Fps & Fapa 7th August
Fps & Fapa 7th August
Fps & Fapa 7th August
07-08-2020
Subject : Site Progress Report ( Internal, External, Ancillary Building )
Vendor : Powerconz
Service
1 : Fire Fighting & FAPA System
Resource Sheet – Manpower
Contractor Staff Contractor Labour
Sr.No Manpower No.s Sr.No Manpower Area No.s
7 Quality Engineer
8 Contracts
9 Admin
10 Store In charge
11 Purchase
12 Accounts
13 Safety Asst. 1
2
2
SITE TOOL BOX TALK (TBT) REPORT & PICTURES
3
SITE TOOL BOX TALK (TBT) REPORT & PICTURES
4
Ware House – Internal Sprinkler Below Mezzanine
Sl. No Activities Description Start Date End Date Current Status as on date
Electrical/FPS/HVAC Works
5
Ware House – Below Mezzanine
Progress till Date
8 Final Painting
7
Progress Pictures - Below Mezzanine Sprinkler
7th
Progress
8
Ware House – Internal Sprinkler Above Mezzanine
Sl. No Activities Description Start Date End Date Current Status as on date
FPS
1 08-Aug-20 50 % Completed
22-July-20
Erection Activities
2 Testing 14-Aug-20 10-Aug-20
3 Snag Work 09-Aug-20 10-Aug-20
4 Measurement 09-Aug-20 10-Aug-20
5 As Build 09-Aug-20 10-Aug-20
6 Handing Over Draft Copy Submision 09-Aug-20 10-Aug-20
7 Handing Over hot Copy Submision 09-Aug-20 10-Aug-20
8 System Commissioning 09-Aug-20 10-Aug-20
9 Completion Certificate 09-Aug-20 10-Aug-20
9
Ware House – Internal
Progress till Date
2 Support fabrication & Fixing Zone 2&4 - 12/12 Nos 12/12 Erection Balance
3 Header erection Not Planed
4 Branch Fabrication Zone 2&4 - 356 / 376 286 / 376 Pipe Required
5 Branch pipe Erection Zone 2&4 - 0 / 376 0 / 376 163 Mtrs Erection Done
6 Tapping with header & Final Welding Not Started
7 Sprinkler Fixing & Final Painting Not Started
10
Progress Pictures – Above Mezzanine
11
Progress Pictures – Above Mezzanine
12
Ware House – Ancillary Building
Sl. No Activities Description Start Date End Date Current Status as on date
FAPA
1 • Till 13th Bay Beam Device Completed
• PA & FAS Till 13th Bay Completed With
Device
14-Jul-20 05-Aug-20 • Ancillary Building 1st,2nd Set Toilet with
Erection Activities Cabling and Device & Canteen Cabling Done
2 Pre Commissioning 06-Aug-20 08-Aug-20 Zone -1 and 1st & 2ndSet Toilet 1 Completed
3 Fire Logic testing 08-Aug-20 09-Aug-20
4 Testing 08-Aug-20 09-Aug-20
5 Snag Work
6 Measurement 10-Aug -20 11-Aug-20
7 As Build 10-Aug -20 11-Aug-20
8 Handing Over Draft Copy Submission 10-Aug -20 11-Aug-20
9 Handing Over hot Copy Submission 10-Aug -20 11-Aug-20
10 Completion Certificate
14
Progress Pictures – FA & PA Inside Rack Area
15
Progress Pictures – FA &PA
16
Ware House – Ancillary Building
Sl. No Activities Description Start Date End Date Current Status as on date
FPS
17
Ware House – Ancillary Building
Progress till Date
18
Progress Pictures – Ancillary Building
19
Progress Pictures – Ancillary Building
20
Quality Observation / Compliance Pictures
21
Quality Observation / Compliance Pictures
22
Quality Observation / Compliance Pictures
23
Handing Over Documents Submission Status
Sl. Description Submission Date of Submission Remarks
No Status
1 CONTRACT SPECIFICATIONS/PO COPY yes
Yes
2 WORK COMPLETION CERTIFICATE
5 GA DRAWINGS YES
6 OPERATIONAL MANUALS / DATASHEETS / CATALOGS OF ALL SUPPLIED AND INSTALLED ITEMS YES
8 WILL BE
ATTIC STOCK LIST SUBMITED
9 RECOMMENDED SPARE PARTS & CONSUMABLES LIST N/A
25