PROCESS FLOW DIAGRAM

Material Balance

 Thermic Fluid
Q = m x Cp x T
10,00,000 = m x 0.5 x 20 = 100000kg/hr
Hence, m = 1,00,000 kg/hr
Vol flow rate = 100000/ 800 = 125 m3/hr

 Furnace Oil
required = 10,00,000/(9650x0.83) = 124.842 kg/hr
Vol flow rate = 124.842/900 = 0.137 m3/hr
 Air
Basis : 100 kg fuel
84 kg C  84/12 x 32 = 224 (CO2)
11 kg H 11/2x16 = 88 (H2O)
3.5 kg S
Total = 315.5 kg
Total O2 required theoretically = 315.5 x 124.8/100 = 393.89 kg/hr
CONSIDERING 20 % Excess
Therefore, O2 supplied = 472 kg/hr
Kmoles of O2 = 472/32 = 14.78
Hence Air required = 14.78x 29/0.21 = 2039.8 kg/hr
Density of air at 1 atm pressure & 30 deg C
= 29 / (22.4x303/273) = 1.167 kg/m3
Hence, volumetric flow rate of air reqd = 2039.8 /1.167 = 1757.75
m3/hr
ELECTRICITY:
1. THERMIC FLUID PUMP:
POWER = (PRESSURE DEVELOPED X VOL. FLOW
RATE)/ EFFECIENCY
= (400 KPa X 125 X1000)/(3600 X 0.6 X 1000)
= 23.14 KW (ASSUMING PRESSURE
DEVELOPED = 4-5 BAR)
POWER = 23 KW
2. FUEL PUMP:
POWER = (PRESSURE DEVELOPED X Q)/EFF.
= 20 X 100000 X 0.1387/(3600 X 1000 X .5)
= 0.154KW
POWER = 0.15 KW
3. Air blower:
(pressure = 200 mm water column)
Power = (.2 x 1000 x 9.81) X 1757.75)/3600 X 1000 X .8
= 1.12 KW

BASIS OF DESIGN
 No. of hours per day, plant is operational: 16
 No. of days per annum, plant is operational: 300
 Raw materials and utilities
o Thermic Fluid
o Furnace oil
o Electricity
 Consumption of raw materials:
o Thermic fluid = 1,00,000 Kg/ hr
o Furnace oil = 98.04 Kg/hr
o Electricity =
 AIR = 2039.8 Kg/hr
EQUIPMENT LIST:
1. Burner Assembly (2.2 x 1.5 x 3)
2. Storage Tank
3. Pump : a) thermic fluid pump : 22 KW (1 S + 1 W)
b) fuel pump : 1/6 hp
4. Expansion cum De-aerator Tank (5 – 10 % rise in volume)
5. Blower : 2hp