Effects of Communication in Project Delivery
Effects of Communication in Project Delivery
1.0 INTRODUCTION
(http://www.economywatch.com/world-industries/construction).
industries/construction/world.html)
growth (Walsh and Sawhney, 2002). Its contribution to GDP in the U.S in
1
Over the last decade, several changes have occurred in Nigeria, which
have helped all sectors of the economy, especially the construction sector.
The construction industry has outgrown all other sectors of the Nigerian
economy with double digit growth rates in the last three years (2005 –
2008). Also, there are several opportunities in the industry especially in the
other service industries, (Aibinu and Jagboro, 2002). The contribution of the
in the industry is usually accompanied with time delay and cost increase as
2000). Aibinu and Jagboro (2002) explain that though the construction
in the Nigerian economy. The fiscal projections for 2001 for instance show
that out of the N892 billion expenditure proposed, N480 billion representing
communication such as face to face meetings, phone calls and the exchange
Stewart, 2003).
amongst the distinct professions all of whom have conflicting priorities and
time as this helps make the profession strong and successful, it also explains
new roles and competencies. This made a change in culture necessary for the
4
Communication improvements in early phases of projects
stakeholders involved.
diverse and every project is unique. Even where identical buildings are
under construction, site conditions in each will differ and introduce new
challenges while the long periods between the decision to invest and the
communication on site?
delivery?
1.3.1 Aim
1.2.1 Objectives
6
ii. Determination of the contribution or influence of the
1.3 METHODOLOGY
twenty-eight construction companies out of which the sample size for the
construction firms. The types of data to be collected are questions that are
7
The questionnaires are to be distributed through direct contact and to
such a way that the options of the respondents will be required on the subject
of the dissertation and split into five sections. Section A will consist of fixed
response questions that will give information about the respondent and the
and open end questions based on the objectives of the study as well as
proffered solutions to aid in achieving the aim of the study. The respondents
are to tick any of the options which portrayed their own opinions. The open
end aspects of the questionnaire will give an insight into personal views of
The analytical tools to be used are the descriptive statistical tools like
8
Each section of the questionnaire will be analyzed using the Relative
afterwards.
1.4 SCOPE
construction industry in Ilorin, Kwara State. The study is carried out at the
9
CHAPTER TWO
10
In spite of the huge capital outlay, public utilities are unable to cope
in developed societies.
countries support the fact that infrastructure capital has a significant and
countries need infrastructure, and more importantly the services that stem
higher maintenance costs from many years of neglect; and then costs
11
where there is complete inoperation of the facilities. Facility failures have
far reaching implications beyond this. For example the idle time of labour,
yet they still have to be remunerated; there is also the cost of lost production,
the utilities in operation had very low rates of return and that several
development needs. Between 1996 and 2000, the building and the
GDP at current basic prices; while between 2000 and 2004 the value fell to
0.78% (CBN Annual Reports 2006) whereas the relative contribution of the
finance and insurance sector was 1.23% and 1.17% during these periods
to Nigeria’s Economy
12
Two reasons can be given for the net marginal contribution of the
would require reforms that cut across all the sectors. The current quest for
sector investment may be the break the construction industry needs to make
project because all projects are executed by humans and they interact by way
and status reports. Mehra (2009) also noted that projects fail when
(Mehra, 2009).
14
With inference from the above definitions, communication can
experiences for the mutual benefit of the parties involved in ensuring timely
project delivery”.
15
There are various ways and methods of communicating information in
is well documented and stored for future reference. Scope of work and
commonly issued when one entity passes down work to another: for
1) Formal Written – This takes the form of Project Plan, Project charter,
expressions as well as our postures and gestures and account for about
our voice and account for about 38% of what is perceived and
understood by others.
more than one in some cases). Both parties have their own experiences, their
perceptions, their ideas, etc; hence they may experience, perceive, and
interpret things differently. The same event will always be perceived a little
receiver.
17
Medium of
Transmission
Feedback through
appropriate medium
project team member. This means that sender must attempt to take the
way intended.
18
3. Medium – Messages may be sent using traditional mail, email, phone
message as intended.
transfer the information in the message. The purpose is to ensure that both
seen.
20
2.2.5 Barriers to Communication
message
besides listening
21
Any of the above barriers to communications can create interferences or
negatively.
CONSTRUCTION INDUSTRY.
c) The problem of the erection site being far from the specialist head office
1. Conception/Design stage
22
2. Approval by the planning authority
4. Contractor’s Organisation
such as the size of the building, nature of the building, funds available,
building function and time limitation of the project will be made available to
the consultants.
requirements after carrying out feasibility studies with the other consultants
and communicates it to the rest of the members of the design team for
collective action.
start preparing the working drawings, schedule and specification and at the
same time seeking the opinion of the quantity surveyor who sees to the cost
23
implication of the project to see if the project design is still within the
approved budget.
1. Structure Plans
These look at the overall area in relation to its surroundings and lay down
industry, population and education. These plans are not detailed, but tend
to be proposed statements of policy for the area with regard to the various
2. Local Plans
These are prepared to examine in detail the local area under construction,
and to prevent problems that might arise from complications due to conflicts
24
a local plan proposing a road widening scheme in the future, which will
many cases could have been overcome, had there been consultation between
the architect and builder at an earlier stage. Shutt (1992) stated that builders
are seldom aware of many such problems until the job has progressed
long after the project has started. This point alone raises communication
On the other hand, many builders cause a lot of delays. There are
to have to seek the architect’s advice, or ask for details about certain points,
but it is not mentioned until such a late stage that delay occurs.
25
Within a building company, the type of communication system and
the speed with which it works are to a large extent a function of the size of
the organisation (Shutt, 1992). The smaller the company, the faster
network has to be developed that ensure that the information necessary for
overload “in” trays with the majority of the information being irrelevant to
The construction site is the place where the efforts made by the
design team in visualizing the client’s requirements will be put into practice
discuss the progress of the project to date, the difficulties and delays arising
between the parties can be greatly improved with the aid of site meetings
which could hold weekly. All the relevant parties like the architect, contract
26
2.4 STAKEHOLDERS IN THE CONSTRUCTION INDUSTRY
within the working group in the construction industry only when the
involve the team effort of the client, quantity surveyor, architect, consulting
27
Bills and reconciliation of material.
maintaining quality
28
Monitor the structural works for conformance with the
manual.
Engineer
2.4.1.3 Architect
29
Issue of variation orders altering extent, nature or quantity of
the works
Sees to the cost implication of the project and ensures that the
Examines the Bill of Quantity and helps in deciding the best for
of a facility
30
Valuing construction work for interim payments, valuing
early stage to ensure that good value is obtained for the money
to be expended.
31
Provides information to the pertinent parties and general public
to keep them informed and in the case that any issues arise
other, they all must communicate effectively to make the project work.
Maslej (2006) noted that larger and more complex projects will often require
32
OWNER
Prime
Consultant
Surveyo Sub -
Sub -
Contractors rs Contractors
Sub - Supplie
Supplie Contractors
rs
rs
Supplie
rs
33
internally, that is, within the company (Maslej, 2006). Figure 2.4 below
Officer in
Charge
Project Superintende
Engineer nt
Foreme Subcontractor
n s
Second –
Craftspeopl Foreme tier
e n Sub -
contractors
Craftspeopl
e
Quite often, it has been stated that the major problem facing the
DETR, 1998). Many atimes, poor communication has caused delays in the
equally charges for the extended time provided the delay was not his fault.
design and construction process. This often results in cost, schedule and
35
2005, p.67) The construction industry requires standards if it hopes to
survey strongly indicate that new tools for communication are desperately
needed in the business and that poor communication has a strong detrimental
thesis similarly agree they witness problems in their line of work as a direct
those surveyed for this study recognize the communication problem in the
Construction work demand has been on a constant rise for the past
the many labour shortages within the construction industry that begin to
4. Language Barrier
(Maslej, 2006)
time is wasted in the assembly process. To achieve this trades are scheduled
work immediately after the foundations are completed by the concrete crew.
If the concrete crew has to correct their work due to miscommunication this
in turn will delay the framing crew who will then delay all the consecutive
37
crews. Conclusively, it only takes a small misunderstanding to lead to
met.
Lack of proper project supervision can lead to schedule delays and can
significantly increase the cost of any given project. Poor communication and
Maslej (2006) also noted that language barrier was a strong contributor to
associated with hiring employees who cannot communicate freely with other
workers. Apart from the fact that the contractors take on a larger workload
Many of these immigrants have little or no English skills which can cause
The four most common causes of all deaths and fatal injuries in
machinery or some other equipment, electrical shock which are all related to
39
Dunbar (2006) stated that the purpose of a construction specification is to
that was fair and equitable. He further suggested that well written
specification writers make that are responsible for desired project quality not
CHAPTER THREE
3.1 INTRODUCTION
stressing on the inclusiveness of the chosen area of this study, the research
40
design which describes the major procedure followed in carrying out the
project, the method of data collection and finally, the analysis of data
sample size for the study is twenty construction firms. The reason for
3.3 SAMPLING
prepared in such a way that the options of the respondents were required on
the subject of the dissertation. The questionnaire was split into five sections.
41
Section A consists of fixed response questions to obtain demographic data
about the respondent and the construction firm where he works. Sections B
to E will have both fixed response and open end questions based on the
aim of the study. The respondents are to tick any of the options which
portrayed their own opinions. The open end aspects of the questionnaire will
give an insight into personal views of the respondents based on their wealth
of experience.
contact in order to supply the necessary data to be used for the project
work. Responses were collected on individual basis and also interviews were
In some cases, the difficulties are that professionals were not available
and when available to fill questionnaires and some opted for oral interview
professionals collected questionnaires and never filled them till date despite
regular visits to their sites which has resulted into time waste. Some
42
professionals actually claimed that they could not find the questionnaires
and asked for another copy but still did not fill them.
CHAPTER FOUR
The information and data collected from the professionals from the
Construction firms
Surveyors
Contractors 30 25 28%
Engineers 30 18 20%
Total 150 90 100%
Source: Field Survey (2009)
Table 4.1 shows that 90 questionnaires out of the total 150 questionnaires
44
The sample size of respondents is as analyzed below.
Engineers
Builders
Architects
Builders
Contractors Contractors
Engineers
Quantity Surveyors
Above 20 years
0-5 years
6-10 years
11-15 years
6-10 years 16-20 years
11-15 years Above 20 years
Table 4.3 clearly indicates that majority of the respondents are those whose
Above 20 years
0-5 years
6-10 years
0-5 years
11-15 years 6-10 years
11-15 years
16-20 years 16-20 years
Above 20 years
DESIGN STAGE
1 Incomplete and inaccurate drawings make 3 0 9 16 6 0.90 1
architect only
from Constructware.
Construction projects
communication on site 8
2 Site meetings lead to a faster flow of information 0 0 9 29 6 0.91 2
schedules 6
48
4 Site meetings are an important channel of 0 0 20 32 3 0.84 4
means of communicating 6
8 Poor communication is greatly reduced by 3 1 24 19 2 0.72 8
that the use of simple and direct language will enhance communication on
site. This agrees with Mehra (2009) assertion that variations in language are
CONSTRUCTION FIRMS
1 Situating the specialist near the site 6 3 2 40 2 0.74 1
49
7 6
3 Concise and written instructions 9 6 2 31 1 0.70 2
From the results of the analysis in Table 3.7, a larger number of the
respondents think that situating the specialist near the site will enhance
project delivery. This agrees with Shutt (1992) whose opinion is that having
Construction firms
50
S/N SUGGESTED SOLUTIONS 1 2 3 4 5 R.I.I RANK
1 Having a standard method of 0 0 14 16 61 0.90 1
communicating
of ambiguities
communication technology
distinct
Construction Management as
training
design stage
51
communication. This agrees with Shutt (1992) view that a communication
52
CHAPTER FIVE
RECOMMENDATIONS
following points;
on site.
3) Having a specialist from the construction firm situated near the site
will help improve the communication between the firm and the site.
5.2 CONCLUSION
felt not only within the construction industry but outside its walls.
5.3 RECOMMENDATIONS
53
1. Construction documents and drawings must be detailed in such a way
3. Having a site office with a resident engineer for as long as the project
exists will provide a link between the construction firm and the site
increasing productivity.
54
REFERENCES
Aibinu, A.A., and Jagboro, G.O. (2002). The effects of construction delays on
management in progress: tools and strategies for the ‘90s’ (Pp. 167-
Crose, N., Green, R., Mills, B. and Toner, P. (1999). Constructing the
55
Industry’s First Contractual Communication Specification. Retrieved
http://www.construcware.com/Common/Downloads/nr_comspec_08_
05.pdf
2009, from
http://www.opsu.edu/UnivSchools/LiberalArts/russGuthrie/SPCH111
3/CommDefinitions.rtf.
http://www.opsu.edu/UnivSchools/LiberalArts/russGuthrie/SPCH111
3/CommDefinitions.rtf.
56
Dexter, A. (2005, July). How to remove language barriers. Retrieved November
Health & Safety, 70(1), 37- 38. Retrieved October 29, 2006, from
38619475.
Netherlands
57
Jergeas, G. (2005) Cost/Schedule overrun in mega construction projects.
http://www.schulich.ucalgary.ca/ProjectManagement/Jergeas/APEGG
AMegaprojects2b- 2004.pdf
operate schemes: their role and place in developing countries (pp. 47-
Management Summarized.
Stewart, R.A. & Mohamed, S. (2003). Evaluating the value IT adds to the
Technology, Stockholm
http://www.economywatch.com/world-industries/construction
59
60