Technical Specification of 11Kv & 33Kv Oil Immersed CT:PT (Metering Equipment) Units
Technical Specification of 11Kv & 33Kv Oil Immersed CT:PT (Metering Equipment) Units
Technical Specification of 11Kv & 33Kv Oil Immersed CT:PT (Metering Equipment) Units
1.0 SCOPE: -
1.2 The specification covers Oil immersed naturally Air cooled (type ONAN)
outdoor type 11 KV and 33 KV metering equipment (ME) units which shall
comprise 3 nos C.Ts conforming to IS-2705: 1992 and 1 no three phase
PT conforming to IS: 3156:1992. 11 KV and 33 KV ME units shall be
suitable for 50 Hz frequency & for service under the system conditions
having frequency fluctuations of +/- 4% and voltage fluctuation of + 9% /
-13.5%.
2.0 STANDARDS:
All the parts & surface, which are subject to corrosion shall either be
made of such material or shall be provided with such protective finish,
which provides protection from any injurious effect of humidity.
S. Particulars Requirement
11 KV 33 KV
no
1 Frequency. 50 HZ
2 Specification of CT and PT of Metering Unit
A Current Transformer
i CT Ratio As per schedule I As per schedule I
ii Dual CT ratio for Energy Audit 300-150/5A 400-200/5A
iii Accuracy Class 0.5
iv VA burden 10 VA
v Power Frequency withstand 28KV(rms) 70KVrms
voltage
vi Lightning impulse with stand 75 KV (peak) 170 KV peak.
voltage
vii Short time thermal current rating (i) 6.4 KA for 1 Sec. for CT having
in KA. primary current up to 15 AMP for
single ratio.
110V 110V
ii VA burden per phase 30 VA
iii Class of accuracy 0.5
iv Power Frequency withstand 28 KV (rms) 70 KV (rms)
voltage
v Lightning impulse with stand 75 KV peak 170 KV peak
voltage
vi Winding connection Star/ Star Star/ Star
3 Maximum attainable winding 85° C
temperature
4 a Minimum phase to phase 255mm 430mm
distance
b Shortest distance between metal 190 mm 380mm
part & earth
c Creepage distance of HV bushing 300mm (Min) 900mm (Min)
5 Gauge of the MS tank - Min 5 mm for top cover and bottom
6.0 CT: PT
6.2 The primary of PTs shall be 3 phase star connected with HV side neutral
floating. The primary winding has to be designed for unearthed neutral for
the highest system voltage i.e. 36 KV for 33 KV and 12 KV for 11 KV. PT
winding should have uniform insulation throughout from terminal to
neutral end, and not the graded insulation. The 11 KV metering unit
should be suitably designed for with-standing the unbalanced voltages
developed due to single phasing operation during load regulatory
measures in 11KV distribution system. It should be capable of
withstanding the disturbance of back e.m.f., magnetic characteristic and
consequential mechanical inter-play of forces, if any, under such single
phasing. Secondary winding of PT should be three phase star connected
with neutral brought out. On secondary side of PT four terminals shall be
marked as r, y, b and n. No PT fuses are to be provided either on primary
side or on secondary side.
6.3 The conductor in the secondary winding of the CT shall not be less than
14 SWG/3.24 sq.mm.
6.4 Normal current density shall not be more than 1.5 Amps/ sq.mm. in
primary winding of the CT.
7.3 The tank should be given three coats of rust preventing paint and
finished with light grey No.631-IS-5 on all external surfaces. The internal
surface of the tank shall be painted with two coats of a suitable oil-
insoluble paint.
7.4 The ME shall be supplied complete with duly filled Transformer oil
conforming to IS:335–1982 with latest amendment thereof. The test
certificate of oil being used shall be provided at the time of inspection.
The oil in the ME shall be filled under vacuum. Oil drain valve or sampling
cock or non return type oil filling valve provided to facilitate factory
processing shall be sealed before dispatch of MEs.
7.5 The ME shall be hermetically sealed and shall be provided with a oil
conservator, having oil level gauge, of adequate size to facilitate
expansion/ contraction of oil due to change in temperature. The total
volume of conservator shall be such as to contain 10% quantity of the oil.
Normally minimum 3% quantity of the total oil shall be contained in the
conservator. The volume above the oil level in the conservator tank shall
be filled with Nitrogen gas conforming to commercial grade as per
IS:1747:72.
7.8 The pressure of Nitrogen gas, pressure release device and explosion vent
diaphragm shall be properly coordinated.
7.9 The ME shall be fitted on HV side with outdoor type porcelain bushings of
appropriate voltage & current. These bushings shall conform to
IS:2099:1986. Further, sealing arrangement shall be such that oil should
not leak out from the bushing/ME tank. For gasket joints, wherever used,
nitrite butyl rubber gaskets/neoprene or any other improved material
shall be used. The gasket shall be fitted in properly machined groove with
adequate space for accommodating the gasket under compression. It
should be ensured that the quality of gaskets used between the joints and
also for mounting of oil level indicator will be of best quality to avoid
leakage of oil. The quality of gasket should be selected keeping in mind
the ambient temperature of 50ºC. The end turns insulation of PT HV
winding towards bushing side should be appropriately enhanced. The
dimensions and electrical characteristics of the bushing shall be in
accordance with relevant ISS and its subsequent amendments, if any. The
minimum electrical clearance between phases and phase to earth shall be
provided as specified in relevant ISS.
7.10 The insulating materials for winding between HV & LV between interlayer
of the winding and for end turn shall be as per relevant ISS. However,
end turns have to be provided with enhanced insulation and lead
connecting the bushing shall be provided extra insulation of fiber glass
sleeve.
7.11 The metering equipment shall have a built-in secondary terminal box.
Entry of cable into the box on the dual ratio metering unit shall be
through one no. gland & check nut. Metallic cable gland to suit 12 core
2.5 Sq.mm armoured copper cable shall be supplied with ME. For single
ratio ME, entry of the cable shall be through GI pipe of size (1.25" dia)
40mm dia, therefore one no. cable entry to suit 40mm dia. GI pipe shall
be provided.
7.12 In single ratio MEs, the location of the secondary terminal box shall be
with top fitting cover and the level of the cover shall be aligned with top
cover of ME. For Dual ratio MEs, the secondary box may be provided on
side wall of the tank with side cover. The ratio changing arrangement (for
dual ratio ME only) should be provided on secondary side. The top of the
tank will have slope to drain the rainwater. The fixing of conservator on to
the top cover of metering unit shall be such as to avoid the collection of
air pockets inside tank.
7.13 Top cover flange of metering unit should be provided with holes for
proper sealing arrangement at all four corners of the tank and cover.
Secondary terminal box cover should have 8 nos. nuts & bolts with hole
for sealing arrangement. For this, 8 nos. holes should be provided on the
cover & flange of secondary terminal box at the corners & middle of each
face for fixing nut bolts.
b. All castings shall be free from blow holes, surface blisters, cracks
and cavities. All sharp edges should be rounded off.
8.0 Earthing:
The assembly comprising of chassis, frame work and the fixed parts of the
metal casing of the combined CT:PT metering equipment shall be provided
with two separate earthing terminals in accordance with clause 5.2 of
IS:3156 (part-I)
9.0 TESTS:
The design of metering unit shall be type tested for short time current
test, temperature rise test, lightning impulse test, accuracy test, high
voltage power frequency voltage withstand test as per IS-2705/1992 and
IS-3156/1992 (with latest amendment) from CPRI, ERDA or any other
NABL accredited lab.
10.0 Guarantee:
The MEs shall have to be guaranteed for a period of 18 months from the
date of supply or 12 months from the date of use, whichever is earlier.
During performance guarantee period, if any defect is observed in MEs,
the same shall have to be replaced by the supplier free of cost within 30
days of intimation.