07 06 13 PDF
07 06 13 PDF
07 06 13 PDF
TO CC.
1.00 2.00
Report No : Date :
Rev. 2
K. Surachead P. Worachart P. , Preecha K., Chotepong S., Aphichart S., K. Kawin T., Krisada B., Leartsak Ch., Deaunphen R.
WEATHER CONDITION 3.00 4.00 5.00 6.00 7.00 8.00 S 9.00 S 10.00 S Symbols Yesterday = 11.00 S 12.00 C 13.00 C Cloudy (C), 14.00 C 15.00 C 16.00 C 17.00 C 18.00 C
24.00
Sunshine (S),
MANPOWER REPORT Normal Time man hours Over Time man hours Normal Time man hours Over Time man hours
No.
Description
Total M/D
Total MH
No.
Description
Total M/D
Total MH
ENSURE INTERNATIONAL CO., LTD. A 1 2 3 4 5 6 7 8 9 10 11 B 1 2 3 4 5 6 7 8 9 10 11 12 13 14 Foreman Welder Fitter Pipe Fitter Structure Helper Driver Scaffolder Fire wach man Insulation Safety Technic Qc Inspector Carpenter Mason Electrician Total A+B No. 1 2 3 No. 1 2 3 4 5 6 7 8 9 10 11 12 Grinding M/C 4" Grinding M/C 7" Activities (Yesterday) Fit-up and welding Hopper Reactor Area Shop Description Welding M/C 300 Amp. Unit ea ea ea Unit Set Set Set Set Set Set Set Set Set Set Set Set Q'ty 8 16 12 Q'ty 1 1 1 1 1 1 1 2 1 1 24 4 No. 4 5 6 No. 1 2 3 4 5 6 7 8 9 10 11 12 13 Drill Generator Haib 5 T CONSTRUCTION ACTIVITIES Activities (Today) Fit-up and welding Hopper Reactor Area Shop Unit Set Set Set Set Set Set Set Set Set Set Set Set Set Q'ty 1 1 1 1 1 1 1 2 1 1 24 2 4 No. 1 2 3 4 5 6 7 8 9 10 11 12 13 Activities (Tomorrow) Fit-up and welding Hopper Reactor Area Shop Unit Set Set Set Set Set Set Set Set Set Set Set Set Set Q'ty 1 1 1 1 1 1 1 2 1 1 24 2 4 Project Manager Site Manager Site Engineer Safety Office QA/QC Manager Draftman Material Control Administrator Storekeeper Document Control Supervisor Direct 9 13 36 22 8 2 6 5 5 1 3 7 3 3 72 104 288 176 64 16 48 40 40 8 24 56 24 24 1 1 1 7 27 5 5 5 9 13 36 22 8 2 6 5 5 1 3 7 3 3 141 72 104 288 203 64 21 48 45 40 8 24 56 24 29 1,183 Description 1 3 2 4 Indirect 1 1 4 1 1 8 8 32 8 8 8 24 16 32 1 1 1 5 3 5 1 1 4 1 1 1 3 2 4 8 8 32 13 8 11 24 16 37 A 1 2 3 4 5 6 7 8 9 10 11 B 1 2 3 4 5 6 7 8 9 10 11 12 13 14 Foreman Welder Fitter Pipe Fitter Structure Helper Driver Scaffolder Fire wach man Insulation Safety Technic Qc Inspector Carpenter Mason Electrician Total A+B Unit ea ea ea Q'ty 4 4 1 No. 7 8 9 Crane 100T. Crane 50T. Trailer Description Project Manager Site Manager Site Engineer Safety Office QA/QC Manager Draftman Material Control Administrator Storekeeper Document Control Supervisor Direct 9 14 36 22 9 3 6 4 9 3 3 7 4 3 72 112 288 176 72 24 48 32 72 24 24 56 32 24 9 14 36 22 9 3 6 4 9 3 3 7 4 3 151 Unit ea ea ea 72 112 288 176 72 24 48 32 72 24 24 56 32 24 1,208 Q'ty 2 3 2 4 Indirect 1 1 4 1 1 8 8 32 8 8 16 24 16 32 1 1 4 1 1 2 3 2 4 8 8 32 8 8 16 24 16 32
Fit-Up & Welding Pipe 66" 304H For Hydrotest Shop Fit-Up & Welding Pipe 28" 800HT For Hydrotest Shop Cutting Mix Sump Reactor Cutting Elbow Pipe 66" 55 Welding Plug Handrail For Trim Cooler Welding Plug Handrail For Reactor Remove Pump 03P005A/B Installation Pump For 03P030A Chipping Fireproof Reactor 03R001 Loot Bolt Reactor 03R001 Chipping Box Out For Install Damper Shop Shop Shop Shop 03A 03B 03B 03B OSBL
Fit-Up & Welding Pipe 66" 304H For Hydrotest Shop Fit-Up & Welding Pipe 28" 800HT For Hydrotest Shop Cutting Mix Sump Reactor Cutting Elbow Pipe 66" 55 Welding Plug Handrail For Trim Cooler Welding Plug Handrail For Reactor Remove Pump 03P005A/B Installation Pump For 03P030A Chipping Fireproof Reactor 03R001 Levering Pump For 05P015A/B Chipping Box Out For Install Damper Shop Shop Shop Shop 03A 03B 03B 05 OSBL
Fit-Up & Welding Pipe 66" 304H For Hydrotest Shop Fit-Up & Welding Pipe 28" 800HT For Hydrotest Shop Cutting Mix Sump Reactor Cutting Elbow Pipe 66" 55 Welding Plug Handrail For Reactor Remove Pump 03P005A/B Installation Pump For 03P030A Chipping Fireproof Reactor 03R001 Levering Pump For 05P015A/B Chipping Box Out For Install Damper Shop Shop Shop 03A 03B 03B 05 OSBL
Page 1 of 1