REMOVAL
Urethane Foam
160 (6.30)
60 (2.36)
mm (in.)
F25722
BP-20
Symbol meaning
F25723
BP-21
Symbol meaning : MIG Plug Weld : Tack Weld : Cut and Join Location : Butt Weld : Body Sealer
F25724B
INSTALLATION
45 (1.77)
20 (0.79)
mm (in.)
F25724
INSTALLATION POINT 1 Before temporarily installing the new parts, weld the center body pillar lower reinforce, front body pillar lower reinforce and cowl side panel with the standard number of welding points.
BP-22
Symbol meaning : MIG Plug Weld : Tack Weld : Cut and Join Location : Butt Weld : Body Sealer
F25724B
10 (0.39)
mm (in.)
F25725
INSTALLATION POINT 1 Inspect the fitting of the related parts around the new parts before welding. This affects the appearance of the finish. 2 Temporarily install the new parts and measure each part of the new parts in accordance with the body dimension diagram. (See the body dimension diagram) 3 After welding the center body pillar lower reinforce, front body pillar lower reinforce and cowl side panel to the vehicle side, install the front body upper outer pillar and center body outer pillar.
BP-23
Urethane Foam
F25807
INSTALLATION POINT 1 Inspect the fitting of the related parts around the new parts before welding. This affects the appearance of the finish. 2 Temporarily install the new parts and measure each part of the new parts in accordance with the body dimension diagram. (See the body dimension diagram) 3 Before installing a new part, apply body sealer. HINT: 1) Apply sealer in an even, continuous bead. 4 After welding the center body pillar lower reinforce and front body pillar lower reinforce to the vehicle side, install the front body upper outer pillar, center body outer pillar and No.6 pillar outer bracket. 5 After welding, apply the polyurethane foam to the corresponding parts. (See the paint.coating) 6 After welding, apply body sealer and undercoating to the corresponding parts. (See the paint.coating) 7 After applying the top coat, apply anti-rust agent to the internal panel portion of the closed section structural weld points.