 30 50 30 60 40 360
Aggregate Planning and Master Scheduling 197
Safety stock of inventory required 10 units Inventory carrying cost Rs. 35/period
SOLUTION: The cost associated with changing the employment level is calculated in Table 8.9.
The number of workers required is first determined by dividing the forecast amount by the worker
output of 4 units per month. Fractional values have been rounded up. Beginning with the current
level of 10 workers, the number that must be hired, or laid off, is then determined. Costs are then
computed for
(1) regular-time hours, (2) hiring and layoff, and (3) carrying safety stock. These are added to get
the total plan cost of Rs. 470,450.
Table 8.9 Cost calculations for varying work force to match demand
PERIOD 1 2 3 4 5 6 7 8 9
Production forecast (units/mo) 40 25 55 30 30 50 30 60 40
WORK-FORCE SIZE DATA
No. Workers required 10 7 14 8 8 13 8 15 10
(fost./o/p of 4 units/wk-mo)
(a) No. hired @ beg. of mo 0 0 7 0 0 5 0 7 0
(b)No. laid off @ beg. of mo 0 3 0 6 0 0 5 0 5
COSTS
Regular time cost, Rs. 48, 000 33,600 67,200 38,400 38,400 62,400 38,400 72,000
(No. Wkr)(Rs.30/wkr-hr)
(l60 hr/wkr-mo)
Hiring or layoff cost, Rs.: 0 1,500 4,200 3,00 0 3,000 2,500 4,200 2,500
@(a) (Rs.600) or (b) (Rs.500)
Inventory carrying cost 350 350 350 350 350 350 350 350 350
(10 units) (Rs.35/unit-period)
ILLUSTRATION 7: Produce at a constant rate: Using the demand shown in Table 8.8 (plus
10 more units in periods 8 and 9), develop an aggregate plan based upon the use of the 10
regular-time production workers at a constant rate, with inventories used to satisfy peak
demand. The inventory carrying cost is Rs. 35 per unit per period. Some subcontracting can
be used at a labour cost of Rs. 50 per hour if necessary. Assume a constant output rate of 40
units per period. No safety stock is required, but total demand of 380 units must be met.
198 Operations Management
The costs associated with producing at a constant rate and using—inventories to help meet non-
uniform demands are shown in Table 8.10. Note that the constant production rate of 40 units per
period yields 360 units, which is 20 units short of total demand. Insofar as the additional demand is
in periods 8 and 9—when demand already consumes all production-the additional demand will be
subcontracted out in these two periods. The labour cost for each subcontracted unit is (40 hours per
unit) (Rs. 50 per hour) = Rs. 2,000 per unit, so for the 10 units in periods 8 and 9, the subcontracting
costs are Rs. 20,000 in each period.
Table 8.10 Costs calculation for using inventories to meet demand
Period 1 2 3 4 5 6 7 8 9
Production forecast 40 25 55 30 30 50 30 70 50
PRODUCTION DATA
Output: Regular time 40 40 40 40 40 40 40 40 40
Subcontract – – – – – – – 10 10
Output-forecast 0 15 –15 10 10 –10 10 –20 0
Inventory:
Beginning-of-period 0 0 15 0 10 20 10 20 0
End-of-period 0 15 0 10 20 10 20 0 0
Average inventory 0 7.5 7.5 5 15 15 15 10 0
COSTS
Regular-time cost, Rs. 48,000 48,000 48,000 48,000 48,000 48,000 48,000 48,000 48,000
(L0)(Rs.30/hr)(L60 hr)
Subcontract – – – – – – – 20,000 20,000
(@ Rs. 2,000/per unit)
Inventory carrying cost 0 263 263 175 525 525 525 350 0
(avg. inv.) (Rs.35/period)
Total cost for plan = SRegular-time employment + SSubcontract cost + SInventory carrying cost
= Rs. 474,826
Inventory costs under this format are computed by first determining how many units go into (or
out of) inventory. This amount (i.e., the output minus production forecast) is shown in the table. For
period 1, where forecast and output are both 40 units, it is zero. For period 2, when 40 units are
produced and only 25 are needed, 15 go into inventory. The beginning- and end-of-period inventory
rows in the table show how the inventory balance fluctuates. Average inventory is the sum of
beginning- plus end-of-period inventory divided by two. The inventory carrying cost is the average
amount multiplied by the Rs. 35 per period carrying charge.
ILLUSTRATION 8: Custom Furniture Co. currently has 100 employees and has forecast
quarterly demand as shown in Table 8.11. The historical average production rate is 40 units
per employee per quarter, and the firm has a beginning (safety stock) inventory of 1,000
units. The hiring and training cost is Rs. 400 per employee, and the layoff cost is Rs. 600 per
employee. Inventory is carried at a cost of Rs. 8 per unit per quarter. Use the data to develop
an aggregate plan that uses variable employment and inventory to meet demand.
Table 8.11 Quarterly demand forecast for furniture manufacture
Quarter 1 2 3 4 Total
Demand 3,500 5,000 4,000 3,450 15,950
SOLUTION: One alternative plan is shown in Table 8.12. (Many others, including better ones, are
possible.) The planner has chosen to build some extra inventory in quarter 1 with the workers
already on the payroll. Producing at a rate of 40 units per employee, the first quarter production of
4,000 units is 500 more than demand (3,500), so the ending inventory equals the beginning 1,000 plus
500, or 1,500 units. This results in a carrying cost of Rs.8 (1,500) = Rs.12,000. Twenty employees
are hired at the beginning of quarter 2 to help meet the larger demand during the quarter. This results
in a hiring cost of Rs.400 (20) = Rs.8,000. Employment is cut back again at the beginning of quarter
3, as the firm dips into safety stock, and employment is restored to its original level at the beginning
of quarter 4. (Note: This firm bases inventory cost on ending inventory balance.)
Table 8.12 Aggregate plan for varying work force and inventory levels
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)
Qtr. Fcst. or No. of Change Total Cum. Cum. Ending Inv. cost Empl. chg cost
demand empl. in empl. prodn. prodn. demand inv. @Rs.8 @Rs.400 or
Rs. 600
1 3,500 100 – 4,000 4,000 3,500 1,500 12,000 –
The total (comparative) cost for this is Rs. 34,800 + Rs. 40,000 = Rs. 74,800. Note that inventory
and employment costs are not well balanced, and employment is the lowest during quarter 3 when
demand is relatively high. With some additional trials, the planner could undoubtedly develop a plan
that would result in a lower total cost. Large fluctuations in production often result in more problems
(and higher costs) than more steady-state operations.
200 Operations Management
A useful version of the linear-programming model (the transportation algorithm) views the aggregate
planning problem as one of allocating capacity (supply) to meet forecast requirements (demand) where
supply consists of the inventory on hand and units that can be produced using regular time (RT),
overtime (OT), and subcontracting (SC), etc. Demand consists of individual-period requirements plus
any desired ending inventory. Costs associated with producing units in the given period or producing
them and carrying them in inventory until a later period are entered in the small boxes inside the cells
in the matrix, as is done in the standard transportation linear-programming format.
ILLUSTRATION 9: Given the accompanying supply, demand, cost, and inventory data
(Tables 8.14, and 8.15) for a firm that has a constant work force and wishes to meet all
demand (that is, with no back orders), allocate production capacity to satisfy demand at
minimum cost.
Table 8.14 Supply capacity (units)
Period Regular time Overtime Subcontract
(Rs. 100/unit) (Rs. 125/unit) (Rs. 130/unit)
1 60 18 1,000
2 50 15 1,000
3 60 18 1,000
4 65 20 1,000
*50 per cent of cost is labour.
Table 8.15 Demand and inventory
Demand:
Period 1 2 3 4
Units 100 50 70 80
Initial = 20, Final = 25 Carrying cost = Rs. 2 per
unit-period
Aggregate Planning and Master Scheduling 201
The initial linear-programming matrix in units of capacity is shown in table 8.16, with entries
determined as explained below. Because total capacity exceeds demand, a slack demand of unused
capacity is added to achieve the required balance in supply versus demand.
Table 8.16 Linear programming format for scheduling
Overtime 125 0 20
Subcontract 130 0 1000
Demand 100 5 70 105 4001 4326
Initial inventory: There are 20 units available at no additional cost if used in period 1. Carrying
cost is Rs. 2 per unit per period if units are retained until period 2, Rs. 4 per unit until period 3, and
so on. If the units are unused during any of the four periods, the result is Rs.6 per-unit cost, plus
Rs. 2 per unit to carry it forward to the next planning horizon, for Rs. 8 total if unused.
Regular time: Cost per unit-month is Rs.100 if units are used in the month produced; otherwise,
a carrying cost of Rs. 2 per unit-month is added on for each month the units are retained. Unused
regular time costs the firm 50 per cent of Rs. 100 = Rs. 50.
Overtime: Cost per unit is Rs. 125 if the units are used in the month produced; otherwise, a
carrying cost of Rs. 2 per unit-month is incurred, as in the regular-time situation. Unused overtime
has zero cost.
Subcontracting: Cost per unit is Rs.130 plus any costs for units carried forward. This latter
situation is unlikely, however, because any reasonable demand can be obtained when needed, as
indicated by the arbitrarily high number (1,000) assigned to subcontracting capacity. There is no cost
for unused capacity here.
Note: If the initial allocations are made so as to use regular time as fully as possible, the solution
procedure is often simplified. Overtime and subcontracting amounts can also be allocated on a
minimum-cost basis.
Final inventory: The final-inventory requirement (25 units) must be available at the end of
period 4 and has been added to the period 4, demand of 80 units to obtain a total of 105 units.
Since no back orders are permitted, production in subsequent months to fill demand in a current
month is not allowed. These unavailable cells, along with the cells associated with carrying forward
any subcontracted units, may therefore be blanked out, since they are infeasible. The final solution,
202 Operations Management
following normal methods of distribution linear programming, is shown in table. 8.17. This result
flows from a least-cost allocation.
Table 8.17 Master Schedule for Furniture Company
Overtime 125 0 20
20
Subcontract 130 0 1000
0 100
Demand 100 5 70 105 4001 4326
The optimal solution values can be taken directly from the cells. Thus in period 2, the planners
will schedule the full 50 units to be produced on regular time plus 12 units on overtime to be carried
forward to period 4. This leaves 3 units of unused overtime capacity and no subcontracting during
that period. Because of the similar carrying cost for units produced on regular time or overtime, it
does not matter which physical units are carried forward, once overtime production is required.
Thus, different optimal solutions (but with identical costs) may be obtained.
into specific material and capacity requirements by the Material Requirements Planning (MRP) and
Capacity Requirements Planning (CRP) systems. Thus, the MPS essentially drives the entire
production and inventory system.
The major inputs to the master production schedule are:
1. Forecasts of demand, e.g., of end items and service parts.
2. Customer orders, i.e., including any warehouse and interplant needs.
3. Inventory on-hand from the previous period.
Forecasts of demand are the major input for make-to-stock items. However, to be competitive,
many make-to-order firms must anticipate orders by using forecasts for long lead-time items and by
matching the forecasts with customer orders as the orders become available.
Two-time fence can be identified in MPS: A demand and a planning time fence.
(a) A demand time fence is the firm or ‘frozen’ portion of the master schedule (beginning
with the current period) during which no changes can be made to the schedule without management
approval.
(b) A planning time fence is the portion of the master schedule (also beginning with the
current period) during which changes will not automatically be made (i.e., via computer) to
accommodate demand. This gives the master scheduler a manageable base to work from and still
allows some discretion in overriding the constraint.
Question: How does master scheduling differ under manufacturing strategies of (a) make-to-
stock, (b) assemble-to-order, and (c) make-to-order?
See Figure 8.3 where the shorter line segments represent fewer items. In (a) make-to-stock
204 Operations Management
operations, the (fewer) end items are stocked, to support customer service, and the master production
schedule (MPS) is structured around those end items. In (b) assemble-to-order plants, such as in
automobile manufacturing, the master scheduling is done for the major sub-assembly-level items. In
(c) make-to-order products, such as customized furniture, there are fewer raw materials than end
items; the end items may even be one of a kind. Here, the master schedule is typically structured
around the raw material usage.
No.of end items MPS
MPS
No.of major
assemblies
SOLUTION
(a) Product appears to be made for stock in response to a forecast; no customer orders are shown.
(b) The planning time fence is 6 weeks, and the schedule calls for four production runs (i.e., of
25 units each in weeks 2, 3, 5, and 6).
(c) No production is needed in week 1 because the beginning inventory of 30 is more than
enough to meet the forecast demand of 20 needed in week 1.
Projected Available Balance = Previous available balance + MPS – Current period requirements
(@ end of period) = 30 + 0 – 20 = 10 units.
(Note: No changes are normally accepted up to the Demand Time Fence (DTF). Prior to the
DTF the Projected Available Balance is based upon customer orders only, and disregards the
forecast.)
(d) The MPS amount in week 3 (25 units). All MPS items become projected requirements in the
MRP system.
(e) We cannot tell the extent to which capacity is utilized without additional information from the
capacity planning system. One of the uses of the MPS is to provide the information to drive
rough-cut capacity planning. However, no production of blood analyzer units is scheduled for
weeks 1 and 4, so the production facilities might be idle at that time-unless they are being used
for another product.
ILLUSTRATION 11: Find the ATP inventory values for the master schedule shown in
Table 8.20.
Table 8.20 Master schedule for tractor levellers
On-hand 23 Lot size 25 Planning time fence 6
Period 1 2 3 4 5 6 7 8 9
Forecast 10 10 10 10 20 20
Customer orders (booked) 13 5 3 1
Projected available balance 10 0 15 5 10 15
Master production schedule 25 25 25
Available-to-promise
Available-to-Promise values are computed for the current period (1) and for other periods when
the MPS shows that a lot will be produced.
For period
1. ATP1 = (On-hand Inv.) – (orders in periods 1 and 2) = 23 – (13 + 5) = 5
2. ATP3 = (MPS amount in 3) – (orders in periods 3 and 4) = 25 – (3 + 1) = 21
3. ATP5 = (MPS amount in 5) – (orders in period 5) = 25 – 0 = 25
4. ATP6 = (MPS amount in 6) – (orders in period 6) = 25 – 0 = 25
The last row should have values of 5, 21, 25 and 25 in the columns for periods 1, 3, 5 and 6
respectively.
ADDITIONAL ILLUSTRATIONS
ILLUSTRATION 12: From the following forecast determine the monthly inventory balances
required to follow a plan of letting the inventory absorb all fluctuations in demand. In this
case, we have a constant work force, no idle time or overtime, no back orders, no use of
subcontractors, and no capacity adjustment. Assume that the firm does not use safety stock
or cushion inventory to meet the demand.
Table 8.21
Month Jan. Feb. Mar. Apr. May June July Aug. Sept. Oct. Nov. Dec.
Forecast 220 90 210 396 616 700 378 220 200 115 95 260
demand
Production 22 18 21 22 22 20 21 22 20 23 19 20
days
SOLUTION
ILLUSTRATION 13: Given the data of Illustration 12, suppose the firm has determined that
to follow a plan of meeting demand by varying the size of the work force would result in
hiring and layoff costs estimated at Rs.12,000. If the units cost Rs.100 each to produce, the
carrying costs per year are 20 per cent of the average inventory value, and the storage costs
(based on maximum inventory) are Rs. 90 per unit, which plan results in the lower cost:
varying inventory, or varying employment?
*Incremental cost of OT = overtime cost – regular time cost = Rs. 9 – Rs. 6 = Rs. 3.
210 Operations Management
Table 8.27 Plan 3 (Use Inventory and Stockout Based on Constant 20-Worker Force)
Note that plan 3 assumes that a Stockout cost is incurred if safety stock is not maintained at
prescribed levels of 20 per cent of forecast. The firm is in effect managing the safety-stock level to
yield a specific degree of protection by absorbing the cost of carrying the safety stock as a policy
decision.
Summary
Plan 1: Rs. 10,500 hiring + Rs. 14,000 layoff = Rs. 24,500
Plan 2: Rs. 8,400 overtime + Rs. 28, 200 idle time = Rs. 36,600
Plan 3: Rs. 8,640 Stockout + Rs. 960 inventory = Rs. 9,600 (least-cost plan)
ILLUSTRATION 15: Use the data from Illustration 14 except modify as follows: Monthly
demand and number of workdays per month are as shown below, employees work 8 hours
per day, and time to produce one unit is 40 hours. Regular-time cost is (Rs.30 per hour) (40
hours per unit) = Rs.1,200 per unit, and subcontract time cost is (Rs.50 per hour) (40 hours
per unit) = Rs.2,000 per unit. Produce with a (minimal) constant work force of six workers on
regular time and subcontract to meet additional requirements.
SOLUTION
Table 8.28
(1) Month Jan. Feb. Mar. April May June July Aug. Sept. Total
(3) Workdays/mo 22 18 21 22 22 20 21 22 20
(5) Reg.-time prod. 26.4 21.6 25.2 26.4 26.4 24.0 25.2 26.4 24.0
[4] 740 hr/unit
(6) Units subcon’t 13.6 3.4 29.8 3.6 3.6 26.0 4.8 33.6 16.0
(2)-(3)
(7) Subcon’t cost 27,200 6,800 59,600 7,200 7,200 52,000 9,600 67,200 32.000 268,800
(6) (Rs.2,000)
(8) Reg.-time 31,680 25,920 30,240 31,680 31,680 28,800 30,240 31,680 28,800 270,720
cost(5)
(Rs.1,200)
The total cost of this plan is Rs. 268,800 + Rs. 270,720 = Rs. 539,520.
ILLUSTRATION 16: Idaho Instrument Co. produces calculators in its Lewiston plant and
has forecast demand over the next 12 periods, as shown in Table 8.29. Each period is 20
working days (approximately 1 month). The company maintains a constant work force of 40
employees, and there are no subcontractors available who can meet its quality standards. The
company can, however, go on overtime if necessary and encourage customers to back-order
calculators. Production and cost data follow.
Table 8.29
Period Units Period Units Period Units
1 800 5 400 9 1,000
2 500 6 300 10 700
3 700 7 400 11 900
Production capacity:
Initial inventory: 100 units (final included in period 12 demand)
RT hours: (40 employees)(20 days/period)(8 hr/day) = 6,400 hr/period OT hours:
(40 employees) (20 days/period) (4 hr/day) = 3,200 hr/period Standard labor hours per unit: 10 hr
Costs:
Labor: RT = Rs. 6/hr OT = Rs. 9/hr
Material and overhead: Rs. 100/unit produced
Back-order costs: apportioned at Rs. 5/unit-period (and increasing in reverse) Inventory carrying
cost: Rs. 2/unit-period
Assume that five periods constitute a full demand cycle, and use the transportation linear
programming approach to develop an aggregate plan based on the first five periods only. (Note: A
planning length of five periods is useful for purposes of methodology, but in reality the planning
horizon should cover a complete cycle, or else the plan should make inventory, personnel, and other
such allowances for the whole cycle.)
212 Operations Management
SOLUTION
RT capacity, avail. /period = 6,400 hr/10 hr/unit = 640 units
OT capacity, avail./period = 3,200 hr/10 hr /unit = 320 units
RT cost = (10 hr/unit)(Rs. 6/hr) + Rs. 100 mat's. And OH = Rs. 160/unit
OT cost =(10 hr/unit)(Rs. 9/hr)+Rs. 100 mat' I. And OH=Rs. 190/unit
Table 8.30
60 500 60 20 640
Overtime 195 190 192 194 196 0
320 320
Regular 170 165 160 162 164 80
Period 3
640 640
Overtime 200 195 190 192 194 0
320 320
Regular 175 170 165 160 162 60
Period 4
640 640
Overtime 205 200 195 190 192 0
320 320
Regular 180 175 170 165 160 60
Period 5
400 640
Regular 210 205 200 195 190 0
320 320
Demand 800 500 700 900 400 1600 4900
ILLUSTRATION 17: Taiwan Shoe Company schedules running shoe production in lot sizes
of 40 units (each of which consists of a carton of pairs). They have a beginning inventory of
45 units and have developed a forecast of demand as shown in Table 8.31. The company has
received orders for 22 units in week 1, 9 units in week 2, 4 units in week 3, 15 units in week
4, and 5 units in week 5. Set up a master production schedule, and find the ATP inventory
values for weeks 1 through 8.
Aggregate Planning and Master Scheduling 213
Period 1 2 3 4 5 6 7 8
Forecast 20 20 30 20 20 13 15 20
SOLUTION
Period 1 2 3 4 5 6 7 8
Available-to-promise 14 36 20 40
See Table 8.31. The period 1 balance is 45–22 (i.e., 22, because orders are larger than
forecast) = 23, and period 2 balance is 23 – 20 = 3. Period 3 balance would be a negative (3 – 30),
so a lot size of 40 goes into the MPS in week 3, resulting in a balance of (3 + 40) – 30 = 13.
For period 1, ATP = (On-hand Inv.) – (Orders in periods 1 and 2) = 45 – (22 + 9) = 14; and ATP3
= (MPS amount in 3) – (Orders for period 3) = 40 – (4) = 36. For week 4, ATP4 =
(MPS amount in 4) – (Orders for periods 4, 5 and 6) = 40 – (15 + 5) = 20.
EXERCISE
1. What is aggregate planning?
2. What is scheduling, and does it differ from aggregate planning?
3. What focused strategies are employed by production planners to meet nonuniform demands?
4. What are the major inputs to master production schedule?
5. What determines the planning horizon length (time span) of a master schedule?
6. How do firms accommodate changes in their master schedule?
7. What is meant by the terms (a) demand time fence and (b) planning time fence?
8. How does master scheduling differ under manufacturing strategies of (a) make-to-stock,
(b) assemble-to-order, and (c) make-to-order?
9. What is available-to-promise inventory, and it is determined?
10. Rainwear Manufacturing, Inc., produces outdoor apparel that has a demand projected to be as shown
in Table 8.32. The plant has a 2-week vacation shutdown in July, so the available production days per
month are 22, 19, 21, 21, 22, 20, 12, 22, 20, 23, 19, and 21, respectively.
214 Operations Management
Table 8.32
(a) Prepare a chart showing the daily production requirements. (b) Plot the demand as a histogram and
as a cumulative requirement over time. (c) Determine the production rate required meeting average demand,
and plotting this as a dotted line on your graph.
Ans. (a) Chart should show January through December daily demands of 200, 250, 300, 300, 200, 100, 100,
150, 250, 400, 400 and 350.
(b) Histogram should show cumulative production days on x-axis, production rate (units per day) on y-
axis. Cumulative requirement should show cumulative production days on x-axis and cumulative demand
(units) on y-axis.
(c) 255.4 units
11. The Speedee Bicycle Co. makes 3-speed bikes that sell for Rs. 100 each. This year's demand forecast
is shown in Table 8.33. Units not sold are carried in stock at a cost of 20 per cent of the average
inventory value per year, and storage costs are Rs. 2 per bike per year, based upon maximum inventory.
Table 8.33 Bike demand forecast
Units 30 120 60 70
(a) Plot the demand as a histogram on a quarterly basis, and show the average requirement as a dotted
line on your graph. (b) Assume Speedee wishes to maintain a steady work force and to produce at a uniform
rate (that is, with no overtime, back orders, subcontracting, or capacity changes) by letting inventories
absorb all fluctuations. How many bikes must they have on hand on January 1 in order to meet the forecast
demand throughout the year? (c) For an incremental amount of Rs. 400 in labor costs (total), Speedee can
vary its work-force size so as to produce exactly to demand. Compare the costs of producing at a uniform
versus variable rate, indicate which plan is less costly, and show the net difference in cost.
Ans. (a) Histogram should show quarters on x-axis and production rate (units per quarter) on y-axis. (b) 10
(c) Variable rate is Rs.50 per year less costly
12. An aggregate planner at Duotronix has estimated the demand requirements (Table 8.34) for forthcoming
work periods, which represent one complete demand cycle for them. The company is a "going concern"
and expects the next demand cycle to be similar to this one. Five plans are being considered.
Table 8.34
Plan 1: Vary the labour force from an initial capability of 400 units to whatever is required to meet
demand. See Table 8.35.
Aggregate Planning and Master Scheduling 215
Table 8.35
Amountof Incremental cost to change labour force
of change
Increase Decrease
200 units Rs. 9,000 Rs. 9,000
400 units 15,000 18,000
Plan 2: Maintain a stable work force capable of producing 600 units per period, and meet demand by
overtime at a premium of Rs. 40 per unit. Idle-time costs are equivalent to Rs. 60 per unit.
Plan 3: Vary inventory levels, but maintain a stable work force producing at an average requirement
rate with no overtime or idle time. The carrying cost per unit per period is Rs. 20.
Plan 4: Produce at a steady rate of 400 units per period and accept a limited number of back orders
during periods when demand exceeds 400 units. The Stockout cost of lost sales is Rs.110 per unit.
Plan 5: Produce at a steady rate of 200 units per period, and subcontract for excess requirements at a
marginal cost of Rs.40 per unit.
Graph the forecast in the form of a histogram, and analyze and relevant costs of the various plans. You
may assume the initial (period 1) work force can be set at a desired level without incurring additional cost.
Summarize your answer in the form of a table showing the comparative costs of each plan.
Ans. Graph shows period on x-axis and demand level on y-axis. Plan costs are as follows: plan 1 = Rs.
90,000, plan 2 = Rs. 140,000, plan 3 = Rs. 160,000, plan 4 = Rs. 220,000, plan
5 = Rs. 160,000.
5 shown in Table 8.36 is the expected demand for an end item X, which has a beginning inventory of 30
units. The production lot size is 70 units, and the firm maintains a safety stock of 5 units.
Table 8.36
Week number
1 2 3 4 5 6 7 8
Customer forecast 5 5 5 30 15 5 25 25
Service forecast – – 20 – – 20 – –
International orders – – – 30 – 25 – 40
Warehouse orders – 5 – 10 20 – 30 –
Complete a master schedule by determining the projected inventory balance, MPS entries, and the ATP
amounts.
216 Operations Management
REFERENCES
1. Joseph G. Monks, Theory and Problems of Operations Management, Tata McGraw-Hill
Publishing Company Limited, 2nd Edition, 2004.
2. Joseph G. Monks, Operations Management, McGraw-Hill International Edition, 3rd Edition.
3. S. Anil Kumar, N. Suresh, Production and Operations Management, New Age International
Publishers, 2nd Edition, 2008.
MATERIAL AND CAPACITY REQUIREMENTS
9
PLANNING (MRP AND CRP)
CHAPTER OUTLINE
9.1 MRP and CRP Objective 9.6 CRP Inputs and Outputs
9.2 MRP Inputs and Outputs 9.7 Loading
9.3 MRP Logic • Exercise
9.4 System Refinements • References
9.5 Safety Stock, Lot Sizing and System
Updating
• Dependent demand: Demand for a component that is derived from the demand for other
items.
• Parent and component items: A parent is an assembly made up of basic parts, or
components. The parent of one subgroup may be a component of a higher-level parent.
• Bill of materials: A listing of all components (subassemblies and materials) that go into an
assembled item. It frequently includes the part numbers and quantity required per assembly.
• Level code: The level on which an item occurs in the structure, or bill-of-materials format.
• Requirements explosion: The breaking down (exploding) of parent items into component
parts that can be individually planned and scheduled.
• Time phasing: Scheduling to produce or receive an appropriate amount (lot) of material so
that it will be available in the time periods when needed-not before or after.
• Time bucket: The time period used for planning purposes in MRP-usually a week.
• Lot size. The quantity of items required for an order. The order may be either purchased
from a vendor or produced in-house. Lot sizing is the process of specifying the order size.
• Lead-time offset: The supply time, or number of time buckets between releasing an order
and receiving the materials.
Figure 9.1 describes MRP and CRP activities in schematic form. Forecasts and orders are
combined in the production plan, which is formalized in the master production schedule (MPS). The
MPS, along with a bill-of-material (BOM) file and inventory status information, is used to formulate
the material-requirements plan. The MRP determines what components are needed and when they
should be ordered from an outside vendor or produced in-house. The CRP function translates the
MRP decisions into hours of capacity (time) needed. If materials, equipment, and personnel are
adequate, orders are released and the workload is assigned to the various work centers.
End items, such as TV sets, have an independent demand that is closely linked to the ongoing
needs of consumers. It is random but relatively constant. Dependent demand is linked more closely
to the production process itself. Many firms use the same facilities to produce different end items
because it is economical to produce large lots once the set-up cost is incurred. The components that
go into a TV set, such as 24-inch picture tubes, have a dependent demand that is governed by the lot
size. Dependent demand is predictable.
MRP systems compute material requirements and specify when orders should be released so
that materials arrive exactly when needed. The process of scheduling the receipt of inventory as
needed over time is time phasing.
(C 20) constitute a subassembly that is combined with base (A 10) and two springs (B 11) to
complete the end-item bracket (Z 100). However, the same clamp (C 20) is also a component of the
base (A 10). To facilitate the calculation of net requirements, the product tree has been restructured
from where the clamp components might have been (shown dashed) to the lower level consistent
with the other (identical) clamp. This low-level coding enables the computer to scan the product
structure level-by-level, starting at the top, and obtain an accurate and complete count of all
components needed at one level before moving on to the next.
Bill of materials for Z 100 bracket is shown below:
Be
Bill of Materials
Item: Z 100 Bracket Level 0
SINGLE-LEVEL BOM
Table 9.1 (a) depicts a single-level bill of materials for Z 100 bracket. It is a less intuitive but more
efficient means of storing the information on computer. In the single-level bill each entry (on the left)
contains only an item or part number followed by a list of the part numbers and quantities of components
needed to make up the parent item only. This type of listing avoids the searches for duplicate items
down through several levels of a tree. On the other hand, it necessitates that the computer search
through many single-level bills to find all the components that are included in a product that has several
levels of code. Single-level bills frequently contain “pointers” to link the records of components with
their parents and accommodate the retrieval of a complete bill of materials for an item.
Table 9.1 (b) Single-level BOM
Number Description
Zl00 Bracket
A10 (1) Base
B 11 (2) Spring
C20 (4) Clamp
Al0 Base
C20(1) Clamp
D21 (2) Housing
C20 Clamp
E30 (1) Handle
D21 Housing
F31 (2) Bearing
G32(1) Shaft
ILLUSTRATION 1: Determine the quantities of A10, B11, C20, D2l, E30, F3l, and G32
needed to complete 50 of the Z100 brackets depicted in Fig. 9.2.
SOLUTION
Table 9.2 Determining BOM requirements
Component Dependency Effect Requirements
A (base) 1A per Z 1
B (spring) 2B’s per Z 2
C (clamp) (IC per A)’ (IA per Z) + (4C’s per Z) 5
D (housing) (2D’s per A)’ (IA per Z) 2
E (handle) (IE per C) (IC per A)’ (IA per Z) + (IE per C)’ (4C’s per Z) 5
F (bearing) (2F’s per D) . (2D’s per A) . (IA per Z) 4
G (shaft) (IG per D) . (2D’s per A) . (lA per Z) 2
222 Operations Management
First determine the requirements for one bracket as shown in Table 9.2, and then multiply by 50.
Note that parts C and E are used in two different subassemblies, so their separate amounts must be
summed. For 50 brackets, each of the requirements column amounts must be multiplied by 50 to
obtain the gross requirements.
ILLUSTRATION 2: 1. Given the product structure tree shown in Figure 9.3 for wheelbarrow
W099, develop an indented bill of materials.
Fig. 9.3
Table 9.3
Bill of Materials
Item:0010 flashlight Level: 0
Part No. Description No. Level
1001 Head assembly 1 1
2001 Plastic head 1 2
4001 Plastic powder 1 4
2002 Lens 1 2
2003 Bulb assembly 1 2
3001 Bulb 1 3
3002 Bulb holder 1 3
2004 Reflector 1 2
1002 Batteries 2 1
I
1003 Body assembly 1 1'
2005 Shell assembly 1 2'
3903 On-off switch 1 3
4002 Knob 1 4
4003 Metal slides 2 4
3004 Connector bars 2 3
3005 Plastic shell 1 3
4001 Plastic powder 3 4
2006 Spring 1 2
Gross requirements are the total quantities needed to produce the 200 flashlights, whereas net
requirements are the quantities needed in addition to existing inventory levels (or scheduled receipts).
The net requirements must therefore take into account the components already assembled (or
hidden) in completed assemblies.
We shall first determine the gross requirements by taking account of all dependencies. For
example the gross requirements of connector bars (No. 3004) are (2 connector bars per shell
assembly) times (1 shell assembly per body assembly) times (1 body assembly per flashlight) times
(200 flashlights), or 2 × 1 × 1 × 200 = 400. See Table 9.5.
Then we complete the on-hand inventory by totaling both the individual stock items on hand plus
any units of the same item that are already in subassemblies or assemblies. For example, the on-
hand inventory of lenses consists of 12 lenses in stock plus 10 lenses already installed in the head
assemblies. Requirements will be computed on a level-by-level basis so that components used in
more than one subassembly (such as the plastic powder, no. 4001) can be combined.
224 Operations Management
Table 9.5
6. Planned-order release: The planned amount to be ordered in the time period adjusted by
the lead-time offset so that materials will be received on schedule. Once the orders are actually
released, the planned-order releases are deleted from the form and the planned-order receipts they
generated are changed to scheduled receipts.
The master production schedule dictates gross or projected requirements for end items to the
MRP system. Gross requirements do not take account of any inventory on hand or on order. The
MRP computer program then “explodes” the end-item demands into requirements for components
and materials by processing all relevant bills of materials on a level-by-level (or single-level) basis.
Net requirements are then calculated by adjusting for existing inventory and items already on order
as recorded in the inventory status file.
Net requirements = gross requirements – (on hand/available + scheduled receipts) … 9.1
Order releases are planned for components in a time-phased manner (using lead-time data from
the inventory file) so that materials will arrive precisely when needed. At this stage the material is
referred to as a planned-order receipt. When the orders are actually issued to vendors or to in-house
shops, the planned receipts become scheduled receipts. The inventory on hand at the end of a period
is the sum of the previous period on-hand amount plus any receipts (planned or scheduled) less the
gross requirements.
On hand/available = on hand at end of previous period + receipts – gross requirements …9.2
ILLUSTRATION 4: A firm producing wheelbarrows is expected to deliver 40 wheelbarrows
in week 1, 60 in week 4, 60 in week 6, and 50 in week 8. Among the requirements for each
wheelbarrow are two handlebars, a wheel assembly, and one tire for the wheel assembly.
Orders quantities, lead times, and inventories on hand at the beginning of period 1 are shown
in Table 9.6.
Table 9.6 BOM and inventory data for wheelbarrow components
*90 wheel assemblies are also needed in period 5 for a garden tractor shipment.
A shipment of 300 handlebars is already scheduled to be received at the beginning of week 2
(i.e., a scheduled receipt). Complete the MRP for the handlebars, wheel assemblies, and tires; and
show what quantities or orders must be released and when they must be released to satisfy the
master schedule.
SOLUTION: Table 9.7 depicts the master schedule and component part schedules. We shall assume
that the customer completes the final assembly, so no time allowance is required there. Note that
because each wheelbarrow requires two handlebars, the gross requirements for handlebars are
double the number of end products. Thus the gross requirements in period 1 are 40 × 2 = 80 units.
226 Operations Management
Table 9.7 Master schedule and MRP component plans for wheelbarrows
Master Week number 1 2 3 4 5 6 7 8
schedule
(wheelbarrow)
Quantity 40 60 60 50
Item ID: HB Gross requirements 80 120 120 100
Level code: 1 Scheduled receipts 300
On hand: 100 On hand/Available 20 320 320 200 200 80 80 280
Lot size: 300 Net requirements 20
LT (wk): 2 Planned-order receipts 300
Safety stock: 0 Planned-order release 300
* Requirements from another product (garden tractor) that uses the same wheel assembly.
The 100 handlebars on hand at the beginning of period 1 are adequate to supply the gross
requirement of 80 handlebars, leaving 20 on hand at the end of period 1. With the (scheduled)
receipt of 300 handlebars in period 2, the on-hand inventory remains adequate until the end of week
8, when 80 units are on hand. However, the gross requirement for 100 units in period 9 exceeds the
on-hand inventory. This results in net requirements (using Eq. 9.1) of 100 – 80 = 20 units.
To satisfy this, a planned-order receipt for the standard order quantity (300) is scheduled for the
beginning of period 8. In so far as the handlebars have a 2 week lead-time, the planned order for the
handlebars must be released 2 weeks earlier (week 6). The planned order receipt will result in a
projected end-of-period on-hand inventory (using Eq. 9.2) of 80 + 300 – 100 = 280 units.
Material and Capacity Requirements Planning (MRP and CRP) 227
2. Variable lead times from suppliers are a common source of uncertainty to many firms.
3. Firms may experience machine breakdowns, scrap losses, and last-minute customer changes.
Lot sizing: Order quantities are not always specified in advance. Different lot-sizing methods
are in use, they are (1) fixed-order quantity amounts, e.g., 300 handlebars; (2) EOQ or ERL amounts;
(3) lot for lot, which is ordering the exact amount of the net requirements for each period; (4) fixed-
period requirements, e.g., a 2-month supply; and (5) various least-cost approaches, e.g., least-unit
cost, least-total cost.
The part-period algorithm is a method that uses a ratio of ordering costs to carrying costs per
period, which yields a part-period number. Then requirements for current and future periods are
cumulated until the cumulative holding cost (in part-period terms) is as close as possible to this number.
System updating: MRP system designs typically use one of two methods to process data,
update files, and ensure that the system information is valid and conforms with actual: (1) regenerative
processing or (2) net change processing.
Regenerative MRP systems: use batch processing to replan the whole system (full explosion
of all items) on a regular basis (e.g., weekly).
Net change MRP systems: are online and react continuously to changes from the master
schedule, inventory file, and other transactions.
Early MRP installations were largely of the regenerative type, but then as net change systems
became perfected, more firms began installing them. However, being “activity driven,” net change
systems are sometimes “nervous” and tend to overreact to changes. The major disadvantage of
regenerative systems is the time lag that exists until updated information is incorporated into the system.
System application: Although MRP systems are widely used, they are most beneficial in
manufacturing environments where products are manufactured to order, or assembled to order or to
stock. MRP does not provide as much advantage in low-volume, highly complex applications or in
continuous flow processes, such as refineries. It does, however, enjoy wide application in metals,
paper, food, chemical, and other processing applications.
Demand in period
Products
1 2 3 4 5 6 7 8
X 50 300 200 250
Y 30 400
Material and Capacity Requirements Planning (MRP and CRP) 229
Y 0
A 1
B 1
D 2
Next, set up an MRP format for all items (see Table 9.9), and enter the end-item gross
requirements for X and Y. They both have low-level codes of 0 and so can be netted out using order
quantities that match their requirements (preserving safety stocks, of course). This results in planned-
order releases of 200 and 250 units for X (periods 4 and 6) and 400 units of Y (period 4).
Next, explode the planned-order releases for X and Y (that is, multiply them by the quantities
required of the level l items, A and B). (Note that C and D are not level l items.) Projected requirements
for A (200 and 250 units) are direct results of the planned-order releases for X. Two units of B are
required for each X, so item B’s projected requirements in periods 4 and 6 are 400 and 500,
respectively. Items A and B are then netted, and the order release dates and amounts are set.
Next, explode the level 2, planned-order releases to the level 3 items. The arrows in Table 9.9 show
that requirements for C and D come from planned-order releases for both B and Y. End item Y requires
4 units of D, so the projected requirements in period 4 are 2,100 units, with 1,600 from Y (that is, 4 × 400)
and 500 from B. Together, they generate a planned-order release for 2,000 units of D in period 2.
230 Operations Management
Table 9.9
Week number 1 2 3 4 5 6 7 8
Item ID: X Gross requirements 300 300 200
Level code: 0 Scheduled receipts
On hand: 100 On hand/Available 50 50 50 50 50 50 50 50
Lot size: LFL Net requirements 150 200
LT (wk): 2 Planned-order receipts 200 250
Safety stock: 50 Planned-order releases 300 250
contd.
Material and Capacity Requirements Planning (MRP and CRP) 231
9.7 LOADING
There are two basic techniques for planning the control of a production system. One of these is
loading; the other is scheduling. Of the two loading is the easier to do. But scheduling can give more
control and is more detailed, although it is usually done for a shorter time period. A load is the
amount of work assigned to a facility work centre or operator, and loading is the assignment of
work. Loading does not specify the sequence in which the work is done or when it is to be done.
Loading is the aggregate assignment of jobs to specific entities. Inputs necessary for loading include:
232 Operations Management
• Routing
• Standard hours per operation or work centre
• Gross machine/man-hour available
• Efficiency factors
• Due date.
Loading is closely tied to capacity planning in the sense that loading is the first indication that
capacity levels need adjusting.
2. Develop efficiency factors by load centers 5. Load schedule orders into load centers
3. Determine capacity by centers 6. Unload completed hours
Step 1: The first step in machine loading is to choose the load centers. Some companies load by
department only if all the machines are interchangeable. When different machine centers within the
department have different capacities, the typical approach is to break the machines down into
similar machine groups. For example, all 24 inch boring machines might be included in the same
group, if jobs are interchangeable among the machines. The trend is to group as many machines
together as possible since doing so will reduce the complexity of the loading problem and tend to
stabilize the load.
Step 2: The second step is to develop efficiency factors by load centers/work stations. A load
center with two people is theoretically capable of 80 hours of production per week, but actual output
might be considerably less than 80 hours of production per week, indirect activities, or other non-
value adding activities. If they are working on incentives, they could be turning out more than 80
standard hours of production.
Step 3: The third step is to determine the gross capacity by load centers. This capacity is either
human or machine dependent. A center is machine dependent if all machines have at least one
operator assigned. A center is human dependent if there are more workers than machines and
machine stand idle while all workers are busy. With the number of people or machine as an input, the
gross capacity is the gross number of hours that the resources are available per planning period. The
center’s capacity is then the gross capacity times of the efficiency factor.
Step 4: The fourth step is to choose the loading method, which may be either to finite or to
infinite capacity. Infinite capacity loading means showing the work for a work center in the time
Material and Capacity Requirements Planning (MRP and CRP) 233
period required, regardless of the work center’s capacity. Finite capacity loading means putting no
more work into a work center than it can be expected to execute.
Step 5: The fifth step is to load the scheduled orders into the load centers while at the same
time considering the capacity and other restrictions.
Step 6: The sixth step is to select the unloading technique. Unloading is the process of removing
the planned work from the work center load as jobs are partially or totally completed. Manual
systems may require shortcuts, such as considering a job to be completed when the first lot of pieces
is reported. This saves posting many partial lots and recalculating load balances, but the load is
always understated by the number of hours remaining on jobs unloaded. Another short-cut relieves
the load only when the last lot is completed, giving a load constantly overstated by the hours completed
but not removed. The number of hours to be unloaded must be equal to the number of hours loaded
for each job.
A work center load, based on the actual work order released, is a good short-tenn technique for
highlighting the under load or overloads on work centers and showing the need for overtime, temporary
transfer, subcontracting or other short-range adjustments.
Companies have successfully used computer machine loads over longer planning periods to
assist capacity planning. Forecasts of individual finished products to be manufactured during this
period can be exploded into detailed requirements of production hours for each of major work
centers. The machine hours based on these aggregate hours will give dependable data on the average
capacity required to meet the forecasted demand on manufacturing facilities.
The work may be assigned by the nature of the job. If the work can be done by more than one
center, it must be assigned to just one. If it can be done by only one work center, then there is no
alternative, but to one work center. The work may be assigned on an individual job basis, but if the
jobs are repetitive, they may be assigned on a standard basis by the use of routings. Standard
routings shows all operations that must be done to make the part or assembly. If the standard
routings are not available, someone must assign the individual jobs to the facilities and must estimate
the work content of the assignments. The work contents must be in terms that are comparable
between jobs. Measures that can be used are hours, pieces, batches, gallons and so on per hour, per
shift, per day and so on.
Work assignments must be accumulated by the facility in order to calculate the load on each
facility. One method is to use a ledger in which the job members and job loads are entered by each
facility. When the job is completed, it is marked off. The jobs are then added periodically to obtain
the load on the facility.
Another method is to accumulate the assignments in ‘buckets’ one bucket for each facility. The
bucket may be box, a file, a peg and so on. A ticket is prepared for each job assigned to the facility
and is placed in the bucket. A perpetual total of the facility load may be kept for each bucket. Job
tickets, as added to the bucket are added to this total. When completed and removed from the
bucket, they are deducted from the total. If a computer is available, bucket may be computer file. If
standard routings are available, these can be kept as computer files.
EXERCISE
1. (a) What is meant by “time phasing” (b) What is a “time bucket”?
2. (a) Why is the BOM file sometimes called a product structure tree? (b) Suppose a 5-level BOM has
one subassembly (AX205) on level 2 and another (BY407) on level 4. Which subassembly has a level
code nearest the end item?
3. Why do MRP programs use single-level BOMs?
4. What is the advantage of low-level coding?
5. What are the three essential sources of data for an MRP program?
6. What must take place to change a planned-order release to a scheduled receipt?
7. By using a time-phased plan for component inventories, a firm can reduce average inventory levels
from 105 units to 42.5 units. If the average component value is Rs.12 and the reduction applies to
4,000 components, how much of a saving would result? Use inventory-carrying costs of 30 per cent
per year.
8. Determine the net requirements for the three items shown in table.
Material and Capacity Requirements Planning (MRP and CRP) 235
Gross requirements 55 14 28
On-hand Inventory 18 2 7
Components A B C D E
Inventory on hand and on order 20 10 15 30 100
REFERENCES
1. Everett, E. Adam, Jr. Ronald J. Ebert, Production and Operations Management, Prentice-
Hall of India Private Limited, 5th Edition, 1994.
2. R. Pannerselvam, Production and Operations Management, Prentice-Hall of India Private
Limited, 9th print, 2004.
3. Joseph, G. Monks, Theory and Problems of Operations Management, Tata McGraw-Hill
Publishing Company Limited, 2nd Edition, 2004.
4. Joseph G. Monks, Operations Management, McGraw-Hill International Edition, 3rd Edition.
5. S. Anil Kumar, N. Suresh, Production and Operations Management, New Age International
Publishers, 2nd Edition, 2008.
This page
intentionally left
blank
SCHEDULING AND CONTROLLING PRODUCTION
10
ACTIVITIES
CHAPTER OUTLINE
10.1 Introduction 10.10 CDS Heuristic
10.2 Concept of Single Machine Scheduling 10.11 Job Shop Problem
10.3 Measures of Performance 10.12 Types of Schedules
10.4 Shortest Processing Time (SPT) Rule 10.13 Heuristic Procedures
10.5 WSPT Rule 10.14 Priority Dispatching Rules
10.6 Earliest Due Date (EDD) Rule 10.15 Two Jobs and M Machines Scheduling
10.7 Minimizing the Number of Tardy Jobs • Exercise
10.8 Flow Shop Scheduling • References
10.9 Johnson's Problem
10.1 INTRODUCTION
Scheduling is the allocation of starts and finish time to each particular order. Therefore scheduling
can bring productivity in shop floor by providing a calendar for processing a set of jobs.
The single machine-scheduling problem consists of n jobs with the same single operation on
each of the jobs, while the flow shop-scheduling problem consists of n jobs with m operations on
each of the jobs. In this problem, all the jobs will have the same process sequences. The job shop-
scheduling problem contains n jobs with m operations on each of the jobs; but, in this case, the
process sequences of the jobs will be different from each other.
Under these conditions, one can see one-to-one correspondence between a sequence of the n
jobs and a permutation of the job indices 1, 2, ... n. The total number of sequences in the basic single
machine problem is n! which is the number of different permutation of n elements. The following
three basic data are necessary to describe jobs in a deterministic single machine-scheduling problem.
Processing time (tj ): It is the time required to process job j. The processing time, tj will
normally include both actual processing time and set-up time.
Ready time (rj ): It is the time at which job j is available for processing. The ready time of a job
is the difference between the arrival time of that job and the time at which that job is taken for
processing. In the basic model, as per condition I, rj = 0 for all jobs.
Due date (dj ): It is the time at which the job j is to be completed.
Completion time (Cj ): It is the time at which the job j is completed in a sequence. Performance
measures for evaluating schedules are usually function of job completion time. Some, sample
performance measures are Flow time, Lateness, Tardiness, etc.
Flow time (Fj ): It is the amount of time job j spends in the system. Flow time is a measure,
which indicates the waiting time of jobs in a system. This in turn gives some idea about in-process
inventory due to a schedule. It is the difference between the completion time and the ready time of
the job j. i.e. Fj = Cj – rj.
Lateness (Lj): It is the amount of time by which the completion time of job j differs from the
due date (Lj = Cj – d). Lateness is a measure which gives an idea about conformity of the jobs in a
schedule to a given set of due dates of the jobs. Lateness can be either positive lateness or negative
lateness. Positive lateness of a job means that the job is completed after its due date. Negative
lateness of a job means that the job is completed before its due date. The positive lateness is a
measure of poor service. The negative lateness is a measure of better service. In many situations,
distinct penalties and other costs are associated with positive lateness, but generally, no benefits are
associated with negative lateness. Therefore, it is often desirable to optimize only positive lateness.
Tardiness (Tj ): Tardiness is the lateness of job j if it fails to meet its due date, or zero, otherwise
T j = max {O, Cj – dj}
= Max {O, Lj }.
1 n
Mean tardiness: T = n ∑ T j
j =1
Max{Fj }
Maximum flow time: Fmax = 1≤ j ≤ n
Max{T j }
Maximum tardiness: Tmax = 1≤ j ≤ n
Scheduling and Controlling Production Activities 239
where
f (Tj) = I, if Tj > 0, and f (Tj) = 0, otherwise.
Job (j) 1 2 3 4 5
Find the optimal sequence, which will minimize the mean flow time and also obtain the
minimum mean flow time.
SOLUTION
No. of jobs = 5
Arrange the jobs as per the SPT ordering
Job (j) 2 3 5 4 1
Therefore, the job sequence, which will minimize the mean flow time, is 2-3-5-4-1.
Computation of Fmin
Job (j) 2 3 5 4 1
Since, the ready time rj = 0 for all j, the flow time (Fj) is equal to Cj for all j.
1 n 1 1
F = ∑ Fj = 5 (4 + 9 + 17 + 31 + 46) = 5 (107) = 21.4 hours
n j =1
Therefore, the optimal mean flow time = 21.4 hours.
240 Operations Management
∑w
j =1
j ⋅ Fj
Fw = n
∑w
j =1
j
In single machine scheduling problem, sequencing the jobs in increasing order of weighted
processing time is known as Weighted Shortest Processing Time (WSPT) sequencing. The weighted
processing time of a job is obtained by dividing its processing time by its weight.
I LLUSTRATION 2: Consider the following single machine-scheduling problem with weights:
Job (j) 1 2 3 4 6
Weight (w) 1 2 1 2 3
Determine the sequence, which will minimize the weighted mean flow time of the above
problem. Also find the weighted mean flow time.
SOLUTION
Job (j) 1 2 3 4 5
Weight (wj) 1 2 1 2 3
T/wj 15 2 5 7 2.67
Arrange the jobs in the increasing order of tj / wj (i.e. WSPT ordering). From the above table,
we get the following relation.
t2/w2 ≤ t5/w5 ≤ t3/w3 ≤ t4/w4 ≤ t1/w1
Therefore optimal sequence, which will minimize the weighted mean flow time, is,
2 – 5 – 3 – 4 – 1.
Fw Calculation:
Job (j) 2 3 5 4 1
Tj 4 5 8 14 15
Cj (Fj) 4 9 17 31 46
Fj * W j 4 9 17 31 46
Scheduling and Controlling Production Activities 241
∑ w .F
j =1
j j
(8 + 36 + 17 + 62 + 46) 169
Fw = = = = 18.78 hours.
n
(2 + 3 + 1 + 2 + 1) 9
∑w j =1
j
Job (j) 1 2 3 4 5 6
Determine the sequence which will minimize the maximum lateness (Lmax). Also, determine Lmax
with respect to the optimal sequence.
SOLUTION: Arrange the jobs as per EDD rule (i.e. in the order of their due dates). The EDD
sequence is 2-4-3-1-5-6.This sequence gives a minimum value for Lmax.
Lateness (Lj) –2 4 11 18 27 35
From the table, the maximum is 35. This is the optimal value for Lmax. The Lmax of any other non-
EDD sequence will not be less than 35.
If the EDD sequence yields zero tardy, or it yields exactly one tardy job, then it is an optimal
sequence for minimizing the total number of tardy jobs (NT), If it yields more than one tardy job, the
EDD sequence may not yield the optimal solution. An exact algorithm for the general case is given
below. The final sequence consists of two streams of jobs as given below:
(a) First, a set (E) of early jobs, in EDD order.
(b) Then, a set (L) of late jobs, in any order.
This algorithm gives optimal sequence, which will result in minimum number of tardy jobs (NT).
HODGSON’S ALGORITHM TO MINIMIZE NT
Step 1: Arrange the jobs in EDD order and assume this, as set E. Let set L be empty.
Step 2: If no jobs in E are late, then stop. Find the union of E and L (Note: The remaining jobs in
E should be in EDD order. But the jobs in L can be in any order); otherwise, identify the first late job
in E. Let it be job K.
Step 3: Identify the longest job, among the first K jobs in the sequence. Remove this job from E
and place it in L. Revise the completion times of the jobs remaining in E and return, to Step 2.
This algorithm is demonstrated using the following problem.
ILLUSTRATION 4 A computer systems consulting company is under contract to carry out
seven projects, all with deadliness assured in days from now. The consultants are a small
group and they work together on each project, so that the project will be started and completed
sequentially. Under the terms of contract, the consultants will receive Rs. 24,000 for each
project completed on time, but they will incur Rs. 40,000 in penalties for each project completed
late. Each project has an, associated duration, which is the anticipated number of days
required to carry out the project as shown below.
How should the projects be sequenced in order to maximize net revenues?
Project ID 1 2 3 4 5 6 7
Duration (Dj) 2 4 6 8 10 12 14
Deadlines (d) 6 12 30 19 12 18 24
SOLUTION: From the statement of the problem, one can identify that the objective is to maximize
net revenues. This can be achieved by simply obtaining a sequence, which will minimize the number
of tardy jobs (NT), Hence, we apply Hodgson’s algorithm to minimize NT.
Step 1: The earliest due date order is shown below:
a ij 2 12 12 18 19 24 30
Project (j) 1 2 5 6 4 7 3
Place the above sequence of projects which is in EDD order in set E. Therefore,
Set E = (1, 2, 5, 6, 4, 7,3)
Set L = (Empty).
Scheduling and Controlling Production Activities 243
Duration (tj) 2 4 10 12 8 14 6
Tardy/non-tardy (1/0) 0 0 1 1 1 1 1
In the above table, in the last row, 0 means that the project is non-tardy and 1 means that the
project is tardy.
As per the sequence in the set E, there are five tardy projects. The first tardy project is 5, which
is in the third position [3].
Step 3: The project with the largest duration among the first-three projects in the sequence is 5.
Remove this project and append it to L. Therefore
L = {5}
E = {1, 2, 6, 4, 7, 3}.
The completion times of the projects in the set E are revised as shown below:
Project (j) 1 2 6 4 7 3
Duration (t) 2 4 12 8 14 6
Tardy/non-tardy 0 0 0 1 1 1
Step 2: From Step 3, it is clear that there are three tardy projects. The first tardy project is 4,
which is in the fourth position of the sequence in the set E.
Step 3: The project with the longest duration among the first-four projects is 6. Remove the
project-6 from the set E and append it to the set L. Therefore
E = {1, 2, 4, 7, 3}
L = {5, 6}.
The completion times of the projects in the set E are revised as shown:
Project (j) 1 2 4 7 3
Duration (tj) 2 4 8 14 6
Tardy/non-tardy 0 0 0 1 1
244 Operations Management
Step 2: From the table shown in Step 3 it is known that there are two tardy projects. The first
tardy project is 7, which is at the fourth position in the set E.
Step 3: The project with the longest duration. Among the first-four projects in the set E are 7.
Remove this job from the set E and append it to the set L.
E = {1, 2, 4, 3}
L = {5, 6, 7}.
The completion times of the projects are revised as shown below:
Project (j) 1 2 4 3
Duration (t) 2 4 8 6
Tardy/non-tardy 0 0 0 0
Step 2: From the table in the previous step, it is clear that all the projects are non-tardy jobs.
Hence, we reached the optimal sequence in E.
Now merge E and L to get the complete sequence.
Final sequence = E L={1,2,4,3,5,6,7}
In the above optimal sequence, total number of tardy projects is 3, which is the minimum value.
4 7 8
If the sequence of the job is 2-1-4-3, then the corresponding makespan is computed as shown in
Fig.10.1. Here the makespan is 25. Also, note the inserted idle times on machine 2 are from 0 to 3,
4 to 8 and 12 to 15.
Machine 2
Machine 1
JFJ
Machine 2
Machine 1
In the above two sequences, 2-1-4-3 and 3-4-1-2, the first sequence has lesser makespan. Like
this, one can enumerate all 4! sequences, then select the sequence with the minimum makespan as
the optimal sequence. Since, n! grows exponentially with n, one needs some efficient procedure to
solve the problem. For large size of n, it would be difficult to solve the problem. Under such situation
we can use some efficient heuristic.
In the above table, tij represents the processing time of the job i on the machine j.
SOLUTION: The workings of the algorithm are summarized in the form of a table, which is shown
below:
Stage Unscheduled jobs Minimum tik Assignment Partialsequence
1 1, 2, 3, 4, 5, 6 T42 4 = [6] ×××××4
2 1, 2, 3, 5, 6 T21 2 = [1] 2 ××××4
3 1, 3, 5, 6 T12 1 = [5] 2×××14
4 3, 5, 6 T51 5 = [2] 25××14
5 3, 6 T62 6 = [4] 25×614
6 3 T31 3 = [3] 253614
The optimal sequence is 2-5-3-6-1-4. The makespan is determined as shown below. In the
following table:
[Time-in on M/c 2 = max [M!c 1 Time-out of the current job, M/c 2 Time-out of the previous job]
Processing time Idle time
Job Machine 1 Machine 2 on machine
Time-in Time-out Time-in Time-out
2 0 2 2 5 2
5 2 10 10 19 5
3 10 23 23 37 4
6 23 35 37 48 0
1 35 40 48 52 0
4 40 50 52 53 0
One can extend Johnson’s algorithm to the problem shown in Table 10.1 if anyone of the following
two conditions is satisfied.
If min ti1 ≤ max ti2
or if min ti3 ≤ max ti2
If anyone of the above conditions is satisfied then, we can extend the Johnson’s algorithm in the
following way.
Create a hypothetical problem with two machines and n jobs as shown in Table 10.2.
The objective is to obtain optimal sequence for the data given in the Table 10.2. Later, the
makespan is to be determined for the optimal sequence by using the data of the original problem
shown in table.
This concept of extending Johnson’s algorithm to this type of problem is demonstrated using an
example problem.
Table 10.2 Hypothetical problem for the problem in Table 10.1
Job M/c c–A M/c c–B
1 t11 + t12 t12 + t13
2 t21 + t22 t22 + t23
3 t31 + t32 t32 + t33
. .
i ti1 + ti2 ti2 + ti3
. .
n tn1 + tn2 tn2 + tn3
ILLUSTRATION 6: Consider the following 3 machines and 5 jobs flow shop problem:
Processing time
Job M/c–1 M/c–2 M/c–3
1 8 5 4
2 10 6 9
3 6 2 8
4 7 3 6
5 11 4 5
SOLUTION
In the above table,
Min (til)=6 Max (ti2) = 6
Since the condition min (ti l) ≤ max (ti 2) is satisfied, we can extend the Johnson’s algorithm to
this problem. So the modified problem may be given as follows:
Job Machine A Machine B
1 13 9
2 16 15
3 8 10
4 10 9
5 15 9
Scheduling and Controlling Production Activities 249
3 0 6 6 8 8 16 6 8
2 6 16 16 22 22 31 8 6
5 16 27 27 31 31 36 5 0
1 27 35 35 40 40 44 4 4
4 35 42 42 45 45 51 2 1
ILLUSTRATION 6: Find the makespan using the CDS heuristic for the following flow shop
problem:
Job j t j1 t j2 t j3 t j4
1 4 3 7 8
2 3 7 2 5
3 1 2 4 7
4 3 4 3 2
SOLUTION
Job (j) M/c–1 tj1 M/c–1 tj2
1 4 8
2 3 5
3 1 7
4 3 2
Stage 2
Job (j) M/c–1 M/c–2
T j1 t j2
1 7 15
2 10 7
3 3 11
4 7 5
After applying Johnson's algorithm to the above problem, we get the sequence, 3-1-2-4. The
makespan calculation is summarized in the following table:
Scheduling and Controlling Production Activities 251
4 10 9
The application of Johnson’s algorithm to the above data yields the sequence 3-2-1-4. The
determination of the corresponding makespan is shown below:
M/c–1 M/c–2 M/c–3
Job
In Out In Out In Out
3 0 1 3 7 7 14
2 1 4 11 13 14 19
1 4 8 14 21 21 29
4 8 11 21 24 29 31
stage sequence Makespan
1 3-2-14 31
2 3-1-2-4 30
3 3-2-1-4 31
The time complexity function of the job shop problem is combinatorial in nature. Hence, heuristic
approaches are popular in this area.
Unlike the flow shop model, there is no initial machine that performs only the first operation of
a job nor there is a terminal machine that performs only the last operation of a job.
In the flow shop, an operation number in the operation sequence of a job may be same as the
position number of the required machine. Hence, there is no need to distinguish between them. But,
in the job shop case, different jobs will have different operation sequences. So, we cannot assume a
straight flow for the job shop problem. Each operation j in the operation sequence of the job i in the
job shop problem will be described with triplet (i, j, k) where k is the required machine for processing
the jth operation of the ith job.
Consider the following data of a job shop scheduling involving four jobs, three operations and
hence three machines.
The first table consists of operation processing times and the second table consists of operation
(process) sequences of the jobs. The set of machines required for a given job constitute a routing.
For example, job 4 has a routing of 1-3-2.
Processing times (hrs) Routing
Operations Operations
1 2 3 1 2 3
Job 1 2 3 4 Job 1 1 2 3
Job 2 4 4 1 Job 2 3 2 1
Job 3 2 2 3 Job 3 2 3 1
Job 4 3 3 1 Job 4 1 3 2
operation on n different machines. In the former case, where the completion of an earlier operation
on the same machine is constrained, it may still be possible to find obvious means of improvement.
Even when no local-shifts are possible, a better schedule can obviously be devised by shifting
operations to the left and beyond other operations already scheduled on some machine. This type of
adjustment in which some operation. is begun earlier without delaying any other operation is called
a global left-shift or simply a left-shift. The set of all schedules in which no global left-shift can
be made is called the set of active schedules. It is clearly a subset of the set of semi-active schedules.
The set of active schedules dominates the set of semi-active schedules in terms of optimizing
any regular measure of performance. So it is sufficient to consider only active schedules.
If no machine is kept idle at a time when it could begin processing some operation then it is
called a non-delay schedule. We can identify a subset of schedules from the set of active schedules
satisfying this property, which is known as a set of non-delay schedules.
All non-delay schedules are active schedules, since no left-shift is possible. There is no guarantee
that the non-delay subset will contain an optimum. The Venn diagram showing the relative sizes
between different types of schedules is shown in the following Fig. 10.3. There will be at least one
optimal schedule in the set of active schedules.
All
S-A
Note:
A All–All the schedules
S–Sem-active Schedules
ND A–Active schedules
ND–Non-delay schedules
Step 3: For each operation which belongs to S, that requires machine m* and satisfies the condition
Pj < q*, identify an operation according to a specific priority and add this operation to PI as early as
possible, thus creating only one partial schedule, PI +1 for the next stage.
Step 4: For each new partial schedule PI + 1 created in Step 3, update the data set as follows:
(a) Remove operation j from SI.
(b) Form SI + I by adding the direct successor of operation j to SI.
(c) Increment t by one.
Step 5: Repeat from Step 2 to Step 4 for each PI + 1 created in Step 3 and continue in this manner
until all active schedules are generated.
Similarly, another heuristic can be devised from the non-delay schedule generation algorithm by
replacing the condition Pj < q* with Pj = p* in Step 3. These two heuristic algorithms (one for
active dispatching and the other for non-delay dispatching) may construct different schedules. The
quality of the solution obtained by these heuristics mainly depends on the effectiveness of priority
rules which are used in them.
A sample set of priority rules are presented below:
(a) SPT (shortest processing time): Select the operation with the minimum processing time.
(b) FCFS (first come first served): Select the operation that entered SI earliest.
(c) MWKR (most work remaining): Select the operation associated with the job having the
most work remaining to be processed.
(d) MOPNR (most operations remaining): Select the operation that has the largest number
of successor operations.
(e) LWKR (least work remaining): Select the operation associated with the job having the
least work remaining to be processed.
(f) RANDOM (Random): Select the operation at random.
ILLUSTRATION 8: Use graphical method to minimize the time needed to process the following
jobs on the machines shown (i.e. for each machine, find the job which should be scheduled
first). Also, calculate the total time elapsed to complete both jobs.
Job 1 Sequence A - B - C - D - E
Time (hrs). 3 4 2 6 2
Job 2 Sequence B - C - A - D - E
Time (hrs) 5 4 3 2 6
SOLUTION: As per the procedure stated, the above data is presented in the form of a graph as
shown in Figure 10.4.
The line from the origin to the top right corner shows the processing details and makespan. The
makespan (time taken to complete both the jobs) is 22 hours. The start and completion times for both
jobs are given in Table 10.2.
Start and completion times of jobs
E 20 22 E 14 20
Job 1
20
E E
14
D D
12
A
A
9
C C
5
B B
Job 2
0 3 7 9 15 17
A B C E F
Fig. 10.4 Schedule for 2 jobs and % machines
256 Operations Management
Based on Figure and Table one can easily observe that the total idle for job1 is 5 hours (2+3).
Hence the total for completing the job 1 is its sum of the processing times plus its idle time, i.e.
17 hrs + 5hrs = 22 hrs.
For job 2, there is no idle time. Hence the total time taken to complete the job 2 is its sum of the
processing times, i.e. 20 hrs.
The makespan is the maximum of these two quantities.
Therefore, Max (22,20) = 22 hrs.
EXERCISE
1. Briefly discuss different measures of performance in single machine scheduling with independent
jobs.
2. Consider the following problem in single machine scheduling with independent jobs.
job 1 2 3 4 5 6 7 8
Processing time (tj) 5 12 8 10 3 15 8 6
Due date (dj) 10 16 11 16 6 25 12 14
Weight (wj) 2 1 1 2 3 4 2 3
Obtain the optimal schedule for each of the following performance measures:
(a) To minimize mean flow time.
(b) To minimize the maximum lateness.
(c) To minimize weighted mean flow time.
3. Distinguish between single machine scheduling and flow scheduling.
4. What are the assumptions in flow shop scheduling?
5. Consider the following two machines and 6 jobs flow shop problem.
Find the optimal schedule for the above flow shop problem using branch and bound technique. Also,
determine the corresponding makespan.
8. Explain the following:
(a) Active-schedule.
(b) Semi-active schedule.
(c) Non-delay schedule.
9. Write short notes on dispatching rules.
10. Use graphical method to minimize the needed to process the following jobs on the machines shown
(i.e. for each machine find the job which should be scheduled first). Also, calculate the total time
elapsed to complete both jobs.
Job 1 Sequence A - B - C - D - E
Time (hrs) 2 6 5 4 7
Job 2 Sequence C - B - D - A - E
Time (hrs) 6 5 7 4 8
REFERENCES
1. Everett, E. Adam, Jr. Ronald J.Ebert, Production and Operations Management, Prentice-
Hall of India Private Limited, 5th Edition, 1994.
2. R.Pannerselvam, Production and Operations Management, Prentice-Hall of India Private
Limited, 9th print, 2004.
3. Joseph, G.Monks, Theory and Problems of Operations Management, Tata McGraw-Hill
Publishing Company Limited, 2nd Edition, 2004.
This page
intentionally left
blank
GLOSSARY
ABC classification: Classification of inventory into three groups: an A group comprising items with a large
dollar volume; a B group comprising items with moderate volume and moderate dollar volume; and a C
group comprising items with a large volume and small dollar volume.
Acceptance number: The number of sample units specified in a sampling plan that must conform to specifications
if the shipment is to be accepted.
Acceptance sampling: A statistical quality control technique used in deciding to accept or reject a shipment of
input or output.
Accounting life: Length of an asset’s life determined for the purpose of a depreciation schedule.
Action bucket: In the MRP record for the current week, a cell calling for immediate action to meet the MPS goal.
Activity: In PERT, project work needed to be accomplished, symbolized by an arc.
Activity charts: A graphic tool to analyze and time the small, physical actions of worker and machine in
performing a routine, repetitive, worker-machine task so that idle time can be identified.
Adaptive exponential smoothing: An average method in which a smoothing coefficient is not fixed but is set
initially and then allowed to fluctuate over time based upon changes in the demand pattern.
Aggregate capacity planning: The process of testing, the feasibility of aggregate output plans and evaluating
overall capacity utilization.
Aggregate output planning: The process of determining output levels (units) of product groups over the
coming 6 to 18 months on a weekly or monthly basis; the plan identifies the overall level of outputs in
support of the business plan.
Allocated quantity: The quantity of an item in inventory that has been committed for use and is not available to
meet future requirements.
Allowance fraction: The fraction of time lost on a job because of workers’ personal needs, fatigue, and other
unavoidable delays; the remaining fraction of time is the available fraction.
Andon: A warning light used as a visible control technique in total quality control.
Applied research: Research for the advancement of scientific knowledge that has specific commercial uses.
Appraisal costs: Costs of evaluating, measuring, or inspecting for quality at the plant and in the field.
Arc: In network modeling, an arrowed line segment; the symbol for a project activity.
Assembly line technology: A process technology suitable for a narrow range of standardized products in high
volumes.
260 Operations Management
Assignment algorithm: A linear program to assign jobs so that a specific criterion is optimized.
Attribute characteristic: A product characteristic that can be measured by a rating of good or bad.
Available fraction of time: The fraction of time remaining after accounting for time lost on a job because of
worker’s personal needs, fatigue, and other unavoidable delays.
Available quantity: The quantity of an item expected to be: available at the end of a time period to meet
requirements in succeeding periods. Calculated as scheduled receipts plus planned order receipts minus
gross requirements for the period, plus amounts available from the previous period.
Back orders: Outstanding or unfilled customer orders.
Backward scheduling: Determining the start and finish times for waiting jobs by assigning them to the latest
available time slot that will enable each job to be completed just when it is due, but not before.
Base stock level: The inventory level up to which stocks are replenished, fixed by a periodic inventory control
operating doctrine.
Basic research: Research for the advancement of scientific knowledge that is not intended for specific commercial
uses.
Batch production: American Production and Inventory Control Society (APICS) defines batch production as a
form of manufacturing in which the job pass through the functional departments in lots or batches and
each lot may have a different routing define batch production. It is characterized by the manufacture of
limited number of products produced at regular intervals and stocked awaiting sales.
Batch technology: A process technology suitable for a variety of products in varying volumes.
Behavioral management: One of three primary theories of management, emphasizing human relations and the
behavioral science.
Behavioral science: A science that explores how human behavior is affected by variables such as leadership,
motivation, communication, interpersonal relationships and attitude change.
Bias: A forecast error measure that is the average of forecast error with regard to direction and shows any
tendency consistently to over or under forecast; calculated as the sum of the actual forecast error for all
periods divided by the total number of periods evaluated.
Bill of materials: A document describing the details of an item’s product build-up, including all component
items, their build-up sequence, the quantity needed for each, and the work centers that perform the build-
up sequence.
Blanket rule: A general policy for inventory control that can be modified as needed in light of total inventory
costs.
Bottleneck operation: The station on an assembly line that requires the longest task time.
Break-even analysis: A graphical and algebraic representation of the relationships among volume of output,
costs and revenues.
Break-even point: The level of output volume for which total costs equal total revenues.
Breakthrough: A solution to a chronic problem; a dramatic change for the better in quality, stimulated by
concentrated, analytic, company-wide quality improvement programs.
Buffer stock: Inventories to protect against the effects of unusual product demand and uncertain lead-time.
Business plan: A statement of an organization’s overall level of business activity for the coming 6 to 18 months,
usually expressed in terms of dollar volume of sales for its various product groups.
Glossary 261
Capacity: A facility’s maximum productive capability, usually expressed as volume of output per period of time.
Capacity planning: Design of the production system involves planning for the inputs, conversion process and
outputs of production operation.
Capacity requirement planning (CRP): A capacity requirement planning is an iterative process of modifying
the MPS or planned resources to make capacity consistent with the production schedule.
Cardex file system: A manually operated inventory control system in which an inventory card represents each
stock item with transactions kept on the card.
Carrying (holding) costs: Costs of maintaining the inventory warehouse and protecting the inventoried items.
Causal forecasting models: A statistical forecasting model based on historical demand data as well as on
variables believed to influence demand.
Cellular layout: The arrangement of a facility so that equipment used to make similar parts or families of parts
is grouped together.
Central limit theorem: A statistical hypothesis that the sampling distribution approaches normality as the size
of the samples increases, regardless of the distribution of the measurements of individual sample units.
Chance event: An event leading potentially to several different outcomes, only one of which will definitely
occur; the decision maker has no control over which outcome will occur.
Change agent: The facilitator of change; the role of the production/operations manager in bringing about
behavioral changes in other people.
Chronic problem: A long-term problem that causes continually poor quality, usually addressed through
breakthrough measures.
Classical management: One of three primary theories of management, emphasizing efficiency at the production
core, the separation of planning and doing work, and management principles and functions.
Codification: It is a process of representing each item by a number, the digit of which indicates the group, the
sub-group, the type and the dimension of the item.
Combination layout: This is also called the hybrid or mixed type of layout usually a process layout is combined
with the product layout. For example, refrigerator manufacturing uses a combination layout. The process
or functional layout is used to produce various operations like stamping, welding, heat treatment are
carried out in different work centres as per the requirement. The final assembly of the product is done in a
product type layout.
Company-wide quality control (CWQC): A management philosophy and set of activities characterized by
mobilizing the entire work force in the pursuit of quality, by statistical thinking, and by preventing errors.
Computer search: A set of directions that systematically guides a computer in evaluating alternative aggregate
plans.
Computer-aided manufacturing (CAM): Manufacturing systems utilizing computer software programs that
control the actual machine on the shop floor.
Computer-aided design (CAD): Computer software programs that allow a designer to carry out geometric
transformations rapidly.
Computer-integrated manufacturing (CIM): Computer information systems utilizing a shared manufacturing
database for engineering design, manufacturing engineering, factory production, and information
management.
262 Operations Management
Consumer’s risk (type II error) (b): The risk or probability of incorrectly concluding that the conversion
process is in control.
Continuous operations: Operations characterized by standardized, high-volume, capital- intense products
made to store in inventory; by small product mix; by special purpose equipment; and by continuous
product flow.
Continuous technology: A process technology suitable for producing a continuous flow of products.
Control chart: A chart of sampling data used to make inferences about the control status of a conversion
process.
Control limits: (Cl) Upper (UCL) and lower (LCL) boundaries defining the range of variation in a product
characteristic such that the conversion process is in control.
Controlling: Activities that assure that actual performance is in accordance with planned performance.
Conversions process: The process of changing inputs of labor, capital, land, and management into outputs of
goods and services.
Continuous production: Production facilities are arranged as per the sequence of production operations from
the first operations to the finished product. The items are made to flow through the sequence of operations
through material handling devices such as conveyors, transfer devices etc.
Critical fractile: In ratio of shortage costs to the sum of shortage and overstock for the perishable goods
inventory situation.
Critical path: In PERT, a path whose activities are expected to consume the most time.
Critical ratio: The ratio of inspection costs to per cent defective.
Custom-shop service technology: A process technology suitable for capital intensive, high customer contact
services.
Cycle counting: Counting on-hand inventories at regular intervals to verify inventory quantities shown in the
MRP.
Cycle time: Time elapsing between completed units coming off an assembly line.
Decision tree: A diagram used to structure and analyze a decision problem; a systematic, sequential laying out
of decision points, alternatives, and chance events.
Decision variable: A numerical, controllable parameter that, if modified, yields a variety of results.
Decoupling: Using inventories to break apart operations so that the supply of one operation is independent of
the supply of another.
Degeneracy: A quality of a linear transportation-programming problem such that there are too few occupied
cells to enable evaluation of the empty cells.
Delphi technique: A qualitative forecasting technique in which a panel of experts working separately and not
meeting, arrive at a consensus through the summarizing of ideas by a skilled coordinator.
Demand pattern: General shape of a time series; usually constant, trend, seasonal, or some combination of
these shapes.
Demand stability: Tendency of a time series to retain the same general pattern overtime.
Demand-based forecasting models: A statistical forecasting model based solely on historical demand data.
Deming’s 14 points for management: Guidelines for improving quality proposed by Dr. W. Edwards Deming,
as part of total quality control.
Glossary 263
Dependent demand: Demand for an item that can be linked to the demand for another item.
Depreciation: An accounting procedure to recover expenditures for an asset over its lifetime.
Design specifications: The important, desired characteristics of a product or service specified in detail during
the design phase.
Designated truncation time: Predetermined length of time a job is allowed to wait before it is assigned top
priority for processing (see truncated-shortest-processing-time rule).
Detailed capacity planning: An iterative process of modifying the MPS or planned -resources to make capacity
consistent with the production Schedule.
Detailed scheduling: Determining start times, finish times, and worker assignments for all jobs at each work
centres.
Deterministic model: A model in which variable values are known with certainty.
Development: Technical activities concerned with translating basic applied research results into products or
processes.
Direct time study: A work measurement technique that involves observing the job, determining the job cycle,
stopwatch-timing the job cycle, and calculating a performance standard.
Disaggregation: The process of translating aggregate plans for product groups into detailed operational plans
for individual products.
Double sampling: Acceptance sampling based on a first, small sample and, if results are inconclusive, a second,
larger sample.
Dummy activity: In PERT, a fictitious activity consuming no time, symbolized by a dashed arc.
Earliest beginning time: In PERT, the minimum amount of time that must be consumed before an activity can
begin.
Earliest-due-date rule (EDD): Priority rule that gives top priority to the waiting job whose due date is earliest.
Economic life: Length of time an asset is useful.
Economic order quantity (EOQ): The optimal order quantity, fixed by a Q/R inventory control operating
doctrine.
Efficiency: A measure (ratio) of outputs to inputs.
Empirical-rational change strategy: A strategy for change that assumes people change their behavior when
they believe it is in their own self-interest to do so.
Ergonomics (human engineering): ILO defines human engineering as — ‘The application of human biological
sciences along with engineering sciences to achieve optimum mutual adjustment of men and his work, the
benefits being measured in terms of human efficiency and well-being.
Event: In PERT, the beginning or ending of an activity, symbolized by a node.
Expected beginning time (TB): In PERT, the amount of time expected to be consumed before an activity can
begin.
Expected completion time (Tc): In PERT, the amount of time expected to be consumed once an activity begins.
Expected time (te): In PERT, the amount of time an activity is expected to consume
Expediting: Tracking a job’s progress and taking special actions to move it through the facility.
Exponential smoothing: An averaging method that exponentially decreases the weighting of old demands.
264 Operations Management
Factory building: Factory building is a factor, which is the most important consideration for every industrial
enterprise. A modem factory building is required to provide protection for men, machines, materials,
products or even the company’s secrets.
External failure costs: Costs attributable to the failure of products in the field.
Factor ratings: A decision procedure in which each alternative is rated according to each factor relevant to the
decision, and each factor is weighted according to importance.
Feasible (infeasible) solutions: Solutions that satisfy (do not satisfy) the restrictions of a linear programming
problem.
Feedback: Information in the control process that allows management to decide whether organizational activities
need adjustment.
Finite loading: A scheduling procedure that assigns jobs into work centers and determines their starting and
completion dates by considering the work centers’ capacities.
Firm planned order: A planned order release scheduled within the MRP time fence.
First-come-first-served rule (FCFS): Priority rule that gives top priority to the waiting job that arrived earliest
in the production system.
Fishbone (cause and effect) diagram: A schematic model of quality problems and their causes; used to diagnose
and solve these problems.
Fixed-position layout: The arrangement of a facility so that the product stays—in one location; tools, equipment,
and workers are brought to it as needed.
Flexibility: The capability of a manufacturing system to adapt successfully to changing environmental
conditions and process requirements.
Flexible manufacturing system (FMS): A computer controlled process technology suitable for producing, a
moderate variety of products in moderate volumes.
Flow diagram: Flow Diagram is a drawing, of the working area, showing the location of the various activities
identified by their numbered symbols and are associated with particular flow process chart either man type
or machine type.
Flow process chart: A graphic tool to analyze and categorize interstation activities so that the flow of the
product throughout the overall production process is represented.
Flow time: The total time that a job is in the system; the sum of waiting time and processing time.
Forecast: Use of past data to determine future events, an objective computation.
Forecast error: The numeric difference of forecasted demand and actual demand.
Forward scheduling: Determining the start and finish times for waiting jobs by assigning them to the earliest
available time slots at the work center.
Fraction defective: The ratio of defective units to total units.
Gang process chart: A graphic tool to trace the interaction of several workers with one machine.
Gantt chart: A bar chart showing the relationship of project activities in time.
Gantt load chart: A graph showing work loads on a time scale.
Gantt scheduling chart: A graph showing the time requirements of waiting jobs; scheduled for production at
machines and work centers.
Glossary 265
Governmental industrial planning: Activities of the Japanese Ministry of International Trade and Industry
that formulate industrial policy and determine the patterns of future growth and decline among the various
industries, comprising the Japanese economy.
Gradual replacement models: A deterministic inventory model characterized by demand being withdrawn
while production is underway; no stockouts, constant and known demand, lead time and unit costs.
Graphical planning procedure: Two-dimensional model relating cumulative demand to cumulative output
capacity.
Gross requirements: The overall quantity of an item needed during a time period to meet planned output
levels. Planned output for end items is obtained from the MPS. Planned output for lower-level items is
obtained from the MRP.
Group technology: A way of organizing and using data for components that have similar properties and
manufacturing requirements.
Heuristic: A procedure in which a set of rules is systematically applied; an algorithm.
Histogram: A bar graph of frequency distributions.
Homogeneous resources: Resources for which units supplied by one source are qualitatively equivalent to
units supplied by any other source.
Human relations: Phenomenon recognized by behavioral scientists that people are complex and have multiple
needs and that the subordinate-supervisor relationship directly affects productivity.
Implementation: Activities concerned with designing and building pilot models, equipment, and facilities for,
and with initiating the marketing channels for, products or services emerging from research and development.
In-control process: A process for which all variations are random.
Indented bill of materials: A chart showing an end item’s components, level by level, with increasing indentations
to reflect the lower levels.
Independent demand: Demand for an item that occurs separately of demand for any other item.
Individual risk taking propensity: The degree to which an individual tends to take or avoid risks.
Infinite loading: Assigning jobs to work centers without considering the work center’s capacity (as if the
capacity were infinite).
Initial solution: The feasible solution tested first using the simplex method in solving a linear programming
problem.
Input/output control: Activities to monitor actual versus planned utilization of a work center’s capacity.
Inputs: Labor, capital, land, or management resources changed by a conversion process into goods or services.
Inspection: The observation and measurement of inputs and outputs.
Intermittent operations: Operations characterized by made-to-order, low-volume, labor intense products; by a
large product mix; by general-purpose equipment; by interrupted product flow; and by frequent schedule
changes.
Internal failure costs: Costs attributable defects in production at the plant.
Internal rate of return: Interest rate at which the present value of outflows equals the present value of inflows.
Intuitive forecasts: Forecasts that essentially are a manager’s guesses and judgments concerning future
events; qualitative forecasting methods.
266 Operations Management
Inventory: Stores of goods and stocks, including raw materials, work-in-process, finished products, or supplies.
Inventory control: Activities that maintain stock keeping items at desired levels.
Inventory modeling: A quantitative, method for deriving a minimum cost operating doctrine.
Inventory status file: The complete documentation of the inventory status of each item in the product structure,
including item identification, on-hand quantity, safety stock level, quantity allocated, and lead-time.
Iso-profit line: Points in the solution space of a linear programming problem whose corresponding profits are
identical.
Item level: The relative position of an item in the product structure; end items are upper-level; preliminary items
in the product structure are lower level.
Job: A group of related tasks to activities that needs to be performed to meet organizational objectives.
Job design: Activities that specify the content of each job and determine how work is distributed within the
organization.
Job enrichment: Redesigning jobs to give more meaning and enjoyment to the job by involving employees in
planning, organizing, and controlling their work.
Job rotation: Moving employee into a job for a short period of time and then out again.
Job satisfaction: Employee perceptions of the extent to which their work fulfills or satisfies their needs.
Job shop production: Job shop production are characterized by manufacturing of one or few quantity of
products designed and produced as per the specification of customers within prefixed time and cost.
Job shop technology: A process technology suitable for variety of custom-designed products in small volumes.
Just-in-time (JIT): A manufacturing system whose goal it is to optimize processes and procedures by
continuously pursuing waste reduction.
Kaizen: The Japanese concept of continuous improvement in all things.
Kanban: Literally a ‘visual record’ a method controlling material flow through a JIT manufacturing system by
using cards to authorize a work station to transfer or produce materials.
Labor efficiency: The ratio of outputs to labor input, the labor-actually worked to achieve their output; a partial
factor productivity measure.
Labor standard: A quantitative criterion reflecting the output expected from an average worker under average
conditions for a given time period.
Labor turnover: A measure of the stability or change in an organization’s work force; the net result of employee
terminations and entrances.
Latest beginning time (TL): In PERT, the maximum amount of time that can be consumed before an activity
begins, if the project is to be completed on time.
Layout: Physical location or configuration of departments, work centers, and equipment in the conversion
process; spatial arrangement of physical resources used to create the product.
Lead-time: The time passing between ordering and receiving goods.
Lead-time demand: Units of stock demanded during lead-time; can be described by a probability distribution in
stochastic situations.
Lead-time offsetting: The process of determining the timing of a planned order release; backing off from the
timing of a planned order receipt by the length of lead-time.
Glossary 267
Least slack rule (LS): A priority rule that gives top priority to the waiting job whose slack time is least; slack
time is the difference between the length of time remaining until the job is due and the length of its
operation time.
Level output rate plan: An aggregate plan calling for a constant rate of output for all time periods of production.
Line balancing problem: Assigning tasks among workers at assembly line stations so that performance times
are made as equal as possible.
Linear decision rules (LDRs): A set of equations for calculating optimal work force, aggregate output rate, and
inventory level.
Linear programming: Mathematical method for selecting the optimal allocation of resources to maximize
profits or minimize costs.
Load: The cumulative amount of work currently assigned to a work center for future processing.
Load-distance model: An algorithm for laying out work centers to minimize product-flow, based on the number
of loads moved and the distance between each pair of work centers.
Longest-operation-time (LOT) rules: A line-balancing heuristic that gives top assignment priority to the task
that has the longest operation time.
Lot splitting: Processing only part of a job at one time, then the rest of the job at a later time.
Lot-for-lot ordering: A lot sizing policy in which order quantity equals net requirements for the period.
Machine life: Length of time an asset is capable of functioning.
Management coefficients model: A set of equations that represent historical patterns of a company’s aggregate
planning decisions.
Manufacturing resources planning (MRPII): An integrated information system that shares data among and
synchronizes the activities of production and the other functional areas of the business.
Manufacturing accounting and production information control system (MAPICS): IBM’s computerized common
data base system for manufacturing information and control.
Marginal efficiency of capital (MEC): A concept from finance espousing that a firm should invest in opportunities
whose return is greater than the cost of capital.
Markup: The ratio of profits to sales.
Mass production: Manufacture of discrete parts or assemblies using a continuous process are called Mass
production. This production system is justified by very large volume of production. The machines are
arranged in a line or product layout. Product and process standardizations exist and all outputs follow the
same path.
Mass service technology: A process technology suitable for labor intensive, low customer contact services.
Master production scheduling (MPS): A schedule showing week by week how many of each product must be
produced according to customer orders and demand forecasts.
Material requirements planning (MRP): A system of planning and scheduling the time-phased materials
requirements for production operations.
Material handling: Haynes defines ‘Material handling embraces the basic operations in connection with the
movement of bulk, packaged and individual products in a semi-solid or solid state by means of gravity
manually or power-actuated equipment and within the limits of individual producing, fabricating, processing
or service establishment’.
268 Operations Management
Materials management: Activities relating to managing the flow of materials into and through an organization.
Mathematical modeling: Creating and using mathematical representations of management problems and
organizations to predict outcomes of proposed courses of action.
Matrix organization: An organization that combines functional and project bases for groupings of organization
units.
Maximum allowable cycle time: Maximum time allowed to elapse between completed units coming off an
assembly line, if. 9 given capacity is to be achieved.
Mean absolute deviation (MAD): A forecast error measure that is the average forecast error without regard to
direction; calculated as the sum of the absolute value of forecast error for all periods divided by the total
number of periods evaluated.
Mechanization: The process of bringing about the use of equipment and machinery in production and operations.
Method study: is the systematic recording and critical examination of existing and proposed ways of doing
work, as a means of developing and applying easier and more effective methods and reducing costs.
According to British Standards Institution (BS 3138): “Method study is the systematic recording and
critical examination or existing and proposed ways or doing work as a means or developing and applying
easier and more effective methods and reducing cost.”
Methods time measurement: A widely accepted form of predetermined time study.
Ministry of international trade and industry (MITI): The unit of Japanese government responsible for industrial
planning for the activities that formulate industrial policy and determine the patterns of future growth and
decline among the various industries comprising the Japanese economy.
Mixed strategy: Aggregate planning strategy that incorporates or combines some elements from each of the
pure aggregate planning strategies.
Modeling management: One of three primary theories of management, emphasizing decision-making, systems,
and mathematical modeling.
Modular design: The creation of products from some combination of basic, preexisting subsystems.
Most likely time (tm): In PERT, the single best guess of the amount of time an activity is expected to consume.
Multiechelon inventories: Products stocked at various levels—factory, warehouse, retailer, customer in a
distribution system.
Multiple activity chart: It is a chart where activities of more than subject (worker or equipment) are each
recorded on a common time scale to show their inter-relationship.
Multiple sampling: Acceptance sampling based on many small samples.
Multistage inventories: Parts stocked at more than one point of the sequential production process.
Natural limits: Three standard deviations above and below the average of sample unit measurements.’
Net change method: Method for updating the MRP system in which only those portions of the previous plan
directly impacted by informational changes are reprocessed.
Net present value: The result of discounting all cash flows of an investment back to their present values and
netting out the inflows against the outflows.
Net requirements: The net quantity of an item that must be acquired to meet the scheduled output for the
period. Calculated as gross requirements minus scheduled receipts for the period minus amounts available
from the previous period.
Glossary 269
Network: in PERT: the sequence of all activities, symbolized by nodes connected by arcs.
Network modeling: Analyzing the precedence relationships of project activities and depicting them graphically.
Next-best rule (NB): A priority rule that gives top priority to the waiting job whose, setup cost is least.
Node: In network modeling, a circle at one end of an arc; the symbol for the beginning or ending of a project
activity.
Noise: Dispersion of demand about a demand pattern.
Nominal group technique: A qualitative forecasting technique in which a panel of experts working together in
a meeting, arrive at a consensus through discussion and ranking of ideas.
Normal time: The average cycle time for a job, adjusted by a worker rating to account for variations in normal
performance.
Normative-reeducative change strategy: A strategy for change that assumes people change their behavior
only after changing their attitudes and values.
Objective function: A mathematical equation that measures the value of all proposed decision alternatives, a
linear programming equation.
Occupational safety and health administration (OSHA): A division of the U. S. government created by the
Williams-Steiger Occupational Safety and Health Act of 1970 to develop and enforce standards for job-
related safety and health.
Office automation (OA): Computer-based systems for managing information resources.
Open order: A customer order (job) that has been launched into production and is in process.
Operant conditioning: A technique to modify behavior by direct rewards and punishments.
Operating characteristic (OC) curve: Given a sampling plan, the graph of the probability of accepting a
shipment as a function of the quality of the shipment.
Operating doctrine: Inventory control policies concerning when and how much stock to reorder.
Operating system: An operating system (function) of an organization is the part of an organization that
produces the organization’s physical goods and services.
Operation chart: A graphic tool to analyze and time elementary motions of the right and left hand in performing
a routine, repetitive task.
Operation set-back chart: A time-scaled chart showing the sequence, component, of product build-up.
Operations management: Management of the conversion process, which converts land, labor, capital, and
management inputs into desired outputs of goods and services.
Operations splitting: Processing part of a job at one work center and the rest at another.
Operations system: The part of an organization that produces the organization’s physical goods or services.
Operation process chart: It is also called outline process chart. An operation process chart gives the bird’s eye
view of the whole process by recording only the major activities and inspections involved in the process.
Opportunity costs: Returns that are lost or forgone as a result of selecting one alternative over another.
Optimistic time (to): In PERT, the least amount of time an activity is expected to consume.
Organization development (OP): Managing organizational change by applying knowledge from psychology,
sociology, and other behavioral sciences.
Optimized production technology (OPT): A production planning system that emphasizes identifying bottleneck
work centers, and careful management of materials and resources related to those bottlenecks, to maximize
output and reduce inventories.
270 Operations Management
Order quantity: As part of the operating doctrine, the amount of stock that should be reordered.
Organizing: Activities that establish a structure of tasks and authority.
Out-of-control process: A process for which some variations are nonrandom (sporadic).
Outputs: Goods or services changed by a conversion process from labor, capital, land or management resources.
P- chart: A control chart using sample fractions defective.
PERT language: The terms and symbols specific to PERT.
Pareto analysis: Frequency distributions of quality cost sources.
Part-period method: A lot sizing policy in which order quantity varies according to a comparison of holding
versus ordering costs.
Path: In PERT, a portion of the network, including the first and last activities, for which each activity has a
single immediate successor.
Path time (Tp): In PERT, the amount of time expected to be consumed by activities on a path.
Payback period: Length of time required to recover one’s investment; the ratio of net income to net annual
income from investment.
Parameters of purchasing: The success of any manufacturing activity is largely dependent on the procurement
of raw materials of Right quality, in the Right quantities, from Right source, at the Right time and at Right
price popularly known as five ‘R’s’ of the efficient purchasing.
Pegging: The process of tracing through the MRP records and all levels in the product structure to identify
how changes in the records of one component will affect the records of other components.
Percent defective: The per cent of units that are defective.
Periodic inventory system: An operating doctrine for which reorder points and order quantities vary; stocks
are replenished up to a fixed base stock level after a fixed time period has passed.
Pessimistic time (tp): In PERT, the greatest amount of time an activity is expected to consume.
Physical distribution: Activities relating to materials management as well as to storing and transporting
finished products through the distribution system to customers.
Planned order: A customer order (job) that is on the books and planned for production but that has not yet
been launched into production.
Planned order receipts: The quantity of an item that is planned to be ordered so that it will be received at the
beginning of the time period to meet net requirements for the period. The order has not yet been placed.
Planned order release: The quantity of an item that is planned to be ordered and the planned period for
releasing this order that will result in the order being received when needed. It is the planned order receipt
offset in time by the item’s lead-time. When this order is placed (released), it becomes a scheduled receipt
and is deleted from planned order receipts and planned order releases.
Planning: Activities that establish a course of action and guide future decision-making.
Planning for operations: Establishing a program of action for converting resources into goods or services.
Planning the conversion system: Establishing a program of action for acquiring the necessary physical facilities
to be used in the conversion process.
Plant layout: Plant layout refers to the physical arrangement of production facilities. It is the configuration of
departments, work centres and equipment in the conversion process. It is a floor plan of the physical
facilities, which are used in production. According to Moore, “Plant layout is a plan of an optimum
Glossary 271
arrangement of facilities including personnel, operating equipment, storage space, material handling
equipment and all other supporting services along with the design of best structure to contain all these
facilities.”
Poke a yoke: Literally, “fool proofing.” Total quality control techniques that foolproof production from defects.
Power-coercive change strategy: A strategy for change that makes use of political, economic, or other forms of
influence to force behavioral changes in other people.
Pre-automation: An analysis that is performed before automating a production process to reveal unnecessary
equipment and activities so that they can be eliminated rather than automated.
Predecessor task: A task that must be performed before performing another (successor) task.
Predetermined time study: A work measurement technique that involves observing or thinking through a job,
recording job elements, recording reestablished motion units, and calculating a performance standard.
Prediction: Subjective estimates of the future.
Prevention costs: Costs of planning, designing, and equipping a quality control program.
Preventive maintenance: (PM) JIT philosophy espousing daily, extensive check ups and repairs for production
equipment, lengthening their useful life well beyond the traditional time frame.
Principles of motion economy: A broad set of guidelines focusing on work arrangements, the use of human
hands and body, and the use of tools.
Priority sequencing rule: A systematic procedure for assigning priorities to waiting jobs, thereby determining
the sequence in which jobs will be processed.
Probabilistic PERT: A modification of PERT to consider the variance se2 and the mean mp of the expected times.
Process layout: The arrangement of a facility so that work centers or departments are grouped together
according to their functional type.
Process capability: The ability of a conversion process to produce a product that conforms to design
specifications; a range of variation from the design specifications under normal working conditions.
Process design: Process design is a macroscopic decision-making of an overall process route for converting
the raw material into finished goods.
Process management: One of several theories of classical management, emphasizing management as a
continuous process of planning, organizing, and controlling to influence the others’ actions.
Process technology: Equipment, people, and systems planning activities that establish a course of action and
used to produce a firm’s products and services.
Product layout: The arrangement of a facility so that work centers or equipment are in a line to afford a
specialized sequence of tasks.
Product explosion: The process of determining from the product structure and planned order releases the
gross requirements for components.
Product group (family): A set of individual products that share or consume common blocks of capacity in the
manufacturing process.
Product life cycle: Pattern of demand throughout the Product’s life; similar patterns and stages can be identified
for the useful life of a process.
Product mix problem: A decision situation involving limited resources that can be used to produce any of
several combinations of products.
272 Operations Management
Product reliability: The probability that a product will perform as intended for a prescribed lifetime under
specified operating conditions.
Product structure: The levels of components to produce an end product. The end product is on level 0,
components required for level 0 are on level, and so on.
Production smoothing: Production planning that reduces drastic period-to-period changes in levels of output
or work force.
Productivity: Efficiency; a ratio of outputs to inputs. Total factor productivity is the ratio of outputs to the total
inputs of labor, capital, materials, and energy; partial factor productivity is the ratio of outputs to one, two,
or three of these inputs.
Productivity gain-sharing: Rewarding employees for increases in organization-wide group performance.
Production management: Deals with decision-making related to production processes so that the resulting
goods or services are produced according to specifications, in the amount and by the schedule demanded
and out of minimum cost.
Production planning and control: Production planning and control can be defined as the process of planning
the production in advance, setting the exact route of each item, fixing the starting and finishing dates for
each item, to give production orders to shops and to follow up the progress of products according to
orders. The principle of production planning and control lies in the statement ‘First Plan Your Work and
then Work on Your Plan’.
Production system: The production system of an organization is that part, which produces products of an
organization. It is that activity whereby resources, flowing within a defined system, are combined and
transformed in a controlled manner to add value in accordance with the policies communicated by
management.
Product development and design: is the process of developing a new product with all the features, which are
essential for effective use in the field, and designing it accordingly. At the design stage, one has to take
several aspects of design like, design for selling, design for manufacturing and design for usage.
Professional service technology: A process technology suitable for labor intensive, high customer contact
services.
Program evaluation and review technique (PERT): An application of network modeling originally designed for
planning and controlling the U.S. Navy’s Polaris nuclear submarine project.
Progress reporting: Monitoring the time and cost variances during the progress of a project and depicting
them graphically, including actual costs of work completed (ACWC), budgeted costs of work completed
(BCWC), and budgeted costs of work scheduled (BCWS).
Project: A one-time-only set of activities that have a definite beginning and ending point in time.
Project planning: Activities that establish a course of action for a project.
Project scheduling: Activities that establish the times and the sequence of project tasks.
Project technology: A process technology suitable for producing one-of-a-kind products.
Pull manufacturing system: A system of production in which products is produced only as they are ordered
by customers or to replace those taken for use. A JIT system.
Purchasing: Activities relating to procuring materials and supplies consumed during production.
Push manufacturing system: A system of production in which products are produced according to a schedule
derived from anticipated product demand. An MRP-based or EOQ based system.
Glossary 273
Q/R inventory system: An operating doctrine for which an optimal reorder point R—the trigger level—and an
optimal order quantity Q—the economic order quantity are fixed.
Quality: The degree to which the design, specifications for a product or service are appropriate to its function
and use, and the degree to which a product or, service conforms to its design specifications.
Quality circle (QC): A small group of employees who meet frequently to resolve company problems meet
frequently to resolve company problem.
Quality control (QC): Quality Control may be defined as ‘a system that is used to maintain a desired level of
quality in a product or service’. Quality control can also be defined as ‘that industrial management technique
by means of which product of uniform acceptable quality is manufactured’. It is the entire collection of
activities that ensures that the operation will produce the optimum quality products at minimum cost.
Quality loss function (QLF): A qualitative measure of the effectiveness of quality control, often in terms of the
economic losses a customer suffers after purchasing an imperfect product.
Quality motivation: Programs to motivate workers to improve quality, including incentive and merit pay systems.
Quantity discount: A policy of allowing item cost to vary with the volume ordered; usually the item cost
decreases as volume increases due to economies of scale in production and distribution.
Quasi-manufacturing technology: A process technology suitable for capital intensive, low customer contact
services.
Queue: A waiting line.
Queuing theory: Concepts and models to describe and measure patterns of job arrivals and patterns of
servicing customers and to evaluate the effectiveness of serving customers who wait in lines (queues) to
be served.
R-chart: A control chart using sample ranges.
Random fluctuations: Unplanned or uncontrollable environmental influences (strikes, floods, etc.) that cause
planned and actual output to differ.
Receiving inspection: The inspection of inputs.
Regenerative method: A procedure, used at regular intervals, to update the MRP by completely reprocessing
the entire set of information and recreating the entire MRP.
Regression analysis: A causal forecasting model in which, from historical data, a functional relationship is
established between variables and then used to forecast dependent variable values.
Reinforcement schedule: A more or less formal specification of the timing of a reinforcer for a response
sequence.
Reorder point: As part of the operating doctrine, the inventory level at which stock should be reordered.
Research and development (R&D): Organizational efforts directed toward product and process innovation;
includes stages of basic research, applied research, development, and implementation.
Restrictions: Restraints on the values of the decision variables of a linear programming problem.
Robot: A programmable machine capable of moving materials and performing routine, repetitive tasks.
Robust product: A product that can perform under a wide range of environmental conditions without failing.
Rough-cut capacity planning: The process of testing the feasibility of master production schedules in terms of
capacity.
274 Operations Management
Route sheet: A document that shows the routing of a component, including the work centers and operation
times, tough its production processes.
Routing: The processing steps or stages needed to create a product or to do a job.
Salvage value: Income from selling an asset.
Sample: A set of representative units of output selected and measured as part of sampling.
Sample range: The arithmetic difference of the highest and lowest measurement for a sample.
Sample unit: A representative unit of output selected and measured as part of sampling.
Sampling: The process of selecting and measuring representative units of output.
Sampling inspection: In this method randomly selected samples are inspected. Samples taken from different
patches of products are representatives.
Sampling plan: A plan for acceptance sampling specifying the number of units to sample and the number of
sample units that must conform to specifications if the shipment is to be accepted.
Scheduled receipts: The quantity of an item that will be received from suppliers as a result of orders that have
been placed (open orders).
Scientific management: One of several theories of classical management, emphasizing economic efficiency at
the production core through management rationality, the economic motivation of workers, and the separation
of planning and doing work.
Service level: A treatment policy for customers when there are stockouts; commonly established either as a
ratio of customers served to customers demanding or as a ratio of units supplied to units demanded.
Setup cost: The cost of revising and preparing a work center for processing a job.
Shingo’s seven wastes: Seven sources of manufacturing wastes identified by Shigeo Shingo as targets for
reduction through continuous improvements in the production process.
Shop floor control: Activities that execute and control shop operations; includes loading, sequencing, detailed
scheduling, and expediting jobs in production.
Short processing time rule (SPT): A priority rule that gives top priority to the waiting job whose operation time
at a work center is shortest.
Simple average: Average of demands occurring in all previous periods; the demands of all periods are equally
weighted.
Simple lot size formula (Wilson formula): A deterministic inventory model characterized by one stock point,
no stockouts, and constant and known demand, lead time, and unit cost.
Simple median model: A quantitative method for choosing an optimal facility location, minimizing costs of
transportation based on the median load.
Simple moving average: Average of demands occurring in several of the most recent periods; most recent
periods are added and older ones dropped to keep calculations current.
Simplex method: An algorithm for solving a linear programming problem by successively choosing feasible
solutions and testing them for optimality.
Single sampling: Acceptance sampling based on a single sample.
Slack time: The difference of the length of time remaining until a job is due and the length of its operation time.
Slack time (Ts): In PERT, the amount of leeway time an activity can consume and still allow the project to be
completed on time.
Glossary 275
Slack variable: A variable in a linear programming problem representing the unused quantity of a resource.
Smoothing coefficient: A numerical parameter that determines the weighting of old demands in exponential
smoothing.
Solution space: The possible (meaningful) values of variables in a linear programming problem.
Specialization of labor: Breaking apart jobs into tasks and assigning tasks to different workers according to
their special skills, talents, and tools.
Specification limits (SL) upper (USL) and lower (LSL): Boundaries defining the limits of variation in a product
characteristic such that the product is fit for use; output measuring outside these limits is unacceptable.
Sporadic problem: A short-term problem that causes sudden changes for the worse in quality, usually addressed
through control measures.
Standard: A quantitative criterion established as a basis for comparison in measuring or judging output.
Standard time: The ratio of normal time to the available fraction of time.
Standard usage: An established industrial engineering time standard.
Statistical forecasting models: Casting forward past data in some systematic method; used in time series
analysis and projection.
Statistical process control (SPC): The use of sample statistics to detect and eliminate nonrandom (sporadic)
variations in the conversion process.
Stepping stone procedure: An algorithm of the transportation method of linear programming that uses a set of
occupied cells to evaluate the effect on costs if an empty cell was to become occupied.
Stochastic model: A model in which variable values are probabilistic.
Stock (storage) point: A location of inventory stock keeping an item of inventory.
Stockless production system: A system of production that allows no (or as small as possible) inventories of
raw materials, work-in-process, or finished goods; goes hand in hand with JIT philosophy.
Stockout costs: Costs associated with demand when stocks have been depleted; generally lost sales or
backorder costs.
Stores management: This involves physical control of materials, preservation of stores, minimization of
obsolescence and damage through timely disposal and efficient handling, maintenance of stores records,
proper location and stocking.
Strategic planning: A process of thinking through the organization’s current mission and environment and
then setting forth a guide for tomorrow’s decisions and results.
String diagram: The string diagram is a scale layout drawing on which, length of a string is used to record the
extent as well as the pattern of movement of a worker working within a limited area during a certain period
of time.
Subculture: Regional or ethnic variations of a culture.
Sunk costs: Past expenditures that are irrelevant to current decision.
System: A collection of objects related by regular interaction and interdependence.
System dynamics: A computer-based simulation methodology for developing and analyzing models of systems
and their behavior.
Taguchi method of quality control: A method of controlling quality, developed by Dr. Genichi Taguchi that
emphasizes robust product design and the quality loss function.
276 Operations Management