Saudi Aramco Oil Company: SECTION 02240 Dewatering Part 1 - General
Saudi Aramco Oil Company: SECTION 02240 Dewatering Part 1 - General
Saudi Aramco Oil Company: SECTION 02240 Dewatering Part 1 - General
OPERNS.
ENGG
CERT
PMT
PART 1 - GENERAL 1.1. SUMMARY A. B. This Section includes construction dewatering. Related Sections include the following: 1. 2. Section 02200 - Earthwork. Section 02210 Excavation, Trenching, Backfilling and Compacting
DESCRIPTION
DATE JOB/EWO
1.2.
PERFORMANCE REQUIREMENTS A. Dewatering Performance: Design, furnish, install, test, operate, monitor, and maintain dewatering system of sufficient scope, size and capacity to control ground-water flow into excavations at the site and to provide, stable sub-grades for future Construction. 1. Maintain dewatering operations to ensure erosion control, stability of excavations and constructed slopes, that excavation does not flood, and that damage to sub-grades and permanent structures is prevented. 2. Prevent surface water from entering excavations by grading, dikes, or other means. 3. Accomplish dewatering without damaging existing buildings adjacent to excavation. 4. Remove dewatering system if no longer needed.
REV. NO.
DISCIPLINE ENGINEER
PROJECT ENGINEER
____________ DATE
CERTIFIED _ __________
DATE: ________
1.3.
SUBMITTALS A. Shop Drawings for Information: For dewatering system. Show arrangement, locations, and details of wells and well points; locations of headers and discharge lines; and means of discharge and disposal of water. 1. Include layouts of piezometers and flow-measuring devices for monitoring performance of dewatering system. 2. Include a written report outlining control procedures to be adopted if dewatering problems arise. 3. Include Shop Drawings signed and sealed by the qualified professional engineer responsible for their preparation. Qualification Data: For Installer and professional engineer.
CONSTRUCTION AGENCY
________________ DATE:
OPERATIONS
______________ DATE:_________ REVISION CERTIFICATION EDSD VERIFICATION THIS INDICATES THAT REV. NO.________ OF THIS DRAWING IS COVERED, FOR ALL APPROVAL/CERTIFICATION REQUIREMENTS,, CONTROL NUMBER BY DRAWING COMPLETION CERTIFICATE (DCC) NO.: __________________________ By:
Date:
B.
SECTION 02240
CONSTRUCTION SPECIFICATIONS
KAUST TOWN CENTER RESIDENTIAL & COMMUNITY SUPPORT BUILDINGS
DRAWING NO.
DOC
VE-417361 BI-25-00002
RABIGH
14-Sep-07
JOB/EWO#
1 OF 4
00
ENGG
CERT
PMT
D.
DESCRIPTION
Field Test Reports: Before starting excavation, submit test results and computations demonstrating that dewatering system is capable of meeting performance requirements.
1.4.
DATE JOB/EWO
QUALITY ASSURANCE A. Regulatory Requirements: Comply with water disposal requirements of authorities having jurisdiction. Pre-installation Conference: Conduct conference at Project site to comply with requirements in Division 1 Section "Project Management and Coordination."
B.
REV. NO.
DISCIPLINE ENGINEER
1.5.
PROJECT CONDITIONS A. Existing Utilities: Do not interrupt utilities serving facilities occupied by others unless permitted in writing by Engineer and then only after arranging to provide temporary utility services according to requirements indicated. Project-Site Information: A geotechnical report has been prepared for this Project and is available for information only. The opinions expressed in this report are those of geotechnical engineer and represent interpretations of subsoil conditions, tests, and results of analyses conducted by geotechnical engineer. Company will not be responsible for interpretations or conclusions drawn from this data. 1. Make additional test borings and conduct other exploratory operations necessary for dewatering. 2. The geotechnical report is available with the Company for review. Survey adjacent structures and improvements, employing a qualified professional engineer or land surveyor, establishing exact elevations at fixed points to act as benchmarks. Clearly identify benchmarks and record existing elevations. 1. During dewatering, regularly resurvey benchmarks, maintaining an accurate log of surveyed elevations for comparison with original elevations. Promptly notify Engineer if changes in
SECTION 02240
PROJECT ENGINEER
____________ DATE
CERTIFIED _ __________
DATE: ________
B.
CONSTRUCTION AGENCY
________________ DATE:
OPERATIONS
______________ DATE:_________ REVISION CERTIFICATION EDSD VERIFICATION THIS INDICATES THAT REV. NO.________ OF THIS DRAWING IS COVERED, FOR ALL APPROVAL/CERTIFICATION REQUIREMENTS,, CONTROL NUMBER BY DRAWING COMPLETION CERTIFICATE (DCC) NO.: __________________________ By:
C.
Date:
CONSTRUCTION SPECIFICATIONS
KAUST TOWN CENTER RESIDENTIAL & COMMUNITY SUPPORT BUILDINGS
DRAWING NO.
DOC
VE-417361 BI-25-00002
RABIGH
14-Sep-07
JOB/EWO#
2 OF 4
00
CERT
PMT
ENGG
PART 3 - EXECUTION
DESCRIPTION
3.1.
PREPARATION A. Protect structures, utilities, sidewalks, pavements, and other facilities from damage caused by settlement, lateral movement, undermining, washout, and other hazards created by dewatering operations. 1. Prevent surface water and subsurface or ground water from entering excavations, from ponding on prepared subgrades, and from flooding site and surrounding area. Protect subgrades and foundation soils from softening and damage by rain or water accumulation.
DATE JOB/EWO
2.
REV. NO.
B.
Install dewatering system to ensure minimum interference with roads, streets, walks, and other adjacent occupied and used facilities. 1. Do not close or obstruct streets, walks, or other adjacent occupied or used facilities without permission from Owner and authorities having jurisdiction. Provide alternate routes around closed or obstructed traffic ways if required by authorities having jurisdiction.
DISCIPLINE ENGINEER
PROJECT ENGINEER
____________ DATE
CERTIFIED _ __________
DATE: ________
3.2.
INSTALLATION A. Install dewatering system utilizing wells, well points, or similar methods complete with pump equipment, standby power and pumps, filter material gradation, valves, appurtenances, water disposal, and surfacewater controls. Before excavating below ground-water level, place system into operation to lower water to specified levels. Operate system continuously until drains, sewers, and structures have been constructed and fill materials have been placed, or until dewatering is no longer required. Provide an adequate system to lower and control ground water to permit excavation and placement of fill materials on dry subgrades. Install sufficient dewatering equipment to drain water-bearing strata above and below bottom of excavations.
SECTION 02240
CONSTRUCTION AGENCY
________________ DATE:
OPERATIONS
______________ DATE:_________ REVISION CERTIFICATION EDSD VERIFICATION THIS INDICATES THAT REV. NO.________ OF THIS DRAWING IS COVERED, FOR ALL APPROVAL/CERTIFICATION REQUIREMENTS,, CONTROL NUMBER BY DRAWING COMPLETION CERTIFICATE (DCC) NO.: __________________________ By:
B.
Date:
C.
CONSTRUCTION SPECIFICATIONS
KAUST TOWN CENTER RESIDENTIAL & COMMUNITY SUPPORT BUILDINGS
DRAWING NO.
DOC
VE-417361 BI-25-00002
RABIGH
14-Sep-07
JOB/EWO#
3 OF 4
00
CERT
PMT
ENGG
D.
Reduce hydrostatic head in water-bearing strata below subgrade elevations of excavations. Dispose of water removed by dewatering in a manner that avoids endangering public health, property, and portions of work under construction or completed. Dispose of water in a manner that avoids inconvenience to others. Provide sumps, sedimentation tanks, and other flow-control devices as required by authorities having jurisdiction. Provide standby equipment on-site, installed and available for immediate operation, to maintain dewatering on continuous basis if any part of system becomes inadequate or fails. If dewatering requirements are not satisfied due to inadequacy or failure of dewatering system, restore damaged structures and foundation soils at no additional expense to Owner. 1. Remove dewatering system from Project site on completion of dewatering. Plug or fill well holes with sand or cut off and cap wells a minimum of 36 inches (900 mm) below overlying construction.
E.
DESCRIPTION
F.
REV. NO.
DATE JOB/EWO
DISCIPLINE ENGINEER
G.
PROJECT ENGINEER
____________ DATE
3.3.
OBSERVATION WELLS A. Provide, take measurements, and maintain at least the minimum number of observation wells or piezometers indicated and additional observation wells as may be required by authorities having jurisdiction. Observe and record daily elevation of ground water and piezometric water levels in observation wells. Repair or replace, within 24 hours, observation wells that become inactive, damaged, or destroyed. Suspend construction activities in areas where observation wells are not functioning properly until reliable observations can be made. Add or remove water from observation-well risers to demonstrate that observation wells are functioning properly. 1. Fill observation wells, remove piezometers, and fill holes when dewatering is completed. END OF SECTION 02240
SECTION 02240
CERTIFIED _ __________
DATE: ________
CONSTRUCTION AGENCY
________________ DATE:
B.
OPERATIONS
______________ DATE:_________ REVISION CERTIFICATION EDSD VERIFICATION THIS INDICATES THAT REV. NO.________ OF THIS DRAWING IS COVERED, FOR ALL APPROVAL/CERTIFICATION REQUIREMENTS,, CONTROL NUMBER BY DRAWING COMPLETION CERTIFICATE (DCC) NO.: __________________________ By:
C.
Date:
CONSTRUCTION SPECIFICATIONS
KAUST TOWN CENTER RESIDENTIAL & COMMUNITY SUPPORT BUILDINGS
DRAWING NO.
DOC
VE-417361 BI-25-00002
RABIGH
14-Sep-07
JOB/EWO#
4 OF 4
00