Procedures For The Examination of Plans and Inspection of Construction
Procedures For The Examination of Plans and Inspection of Construction
INSPECTION OF CONSTRUCTION
OF
PLANS
AND
Contents
INTRODUCTION
1.
EXAMINATION OF PLANS
1.1
1.2
1.3
2.
INSPECTION OF CONSTRUCTION
2.1
2.2
2.3
2.4
2.5
2.6
2.7
2.8
2.9
2.10
2.11
2.12
2.13
2.14
2.15
2.16
General
Building layout
Foundations
Structural Frame
Ring Beam
Roof
Floors
Plumbing
Drainage
Septic Tank and Waste Disposal
Water Cistern
Electricity
Final Inspection
Special Inspections
Other Inspections
Safety and Health Inspections
3.
4.
5.
REPORTING
Appendices
Forms
1A.
1B.
2.
4.
Monthly Report
5.
6.
INTRODUCTION
This document is based on discussions and observations of the
procedures used by most of the OECS building inspectorates for the
examination of plans and the inspection of construction. The problems
noted are that generally not enough time is taken for the examination of
the plans and the details on the drawings observed by the Building
Inspectors are not generally in accordance with the requirements of the
Guidelines.
The document does not discuss the procedures for receipt of the
applications, as each Authority will have its own procedures. However,
the examination of plans and the reporting of the examinations must be
carried out in an orderly manner, and attention is therefore given to the
procedures for doing this.
The use of the Building Guidelines and Building Code for buildings to be
erected in Antigua and Barbuda and in St. Kitts and Nevis is now the law
of the land. The Code defines small buildings as those residential and
retail commercial buildings less than 3000 sq. ft. in area, and therefore
covers most (in numbers) of the buildings being constructed in the State.
The requirements of the Code control the design and construction of all
buildings; but the Guidelines are geared for use by the designer and
constructor of small buildings.
The Building Inspectors have to ensure that all developments are carried
out in accordance with the Code and with the relevant plans as approved
by the DCA. The procedures outlined are intended to guide the building
inspectorate in carrying out the required inspections, but each Inspector
must be knowledgeable about the existing building and planning
Regulations and must be aware of the main recommendations detailed in
the Code and Guidelines.
The Sections on the Administration of the Code and on the
Administration of the Guidelines define the inspections which are
mandatory. Site Inspection visits are based on requests by the developer
or builder on the forms as at Appendix 1.
The visits paid to construction sites by the Building Inspectors must be
formal and within normal working hours unless specifically requested by
the builder to carry out an inspection after working hours for a specific
purpose, such as during a concrete pour.
There is also the need for the Building Inspectors to assist builders of
small homes in the construction techniques needed to permit "safe'
Procedures for the Examination of Plans and Inspection of Construction
1.
EXAMINATION OF PLANS
1.1
1.2
1.3
b)
c)
Design of foundations
d)
e)
f)
g)
h)
i)
j)
k)
l)
m)
n)
b)
c)
d)
e)
2.
INSPECTION OF CONSTRUCTION
2.1
General
2.2
a)
b)
Building Layout.
The actual layout of the buildings or developments should be
checked against the approved plans. The Building Inspector
should ask the person in charge of the site to produce a copy of
the approved plans, before beginning the check. While the site
boundaries may be difficult to check by the Building Inspector,
the site boundaries should be marked and the Building
Inspector should satisfy himself that the construction is within
the required distances from the site boundaries and is in
accordance with the approved plans.
2.3
Foundations.
a)
b)
2.4
ii)
iii)
Structural Frame.
a)
2.5
Ring Beam
The Building Inspector should check to see that the size being
used is as per the approved plans and in accordance with the
recommendations of the Guidelines and that the reinforcement
is adequate. The quality of the concrete should also be
examined. Badly constructed formwork produces generally bad
quality concrete. It is expected that the Building Inspector will
guide the small builder in the construction of adequate formwork
for ring beams and lintels.
2.6
2.7
Roof.
a)
b)
Floors
a)
2.8
2.9
b)
c)
Plumbing
a)
b)
c)
2.10
2.12
Water Cistern
a)
b)
c)
Electricity
Inspections should be done in concert with the Electrical
Inspector. The inspections should begin with the placing of
conduits (where required) and at the stage when the conductors
are being pulled. The Electrical Inspector will determine the
stages of inspection and the Building Inspector will be expected
to inform the Electrical Inspector of the progress of the
construction and cooperate in the inspection.
2.13
Final Inspection
The permission to occupy a newly constructed building is
dependent on the issuance of a Certificate of Occupancy. This
certificate can only be issued if the final inspection has taken
Certificate of Occupancy
This certificate should be provided the day after the final
inspection if the inspection shows that the building construction
is satisfactory. If problems are noticed, the builder and
developer must be informed and another inspection planned.
Information to the builder and developer must be confirmed in
writing addressed to the developer or his/her agent as given in
the application form.
2.15
Other Inspections
The Special Inspector should be engaged for examination of
major mechanical and electrical systems such as desalination
plants, mechanical sewerage treatment plants, and power
plants. Reports of the Special Inspector will be sent to the
Director and copies sent to the builder and developer for action
where indicated. Inspections of major civil engineering works
also fall in this category, and should be handled similarly.
2.16
b)
c)
d)
3.
3.1
3.2
b)
c)
3.3
3.4
3.5
3.6
4.
4.1
4.2
4.3
a)
b)
Foundation design
The Senior Building Inspector should inform the builder that the
advice offered is intended to produce buildings which would
conform to the requirements of the Guidelines and the Code.
5.
REPORTING
5.1
b)
c)
d)
e)
f)
g)
f)
h)
i)
APPENDIX 1A
REVIEW OF PLANS OF SMALL DOMESTIC BUILDINGS
(Less than 3,000 Square Feet in Gross Floor Area)
Building elements or parts to be
examined
Building Type by function
Regulations, Code or
Guidelines reference
DCA Regulations
Section 3 of Code
Roof
Structure
Site layout
Location
Floor - dimensions
Floor - concrete
Floor - timber
Ventilation
Section F of Guidelines
Water Storage
Section F of Guidelines
Plumbing
Section F of Guidelines
Parking
Site plan
Access
Section 19 of Code
Foundations
Concrete buildings
Section B of Guidelines
Timber buildings
Section C of Guidelines
Steel buildings
Section D of Guidelines
Section E of Guidelines
APPENDIX 1B
RESULTS OF EXAMINATION OF PLAN SUBMITTED FOR
DEVELOPMENT APPROVAL OR FOR A BUILDING PERMIT (The
relevant section of the Guidelines to be quoted for all items
reviewed)
Building Inspector
Date
Application Number
Date Submitted to the DCA
Type of Development: __________________________________
____________________________________________________
Name of Owner Person Interviewed (if any)
Satisfactory
Not satisfactory
Guidelines
section
Guidelines
section
Development elements
reviewed
Site Layout
Foundation layout, sizes
Concrete ground floorsCompaction, floor thickness
and reinforcement
Concrete suspended floors thickness and reinforcement
Walls (sizes and
reinforcement)
Columns Spacing, sizes and
reinforcement
Roof - type and pitch
Guidelines
Section
Roof member sizes
Septic tank or Cess pit location and sizes
Soakaway Pit - location,
depth and size
Water cistern - location, type,
size, and construction
materials used
Concrete water cistern location, wall thickness,
reinforcement
Electricity (with electrical
inspector)
Plumbing - pipe sizes and
connections
Rain water disposal - size of
gutters and location of
disposal of rain water
Guidelines
Section
APPENDIX 2
REQUEST FOR INSPECTION
(Sample form. Similar forms are to be used for all elements to be
inspected)
Permission Number:
_______________________________
Type of Development:
_______________________________
__________________________
_____
__________________________
_____
Name of Developer:
_______________________________
__________________________
_____
Signature of Builder:
__________________________
______
Proposed date of inspection: _____________________________
Inspection not scheduled: _______________________________
(Reasons)
__________________________
______
__________________________
______
Sgd. Building Inspector
_______________________________
Date:
_______________________________
APPENDIX 3.
BUILDING INSPECTION REPORT FORM
Name of Inspector: _____________________________________
Date and time of inspection: _____________________________
Certificate Number: __________________________________
Date Approved: _______________________________________
Type of Development: __________________________________
Name of Owner: _____________________________________
Person Interviewed: ____________________________________
ELEMENTS INSPECTED
SATISFACTO
RY
Guidelines
reference
Site Layout
Foundation
Floors
Walls
Columns
Belt Beam
Roof
Septic Tank or Cess Pit
Soakaway Pit
NOT
SATISFACTORY
Guidelines
reference
Water Cistern
Electricity
Plumbing
Rain water guttering and
disposal
APPENDIX 4.
Monthly Report Form
(Sample headings only)
BUILDINGS UNDER CONSTRUCTION DURING MONTH OF :
Name of Inspector
Permission
No
Plot and
Parcel No.
Date
Date
Approved
Type of
Development
Stage
Reached
Is Work as
Approved
Comments
APPENDIX 5
DESIGN REQUIREMENTS FOR CONSIDERATION BY BUILDING
CONSULTANTS
Item
No.
AA-1
ARC
HITE
A-2
Description
A-3
A-4
A-7
A-8
Landscaping design
A-9
Fire resistance
A-10
A-5
A-6
A-11
A-12
A-13
A-14
A-15
Con
side
Yes
red
No
A-16
Exterior glazing
A-17
A-18
A-19
BB-1
STRU
CTUR
AL
ENGI
B-2
B-3
B-4
B-5
CC-1
MEC
HANI
C-2
C-3
C-6
C-7
DD-1
CIVIL
ENGI
C-4
C-5
D-2
Site grading
D-3
D-4
Access roads
EE-1
PLUM
BING
E-2
E-4
E-5
E-6
G-1
G-2
G-3
Planting
E-3
APPENDIX 6
CERTIFICATE OF PRACTISING STRUCTURAL ENGINEER
1
Background
The accompanying certificate provides information on the
technical requirements of the structural design of buildings as
required under the provisions of the Code.
This form is to be presented to the Director with the structural
plans for the buildings conforming to the categories listed on the
form. Completion of the form will assist the Director in making
more appropriate decisions with respect to compliance of the
structure with the standards in the Code.
The use of this form does not increase the work of the structural
engineer. On the contrary, it provides a logical framework within
which the engineers work may be organised.
Note:
2.
Design
This form is to be used for submissions of applications to the
Director for a building permit to construct new buildings,
additions to existing buildings and renovations involving
changes of use.
Owner's Name:
Building:
Location:
3.
3.1
Drawings
-
construction details
3.2
3.3
3.4
3.5
3.6
Building Class:
3.7
4.
Design Criteria
4.1
4.2
a)
roof
b)
upper floors
c)
ground floor
Wind Loading:
a)
b)
Terrain Category:
i)
ground roughness
ii)
4.3
4.4
topography
c).
d)
Pressure Coefficients:
i).
ii).
iii)
iv)
v)
Internal (max):
vi).
Internal (min):
Earthquake loading:
i)
Zone Z factor:
ii)
Importance I factor:
iii)
iv)
v)
Soils S factor:
Load combinations:
1.
dead + fluids
1.
4.
5.
6.
5.
Certificate
I/We* certify that:
1
4.
Note: This form was developed with the assistance of Tony Gibbs
PROCEDURES
FOR THE EXAMINATION
OF PLANS
AND
INSPECTION OF
CONSTRUCTION
PROCEDURES
For the
EXAMINATION OF PLANS
and
INSPECTION OF CONSTRUCTION
Prepared by
Alwyn T. Wason P.Eng
for the
Post Georges Disaster Mitigation Project