Power System Operation and Control
Power System Operation and Control
A
D CO
TROL
U
IT-I (2marks)
U
IT-II
1. What is the major control loops used in large generators?
The major control loops used in large generators are 1.automatic voltage
regulator (AVR) 2.automatic load frequency control (ALFC).
2. What is the use of secondary loop?
A slower secondary loop maintains the fine adjustment of the frequency,
and also by reset action maintains proper MW interchange with other pool members.
This loop is insensitive to rapid load and frequency changes but focuses instead on
drift like changes which take place over periods of minutes.
3. What is the adv of AVR loop over ALFC?
AVR loop is much faster than the ALFC loop and therefore there is a
tendency, for the AVR dynamics to settle down before they can make themselves felt
in the slower load frequency control channel.
4. What is the diff.between large and small signal analysis?
Large signal analysis is used where voltage and power may undergo
sudden changes of magnitude that may approach 100 percent of operating values.
Usually this type of analysis leads to differential equations of non-linear type. Small
signal anaysis is used when variable excursions are relatively small, typically at most
a few percent of normal operating values.
5. What is the exciter?
The exciter is the main component in AVR loop. It delivers the DC power
to the generator field. It must have adequate power capacity and sufficient speed of
response (rise time less than 0.1 sec).
6. What is the function of AVR?
The basic role of the AVR is to provide constancy of the generator
terminal voltage during normal, small and slow changes in the load.
U
IT-IV
1. Define economic dispatch problem?
The objective of economic dispatch problem is to minimize the operating cost
of active power generation.
2. Define incremental cost?
The rate of change of fuel cost with active power generation is called
incremental cost. Write the load balance equation? Pg-pd-pl=0.
3. Define base point?
The present operating point of the system is called base point.
4. Define participation factor?
The change in generation required to meet power demand is called as
participation factor.
5. Define hydrothermal scheduling problem?
The objective is to minimize the thermal generation cost with the constraints
of water availability.
6. Define Uncommitment?
Commitment of minmum generator to meet the required demand.
7. Define spinning reserve?
It is the term describe the total amount of generation availability from all units
synchronized on the system.
8. What is meant by scheduled reserve?
These include quick start diesel turbine units as well as most hydro units and
pumped storage hydro units that can be brought online, synchronized and brought up
to full capacity quickly.
9. What are the thermal unit constraint?
Minimum up time, minimum down time crew constraints.
10. Define minimum up time?
Once the unit is running, it should not be turned off immediately.
11. Define min.down time?
Once the unit is decommited, there is a minimum time before it can be
recommended.
12. Define crew constraints?
If a plant consist of two (or) more units, all the units cannot be turned on at the
same time since there are not enough crew members to attend both units while starting
up.
13. What are the two approaches to treat a thermal unit to operating
temperature?
The first allow the unit boiler to cool down and then heat backup to operating
temperature in time for a scheduled turn on. The second requires that sufficient energy
be input to the boiler to just maintain operating temperature.
14. What are the techniques for the solution of the unit commitment problem?
Priority list method dynamic programming Lagrange relation
15. What are the assumptions made in dynamic programming problem?
A state consists of an array of units with specified units operating and the rest
of the time. The startup cost of a unit is independent of the time it has been offline.
There are no costs for shutting down the units.
16. Define long range hydro scheduling problem?
The problem involves the long range of water availability and scheduling of
reservoir water releases. For an interval of time that depends on the reservoir
capacities.
17. What are the optimization technique for long range hydro scheduling
problem?
Dynamic programming composite hydraulic simulation methods statistical
production cost.
18. Define short range hydro scheduling problem?
It involves the hour by hour scheduling of all generators on a system to
achieve minimum production condition for the given time period.
19. Define system blackout problem?
If any event occurs on a system that leaves it operating with limits violated,
the event may be followed by a series of further actions that switch other equipment
out of service. If the process of cascading failures continues, the entire system of it
may completely collapse. This is referred as system blackout.
20. What is meant by cascading outages?
If one of the remaining lines is now too heavily loaded, it may open due to
relay action, thereby causing even more load on the remaining lines. This type of
process is often termed as cascading outage.
U
IT-V
1. What are the functions of control center?
System monitoring contingency analysis security constrained optimal power
flow.
2. What is the function of system monitoring?
System monitoring provides upto date information about the power system.
3. Define scada system?
It stands for supervisory control and data acquisition system, allows a few
operators to monitor the generation and high voltage transmission systems and to take
action to correct overloads.
4. What are the states of power system?
Normal state alert mode contingency mode emergency mode. Define normal
mode? The system is in secure even the occurrence of all possible outages has been
simulated the system remain secure is called normal mode.
5. Define alert mode?
The occurrence of all possible outages the system does not remain in the secure is
called alert mode.
6. What are the distribution factors?
Line outage distribution factor, generation outage distribution factor.
7. Define state estimation?
State estimation is the process of assigning a value to an unknown system state
variable based on measurements from that system according to some criteria.
8. Define max. likelihood criterion?
The objective is to maximize the probability that estimate the state variable x,
is the true value of the state variable vector (i.e, to maximize the P(x)=x).
9. Define weighted least-squares criterion?
The objective is to minimize the sum of the squares of the weighted deviations
of the estimated measurements z, from the actual measurement.
16 MARKS
1. Explain the method availabilities for providing economic operation of power
system. 2. Write short notes on load v curve load duration curve energy curve.
3. Explain about spinning reserve, hot reserve, cold reserve.
4. Explain the solution technology for solving priority list method by dynamic
programming method.
5. Explain about load forcasting & weather sensitive load model.
6. Explain the static state estimation of power system.
7. Explain the algorithm for system when operating non steady state condition.
8. How to detect and identify the bad data?
9. Derive the equation for loss coefficients?
10. Explain about base point and participation factor?
11. Explain the solution technique for solving hydro thermal scheduling problem?
12. Explain the operating states of power system?
13. Explain the preventive action taken for emergency and restorative control?
14. Write short note on long range hydro scheduling problem short range hydro
scheduling problem.
15. Explain the mathematical technique for hydro thermal scheduling problem?
16. Explain about system equivalency?