Chapter Nine Control Loops in Power System
Chapter Nine Control Loops in Power System
9.1 Introduction:
It is necessary in certain studies to know how the various load vary with frequency
and voltage. It is simple to find these relationships analytically if the load consists
of an impedance, for example, consider a series RL load. From the formula.
In other form:
The formulas reveal that both P and Q increase as the square of the voltage
magnitude, also they clarify that P decreases but Q increases with increasing
frequency.
Composite load, which constitute the majority of actual loads, also vary with
voltage and frequency. However, for this type of load the functional relationships
cannot solve analytically. The best for in a practical situation is to estimate, measure,
or by empiric method find the voltage and frequency dependency.
9.1.1 The Real Power Balance and its Effect on Power System:
There are three reason why system frequency should be kept with strict limits:
1. Most types of ac motors run at speeds that are directly related to the frequency.
2. A large number of electrically operated clocks are used. They are all driven
by synchronous motors, and the accuracy of these clocks is a function not only
of frequency error but of the integral of this error.
3. The overall operation of power system can be much better controlled if the
frequency error would kept within strict limits
The frequency is closely related to the real power balance in overall network
Under normal operating conditions the system generators run synchronously and
generate together the power that at each moment is being drawn by all loads plus the
real transmission lines, taking into account that the energy is being transmitted at the
velocity of light, and since it is not stored somewhere in the system.
9.1.2 The Reactive power Balance and Its effect on System Voltage
The unchanged bus voltage profile represent the criterion that balance is kept
between produced and consumed reactive power. Whenever the magnitude of a
particular bus voltage undergoes variations, this means that Q balance is not kept at
the that bus. Consider the two bus system shown in figure (9.1), the load P + j Q is
tapped from load bus 2. Since no generator exists at this bus, the load must be
transmitted via the line from bus 1.
Assume that:
Figure (9.1)
Identifying these three voltage terms in a phasor diagram as shown in figure (9.2)
Figure (9.2)
1. A change in the real load P affects the voltage – drop phasor which is
perpendicular to V1, there will be no change in the magnitude of V2.
2. A change in the reactive load Q affects the voltage – drop phasor which is in
phase with V1. The change of V2 is proportional to Q. ( the dotted voltage
phasor illustrate the change in V2 if the reactive load is doubled)
The opposite effect is during light – load. Due to the shunt capacitance in lines and
cables, there would be a surplus of reactive power. This means that the Q flow will
be reversed in direction and so does the phasor XQ/V1. With the results that the
voltage drop changes to voltage rise. To keep the voltage from going to high, shunt
reactors may connected to a certain points in the network.
Frequency changes occur because system load varies randomly throughout the
day so that an exact forecast of real power demand cannot be assured. The imbalance
between real power generation and load demand (plus losses) throughout the daily
load cycle causes kinetic energy of rotation to be either added to or taken from the
on-line generating units, and frequency throughout the interconnected system varies
as a result.
The topic of maintaining the system frequency constant is commonly known as
AUTOMATIC LOAD FREQUENCY CONTROL (ALFC). It has got other
nomenclatures such as Load Frequency Control, Power Frequency Control, Real
Power Frequency Control and Automatic Generation Control.
The basic role of ALFC is:
1. To maintain the desired megawatt output power of a generator matching with the
changing load.
2. To assist in controlling the frequency of larger interconnection.
3. To keep the net interchange power between pool members, at the predetermined
values.
The ALFC loop will maintain control only during small and slow changes in load
and frequency. It will not provide adequate control during emergency situation when
large megawatt imbalances occur. We shall first study ALFC as it applies to a single
generator supplying power to a local service area.
9.2.1 Real Power Control Mechanism of a Generator:
To help understand the control actions at the power plants, consider the boiler-
turbine-generator combination of a thermal generating unit.
Most steam turbo generators (and also hydro turbines) now in service are equipped
with turbine speed governors. The function of the speed governor is to monitor
continuously the turbine-generator speed and to control the throttle valves which
adjust steam flow in to the turbine (or the gate position in hydro turbines) in
response to changes in "system speed" or frequency.
The real power control mechanism of a generator is shown in figure (9.3). The
main parts are: 1) Speed changer 2) Speed governor 3) Hydraulic amplifier 4)
Control valve. They are connected by linkage mechanism. Their incremental
movements are in vertical direction. In reality these movements are measured in
millimeters; but in analysis they expressed as power increments in MW or p.u.
MW as the case may be. The movements are assumed positive in the directions of
arrows.
The position of the pilot valve can be affected via the linkage system in three
ways:
1. Directly, by moving the linkage point A “raise” or “lower” commands of the
speed governor.
2. Indirectly, via feedback, due position changes of the main piston.
3. Indirectly, via feedback, due to position changes of linkage point B resulting
from speed changer.
Corresponding to “raise” command, linkage movements will be: “A”
moves downwards; “C” moves upwards; “D” moves upwards; “E” moves
downwards. This allows more steam or water flow into the turbine resulting
incremental increase in generator output power. When the speed drops, linkage
point “B” moves upwards and again generator output power will increase.
Figure (9.3)
The governor output command ∆Pg is measured by the position change ∆ xC.
The governor has two inputs:
1. Changes ∆Pref. in the reference power setting.
2. Changes in ∆f in the speed of the frequency of the generator, as measured by
∆xB.
It is to be noted that a positive ΔPref will result in positive ΔPg, A positive
Δf will result in linkage points B and C to come down causing negative ΔPg.
Thus ΔPg = ΔPref – (1/R) Δ f
Taking Laplace transform yields
ΔPg (s) = ΔPref (s) – (1/R) Δf (s)
The block diagram corresponding to the above equation is shown in figure (9.4) R
Figure (9.4)
The speed-versus power output governing characteristic of each unit has
droop, which means that a decrease in speed should accompany an increase in
load, as depicted by the straight line. See figure (9.5)
Figure (9.5)
The speed regulation Ru of the generating unit is defined as the magnitude of the
change in steady-state speed. Expressed in per unit of rated speed, when the output
of the unit is gradually reduced from 1.00 per-unit rated power to zero.
Thus, per-unit regulation is simply the magnitude of the slope of the speed-versus-
power output characteristic when the frequency axis and the power-output axis are
each scaled in per unit of their respective rated values.
In practice, both the frequency and the power can be expressed in per unit.
Where: f2: frequency (Hz) at no load.
f1: frequency (Hz) at rated megawatt out put
fR :rated frequency (Hz) of the unit
SR: megawatt base
9.2.2 Static Performance of Speed Government
At steady state, ΔP0 is equal to ΔPg. i.e. ΔP0 = ΔPg 0, consider the following three
cases.
ΔPg 0 = ΔPref 0 – (1/ R1) Δ f 0
Case A: The generator is synchronized to a network of very large size, so large in
fact, that its frequency will be essentially independent of any changes in the power
output of this individual generator (“infinite” network).
Since Δf0 = 0, the above equation becomes:
ΔPg 0 = ΔPref 0
Thus for a generator operating at constant speed, (or frequency) there exists a direct
proportionality between turbine power and reference power setting. When the
generator is operating at constant frequency, if the speed changer setting is
INCREASED, (DECREASED) turbine output power will increase (decrease) to that
extent.
Example 1: A 100-MW, 50-Hz generator is connected to “infinite” network. How
would you increase its turbine power by 5 MW?
Sol.: Its turbine power can be increased by 5 MW by simply giving a “raise” signal
of 5 MW to the speed changer motor.
Case B: Now we consider the network as “finite”. i.e. its frequency is variable. If
the speed changer is kept at constant setting. i.e. ΔPref = 0.
Since ΔPg 0 = ΔPref 0 – (1/ R) Δ f 0
Then ΔPg 0 = (- 1 / R) Δ f 0
1. The above equations show that for a constant speed changer setting, the static
increase in turbine power output is directly proportional to the static frequency drop.
2. The above equation can be rewritten as Δ f 0 = - R ΔPT 0. This means that the plot
of f0 with respect to PT 0 (or PG 0) will be a straight line with slope of – R.
Case C: In general case, changes may occur in both the speed changer setting and
frequency in which case the relationship ΔPg 0 = ΔPref 0 – (1/ R) Δf 0 applies.
This means that for a given frequency, generation power can be increased or
decreased by suitable raise or lower command. Thus the relationship ΔPT 0 = ΔPref 0
– (1/ R) Δf 0 represents a family of sloping lines. See figure (9.) which represents the
static frequency-power response of speed governor (R = 0.04 p.u.).
The thick line shows that corresponding to 100% rated frequency, the output power
is 100 % of rated output. But for the new speed changer setting as shown by the
dotted line, for the same 100% rated frequency, output power is 50 % of rated output.
Hence the power output of the generator at a given frequency can be adjusted as will,
by suitable speed changer setting. Such adjustment will be extreme importance for
implementing the load division as decided by the optimal policy.
Figure (9.6)
On solving the above, x = 72.73 MW and 200 - x = 127.27 MW. Thus Load on
machine 1 = 72.73 MW; Load on machine 2 =127.27 MW
Which combines with the additional outputs of the other units to satisfy the load
change ∆P of the system. The units would continue to operate in synchronism at the
new system frequency except for the supplementary control exercised by the AGC
system at the energy control center of the area in which the load change occurs. Raise
or lower signals are sent to some or all the speed changers at the power plants of the
particular area. Through such coordinated control of the set points of the speed
governors it is possible to bring all the units of the system back to the desired
frequency f0 and to achieve any desired load division within the capabilities of the
generating units.
Therefore, the governors of units of the interconnected system tend to maintain load-
generation balance rather than a specific speed and the supplementary control of the
AGC system within the individual control area functions so as to:
• Ensure the desired economic dispatch output of each area plant, and
• Allow the area to do its share to maintain the desired system frequency.
The areas are connected to each other by tie-lines. The most important difference
between a normal transmission line and a tie-line is that in normal operation the
power flows in the transmission line is
Sij = Vi Iij*
Which means that it in this case it is essential to take into account the frequency
differences between the two areas
Figure (9.8) shows the block diagram indicates the flow of information in a
computer controlling a particular area.
Position 5 indicates the subtraction of the frequency bias from (Pa – Ps) to
obtain the ACE (Area control error), which may be positive or negative. As
an equation
The ACE (area control error) is continuously recorded within the energy
control center to show how well the individual area is accomplishing these
tasks.
A negative ACE means that the area is not generating enough power to send
the desired amount out of the area. There is a deficiency in net power output.
Without frequency bias, the indicated deficiency would be less because there
would be no positive offset (10 Bf ∆f) added to Ps (subtracted from Pa) when
actual frequency is less than scheduled frequency and the ACE would be less,
the area would produce sufficient generation to supply its own load and the
prearranged interchange but would not provide the additional output to assist
neighboring interconnected areas to raise the frequency.
The load increased by 100 Mw, then the per unit frequency deviation is:
Since fR is 60 Hz, then the frequency is changed by 0.24 Hz, and the new frequency
of operation is 59.76.
The load located for each unit is:
The large number of generators and governors within a control area combine to
yield an aggregate governing speed-power characteristic for the area as a whole. For
relatively small load changes this area characteristic is often assumed linear and then
treated like that of a single unit of capacity equal to that of the prevailing on-line
generation in the area. On this basis, the fo1lowing example demonstrates the steady-
state operation of AGC for a three-area system in which losses are neglected.
Example 6: Three control areas with autonomous AGC system comprise the
interconnected 60-Hz system shown in figure (2). The aggregate speed-droop
characteristics and on-line generating capacities of the areas are:
Each area has a load level equal to 80% of its rated on-line capacity. Area C is
importing 500Mw of its load requirements from area B, and 100Mw pass over the
tie line of area A, which has zero scheduled interchange. Determine:
1. The system frequency deviation and the generation changes of each area when a
full loaded 400Mw generator is forced out of service in area B. The areas
frequencies are: BfA = - 1200 Mw/ 0.1 Hz
Sol. 1)
2)
Ideally, the ACE in areas A and C would be zero. The predominating ACE is
in area B where the 400-MW forced outage occurred. The AGC system of area B
will command the on - line power plants under its control to increase generation t
offset the loss or the 400-MW unit and restore system frequency at 60 Hz. Areas A
and C then return to their original conditions.