Reuse of Foundations
Reuse of Foundations
Contents
Acknowledgements Preface 1 2 3 4 5 6 7 Introduction Principal Drivers for Foundation Reuse Modes of Foundation Reuse Ultimate Bearing Capacity of Pile Foundations Assessment of Pile Integrity and Pile Capacity Case Study Conclusions References Bibliography iii iv 1 4 7 10 17 22 26 27 30
ii
Acknowledgments
After praising and thanking Allaah, I would like to thank my supervisor Dr Richard Goodey for his continuous support and enduring patience from since the beginning of the project right till the very end. I am truly grateful for the help Dr Goodey provided in seeking out the resources and for his review of my drafts especially at times of urgency.
iii
Preface
Foundation Reuse has been reported as a highly relevant issue in modern-day construction, and it concerns developers, building-owners and construction professionals. Eightyfour respondents from the EU attested to its relevance via a questionnaire survey carried out by the RuFUS Project in 2003 (Butcher, et al., 2006). The aim of this project is to provide a technical yet simple outlook on the feasibility of reuse of foundations in contemporary construction. It was not intended for the project to be comprehensive, although care has been taken to specifically discuss this topic from a variety of angles. The initial chapters focus on introducing the topic at hand, reviewing the history and the various modes of reusing foundations; the concluding chapters identify different methods of verifying pile integrity, and discuss technical aspects such as the increase in Ultimate Pile Capacity over time.
iv
1. Introduction
Foundation reuse is not something new, and has been a key aspect in the development of towns and cities, from controlling urban sprawl to preservation of historical heritage. This section shall focus on defining what reuse of foundation is, stating the aims and objectives of the overall project, and finally concluding by briefing the reader on the historical facet of this topic. 1-1 OBJECTIVES This project seeks to verify the principal driving factors for the reuse of foundations, identify the various modes of foundation reuse, analyse the phenomenon of increase in Ultimate Bearing Capacity of pile foundations, and to critically appraise the methods for assessing the capability of piles for reuse. 1-2 WHAT DOES REUSING FOUNDATIONS MEAN? The reuse of foundations entails utilizing existing foundations at a site to provide support for a new structure that is to be built upon it. Butcher, et al. (2006) state that reuse of foundations does not always involve the usage of old foundations in or on the ground; rather foundation reuse may even imply the re-usage of the facade of a building whilst the interior parts of a building is rebuilt.
1-3 HISTORICAL BACKGROUND Reusing foundation for construction of new structures is not a new phenomenon and has been implemented in practice throughout the ages. Chapman, et al. (2007) state the reusing of foundations throughout history to be a norm rather than an exception. In Great Britain, the castles and cathedrals of old were constructed and then reconstructed upon old and existing foundations. During the Elizabethan times, imposed laws
Figure 1: The Great Fire of London, 1666
foundations in a bid to prevent urban congestion. Ackroyd (2001, as cited in Chapman, et al., 2007) quotes that Kind Charles II was informed after the extinguishment of the Great Fire of London, Some persons are already about to erect houses again in the City of London upon their old foundations. With the passage of time, the force loads of buildings increased due to their bulkiness, and the level of performance expected from these buildings increased as well. The methods via which foundation requirements are calculated had become far more reliable and advanced. As a result of all of these, new buildings were often raised on completely new foundations, which avoided aesthetic and structural damage. Flack (2004) reports that up until the 1950s, most of the buildings around London were built on shallow foundations and typically had one basement level. Post-1950s, due to the increase in demand from developers to build taller buildings with longer floor spans, bored piles have been in commonly applied thanks to the presence of London Clay in many construction sites. Bored piling was chosen due to the quickness of installation, quietness and due to this being a cost-effective method to support tall structures. This dramatic change in history was a cause for concern.
As for the most recent times, Chapman, et al. (2006, as cited in Butcher, et al., 2006) state that foundations have been re-engineered and successfully reused on projects such as railway bridges and major building projects such as the Empress State Building and Thames Court.
archaeology underneath the ground, in case of driven piles, standing buildings (of historical importance) also pose a threat to pile driving operations, especially if any damage is preconceived to occur by the operations. Although in most cases the archaeology is preserved in-situ and is hidden from public view; in certain cases the archaeology is incorporated into the new building structures and displayed for viewing, such as in the case of the Guildhall Art Gallery (Ganairis and Bateman, 2004, cited in Butcher, et al., 2006). Existing foundations may be utilized to support
Figure 3: Guildhall Art Gallery Basement with Preserved Roman Amphitheatre
due to the advance in technology and understanding regarding the behavior of piles over time. The Ultimate Bearing Capacity of the existing piles may increase, making them capable of carrying higher loads than performed previously. If there was no time for the capacity of foundations to increase, then one may consider if overcapacity had been incorporated into the previous design for safety reasons. In that case the (additional) reserve capacity means that the piles will be able to carry higher loads, albeit, at a lower safety rating. The relationship between Ultimate Bearing Capacity of piles with time shall be discussed in proceeding chapters. A key driver to the reuse of existing foundation is the economic factor, which is of interest to the developers and buildings owners. As a result of reusing existing foundations, the need for site investigation is reduced; the time taken to construct the new structure is reduced as well, which would otherwise be lengthened due to installation of new piles. The reduction in the project duration further reduces the costs to the developer by bringing closer the profits to be made via sale or renting etc. of the properties, and as a result shortening the time for payback of the (borrowed) capital (which most likely includes interest). Should the developer decide to
remove existing piles, this has proven to be an ardent and a very costly task. Again, reusing existing foundations seems ideal for cost-effectiveness. To add, the change in legislation regarding the disposal of waste and the classification of waste products (such as hazardous waste) adds to the cost of installing new piles (especially in case of bored piling) and removing the existing foundations. The impact of construction-work on the environment also has to be taken into account. The reuse of foundations can significantly reduce the use of natural resources, reduce the total amount of energy used (since more piles will not be removed or installed), induce a reduction in groundwater pollution that is caused by construction, reduce the amount of waste produced, as well as reducing the amount of carbon emission caused by the utilization of plant and equipments (for installing and removing piles). Finally, reusing foundations will allow future buildings to be constructed without difficulty or high expense, which would have otherwise resulted from unnecessary ground congestion. As a result of heavy ground congestion, such that it is very difficult to build new structures atop the site, there would raise cases where the development would proceed to more Greenfield sites, and then under the same regime of installing new piles, over time ruining those sites as well.
3-3 INSTALL NEW PILES; IGNORE EXISTING PILES Thirdly, new pile foundations may be installed without removing the existing piles (and just ignoring them). In these cases, new piles often need to be squeezed in between the existing piles due to the ground congestion caused by the existing piles. If it is not possible to squeeze the new piles in between the existing piles, then the new piles may have to be installed away from the designed column positions. As a result, large transfer structures occur between the columns and the piles; higher capacity piles are thus needed, thereby increasing the cost and time of the program. This is the oft-implemented method in contemporary construction due to the ease of implementation, but unfortunately this leads to an increase in ground congestion and creates problems for future development. Furthermore, if the site consists of existing historical archaeology, then repeatedly installing new piles can cause severe damage, and this is highly undesirable and may act adversely against the developer. 3-4 REMOVE OLD PILES; INSTALL NEW PILES The fourth and final method of reusing foundation is to completely remove the old, existing pile foundations, and then to replace them with new piles. In case of deep obstructions which are on the column grid of the new structure, the piles may need to be removed, especially if the existing piles do not have sufficient load-bearing capacity. Also, in cases where the old foundations were installed through or around archaeological remains, it would be undesirable to install more piles, so the old piles would have to be removed and the new piles installed in the existing grid layout without disturbing the archaeological remains. Reinforced piles may be removed from the ground by cutting out a circle of soil around perimeter of the pile, thereby separating the pile from the surrounding soil, and then lifting the pile from the ground. If the piles were not fully reinforced, then care has to be taken when
removing them as this may lead to rupture of the pile shafts. A standard solution to this is to use rock-boring equipment to break the piles into smaller pieces to be then lifted onto the ground. There are several downsides to this type of foundation reuse. Other than the increase in time and cost of the program, this method risks the lowering of the capacities of the new piles due to the softening of the ground caused by removal of the old piles; voids created by the disturbance may have to be backfilled by material that has to be suitable for both supporting the surrounding soil structure as well as the new piles.
10
dimensions, the methods of pile installation (i.e. driving, boring), the condition of the pile tip whether it is open-ended or close-ended , the conditions of loading (such as piles being loaded under tension or compression), the rate of load application, time elapsed post-installation; all of these are driving factors to the change in ultimate capacity of pile foundations. 4-3 ULTIMATE CAPACITY INCREASE DUE TO CHANGE IN GROUND CONDITIONS The Ultimate Capacity of a pile is usually estimated via static pile formulas and then this is confirmed using pile load tests. As a driven pile is pushed into the ground, the soil around the pile shaft and below the pile tip is heavily disturbed; excess pore pressure also builds up. The nature of the soil in which the pile is driven remains a crucial factor for establishing the duration for the complete dissipation of the excess pore pressure. Therefore, the pile load tests need to be performed taking into consideration the duration of the pore pressure dissipation, otherwise the pile capacity could be underestimated. Soil (such as sand and gravel) that has higher permeability characteristic allows for the pore water pressure to dissipate quicker; vice versa for soil with low permeability characteristic (such as silt and clay). The Ultimate Capacity of piles in low-permeability soil (i.e. silt and clay) increases as a result of the increase in the strength of the soil surrounding the pile shaft (due to reconsolidation). In the case of soil with high permeability (i.e. sand and gravel), pile capacity may increase even after there is a complete dissipation of pore water pressure. The complete dissipation of pore pressure in case of high-permeability soils may take few hours to a few days. 4-4 INCREASE IN ULTIMATE CAPACITY OF BORED PILES The Ultimate Capacity of bored piles may increase over time due to a number of factors. Increase in the earth pressures against the surface of the piles over time may cause creep of soil towards the pile, thereby increasing the radial stress on the pile shaft; hence increasing the pile
11
capacity. Sustained loads on the bored piles can cause the soil structure to progressively become more stable and increase in strength, and the loading and unloading cycles of the piles also have similar effects. 4-5 INCREASE IN ULTIMATE CAPACITY OF DRIVEN PILES Augustesen (2006) reports the increase in Ultimate Capacity for driven piles may be caused by two different factors. The dissipation of excess or negative pore water pressures that increase due to driving the piles lead to an increase in horizontal effective stresses that act against the pile-shaft surface, thereby increasing the mobilized skin friction over time. Ageing is another factor that leads to an increase in Ultimate Capacity for driven piles due the change in the characteristics of the soil structure, change in the interaction between the pile-shaft and the soil, as well as change of stress in the surrounding soil at a given pile. In the case of piles driven into clay, thixotropy and the digenetic bonding of clay particles may play crucial roles. Furthermore, steel-manufactured piles may chemically react (via cation exchange) with the surrounding soil minerals and due to chemical bonding of the pile surface and the soil structure, an increase the pile capacity may occur. Increase in pile capacity may also result from the formation of digenetic bonding between the soil particles themselves following the complete destruction of soil structure that results from the disturbance and displacements caused when driving the piles into the ground. Evangelista and Picarelli (2000) state that digenetic bonding refers to the inter-particle forces caused by matric suction. Matric Suction is defined (Chariot, n.d.) as the suction induced by the soil matrix that causes the water to flow in unsaturated soil. 4-5-1 Increase in Capacity of Piles Driven into Clay Chen, et al. (1999) discovered that when driving a pile into clay, a volume of clay equal to the volume of the pile is displaced in the direction of least resistance. This seems to be an obvious
12
empirical observation based on the fact mentioned earlier. Two zones formed around the pile, the Remoulded Zone, where the displaced clay moved to, and the outer Transition Zone, where the soil parameters changed in their characteristics slightly. The amount of change in the transition zone depends on the properties of the soil, the driving methods, the dimensions of the piles and the pile density. The soil beyond the transition zone retained its original properties. As for the increase in Ultimate Capacity, the driven piles induce high pore pressures within the remoulded zone. As the water dissipates from around the pile surface, reconsolidation occurs in the remoulded zone; as a consequence the undrained shear strength increases resulting in higher pile capacity. In certain cases, the remoulded zone may even become adhesive with the pile surface, and after the process of reconsolidation, the remoulded zone may move simultaneously with the pile, acting as one body, thereby increasing the perimeter of the pile. This results in further increase of pile capacity. 4-5-2 Increase in Capacity of Piles Driven into Sand When driving a pile into a sandy deposit, Chen, et al. (1999) stated that generally the increase in Ultimate Capacity is expected to occur shortly after installing the pile. As stated earlier the duration for the complete dissipation of excess pore pressure may take a few hours to a few days after pile installation. It has also been reported by various researchers (Tavenas and Audy, 1972, cited in Chen, et al., 1999) that over a long period of time the pile driven in sand gains a substantial increase in pile capacity. Chow, et al. (1998 cited in Chen, et al., 1999) reported pile capacity increase by 85% during time intervals of six months and five years after installing openended piles into dense marine sand. Looking at these discoveries, one may conclude that the colossal increase in capacity of piles driven into sand (in the long-term) cannot be explained by the dissipation of excess pore
13
water pressure, since the dissipation occurs very shortly after the pile installation. Therefore, the increase in Ultimate Capacity may be attributed to the aforementioned chemical bonding between the pile surface and soil minerals, digenetic bonding between the soil particles, increase in stiffness and strength of soil due to ageing, or due to the creep of soil towards pile shaft increasing the earth pressures against it. 4-6 ULTIMATE CAPACITY INCREASE OVER TIME Lied (2010) states that during the year 2006, tests conducted by the NGI showed that soil generally demonstrates time-dependant behavior, and the soil grains gain additional strength and stiffness with time due to the time-dependant processes such as ageing. The capacity of piles also increases with time after installation due to the time-dependant processes in the soil. It was also found that the increase in pile capacity with time depends on soil type, albeit, due to insufficient data available which links pile capacity increase with soil parameters, the relationship cannot be confirmed to be absolute. 4-6-1 Case Study Powell and Skinner (2006) report that a test was carried out at Lodge Hill Camp, Chattenden, Kent; the test site was based upon London Clay. This site was originally a Greenfield site designated for testing the performance of foundations piles by the BRE. The piles (numbering 20) used for testing were designed to be economical but large enough to resemble a typical bored pile generally used in construction sites. To ensure reliability of the test results, care was taken to make sure all the piles produced were similar in characteristic. The piles were also designed with low capacities so as to minimize the size of the reaction system, and this was deemed suitable for a testing environment. Furthermore, to ensure that the piles were not affected by the seasonal variations, they were dug 4m beneath the ground
14
surface; and initially (the piles) settled 9.7m deep, since the length of each individual pile was 5.7m (and the diameter of each pile was 300mm). The piles were installed in the ground using a four-stage process: 1. A 400mm bore was drilled using a rotary technique to a depth of 4m. An outer casing (of diameter 380mm) made of light corrugated steel was dropped into the open bore. An inner casing (of diameter 320mm) was then dropped within the outer casing to a depth of 5m. At the top of the bore, the gap between the inner and outer casing was lined with polystyrene filler to prevent any soil or concrete from pouring in between. 2. The main bore was drilled 10m deep into the ground using a 300mm diameter auger. The base of the bore was left unclean so that the pile capacity would be derived primarily from the shaft resistance. 3. A single piece of high grade steel bar (of diameter 32mm) was inserted through the centre of the bore, all the way down to 10m. 4. Concrete (of design strength 35 Nmm-2) was poured into the inner casing right up to the top of the inner casing to fill up the bore and form the bored pile. During the test, the loading on the piles was applied in incremental steps of 25kN for a minimum duration of 1 hour up until the appliance of that loading induced a settlement of 0.1mm per hour. The tests were terminated after the settlement reached the required value of 20-30mm. The piles were tested and then retested. At the end of the test it was found that the virgin piles (which were not previously tested before) had an increase of 25% in Ultimate Capacity, three and a half years after their installation.
15
For example, a pile was tested two and a half months after its instalment in the ground to show that 300kN of loading was required to get a settlement of 3mm. Retested piles however did not show any increase in capacity. The initial capacity of the piles at the time of retesting was lower than that of the piles when they were at the virgin state.
Piling Blanket
Outer Casing
Inner Casing
Concrete Pile
Figure 5: Layout of Tested Piles
16
17
properties of the soil around the pile may change, and hence make changes based on correlations derived from other tests regarding the change in soil parameters during pile installation. 5-2 FORMULAE Skov and Denver (1998), as cited in Augustesen (2006), provide a semi-logarithmic equation that describes a linear relation between time, t, and Ultimate Capacity, Q, of piles in clay:
Where, Q is the vertical ultimate capacity at time, t, following the end of pile installation; Q0 is the reference ultimate capacity determined at reference time, t0; 10 refers to the capacity increase corresponding to a ten-fold increase in time this may be a function of a relevant soil parameter or used as a constant. Meyerhof (1976), as cited in Chen, et al. (1999), stated the Static Pile Capacity in sand may be calculated using the following empirical equation:
Where, Qf is the Shaft Friction; Qb is the End Bearing Capacity; N is the Standard Penetration Test values; As is the area of the pile shaft; and Ap is the cross-sectional area of the pile. The resulting estimated value of pile capacity from the above formulae may not necessarily reflect the actual capacity due to the effect of time. The value should be recalculated after conducting tests following significant amount of resting period.
18
5-3 MAINTAINED LOAD TEST (MLT) Incremental loads are applied at a given rate on the pile in this method until the rate of induced settlement goes below the specified criteria, and the resulting pile settlement is monitored. The total duration of the test last between 24 to 48 hours including time taken to set up the equipment. This method is ideal for testing piles that work directly under load points. MLT is a method that suits all soil conditions and pile types, and can
Figure 6: Maintained Load Test
test for very high loads, i.e. 30MN. However the long duration of
testing and high expense may be off-putting and health and safety risks have to be carried out since the equipment set-up involves working at height. 5-4 CONSTANT RATE OF PENETRATION TEST (CRP) The purpose of this test is to determine the Ultimate Bearing Capacity of a pile, which is derived mainly in terms of the shaft friction. The pile is loaded at a constant rate until failure or a maximum specified test load is achieved. The duration of this test is less than 24 hours excluding the equipment set up. The measured penetration of the pile is then plotted against the load applied. CRP is ideal for all pile types. However, it only suits cohesive soils, and due to the high rate of loading, the Ultimate Capacity may be over-predicted.
19
5-5 DYNAMIC LOAD TEST A pile head is subjected to hammer blows from which the measured response parameters are analyzed to predict the resistance of the soil that would be mobilized by the pile under static load conditions. The settlement performance of the piles can also be predicted. The duration for the test can range between 15 to 30 minutes only depending on the type of pile. Furthermore, this method is also relatively cheap and suitable for bored and driven
Figure 7: Dynamic Load Test
piles. Due to the high rate of loading, this test cannot take into account matters such as consolidation or creep.
5-6 TESTING PILE INTEGRITY Testing the integrity of existing piles is a crucial factor to be considered before putting them to use. Different integrity tests deal with pile materials or even test both the pile and the soil together. Pile Integrity Tests are better than the Pile Loading Tests for a number of reasons. Pile Loading Tests are not cost or time-effective, only a small range of piles are tested hence faulty piles may be ignored, and the actual dimensions of the piles cannot be determined using the load tests either. Pile Coring and Excavation are traditional methods employed to test the integrity of piles. Cores are drilled in piles using percussion equipment and then the inner structure is examined using a camera which relays the video on a screen. The size of the coring is around 50-100mm in diameter. The pile integrity is determined by the drill resistance, as well as the composition and colour of the material. This method is relatively quick. Excavating piles results in pile-exposure up to ground level after which the piles may be observed for their material constituent and their dimensions (Simons and Menzies, 2000).
20
Gardner and Moses, (1973) as cited in Simons and Menzies (2000), mention Sonic Testing as a method to test pile integrity. Sonic pressure waves are passed horizontally between a transmitter and receiver that are vertically cast into the piles. An oscilloscope records the time taken for sound waves to travel from the transmitter to the receiver. Zones of weak concrete appear as fainting marks of signals on the oscilloscope and lengthen the travel time. Sonic Pile tests may be used to determine the length of the pile as well. Also, stated is the method of Vibration Testing in which a motor vibrates vertically and exerts a force on the pile head. This method does not require much preparation of the pile or pile head, and is primarily used to detect major defects. The results may be affected by extraneous vibrations caused by moving plant at site, so the test either has to be carried out at night or after placing the entire site at standstill. This test method boasts the capability to determine pile length, mass, stiffness, as well as the recognising the damping effect of the soil that surrounds the pile. 5-6-1 Case Study In terms of practical application, Hungspruke, et al. (2003) state that Ultrasonic tests were performed at a building in Buenos Aires, on the existing concrete columns to determine their actual strength by comparing the results with the concrete samples which were earlier tested for strength. Gamma-ray test was also carried out to determine the location of the steel reinforcement as par the depictions on the drawings of the original structure; and based upon these results the column capacity was evaluated and judged against the super-imposed loads from the new structure.
21
6. Case Study
Examining practical applications of foundation reuse can provide better understanding of the procedures involved. This section shall provide an outlook on two cases where foundations were reused, the reason for the reuse, and the benefits gained thereof. 6-1 BELGRAVE HOUSE
Belgrave House was originally designed by Ove Arup and it was raised to a seven-storey structure above a single-storey basement. It is located on Buckingham Palace Road. The building site is restricted by Victorian-style buildings on one side. The area that covered the old development was roughly 110m in length and 43m in width. The existing piles relied upon the 45m+ thick layer of London Clay which rested 7.5m below the ground level. The new structure, for which the construction work commenced in November 2001, was built on the site of the old structure, which was demolished. During the stage of desk study, it was found that adjacent to the building site, two multistacked tunnels were planned for construction 36m below ground for the New Crossrail. As a result of this, the designer had to take into consideration the ground movement that would be
22
caused by the future tunneling. Furthermore, the new building extended beyond the footprint of the old structure; hence new foundations needed to be installed which were located next to the Crossrail tunnels. Also, on the other side of the building site, the London Undergrounds District and City line passed at a shallow depth. The site plan showed the presence of a congested ground filled with existing underreamed piles which imposed heavy restriction on the design on the new structure. Clearly these existing piles were an obstruction to the construction of new piles; ignoring these existing piles altogether and installing new piles upon which the building structure would completely rely would mean that the ground would be further congested for future developments at the site. Furthermore, the piles could not be removed and replaced by new piles since most piles were under-reamed and not fully reinforced. Hence, Whitbybird retained all the existing piles, and installed reinforced concrete rafts which would then allow the uniform distribution of the structural loads into the existing piles. These rafts catered for better control of ground movements, thereby reducing the effects on the future Crossrail tunnels. The design consultants appointed for the project, Whitbybird, planned rigorous testing procedures to determine the integrity of the existing piles as well as estimating the impact to occur if the piles were to be demolished. Cichy (2006) states the reuse of existing piles had shortened the construction program, resulted in lower foundation costs and minimized the risk that would otherwise occur from the existing obstructions in the ground. All of this was possible due to the reuse of the existing foundations; the need for a lesser number of new piles resulted in lower cost, as well as the time required to install these piles.
23
As for the design strategy in reusing the existing piles, Whitbybird looked into the design drawings, contacted the piling contractor, and this resulted in the attainment of excellent information which proved useful for assessing the feasibility of reusing the existing foundations. Assessments of realistic loads (SLS) and design loads (ULS) was made on each pile as well as examination of case studies on the load-settlement behavior of similar piles in London clay proved very resourceful. When the old building was demolished, the impact on the existing piles had to be checked to test their integrity. The response of the load-settlement was taken to be similar to an unloadreload scenario of a pile load test, i.e. the piles were reloaded after reconstruction. Due to the demolition, there was a risk that the existing piles below the reinforcement cage would crack. To minimize the risk, pile integrity tests were carried out for all exposed piles. Care was also taken to arrange the structural elements of the new building such that eccentric loads were not applied on the existing piles; hence the design of the foundation layout did not require much manipulation, and new piles were installed only where necessary. The durability of the piles was determined by coring samples and performing petrographic examination, which determines the material components which compose the pile shaft. This examination also verifies whether the blend of concrete has been mixed in accurate proportions or with desired materials as required for sustainable durability, otherwise corrosion and deterioration of the piles can occur causing structural instability. To take extra precaution, the presumed load carrying capacity was reduced for the existing piles and diverted to the new piles. A larger sample of existing piles were also tested out in the lab, however the results showed that there was no need for such precautionary measures
24
since the piles had high integrity. The construction work for Belgrave House was completed in the winter of 2003. 6-2 WORLD TRADE CENTRE Currently at the Ground Zero site, the development of the new World Trade Centre will see almost half of the old foundations of the collapsed building being reused. Preliminary desk studies did not provide much design information about the old foundations. So some of the piles were exhumed for testing and most of them proved Okay, albeit some of the concrete strengths were a bit low, that is in the encasement and not in the core. Due to the heavily congested ground condition, difficulty was encountered whilst installing new raking piles to resist the lateral loads which the old piles were unable to cope. The new structure has had to rely fully on vertical piles which are fixed to a thick concrete foundation mat. Mueser Rutledge geotechnical partner George Tamaro said about the congested ground condition, Its like trying to put additional foundations in the back of a porcupine trying to thread needles through needles. Whilst reusing the old foundations, the engineers had to be careful since surplus information was not available about the existing piles. So whilst the new piles were fixed to the foundation mat, the existing piles were pinned, which meant that the lateral load imposed on the original piles would be reduced by a remarkable
Figure 9: Construction work at the World Trade Centre
amount of 60%.
25
7. Conclusions
Reuse of foundations is becoming an increasingly essential requirement at construction sites, particularly in urban centres like London. Ground congestion, preservation of historical heritage, sustainability issues and economical factors all drive for the need to reuse existing foundations at the Brownfield sites. With the advancement of technology, the integrity of pile foundations and their capacity can now be accurately determined, allowing for a swift design plan, considering the need to install new piles only in cases of dire necessity. Reusing foundations benefits the design of the structure which in turn brings about economic benefits as well. With the progress of time, the Ultimate Capacity of pile foundations increases, thereby allowing the piles to carry higher loads than before; the number of piles required is thus reduced. Just as it is important to preserve the historical heritage of a site, catering for future developments on that same site is equally significant. Reusing foundations will prevent the ground from being over-congested, thereby allowing the Brownfield sites to be successfully used over and over again, and all the while using up less Greenfield sites.
26
References
Angela R.T., 2006. Handbook on Pile Load Testing, Federation of Piling Specialists, [online] Available at: <http://www.vulcanhammer.net/> [Accessed 16 March 2011] Anon., 2002. Repeat Performance. European Foundations, Winter Issue, pp.24-26. Augustesen, A.H., 2006. The Effects of Time on Soil Behavior and Pile Capacity. PhD. Aalborg University. Benefits of Driven Piles, 2011. Pile Drivers. [online] Available at: <http://www.piledrivers.org/> [Accessed 16 March 2011] Butcher, A.P., Powell, J.J.M. and Butcher, H.D., Reuse of Foundations for Urban Sites: A Best Practice Handbook, October 2006, HIS BRE Press, EP75 Chapman, T., Anderson, S. and Windle J., 2007. Reuse of Foundations. 1st ed. CIRIA Chapman, T., Marsh, B. And Foster, A. 2001. Foundations for the Future. Proceedings of ICE, 144, pp.36-41. Chariot (n.d.), Glossary of Horticultural Terms [Online] Available at:
<http://users.netconnect.com.au/~ewood/glossary_horticultural.html> [Accessed 14 March 2011] Chen, C.S., Liew S.S. and Tan, Y.C., Time Effects on the Bearing Capacity of Driven Piles. Proceedings of 11th Asian Regional Conference Seoul, South Korea, August 1999. H Alawaji. Kluer Academic Publishers, Netherlands. Cichy, M. 2006. Application of Observational Method to Re-use of Existing Piles. [e-book]
WhitbyBird. Available Through: GeoTechNet <http://www.geotechnet.org/> [Accessed 15 March 2011] EMS Analytical, Inc., 2003. Petrographic Examination [online] Available at:
<http://www.emsltesting.com/petrographic_examination.html> [Accessed 15 March 2011] Evangelista, A. and Picarelli, L. ed.s, 2000. The Geotechnics of Hard Soils-Soft Rocks. 1st ed. Balkema Publishers
27
Flack,
C.,
2004.
Foundations
for
the
Future.
[e-book]
Available
Through:
ARUP
<http://www.arup.com/> [Accessed 15 March 2011] Fleming, D., 2002. Sixties Revival in New York. Ground Engineering, November Issue, pp.18-19. Hungspruke, U., Londono, S., and Sesin A., 2003. Steel Stacks Up. Modern Steel Construction. Guide to Piling, 2007. Van Elle. [online] Available at: <http://www.van-elle.co.uk/> [Accessed 16 March 2011] Jensen, J.L., Augustesen, A. and Srensen, C.S., 2004. The Influence of Time on the Bearing Capacity of Driven Piles. [e-book] Available Through: Dansk Geoteknisk Forening
<http://www.danskgeotekniskforening.dk/> [Access 14 March 2011] Lied, E. K. W., 2010, A Study of Time Effects on Pile Capacity. [e-book] Available Through: NGI <http://www.ngi.no/> [Accessed 14 March 2011] Powell, J.J.M. and Skinner, H. Capacity changes of bored piles with time. Reuse of Foundations for Urban Sites: Proceedings of International Conference, Watford, UK, October 2006. Butcher, A.P., Powell, J.J.M. and Skinner, H.D. (Eds). HIS BRE Press, EP73. Simons, N. and Menzies, B., 2000. A Short Course in Foundation Engineering. 2nd ed. Thomas Telford. LIST OF FIGURES [Title Image] n.d. [image online] Available at: <http://www.harrogate.gov.uk/PublishingImages/Reuse%20logo.jpg> [Accessed 16 March 2011] [Figure 1] Griffier, J., n.d. [image online] Available at: <http://www.propertyhistorian.com/wp/fire-insurance/> [Accessed 16 March 2011]
28
[Figure 2] n.d. [image online] Available at: <http://www.watermangroup.com/projects/get?id=24> [Accessed 16 March 2011] [Figure 3] n.d. [image online] Available at: <http://www.tiredoflondontiredoflife.com/2008_12_01_archive.html> [Accessed 16 March 2011] [Figure 4] Butcher, A.P., Powell, J.J.M. and Butcher, H.D., 2006. Options for New Foundations. [photograph] [Figure 5] Butcher, A.P., Powell, J.J.M. and Butcher, H.D., 2006. Layout of Tested Piles. [photograph] [Figure 6] n.d. [image online] Available at: <http://www.rockal.com/img/loadtest.JPG> [Accessed 16 March 2011] [Figure 7] n.d. [image online] Available at: <http://philtech-engineers.com/_wsn/page2.html> [Accessed 16 March 2011] [Figure 8] n.d. [image online] Available at: < http://www.ramboll.co.uk/projects?linktoallprojects=true&service=9313244DCC71-4997-889A-A9373A9A12F1> [Accessed 16 March 2011] [Figure 9] n.d. [image online] Available at: <http://im.videosearch.rediff.com/thumbImage/videoImages/videoImages1/blip/rdhash3/Tvjerse y-WorldTradeCenterConstruction161.jpg>
29
Bibliography
Chantler, J. and Sivyer, D., 2008. Objection! Sustained. Ground Engineering, March Issue, pp.26. Chu, T.H., 2010. A Self-Learning Manual Mastering Different Fields of Civil Engineering Works (VC-Q&A Method). [e-book] Available Through: Institute of Civil Engineers
<http://www.ice.org.uk/> [Accessed 15 March 2011] Clarke, N., 2006. Crowded Ground. Ground Engineering, December Issue, pp.24-25. Dawson, R., 2001. Foundations Piling Steel to Replace Concrete. Proceedings of ICE, 149(4), pp.205-207. Day, S., 2002. Nam Veteran Back on Civvy Street. Ground Engineering, May Issue, pp.21-23. England, M., Fleming, W.G.K., 1994. Review of Foundation Testing Methods and Procedures. Proceedings of ICE, 107, pp.135-142. Goldfingle, G., 2010. The Pinnacle of Ingenuity. Ground Engineering, March Issue, pp.16-18. Greenman, A., 2007. Out With the Old, in With the New. European Foundations, Summer Issue, pp.24-25. Hayward, D., 2008. Taking the Waters. Ground Engineering, May Issue, pp.22-23. Hertlein, B.H. and Walton, W.H., 2007. Project Experience in Assessment and Reuse of Old Foundations. In: Camp, W., et al. (eds), 2007. GSP 158 Contemporary Issues in Deep Foundations. ASCE. Jardine, R.J., et al., 2007. Some Observations of the Effects of Time on the Capacity of Piles Driven in Sand. Geotechnique, 57(3), pp.323-327. Joseph E. Bowles (1997), Foundation Analysis and Design, McGraw Hill, London Kay, J.N., 1997. Ultimate Capacity of Driven Piles in Sand. Proceedings of ICE, 125, pp.65-70. Phillips, J., 2002. Battersea Powers Up. Ground Engineering, October Issue, pp.17-18.
30
Powrie, W. 2010. Soil Mechanics: Concepts and Applications. 2nd ed. Spon Press, London Retaining Wall: Additional Help, 2011. Edinburgh Napier University. [online] Available at: <http://www.sbe.napier.ac.uk/> [Accessed 16 March 2011] Strauss, J., et al., W.H., 2007. Drivers Affecting Frequency of Foundation Reuse and Relevance to US Cities. In: Camp, W. et al. (eds), 2007. GSP 158 Contemporary Issues in Deep Foundations. ASCE. Troughton, V., 2001. Soil Mixing Gets Up to Speed. Ground Engineering, December Issue, pp.15. Wardle, I.F., et al., 1992. Effect of Time and Maintained Load on the Ultimate Capacity of Piles in Stiff Clay. In: Sands, M.J. (ed), 1992. Piling: European Practice and Worldwide Trends. Thomas Telford.
31