Ibs Method of Construction
Ibs Method of Construction
Ibs Method of Construction
DIAGRAM
PLANT/ MANPOWER
QUANTITY
OUTPUT
DURATIO N
1 days
36
Surveyor incharge will setting the location of ground beam by using the theodalite and marking the point according level stated in plan The point then will mark with wooden stick by labour incharge.
1 point setting = 10 min 70 point x 10 min. = 700min. 700min / 2 theodelite =350 min. 350min/60 min = 6 hour @ 1 day
Diagram 10: Process for checking on the surface at the site of work performed by the employee to a position around.
NO 32.
OPERATION
METHOD
DIAGRAM
PLANT/ MANPOWER
QUANTITY
OUTPUT
DURATION
Precast beam will place at the working area by crane and hung by chain. In this situation about 4 labour need to hold the beam to make sure the beam is place according to point marked. Diagram : labour hung the chain to crane
-2 crane -2 operator crane -1 labour setting out (skilles lobour) -3 labour setting out (unskill labour) 69 no/ ground beam 1 crane = 5 nos/hr 2 crane = 10nos/hr 10nos x 8hr =80nos @ 1 days 1 day
NO
33
OPERATION
METHOD
DIAGRAM
PLANT/ MANPOWER
QUANTITY
OUTPUT
DURATION
After the beam has arranged according to size, selected labor will drill the dole to make connection from one beam to another beam. In this construction, they used the threaded and swaged reinforcement. Three bolt usually will used grade 4.6,grade 8.8 and bolt type of high strength friction grasp then SBA will put for established between precast beam to precast beam.
-1 crane -Gerudi Konkrit -Achor bolt -SBA -2 installer connection Diagram 6: precast beam was arrange by folloeing the size -2 unskilled labour 69 no/ ground beam -1 installer skilled = 20 minute/ nos - 69nos X 20 minute/nos = 1380 minute. -1380 minute/ 2 installer = 690 minute - 690 minute/60 minute =11.5 hour @ 2 day 2 day
NO
OPERATION
METHOD
DIAGRAM
PLANT/ MANPOWER
QUANTITY
OUTPUT
DURATION
Precast slab then will carried by crane that being look by four labour to make sure that the slab is place at right place according to marking. This slab is arranged on the bam and will joint them together by casting a concrete connection or using bolt and nut. Diagram 8: the crane carry the pieces of slab precast 1Crane 1 operator 3 installer .
2 days
NO
OPERATION
METHOD
DIAGRAM
PLANT/ MANPOWER
QUANTITY
OUTPUT
DURATION
35
Casting of slab is arranged on the ground beam using the concrete mix on site. This installation for ground slab involved many labours as the slab is heavy to place and also need to place in right position in order to prevent from any mistake happened.
2 days
Diagram 9: arrangement the precast slab following the size precast slab.
NO
OPERATION
METHOD
DIAGRAM
PLANT/ MANPOWER
1 Site supervisor 1 Skilled Labour
QUANTITY
140 nos column
OUTPUT
1 column/0.17hrs = 5.8 @ 6 column/hrs 140 column/ 6column/hrs = 23 hrs 23 hrs / 8 hrs = 2.8 day @ 3 day
DURATION
36
3 day
-Seting out process is done by supervisor incharge in site. - This process is done to make sure the point for pillar not erected from original point. - This will minimize mistake during installation of column. - Supervisor incharge need to make sure the height og starter bar is 800mm from floor level.
1 Surveyor
Diagram 10: Process for checking on the surface at the site of work performed by the employee to a position around.
NO
OPERATION
METHOD
DIAGRAM
PLANT/ MANPOWER
-Crane mobile -4skilled labour -8 unskilled labour.
QUANTITY
OUTPUT
DURATION
37
Starter bar for each column is install before place the ground slab The height of starter bar for each column is according to point marked before this and the height of each column cracker must use dumpy level to get the high according the cracker size. Precast column is placed inside the starter bar by using the crane and guide by labour in charge.
120pcs/floor.
-1 labour 0.6pcs/hr -12 labour (12x 0.6 pcs) = 7 pcs/hr -1 day (8hr x 7pcs/hr) = 56 pcs/days 120pcs / 56 pcs = 2.2@ 3 day
3 day
NO
38
OPERATION
Column installation.
METHOD
The starter bar that installed before this at height 800mm from floor level will paired with column that hung by crane At the bottom of the column, there are holes provide to easier paired the column with starter bar. Then worker involved will connect the starter bar with the column to assure the column is insert right and in right position.
DIAGRAM
PLANT/ MANPOWER
-3 mobile crane -3 Site supervisor -3 Operator -6 installer(skilled Labour) -12 labour (unskilled labour)
QUANTITY
140 nos column
OUTPUT
-3 crane = 3 column/hr -140 column /3/hr = 46 hour -47/8hour =5.8 @ 6 days
DURATION
6 day
. . .
NO
OPERATION
METHOD 4. As this method of construction use precast column, so the bottom of the column are provided with hole and every connection between column and starter bar are using bolt and nut to connect to slab. As this column made at factory, the diameter for each hole is 50mm. Supervisor involved need to check regularly on this connection as to prevent from failure.
DIAGRAM
PLANT/ MANPOWER
QUANTITY
OUTPUT
DURATION
Diagram 14: detail drawing connection between column and starter bar, using bolt and nut to connect to the slab.
NO
OPERATION
METHOD
DIAGRAM
QUANTITY
OUTPUT
DURATION
Attach probe with bolt and nut from column to floor Probe is attach to make sure the connection between slab to slab is strong enough.
1 column = 2 pcs 1 floor =140 column 140 column x 2 pcs = 280 pcs probe
-1 labour = 4pcs/hr -4 labour = 16 pcs/hr -1 day = 8 hour -16 pcs x 8 hr = 128pcs / day -280 pcs / 128 pcs = 2.2 day @ 3 day
3 days
NO
OPERATION
METHOD
DIAGRAM
PLANT/ MANPOWER
-Thedolite -1 Site supervisor -1 site Surveyor
QUANTITY
OUTPUT
DURATION
41
Supervisor incharge will check column level using theodolite to make sure the column installed in straight position.
1 column / 0.167 hrs =5.98 @ 6 column/ hrs 140 column / 6 column/hrs = 23 hrs 23hrs / 8hrs = 2.9 day @ 3 day
3 day
NO
42
METHOD As the height of column are in different height, shim pad are placed to make sure column in same height. Place the shim pad to the bottom of column and placed it before joint column with starter bar.
DIAGRAM
PLANT/ MANPOWER -1 Site supervisor -4 unskilled worker to put the shim pads
QUANTITY
OUTPUT 1 column / 0.25 hrs = 4 column/hrs 140 column / 4 column/hrs =35 hrs 35 hrs / 8 hrs = 4.4 @ 5 day
DURATION
5 day
NO
44
METHOD
DIAGRAM
Place strut at the corner of column and the grout is then poured into
QUANTITY
OUTPUT 1 column / 0.25 hrs = 4 column/hrs 140 column / 5 column/hrs =28 hrs 28hrs / 8 hrs = 3.5 @ 4 day
DURATION
4 day
the holes that were prepared during casting for the insertion of the starter bar.
Diagram 19
NO
OPERATION
Checked the vertically in column.
METHOD
DIAGRAM
PLANT/ MANPOWER
-1 spirit level
QUANTITY
140 nos column
OUTPUT
1 column / 0.083 hrs =12 column/hrs 140 column / 12 column/hrs = 11.6 hrs 11.6 hrs / 8 hrs = 1.45day@2 day
DURATION
2 day
Spirit level will used to check the vertically in column so that next work can be done. Strut that placed earlier will be open by workers.
NO
OPERATION
METHOD
DIAGRAM
PLANT/ MANPOWER
-1 mobile crane -2 unskilled labour -1 skilled labour
QUANTITY
OUTPUT
DURATION
Precast beam will carried by crane st and held for 1 floor with workers standby in their position to setup the beam to column.
69 nos /floor
-1 beam / 0.42 hrs = 2.38 @ 2 beam/hrs -69 beam / 2 beam/hrs = 34.5 hrs -34.5 hrs / 8 hrs = 4.4 day -5 day / 2 labour = 2.5 day @ 3 days
The position should be in parallel to column to easier to connect from beam hole to column holes.
3 day
Diagram 21: Precast Beam position in the transverse and parallel to the columns and easy for the work of inserting holes into the steel beam columns.
NO
OPERATION
METHOD
DIAGRAM
PLANT/ MANPOWER
-Anchor bolt an nut -Spanner Drill
QUANTITY
OUTPUT
DURATION
47
Anchor bolt sot in into beam and column which is beam and column functioning as connectivity by using a drill to insert anchor bolt. Before insert the anchor bolt and nut. After that, anchor bolt and nut is planted into beam and column and tightened using a spanner.
-1beam / 0.17 hrs = 5.8 @ 6 beam/hrs -140 beam / 6 beam/hrs = 23.3 hrs -23.3 hrs / 8 hrs = 2.9 day @ 3
3 day
NO
OPERATION
METHOD
DIAGRAM
PLANT/ MANPOWER
QUANTITY
OUTPUT
DURATION
48
Workers will put grounting to beam and column to make sure the connection more strength.
Diagram 24 : the labour ready to put grouting to beam for connect to column to established the connection
-1 labour = 0.2 m -4 labour = 0.8 m -1 day = 8hr 0.8 x 8 hr = 6.4 m /day 2 m / 6.4 m/day = 0.3125 = 1 day
1 day
Diagram 24: the labour ready to put grouting to beam for connect to column to established the connection
NO
OPERATION
METHOD
DIAGRAM
PLANT/ MANPOWER
QUANTITY
OUTPUT
DURATION
Labour Constant 1 labour = 0.6pcs/hr 7 labour = 7 x 0.6 pcs = 4.2 pcs/hr 1 day = 8 hr
4 day
49
Diagram 25: Labours are adjusting the hoist for placing the hollowcore slab.