PROJECT STATUS UPDATE

MUYENGA TANK HILL APARTMENTS:

N PROJECT INCHAR STRUCTUR STRUCTUR STRUCTURAL


O GE AL AL DESIGN DRAWINGS
PHILOSOPH
Y
STATUS
1. PAKUBA SAFARI AM/AK Done Done In progress 98%
LODGE Complete
2. SCANIA VK/FA/RK Done Done In progress 95%
SHOWROOM & Complete
WORKSHOP
3. MUYENGA TANK AM/GM Done In progress In progress 30%
HILL APARTMENTS complete
4. GOLF COURSE VK/GM Awaiting Awaiting Awaiting
APPARTMENTS Architectural Architectural Architectural
drawings drawings drawings(structu
ral appraisal of
existing
structure in
progress)
5. EMIN PASHA HOTEL FA/RK Done done In progress 80%
complete

APARTMENT BLOCKS (A, B, C & D):

Foundation layout drawings for blocks A & B done, column and column base details
drawings completed, slab reinforcement details drawings done, roof layout and
details to be completed on 6th November 2010, Details for blocks C & d to follow on
Monday 8th November 2010

CLUB HOUSE:

Scheming completed, production of structural drawings in progress (we are however


waiting for clarifications on the levels around splash pool area.)

SWIMMING POOLS:

Main swimming pool Details to be provided tomorrow 4th November 2010

EXTERNAL WORKS

Walkway and Driveway Drawings to be issued on Monday 8th November 2010

Drainage details to follow on Wednesday 10th November 2010

STRUCTURAL SPECIFICATION OF WORKS:


Structural specifications of works to be issued tomorrow 4th November 2010

EMIN PASHA HOTEL PROPOSED


EXTENSIONS

Drawings to be issued pending date of


BLOCK today drawings issue
kitchen and roof layout and truss
health club details staircases 8/11/2010

beam layout and reinf't foundation


conference hall details layout 4/11/2010
slab layout and reinf't column reinf't
details details 4/11/2010
water tank slab
reinf't 4/11/2010
ramp 8/11/2010
staircase 8/11/2010

roof layout and truss foundation


New office block details details 8/11/2010
first floor slab reinf't
first floor beam reinf't
column reinf't

foundation layout and


Guest suites details roof slab details 5/11/2010
first floor slab layout and
reinf't
first floor beam reinf't
column reinf't