Process Flow Diagram

This document provides a process flow diagram and material balance for a thermic fluid heating system. It calculates material flow rates for thermic fluid, furnace oil, and air needed using heat transfer equations. Electricity requirements are estimated for pumps and blowers. Key operating parameters and a basic equipment list are also provided.

Uploaded by

Pratyaksh Jain
Copyright
© Attribution Non-Commercial (BY-NC)
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
59 views

Process Flow Diagram

This document provides a process flow diagram and material balance for a thermic fluid heating system. It calculates material flow rates for thermic fluid, furnace oil, and air needed using heat transfer equations. Electricity requirements are estimated for pumps and blowers. Key operating parameters and a basic equipment list are also provided.

Uploaded by

Pratyaksh Jain
Copyright
© Attribution Non-Commercial (BY-NC)
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 4

PROCESS FLOW DIAGRAM

Material Balance

 Thermic Fluid
Q = m x Cp x T
10,00,000 = m x 0.5 x 20 = 100000kg/hr
Hence, m = 1,00,000 kg/hr
Vol flow rate = 100000/ 800 = 125 m3/hr

 Furnace Oil
required = 10,00,000/(9650x0.83) = 124.842 kg/hr
Vol flow rate = 124.842/900 = 0.137 m3/hr
 Air
Basis : 100 kg fuel
84 kg C  84/12 x 32 = 224 (CO2)
11 kg H 11/2x16 = 88 (H2O)
3.5 kg S
Total = 315.5 kg
Total O2 required theoretically = 315.5 x 124.8/100 = 393.89 kg/hr
CONSIDERING 20 % Excess
Therefore, O2 supplied = 472 kg/hr
Kmoles of O2 = 472/32 = 14.78
Hence Air required = 14.78x 29/0.21 = 2039.8 kg/hr
Density of air at 1 atm pressure & 30 deg C
= 29 / (22.4x303/273) = 1.167 kg/m3
Hence, volumetric flow rate of air reqd = 2039.8 /1.167 = 1757.75
m3/hr
ELECTRICITY:
1. THERMIC FLUID PUMP:
POWER = (PRESSURE DEVELOPED X VOL. FLOW
RATE)/ EFFECIENCY
= (400 KPa X 125 X1000)/(3600 X 0.6 X 1000)
= 23.14 KW (ASSUMING PRESSURE
DEVELOPED = 4-5 BAR)
POWER = 23 KW
2. FUEL PUMP:
POWER = (PRESSURE DEVELOPED X Q)/EFF.
= 20 X 100000 X 0.1387/(3600 X 1000 X .5)
= 0.154KW
POWER = 0.15 KW
3. Air blower:
(pressure = 200 mm water column)
Power = (.2 x 1000 x 9.81) X 1757.75)/3600 X 1000 X .8
= 1.12 KW

BASIS OF DESIGN
 No. of hours per day, plant is operational: 16
 No. of days per annum, plant is operational: 300
 Raw materials and utilities
o Thermic Fluid
o Furnace oil
o Electricity
 Consumption of raw materials:
o Thermic fluid = 1,00,000 Kg/ hr
o Furnace oil = 98.04 Kg/hr
o Electricity =
 AIR = 2039.8 Kg/hr
EQUIPMENT LIST:
1. Burner Assembly (2.2 x 1.5 x 3)
2. Storage Tank
3. Pump : a) thermic fluid pump : 22 KW (1 S + 1 W)
b) fuel pump : 1/6 hp
4. Expansion cum De-aerator Tank (5 – 10 % rise in volume)
5. Blower : 2hp