Gantt Chart
Gantt Chart
Gantt Chart
Task Name Project Planning Phase Project Identification and Initiation Identify the opportunity by meeting with the users or finding an organization. Writing the Statement of the Problem Writing the Objectives Determine the Scope and Limitations Significance of the Study Writing the System Request Research Methodology Feasibility Analysis Technical Economic Organization Project Management Creates the Work Plan Develop Work Break down Structure Project Work Plan Gantt Chart
Duration 25 days 18 days 5 days 1 day 1 day 2 days 1 day 1 day 1 day 6 days 2 days 2 days 2 days 7 days 7 days 2 days 2 days 2 days
Start Mon 11/28/11 Mon 11/28/11 Mon 11/28/11 Mon 11/28/11 Mon 11/28/11 Mon 11/28/11 Mon 11/28/11 Mon 11/28/11 Mon 11/28/11 Mon 11/28/11 Mon 11/28/11 Mon 11/28/11 Mon 11/28/11 Mon 12/5/11 Mon 12/5/11 Mon 12/5/11 Tue 12/6/11 Wed 12/7/11
Finish Fri 12/9/11 Sat 12/03/11 Sat 12/03/11 Mon 11/28/11 Mon 11/28/11 Tue 11/29/11 Mon 11/28/11 Mon 11/28/11 Mon 11/28/11 Tue 11/29/11 Tue 11/29/11 Tue 11/29/11 Tue 11/29/11 Fri 12/09/11 Thu 12/08/11 Tue 12/06/11 Wed 12/07/11 Thu 12/08/11
Predecessors
Resource Name Cora, Marlyn, Chestere Cora, Marlyn, Chestere Cora, Marlyn, Chestere
3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
3,5,6,7 8 8,9
Cora Cora, Marlyn, Chestere Cora, Marlyn, Chestere Chestere Cora Marlyn Cora, Marlyn, Chestere Cora, Marlyn, Chestere Marlyn Cora Chestere
(Continued)