Why? To identify hazards so that they can be eliminated or controlled. How? Using a number of available procedures.
Sources of Information
Legislation and supporting Codes of Practice HSE guidance Process Information Product Information Relevant national and industry standards Industry and trade association guidance Experienced Personnel Accident/ Incident databases Specialist advice
Brainstorming
Rules
Postpone and withhold your judgement of ideas. Encourage wild and exaggerated ideas. Quantity counts at this stage, not quality. Build on the ideas put forward by others. Every person and every idea has equal worth.
By its very nature a brainstorming session cannot be structured, but it can be guided.
Check List What If Hazid Hazop Task Analysis Fault Tree Analysis Failure Modes & Effects Analysis
Safety Analysis
Qualitative
Check Lists What If Reviews Hazop Reviews
Quantitative
Event Trees Fault Trees Failure Mode and Effects Analysis (FMEA)
Selection of the most appropriate methods for each facility or process and provide the rationale for their selections. Sometimes a combination of methods may be most appropriate. Depends on many factors including the size and complexity of the process and existing knowledge of the process. All Hazard Identification methods are subject to certain limitations. Hazard Analysis depends on good judgement, therefore assumptions made must be documented, understood, and retained for future hazard reviews.
Hazard Identification
Consider each situation to be unique Each may require a different approach Each is dependant upon process complexity
Obvious low hazard or simple process Obvious high hazard or complicated process
Checklist Analysis
A checklist analysis is used to verify the status of a system. The checklist analysis method is versatile, easy to use and can be applied at any stage in the life of a process. It is primarily used to indicate compliance with standards and practices. It is also a costeffective way to identify common and customarily recognized hazards. Checklists also provide a common basis for management review of assessments. Many organizations use standard checklists to control the development of a process or an entire project from initial design through decommissioning. The completed checklist must be approved by all relevant staff members and managers before a project can move from one stage to the next.
Materials Handling. Pumps, conveyors, ducts, piping, procedures Process Equipment and Systems.
Procedures, conformance, loss of utilities, vessels, relief devices, hazards, electrical, ignition sources, compatibility
Waste Disposal. Ditches, vents, characteristics, Sampling. Sample points, procedures, sample analysis Maintenance. Decontamination, vessel opening, procedures
MATERIAL
Do all raw materials continue to conform to original specifications? Yes. The drums are ordered with the same chlorine specification used since startup. Is each receipt of material checked? Yes. The supplier once sent a cylinder of phosgene. Since then, a test is performed by the maintenance staff. In addition, the fusible plugs are inspected for evidence of leakage, before a cylinder is hooked up. Does the operating staff have access to Material Safety Data Sheets? Yes. All staff are familiar with the process chemistry, including the hazards of Chlorine. Is fire fighting and safety equipment properly located and maintained? Yes. This system is on a concrete building roof. Because there are no flammable materials involved in this system, if a fire occurs, there will be no special effort by fire fighting crews to concentrate on the roof area.
EQUIPMENT Has all equipment been inspected as scheduled? Yes. The maintenance personnel have inspected the equipment in the process area according to company inspection standards. Have pressure relief valves been inspected as scheduled? Yes. Have rupture disks been inspected (for having blown) as scheduled? Not applicable. Are the proper maintenance materials (parts, etc.) available? Yes. They include spare pigtails for the supply cylinders, as well as a rotameter and a pressure check valve. Other items must be ordered. Is there an emergency cylinder capping kit? Yes. PROCEDURES Are the operating procedures current? Yes. Are the operators following the operating procedures? No. It is reported that some staff do not always check the cylinder's fusible plugs for leaks. Staff should be re-reminded of this procedural item and its importance. Are new operating staff trained properly? Yes. Training includes a review of the Hazard Analysis for this process and familiarization with MSDSs. How are communications handled at shift change? There are relatively few open items at the end of a shift. The chlorine cylinders need to be changed only about once every 45 days. If an empty chlorine cylinder needs replaced, it has proven to be easy to schedule the change during a shift. Is housekeeping acceptable? Yes. Are safe work permits being used? Yes.
Checklist Advantages
List of hazards identified from previous studies and historical data on operating plants Can be tailored to specific materials, equipment, procedures Very simple and low cost Can be applied to any stage in the life of a process Versatile and easy to use
Checklist Limitations
Does not address new processes, equipment, etc. May miss issues not covered by lists Past data might not contain infrequent, high consequence accident Encourage a tick off mentality Does not deal effectively with hazards that arise from interactions
What If Analysis
What-if analysis is to identify hazards, hazardous situations, or specific accident events that could produce an undesirable consequence. What-if analysis involves the examination of possible deviations from the design, construction, modification, or operating intent of a process.
What If /Checklist
Combines the creative, brainstorming feature of what if analysis and the systematic features of the checklist analysis to try and overcome the random approach of What If.
HAZID (HAZard IDentification) A process where a list of hazards and guidewords is applied to a facility or activity in a systematic manner.
HAZID
Suitable for application during concept selection, and equally for review of basic development concepts when the following level of information is normally available: operations philosophy sparing and maintenance philosophy process flow schemes preliminary layouts fire and explosion strategies.
Hazards Release
Guidewords
Gas Liquid Condensate Other Fuel source Ignition Relief Smoke & gas ingress Fuel Confinement Lifting Maintenance Mechanical failure Primary structures Temporary structures
Fire
Guidewords
Volatiles Liquids Solids Types Handling Protection Aviation Marine Other Corrosion Erosion Earthquake Extreme weather Operational Diving Transport
HAZID
Divide the item under consideration into nodes, which are manageable sections, with clearly defined limits. Apply the first guideword and ask how could this happen? Determine in what manner the hazard might be realised. What would be the consequence of this? List any existing safeguards or precautions.(Preventive or control measures) List any areas for discussion or any actions which need to be taken. Record everything, drawings used, team members, dates.
HAZID Worksheet
HAZARD PHASE CAUSE Leak of process gas containing H2S Loss of Production containment EFFECT/ ESCALATION Toxic gas cloud. Risk to personnel on platform PREVENT The amount of process equipment on the platform is being kept to a minimum, with processing of the gas being performed onshore. CONTROL Platform is designed so that the prevalent wind d irection is away from the muster and evacuation areas. DISCUSSION Arrangements for changing from saver sets to BA sets are not clear. ACTION Action 001: Confirm the command and control strategy with regard to H2S and wearing BA.
Action 002: Develop an evacuation strategy that is Breathing apparatus Command and suitable for a sour gas control with environment. is available on the personnel platform wearing B A Action 003: Develop an will be difficult. intervention schedule and ensure that interventi on is kept Saver sets will be to an absolute minimum by provided to all personnel (typically keeping the amount of process up to 15 minutes equipment to a minimum. protection against H2S)
HAZOP
A formal, systematic and critical examination of the process and engineering intentions of the process design. HAZard Abnormal operations OPerability Normal operations
HAZOP Objectives
To identify the causes of all deviations or changes from the design intent To determine all major hazards and operability problems associated with these deviations To decide whether action is required to control the hazard or the operability problem To ensure that the actions decided upon are implemented and documented
Formal procedure for identifying hazards Basic idea generate a list of all the ways in which process failures can occur Determine what may cause each failure and what the results might be Recommend actions to avoid each failure Not quantitative no trade off between risk and consequences
HAZOP types
Coarse Hazop - Early study to identify basic flaws in design which would be costly to correct later Main Hazop - Primary vehicle for identification of hazards, effects and operability problems Final Hazop - Coverage of systems not sufficiently developed for the Main Hazop Procedural Hazop - Identification of hazards and operability problems arising from procedures such as commissioning, maintenance and other noncontinuous procedures.
Hazid
Final Hazop
Commissioning
Identification Phase
Definition Phase
Execution Phase
Prospective Project
HAZOP Leader
HAZOP Leader
Process Engineer Instrument Engineer Operations Representative
HAZOP Secretary
Specialists
(as required) Maintenance Engineer Pipeline Engineer Metallurgist others
Preparatory Work
Assemble the data Understand the subject Subdivide the plant and plan the sequence Mark up the drawings Devise list of appropriate keywords Prepare table headings and an agenda Prepare a timetable Select the team
Hazop study
Full size Piping & Instrumentation Diagram (P&ID) displayed. Team members are provided with individual reduced size P&ID copies Introductory talk and brief description of the technique are given by the Hazop chairman. A plant description is provided usually by the process engineer, summarizing the processing facilities, including an account of the function of each equipment item.
Node Identification
Divide the facility into process systems and subsystems Follow the process flow of the system under study Isolate subsystems into major components which achieve a single objective
Parameters
FLOW PRESSURE TEMPERATURE LEVEL PHASE COMPOSITION
Guidewords
AN TH ER SE TH ER O EV F R O T R PA AS L EL W SS LE AS O M R E O N
FLOW
Parameters
PRESSURE
TEMPERATURE LEVEL PHASE
p p p p p p
p = possible
Hazop study
Select the appropriate NODE Apply the PARAMETER Apply the GUIDE WORD (or DEVIATION) Agree credibility of deviation Determine the potential CAUSES of the deviation Assess the PROTECTION provided against the deviation and its consequences Agree a RECOMMENDATION for action or further consideration to the problem. Reiterate above steps for other GUIDE WORDS Reiterate above steps for other process PARAMETERS Reiterate above steps for other NODES in review
Operational phases
Maintenance Utility failure Start-up Normal shut down Emergency shut down
Possible CAUSES
Equipment Failure Operational Errors External Events Product Deviations
CREDIBLE SCENARIOS
A single human error with or without established operating instructions A single instrument or mechanical failure A single failure coupled with a single instrument or mechanical failure
RECOMMENDATIONS
Modify the design Add an alarm Add an interlock Develop or change procedure Review the design
Documentation
Summary report HAZOP worksheets List of proposed actions The report is updated when all engineering and some procedural actions are completed. At the end of the project, a final report is issued including HAZOP Procedure HAZOP Follow-up Report List of all actions with status (completed, in progress etc) Complete set of P&IDs as used in the HAZOP study
HAZOP FORM
Parameter: Flow
Process variables
air fuel
produc t
Guide Word Select from official list of words to ensure systematic consideration of possibilities no
no feed flow
2. feed valve closed 3. feed flow meter indicates false high flow (controller closes valve) 4. pipe blockage
4. a) test flow before startup 4. b) place filter in pipe Install remotely activated block valves at feed tanks to allow operators to stop flow
5.a) damage to pipes in radiant section b) pollution and hazard for oil release to plant environment
For 1-5, SIS to stop fuel flow on low feed flow, using separate feed flow sensor
Advantages of Hazop
It uses a systematic and logical approach. It has specific guideword listing and the process under review is subdivided into small sections for analysis It can analyse a combination of failures. The option of addressing continuing sequential failures can be investigated to the final outcome. It provides an insight into operability features. Operation control methods are fully investigated for potential deviating conditions. Operators present can readily deduct what hazards may be present at the facility.
TASK ANALYSIS Systematic examination of a task to be performed, listing all the ways in which it might be performed in an unsafe manner. Introduction of safeguards and controls to prevent or minimise the consequences of a failure. Sometimes called a job safety analysis.
A FMEA has three steps: defining the process, performing the analysis, and documenting the results.
.
Application of FMEA
Risk Assessment
What is the difference between Risk and Hazard? How do we measure risk?
Assessment of a risk involves the rating of two factors which affect the risk
The severity of the hazard The likelihood of an occurrence of harm from the hazard
Risk Assessment
Risk Prioritisation Matrix
Frequent
Medium
High
High
Likelihood
Occasional
Low
Medium
High
Seldom
Low
Minor
Low
Substantial
Medium
Major
Severity
Increasing consequence
Increasing likelihood
Likelihood or Frequency
Level E - Daily Level D - Monthly Level C - Yearly Level B - Every 10 years Level A - Once in a lifetime
Severity or Consequence
Level 5 - Multiple Fatalities Level 4 - Single Fatality, Multiple Injuries Level 3 - Major Injury Level 2 - Minor Injury Level 1 - No Injury, Near Miss
0 1 2 3 4 5
NoInjury Slight Injury Minor Injury Major Injury Single Fatality Multiple Fatalities
I nc
r ea
sin
gR
i sk
IPL1
IPL2
IPL3
Summary
Hazard identification requires many different approaches No one method will give you all the answers No substitute for experience or past records Cultivate the ability to think the unthinkable Remember that all estimates are just that, estimates Update and review as appropriate Never be surprised at what people will do!