Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Control Engineering Design Criteria

Download as pdf or txt
Download as pdf or txt
You are on page 1of 34

Control Engineering Design Criteria

APPENDIX 10E

APPENDIX 10E

Control Engineering Design Criteria


10D1 Introduction
Control of the design, engineering, procurement, and construction activities on the project will be completed in accordance with various predetermined standard practices and project specific programs/practices. An orderly sequence of events for the implementation of the project is planned consisting of the following major activities: Conceptual design Licensing and permitting Detailed design Procurement Construction and construction management Testing and checkout, start-up Project completion

The purpose of this appendix is to summarize the codes, standards, and standard design criteria and practices that will be used during the project. The general control design criteria defined herein form the basis of the design for the control systems of the project. More specific design information is developed during detailed design to support equipment and erection specifications. It is not the intent of this appendix to present the detailed design information for each component and system, but rather to summarize the codes, standards, and general criteria that will be used. Section 2.0 summarizes the applicable codes and standards and Section 3.0 includes the general design criteria for general conditions, instruments, modulating type control systems, motor controls, and control equipment locations.

10E2 Design Codes, Standards, Laws and Regulations


The design specifications for all work will be in accordance with the applicable laws and regulations of the federal government, the State of California, and applicable local codes and ordinances. A summary of codes and industry standards applicable to design and construction follows: American National Standards Institute (ANSI) American Society of Mechanical Engineers (ASME) The Institute of Electrical and Electronics Engineers (IEEE) Instrument Society of America (ISA) National Electrical Manufacturers Association (NEMA) National Electrical Safety Code (NESC) National Fire Protection Association (NFPA) Scientific Apparatus Makers Association (SAMA) American Society for Testing and Materials (ASTM).

PO062006001SAC/344005/062560001 (HBRP_APP10E.DOC)

10E-1

APPENDIX 10E: CONTROL ENGINEERING DESIGN CRITERIA

Other recognized standards will be utilized as required to serve as design, fabrication, and construction guidelines when not in conflict with the above listed standards. The codes and industry standards used for design, fabrication, and construction will be the codes and industry standards, including all addenda, in effect as stated in equipment and construction purchase or contract documents.

10E3 Instrumentation and Control Design Criteria


The instrumentation, control systems, UPS system, and electrical power circuits for critical equipment will be designed in such a way that no single control system, instrument failure, controller failure, fuse, or circuit breaker will interrupt the operation of more than one piece of redundant equipment. The plant will be designed to eliminate common mode failures. The Contractor may propose to use PLC based control system for the Balance of Plant (BOP) equipment/systems and the Reciprocating Engines. The PLC based control system will be acceptable provided it meets all of the applicable requirements specified for the DCS/PLC. The number of different control systems will be minimized as much as possible. The intent is to simplify maintenance and operation of the plant control systems. All control consoles will be of the same manufacturer for the plant main control room. The DCS/PLC and reciprocating control systems will be provided with the following features furnished by the supplier: a. A remote control console/workstation for the reciprocating engines (1 CRT for up to 4 engines) will be located in the plant main control room. In addition, Contractor provides two extra work stations. This console will provide all the functions of the local control consoles for each reciprocating engine. In addition, it will be possible to perform all necessary workstation functions (programming, graphic display changes, etc.) from this console. Two color printers will be mounted in the main control room. These printers will print all alarms, logs, historical data, graphic displays, etc. The Reciprocating Engine control packages will be linked to the Project DCS/PLC by Profibus. This link will be used for data acquisition and monitoring of the Reciprocating Engines. In addition, critical control functions will be hardwired from the Reciprocating Engine control systems to the Project DCS/PLC to allow critical functions to be performed from the Project DCS/PLC. All transmitters and indicators will be capable of being maintained while the unit is on line and will be provided with root valves. Root valves are required for critical trip instrumentation. Certain transmitters on the engines have to be maintained while the unit is stopped. Balance of plant transmitters and indicators can be maintained while operating. Factory Acceptance Testing (FAT) of the complete control package will be performed using Vendors standard testing procedures. All software logics, hardware, graphics, and alarming will also be verified during the FAT. The tests will be performed before

b. c.

d.

e.

10E-2

PO062006001SAC/344005/062560001 (HBRP_APP10E.DOC)

APPENDIX 10E: CONTROL ENGINEERING DESIGN CRITERIA

shipment. Owner approval of information displayed on control screens is required. See Section 4.4 for additional information on FAT. f. g. h. The failure of any transmitter or switch will not shutdown more than one engine. Each Reciprocating Engine has its own control system and a failure of the DCS/PLC system power supplies will not shutdown more than one unit. Mechanical equipment on standby status will automatically start upon a trip of the operating equipment.

Local control and key engine indication will be provided at each engine. All instrumentation and systems will be designed to provide safe and reliable operation of each Unit in accordance with all applicable codes and standards. Main and redundant process transmitter inputs will be provided for critical control loops. Inputs will be brought into different I/O modules for integrity. Current-to-pneumatic (I/P) converters will be used to provide the interface between the electronic control signals and pneumatically actuated control valves. The converters will be responsive to the basic control signals for the system and will have a 3-15 psi output. Feedback from I/P converters mounted on control valves will be sent to the DCS/PLC for control system tuning purposes. Actual Line valve position feedback will be from position transmitters provided for split range control valve applications only, to provide CRT indication for the operators. The control system will be designed to require a minimum of operator action. The control system will include all necessary logic to change the operating mode for selector stations safely under various operating conditions. The control system will be designed to ensure transfer from manual to automatic and vice versa with no operator balancing or upset in the individual control loops. All backup pumps should be able to auto-start from the DCS/PLC on primary pump trip, low suction pressure, and low discharge pressure, at a minimum. The Contractor will provide Owner with a master set of the Contractors and vendors wiring drawings; reciprocating engine and BOP DCS/PLC control system configuration, cabinet arrangement, and power distribution drawings; instrument index; instrument and control valve data sheets; and P&IDs marked with all as-started up changes. All as-started up changes will be incorporated into the final drawings, documents, etc., which are to be submitted to the Owner before Substantial Completion. Project control system will be capable of day-ahead programming of key events (i.e. turning over unit to California ISO remote dispatch). The Contractor will be fully responsible for the interface design with the California ISO remote dispatch system. The Project will be operable from the control room by a single operator under all normal conditions from minimum to full load. The Project will also be remote started, operated, and shutdown and will be under AGC control.

PO062006001SAC/344005/062560001 (HBRP_APP10E.DOC)

10E-3

APPENDIX 10E: CONTROL ENGINEERING DESIGN CRITERIA

10E3.1 Distributed Control System


A microprocessor-based distributed control system (DCS/PLC) will be provided for controlling, monitoring, indication, alarm, and historical functions. CRTs located in the main control room will serve as the primary operator interface. This system will monitor, alarm, and provide limited control of the engine. Remote CRTs will be provided in the main control room for detailed controlling, alarming, and monitoring of the reciprocating engines. A MODBUS or Ethernet communication link for data acquisition will be provided between the engine controls and the DCS/PLC for each engine. Control functions between the DCS/PLC and engine control systems will be via hardwired signals. The DCS/PLC will be as manufactured by a reputable DCS/PLC supplier. Any normally operating auxiliary systems during normal startup and shutdown operation of the Project will be controlled through the DCS/PLC. The DCS/PLC will be capable of allowing control and data to be passed between the CALISO and the plants AGCT or RIG system. The interfacing allows using Ethernet with OPC protocol that will interface with Owners equipment. The microprocessor-based DCS/PLC will be complete with design, engineering, materials, manufacture and assembly, optimization, documentation, testing, and field services. The DCS/PLC will include automatic control and monitoring of the startup, shutdown, and normal operation of the Project systems through redundant Project communication loops. The DCS/PLC will provide automatic and manual control of all major subsystems. The Project will include a master clock system synchronized with satellite (GPS) complete with antenna, accessories, and equipment. This master clock system will provide time synchronization signals for all control systems for the plant requiring time synchronization.

10E3.1.1Performance Requirements
The system will be properly protected from voltage surges that normally occur in a power plant. Inputs, outputs, and other connections will meet the surge withstand requirements of ANSI C37.90a. The devices will have input to output isolation, shielding, separation of circuits, surge suppression, and other measures to meet these provisions. The system will operate satisfactorily without air-conditioning and with ambient temperatures from 40F to 110F at a relative humidity of 20 percent to 95 percent, non-condensing.

10E3.1.2 Functional Requirements


Remote I/O and logic cabinets may be used within the Project. Data highways must be used and must be physically separated from each other and routed in different raceway systems between the remote I/O and logic cabinets and the control room operating consoles. Redundant communication loops are not included. All engineering functions must be able to be performed remotely via an engineering console located in the control room equipment area.

10E-4

PO062006001SAC/344005/062560001 (HBRP_APP10E.DOC)

APPENDIX 10E: CONTROL ENGINEERING DESIGN CRITERIA

The operating staff at the Project will be kept to a minimum. Therefore, a high level of automation and reliability is required. Each system will be capable of operating on full automatic. Fail-in-place lock-up features upon loss of air or signal will be provided as appropriate for the application. The DCS/PLC will alarm all abnormal process and operating conditions, system component failures, loss of air on critical control valves, etc., to ensure safe and efficient operation of the Unit. Alarms will also be provided to meet the requirements of all Applicable Laws and Applicable Standards. The operator will have the ability to tag out equipment (fans, pumps, valves, dampers, etc.) from the CRTs for work performed by maintenance personnel. When a piece of equipment is tagged out by the operator, the operation of that device by the control system will be inhibited in the system logic. The graphics displays will indicate when a device is tagged out.

10E3.1.3 Console Design


The control system will be designed to allow Project operation by a minimum number of operators. All Project systems will be operable from the console to be located in the main control room. The console will consist of, but not limited to, the following: Three DCS/PLC CRTs Three keyboards Sequence-of-events recording Engine control - 1 CRT for up to 4 engines Accessories as required (keyboards, printers, etc.)

10E3.1.4 Hardware Requirements


The following paragraphs define the general requirements for the hardware and software for the DCS/PLC and other microprocessor-based control systems:

10E3.1.5 DCS/PLC Partitioning


The DCS/PLC and reciprocating engine control systems will be divided into subsystems according to the Attachment 12, Preliminary Automation Layout. The logic hardware for each subsystem will be independent from the other subsystems. Critical safety-related communications between subsystems will be through hardwired I/O. All other communication will be by data-highway. The failure of a processor will not shutdown more than one engine. Any portion of the control system whose failure could shutdown more than one engine must have installed redundancy.

10E3.1.6 Power
The failure of a power feed will to the DCS/PLC control systems will not shutdown more than one engine. The primary feed will be 24-Vdc for the control system, and 120-Vac with UPS for the WOIS system. A failure of a power supply will not affect system operation. Failure of any power supply will be alarmed on the CRTs on the main control room and Project maintenance personnel will be capable of replacing power supplies with the system on-line. Modular power supplies may be provided as a substitute for 100 percent power supplies provided they are

PO062006001SAC/344005/062560001 (HBRP_APP10E.DOC)

10E-5

APPENDIX 10E: CONTROL ENGINEERING DESIGN CRITERIA

supplied on an N+1 configuration per cabinet. In addition, loss of any battery backup power should be alarmed in the DCS/PLC.

10E3.1.7 System Failure Protection


No single hardware or software failure will affect normal control of the Plant. Any portion of the control system whose failure could shutdown more than one engine must have installed redundancy. System programs and configurations will reside in nonvolatile memory. Any volatile memory will be easily re-installed. System failures will be alarmed and logged on a printer.

10E3.1.8 DCS Communication Network


The Projects DCS/PLC communication network will consist of a single data-highway loop, to which the DCS/PLC will be connected. DCS/PLC will be connected to the data-highway loop with communication hardware. The communication hardware will have automatic loop transfer capability to provide protection against a single loop failure. Loss of the data-highway loop will be alarmed. The data-highway will permit all devices in each system to interface with one another. Individual points will be scanned, system communications completed, and control signal outputs updated at least once every 1/3 second. All data on CRT displays will be updated at least once every second. CRT graphics displays will be fully displayed with all current live data within 2 seconds after the request for the display has been initiated.

10E3.1.9 Printers
The system will include color graphics-capable quiet printers. Three printers and stands are required. One printer will be dedicated to alarms. Alarms will be printed in red. Cleared alarms will be printed in black. The other printer will be for logs and graphic displays printing.

10E.1.10 Computing Hardware and System I/O


To the maximum extent possible, redundant process equipment (pumps, fans, etc.) will have its control located on different I/O cards. Process status data from an individual piece of equipment will be wired to the same input card, except for signals from redundant transmitters, which will be wired to different input cards. Contractor will identify where redundancy is not possible. The meaning of contact within the scope of this specification will be an electro-mechanical relay contact, or a solid-state switch, such as a triac, transistor, or semiconducting rectifier. Contact ratings will be compatible with the controlled loads. Each subsystem will be shipped with a minimum of 10 percent spare I/O installed. This I/O will be wired out to terminals. The loading of all system controllers will not exceed 60 percent continuously.

10E-6

PO062006001SAC/344005/062560001 (HBRP_APP10E.DOC)

APPENDIX 10E: CONTROL ENGINEERING DESIGN CRITERIA

Sufficient spare rack and cabinet space will be available at shipment to expand the logic capacity and I/O capacity of each subsystem by at least 10 percent by adding the appropriate modules and equipment.

10E.1.11 System Cabinets


Cable entry into system cabinets will be through the top or bottom. Cable supports will be provided in each cabinet. Cables will not block access to any cabinet hardware for equipment inspection, maintenance, or removal and replacement. A high-temperature alarm for each logic cabinet will be provided and displayed on the console CRTs. Terminations from the field will be terminated on vendors standard termination unit. Not more than one wire will be connected to one terminal block point except where jumper wires are necessary, in which case two wires may be connected for internal wiring. Each I/O point including spares will be provided with vendors standard terminals. No more than one wire will be connected to one terminal, except where jumper wires are necessary.

10E.1.12 Electrical Design Criteria


All control devices and components will be heavy-duty type suitable for operation at 120 Vac, 24Vdc, or 125 Vdc. To the maximum extent, insulation of coils will permit continuous operation at a temperature of 130C. If this temperature rating cannot be met with commercially available products, the Contractor will identify such components to the Owner. Contacts for external control circuits will be heavy-duty type. The contacts will have an AC interrupting capacity of ten times their normal rating and will not exhibit excessive arcing or contact bounce. Relays with exposed contacts will not be used. The voltage for contact interrogation is 24 Vdc for the DCS/PLC and reciprocating engine control system. All limit switches will be heavy-duty snap-action types. The DCS/PLC and reciprocating engine control system cabinets will include the following: Cabinet ground bus: Bus for grounding cabinet, rack, and equipment grounds Insulated or common ground bus: Bus for grounding instrument and control cable shields

All cabinet ground buses will be grounded to building steel. Wire markers on both ends of each wire that is longer than 12 inches will be provided with indelible designations in accordance with the DCS/PLC suppliers wiring diagrams.

PO062006001SAC/344005/062560001 (HBRP_APP10E.DOC)

10E-7

APPENDIX 10E: CONTROL ENGINEERING DESIGN CRITERIA

10E3.2 Software Requirements


10E3.2.1 Data Acquisition
A data acquisition system (DAS) will be provided as part of the DCS/PLC and will include a performance and monitoring package to track the unit and plant performance. The system will average, weight average, and integrate pressures, temperatures, flows, calculated values, etc., as required for the performance calculations, logs, etc. The Contractor will provide WISE workstations, which can interface to PG&E via Ethernet and OPC network. The DAS will, as a minimum, perform the following functions: Time-stamp and store all data point at user-specified level of accuracy to common database Redundant hard drive storage of at least 365 days of data Archive storage on optical or other remotely accessible storage system Provide for direct transfer of files in MS Windows software.

Contractors system must communicate with Owners PI system.

10E3.2.1.1 Sequence of Events Recording


The DCS/PLC will provide scanning of not less than 150 digital (contact) inputs for the sequential events recording (SER) system. These inputs will be scanned to discriminate between contact operations, which occur a minimum of one millisecond apart, and print them in their proper sequence when they are opening and closing. Each event will be printed on the log printer as an individual event. The complete time will be parted out in hours, minutes, seconds, and milliseconds with each sequential event contract status change. Contractor will provide its standard SER system in the form of its WISE system. The controls cycling time is limited by the processor cycling time which is between 10 - 50 m-seconds. The actual events reporting occurs in time intervals of maximum of 2 seconds. The DCS/PLC will include sufficient buffer storage in the data acquisition system memory structure for the SER programs to ensure that the system will not fail to detect a contact operation due to storage or print buffer filling. The DCS/PLC will include the SER program to permit storage of the sequence of events log in the Historical Storage and Retrieval (HSR) system in addition to printing the information on the log printer. The HSR will be sized large enough to store all sequence-of-events logs.

10E3.2.1.2 Logging
The system will log pre-selected variables at one hour intervals beginning at 1:00 AM. Values will be printed at the end of each 24-hour period at midnight on the log printer. The variables will consist of calculated values, averaged values, integrated values, instantaneous values, weight-averaged values, or the maximum value for the time period.

10E-8

PO062006001SAC/344005/062560001 (HBRP_APP10E.DOC)

APPENDIX 10E: CONTROL ENGINEERING DESIGN CRITERIA

The variables and the exact format of the log will be agreed to by the Parties. Data will be logged on sheets in column form with data for any given variable tabulated in one vertical column. The data currently being accumulated for the log will be protected in case of system failure. The log program will automatically re-initiate the accumulation of data following a system fail over without loss of data.

10E3.2.1.3 Historical Data Collection, Storage, and Presentation


A historical data collection, storage, and presentation (HCSP) system will be provided that will fully automate the collection, storage, retrieval and presentation of plant data. The HCSP will provide a centralized collection of information, a real-time database and a historical data archive. The HCSP will interface with all of the plant real-time systems (i.e. reciprocating engine control system, BOP, DCS/PLC, etc.) simultaneously and will be capable of reading and writing to these systems. The HCSP will be complete with server, monitor, RAM, hard drive, CD backup, CD ROM drive, etc.

10E3.2.1.4 Graphics Displays


The graphics displays for use by the operators on the CRTs will be developed in accordance with the Contractors standard utility format. Information displayed on the graphic displays are subject to approval by Owner. The DCS/PLC will include spare capacity of 20 percent for the number of graphic pages for future additions.

10E3.2.2 DCS/PLC Interfaces


The DCS/PLC will be designed to interface with other Project systems, specifically the reciprocating engine control system, the chemical feed system, gas metering system, power electronics monitoring/control system, and data acquisition system. Except as noted, packaged systems including the demineralized water treatment will be programmed into the DCS/PLC. The continuous emissions monitoring system (CEMS), the gas compressor system controls, and the fire protection system will be stand-alone systems. Where programmable logic controllers (PLC) are used, these control systems will be a Siemens S7-400 or Siemens S7-300 with a data highway type connection to the DCS/PLC. The DCS/PLC will be configured by the DCS/PLC supplier with information and coordination provided by the Contractor. A consistent control and instrumentation philosophy will apply throughout the plant to minimize diversity of equipment type and equipment manufacturer. Either 48 Vdc or 24 Vdc will be used for the digital input wetting voltage.

10E3.2.3 Reciprocating Engine Control Interface


The DCS/PLC will be designed to control by feed forward action, with system calibration and final correction provided by feedback action. The engine controls will be the manufacturers standard, including the degree to which the use of feedback/feed forward control logic is employed. Engine controls are the Contractors standard, including the degree to which the use of feedback/feed forward control logic is employed. The control equipment furnished will include all feed forward devices and other equipment to provide complete stability under all conditions of dynamic load changes. Feed forward demands will be developed for Reciprocating Engine demand, fuel flow, etc. The system will control

PO062006001SAC/344005/062560001 (HBRP_APP10E.DOC)

10E-9

APPENDIX 10E: CONTROL ENGINEERING DESIGN CRITERIA

the operation of the Reciprocating Engine cylinders, main gas admission valve duration and timing through the Reciprocating Engine control systems. The DCS/PLC will be fully interfaced with the Reciprocating Engine control system. Critical control and protection/trip functions will be hardwired between DCS/PLC and Reciprocating Engine control system. The communication interface to the Reciprocating Engine control system will be provided in accordance with Reciprocating Engine manufacturers requirements for DAS functions and non-critical control signals. The Contractor will be responsible for complete interface between the DCS/PLC and the Reciprocating Engine control systems. The DCS/PLC will interface to the Reciprocating Engine control system to manage the following analog and digital Reciprocating Engine control functions: Startup sequencing through synchronization. Speed and load control. Safety control including: Automatic safe shutdown (ramp down) Selected shutdown (ramp down). Emergency shutdown (fuel shutoff).

The Contractor will provide sufficient manual control capability for Reciprocating Engine speed, generator voltage, and excitation such that a single operator can control the Project from the main electrical panel. Inputs for fuel gas flow to each Reciprocating Engine will be provided.

10E3.3 Testing
A standard factory acceptance test (FAT) of the complete control package including all software, hardware, graphics, and alarming will be provided. The FAT will be performed in the factory by the Contractor and witnessed by the Owner or Owner representative before shipment. See Section 4.4 for additional information on FAT.

10E3.3.1 Tools
One complete set of all special tools, software, and appurtenances required for maintenance and operation will be furnished with each system. The Contractor will itemize the special tools and software that will be furnished. If no special tools and software are required, the Contractor will make a clear statement to this effect before Substantial Completion. Any such tools required will become the property of the Owner.

10E3.3.2 Installation and Operating Instructions


System logic diagrams, configuration drawings, and schematics will be bound in a separate volume of the instruction manual and shipped within two months of system shipment. Drawings will be 11 x 17. The installation and operating instruction books will be complete to provide necessary details for the installation, operation, and maintenance of all control systems and equipment

10E-10

PO062006001SAC/344005/062560001 (HBRP_APP10E.DOC)

APPENDIX 10E: CONTROL ENGINEERING DESIGN CRITERIA

furnished for the Project. Refer to section on Documentation for the detailed requirements for the Instruction Books and Operating Manuals.

10E3.4 Continuous Emissions Monitoring System


The Project will include a continuous emissions monitoring system (CEMS) for the Project. A CEMS will consist of a continuous duty, remote type analyzer subsystem with an extractive probe sampling system for each of the common stack for grouped generating units and a common data acquisition system. A maximum of two analyzer subsystems may be installed in one CEMS shelter. The more stringent of air permit requirements or one CEM per emission point will be provided. The CEMS will be complete in all respects while meeting the requirements of this section. The Contractor will develop the EPA and any local monitoring plans, which will be subject to Owners review. The system will be designed to comply with the Quality Assurance Procedures of 40 CFR Part 75, Appendix B. In addition, the system will be designed to comply with all applicable EPA installation, performance, testing, quality assurance procedures, and requirements set for the in 40 CFR Part 60, as well as all applicable requirements of state and federal air quality permits. The CEM system will be a complete and tested system ready for reliable commercial operation. Failure of any system component or control will be alarmed at the data logger in the control room. Contractor will provide one analyzer/data logger for a maximum of 3 engines. In addition, one spare analyzer/data logger will be included (not installed) for the entire plant. Data loggers can all feed one data acquisition system (DAS). Contractor will provide a backup CEM server/DAS PC, and a separate CEMS workstation to provide data to operations in the control center. Contractor will locate the DAS PC near the CEMS data loggers. Data loggers will store 4 days of 1-minute data and 7 days of hourly data.

10E3.4.1 Analyzer Subsystem


Each generating units analyzer subsystem will consist of one sample transport system and one set of continuous emissions monitors for the following flue gas constituents. The Project will include all analyzers in accordance with Applicable Laws, which include the following: Nitrogen oxides (NOX) dual range (low and high level) Oxygen (O2) Carbon monoxide (CO)

The system will be sized and constructed to provide a transit time from the stack probe to the analyzer no greater than 6 minutes. This transit time will including the time the analyzer requires to achieve a stable reading after a 95 percent step change in sample value in both the upscale and downscale directions (re: 40 CFR Part 75, App. A 6.4 Cycle Time Test criteria).

PO062006001SAC/344005/062560001 (HBRP_APP10E.DOC)

10E-11

APPENDIX 10E: CONTROL ENGINEERING DESIGN CRITERIA

All of the analyzers, data logger, and manual control switches for each unit will be housed in a single standard 19-inch rack. Rack space will not be shared between generating unit systems. The space for pumps, filters, chillers, and other items may be shared between unit systems, but each item must be clearly identified by unit. The CEMS will be complete with analyzers, data logging, calibration gases, etc. At Substantial Completion, the Contractor will furnish a 6-month supply of certified gases in rechargeable cylinders for each flue gas constituent to be monitored. This includes calibration gases for the daily zero and span calibrations, and the low, medium and high range linearity gasses. Each gas cylinder will be supplied with an appropriate two-stage regulator and will be connected to the sample transport system. All tubing on the exterior of the CEMS building will be 316 stainless steel tubing or tubing with a stainless steel jacket. These cylinders will become the property of the Owner and remain on the Project site. Spare parts for both CEMS and Data Acquisition System will be provided.

10E3.4.2 Sample Transport System


Separate sample transport systems will be provided for each generating unit that would have emissions. A separate umbilical bundle will be provided for each unit. This umbilical bundle will be self-limiting heat traced and contain all cable and tubing required to connect the stack probe to the CEMS. Each umbilical will be long enough to reach from the probe to the termination point in the CEMS shelter without splicing. The heat tracing for each umbilical bundle will be the temperature-controlled type and will be an integral part of the umbilical. A temperature controller will be provided inside the CEMS shelter for this heat tracing. Sample probes will have a sufficient length to meet EPA requirements and to obtain a representative sample. Heated probes and the necessary provisions to prevent failure due to moisture or other flue gas constituent will be supplied. If required by the equipment manufacturer, automatic probe cleaning will be furnished. Automatic probe cleaning will be controlled through the CEMS data logger. Provisions for source testing will be provided including test ports, test platforms, ladders and test probes.

10E3.4.3 Stack Gas Monitoring Equipment


Stack gas analyzers will have a proven track record in meeting EPA requirements on multiple units.

10E3.4.4 CEMS Data Logger


CEMS will include all hardware, software, and configuration needed to provide a system that meets all requirements of 40 CFR Part 75 and local air district regulations and permit conditions. The Dataloggers must be Ethernet capable and accessible via a Local Area Network.

10E-12

PO062006001SAC/344005/062560001 (HBRP_APP10E.DOC)

APPENDIX 10E: CONTROL ENGINEERING DESIGN CRITERIA

10E3.4.5 CEMS Enclosure


The Project will include sample conditioning system, analyzers, power supply system, and lighting in a CEMS enclosure/shelter. The enclosure/shelter will be sturdy and suitable for power plant application. The enclosure/shelter will be walk-in, dust-tight, and weather-tight and built in accordance with the local building code requirements. The CEMS enclosure/shelter will have one HVAC system as defined in the Mechanical HVAC section. The analyzers and data-loggers will be connected to the plant UPS. A maintenance switch will be provided to allow manual calibrations. The maintenance switch will provide a signal to the Data Logger as being in Maintenance Mode. Only when the maintenance switch is active will the manual calibration valves and switches be energized.

10E3.4.6 Documentation
Installation, operating, and maintenance instructions will be provided by the Contractor for each item in the CEMS system and building. These instructions will be provided both in hardcopy and on a CD-ROM. Hardcopy manuals may be scanned into Adobe Acrobat 3.0 or later and then included on the CD-ROM. Classroom and hands-on training will be provided.

10E3.4.7 Shipping
The complete CEMS will be shipped to the site assembled with all the CEMS apparatus, analyzer subsystem, sample transport system, and interior shelter features mounted in place.

10E3.4.8 Factory Checkout


The Contractor will check the CEMS at the factory before it is shipped to the site to ensure that the CEMS meets all EPA requirements before shipment.

10E3.4.9 Data Acquisition System


The Contractor will provide a complete data acquisition system (DAS) with software and hardware. The DAS, which will fully comply with all applicable requirements of 40 CFR Part 75 as well as local air district regulations, will be capable of being located in the Projects main control room, or at other location on-site as specified by Owner. It will be capable of interfacing with the data logger on that Project site. The system will collect, store, calculate, edit, display, and print out data and other information as set forth in the requirements that follow. A second operator workstation computer capable of accessing the polling computer data will be required.

PO062006001SAC/344005/062560001 (HBRP_APP10E.DOC)

10E-13

APPENDIX 10E: CONTROL ENGINEERING DESIGN CRITERIA

10E3.4.10 DAS Hardware


The polling computer will include the following items at a minimum: A current Pentium 4 or equivalent processor, with a minimum 512 MB RAM, 32X CD ROM, 4 mm tape backup, 80-GB hard drive, CD RW drive, 8MB AGP video, Ethernet card, and 56K modem. 19-inch video display terminal, high-resolution color flat screen monitor (VGA or superior - 1600 x 1200 at 75 Hz-26mm dot pitch). Report printer All interconnecting cables. Full duplex Ethernet connectivity/capability for Project LAN connection.

The workstation computer will include the following items at a minimum: A current Pentium 4 or equivalent processor, with a minimum 512 MB RAM, 32X CD ROM, 4 mm tape backup, 80-GB hard drive, CD RW drive, 8MB AGP video, Ethernet card, and 56K modem. 21-inch video display terminal, high-resolution color monitor (SVGA or superior - 1600 x 1200 at 75 Hz-26mm dot pitch). Report printer All interconnecting cables. Full duplex Ethernet connectivity/capability for Project LAN connection.

The workstation computer, CRT, printer and other equipment will be mounted on a workstation/desk with an accompanying printer stand. This workstation will be in its own space in the Project control room.

10E3.4.10.1 Software
The system program will provide the following features: Multi-task operation such that data can be collected in background mode allowing report generating or data editing in foreground mode. Printer backup such that a printer failure will not cause the program to stop. All printer output is to be stored, so that when the printer is ready, the system will print in sequence all reports generated during the time the printer was unavailable. Auto-restart such that should a system failure occur, it would automatically restart itself when the failure is cleared. This feature eliminates the need for any manual reloading of the system program. Editing of all data on reports such that the revised data will be included in any requested report, unless otherwise specified.

10E-14

PO062006001SAC/344005/062560001 (HBRP_APP10E.DOC)

APPENDIX 10E: CONTROL ENGINEERING DESIGN CRITERIA

Internal clock/calendar with automatic leap year and operator-controllable daylight savings time adjustments. Keylock feature to limit access to program parameters using multi-level passwords. One level for operators to call up reports One level for engineers to edit report One level for technicians for diagnostics, etc.

Ability to download data in ASCII format. Capability of expanding if other emission monitoring points or types is added. Program backup on a CDROM for reloading should the system fail. The actual source code should be supplied in hard copy format. Software with standard REASONS CODES Video display terminal, to provide Real-time view of all measured and calculated parameters Engine (each) monitor status Visual alarm indication of potential emission standard violations, excessive monitor calibration drift, or monitoring system failure Graphics & trending

Hourly data transfer to the non-volatile memory or C hard drive and then daily transfer to the D hard drive. Software to support remote interrogation by modem Users Manual based on Owner specific software Calculations, record keeping, reporting, bias adjustment, automatic data substitution procedures, and other requirements set forth in 40 CFR Part 75. CEMs Data Acquisition System software will be the Contractors standards and will, to the maximum possible extent, comply with the requirements of this specification.

10E3.4.10.2 Data Communications System


Fiber optic cable will be used between the polling computer and each data logger. This cable will be installed in its own conduit. Communication cables may be coax cable. The Contractor will provide all fiber optic modems and telephone connections required for the Project to interface with Owners data communication system at the designated connection points.

10E3.4.10.3 Reporting and Recordkeeping Requirements


The data acquisition system will automatically compute and cause to have printed all information required pursuant to Applicable Laws and Applicable Standards.

PO062006001SAC/344005/062560001 (HBRP_APP10E.DOC)

10E-15

APPENDIX 10E: CONTROL ENGINEERING DESIGN CRITERIA

10E3.4.10.4 Quality Assurance and Quality Control Data


The data acquisition system will be required to record and maintain data pertaining to daily and periodic monitor calibrations and checks and all other monitoring data quality assurance and quality control procedures. The records generated and maintained will be sufficient to satisfy all applicable quality assurance and quality control provisions of 40 CFR Part 75 and 40 CFR Part 60. Data will be recorded daily for each gaseous pollutant, dilutent, and flow monitor, as applicable. Periodic testing and certification procedures are required to assure monitoring data quality. The data to be recorded periodically for each gaseous pollutant, dilutent, and flow monitor, as applicable, will meet all applicable requirements of 40 CFR Part 75 and 40 CFR Part 60. At requested intervals, such as quarterly, the CEMS will be capable of producing reports based on edited and unedited data. The data acquisition system will compute and cause reports to be printed, when requested by the operator. The data processor will be designed to store sufficient data to produce these reports. Power supply failure will not erase the stored data or the program. The data acquisition system will be capable of compiling and generating quarterly reports pursuant to the requirements of 40 CFR Part 75, and 40 CFR Part 60, as applicable, and of any applicable state regulations, and as required by Owners air quality permits. The data acquisition system will be capable of producing these reports in printed and electronic format suitable for submission per the Project reporting requirements.

10E3.5 Balance-of-Plant Instrumentation Installation Criteria and Installation Details


10E3.5.1 Scope of Specification
The following criteria cover the general requirements for the installation of instrumentation and control systems. The scope of work covered by this specification includes, but is not limited to, installation and support of field instruments, instrument impulse lines, pneumatic signal lines, sample lines, and local instrument cabinets. The use of eyewash stations and showers will be alarmed in the DCS/PLC. No primary sensor full-scale signal level, other than thermocouples, will be less than 10 mV or greater than 125 V. To the extent practical, instrumentation will be standardized. Instrument analog signals for electronic instrument systems will be 4 to 20 mA dc. Instrument analog signals for pneumatic instrument systems will be 3 to 15 psig. Use of pneumatic controls will be limited to applications where sub-supplier standard designs cannot be provided without them.

10E-16

PO062006001SAC/344005/062560001 (HBRP_APP10E.DOC)

APPENDIX 10E: CONTROL ENGINEERING DESIGN CRITERIA

The following units of measurement will be used in process measurement and control. English units are preferred, but metric units may be used when in common practice:
Parameter Temperature Pressure Units of Measurement degrees Fahrenheit (o F) pounds per square inch gauge (psig) inches of water column (in wc) or (inH2O) pounds per square inch absolute (psia) inches of mercury absolute (HgA) Level General Tank Gauge Deviation from normal level Flow Liquids gallons per minute (gpm) pounds per hour (pph or #/hr) Gases and Vapors Standard cubic feet per minute at 60 OF (SCFM) Standard cubic feet per hour at 60 OF (SCFH) Percent Gallons

Solids

pounds per hour (pph or #/hr) tons per day (tpd)

Water Sampling PH Specific conductivity Cation conductivity Degassed cation conductivity Dissolved oxygen Silica or sodium Oxygen scavenger Sulfate, phosphate, chloride pH (pH Units) S/cm S/cm S/cm parts per billion (ppb) parts per billion (ppb) parts per billion (ppb) parts per billion (ppb)

Permanently attached stainless steel tags will be purchased with all major instrument equipment. Each tag will carry the item tag number. This tag is in addition to the nameplate, which provides the manufacturers model number and other data. Thermocouple and test wells will have the material of construction stamped on the well. If tag numbers are assigned to these wells, the number will also be stamped on the well.

PO062006001SAC/344005/062560001 (HBRP_APP10E.DOC)

10E-17

APPENDIX 10E: CONTROL ENGINEERING DESIGN CRITERIA

Instruments in vapor or gas service will generally be mounted above the sensing point. Instruments in liquid, steam, or condensable vapor service will generally be mounted below the sensing point. If accessibility, visibility, or clearance requirements preclude either of these situations, provisions will be made in the instrument piping configuration to ensure proper operation of the instrument. Close-coupled line-mounted pressure and temperature gauges are mounted above the sensing point and are excluded from the aforementioned. Instrument root valves at piping or equipment connections will be accessible from grade, platform, stairway, or permanent ladder. Indicating instruments that must be visible for automatic control adjustment or manual operation will be visible from the adjustment or operating point. If plot or piping arrangement precludes this, other provisions will be made for indication at the adjustment or operating point. Indicating instruments not in the above category will be visible from operating aisles or passageways. Instruments will be located so that required clearances are maintained for walkways, accessways, and operation and maintenance of valves and equipment. Blind transmitting instruments will generally be line-mounted as near the sensing point as practical. Instruments will not be line-mounted when temperature or vibration from hydraulics or operating equipment will affect the operation of the instruments or cause damage to instrument piping. Local recording and/or control instruments, except displacer-type level controllers and flange-mounted transmitters, will generally be remote mounted at grade or outside platform handrails. When practical, remote-mounted instruments will be grouped and have common supports. Instrument piping will generally be routed through pipeways and areas provided for the routing of plant piping, and the piping will be routed such as to protect it from damage during plant operation and maintenance. Routing of instrument piping will be controlled by the Field Control Systems Supervisor or Engineer. Instrument piping will be supported from pipe supports, pipe, and any other permanent structure, except as follows: Instrument piping will not be supported from uninsulated hot (125F and above) or cold (40F and below) pipes. Instrument piping supports will not be welded to stress-relieved equipment or internally lined equipment. Instrument piping supports will be sufficient to maintain the piping in a neat manner. Instrument process piping having horizontal runs greater than 5-0 or combined horizontal and vertical runs greater than 10-0 will be supported. The maximum length of unsupported tubing at a bend will be 4-0.

All instruments and instrument process lines subject to freezing will be heat traced, filled with seal fluid, and purged or otherwise protected from freezing. Preference will be given to heat-traced sensing lines and heated enclosures. The instruments and process lines will be identified on the P&IDs.

10E-18

PO062006001SAC/344005/062560001 (HBRP_APP10E.DOC)

APPENDIX 10E: CONTROL ENGINEERING DESIGN CRITERIA

10E3.5.2 Instrumentation Electrical Requirements


Enclosures for electrical instruments will comply with requirements of the Electrical Area Classification in which they are installed. If the manufacturer of certain instruments cannot provide enclosures suitable for the area, purging of the enclosure with inert, dry air or gas will be given consideration. Cases for locally mounted instruments and devices will be weatherproof as a minimum. Terminals for electrical interconnections including thermocouple wire will be clearly identified to indicate polarity, electrical ground where applicable, and test connection. Terminals for purchased items will normally be identified in accordance with manufacturers standard marking. Electrical conduit connections for locally mounted instruments will normally be internally threaded, where available as manufacturers standard option. Connections will be suitable for the Electrical Area Classification in which the instrument is installed.

10E3.5.3 Pressure Instruments


Main process pressure gauge case sizes will be 4.5 inches; Standard OEM gauges may vary from 4.5 inches Connections will normally be 0.5-inch MNPT for 4.5-inch locally mounted gauges. Receiver gauges and 1.5 to 2.5-inch gauges will be 0.25 inch NPT. Wherever necessary for Project operation, either industrial-type, 4.5-inch diameter pressure gauges with white face and black scale markings or indicating pressure transmitters will be provided. Dials will be white, non-rusting metal or plastic with black figures. Manufacturers standard dial faces will be provided. Dials or pointers will be field adjustable for zero alignment. These requirements do not apply to 1.5-inch and 2-inch gauges. Steam pressure sensing transmitters or gauges mounted above the steam line will be protected by a loop seal or a siphon. Siphons will be installed on pressure gauges in steam service as required by the system design. Pressure gauges on process piping will generally be visible 10 feet from an operators normal stance at floor level and will be resistant to Project atmospheres. Main pressure gauge accuracy will be 0.5 percent of full range per ANSI Specification B40.1, Grade 2A. Standard OEM gauges may vary from these requirements. Pressure devices on pulsating services will be equipped with pulsation dampers. Pressure devices subject to shock during equipment starts, stops or transient conditions will be installed on an isolated gauge panel. In general, pressure instruments will have linear scales with units in psig. Fire protection system pressure gauges will be designed in accordance with Underwriters Laboratories (UL) standards. Pressure test points will be equipped with isolation valve and cap or plug.

PO062006001SAC/344005/062560001 (HBRP_APP10E.DOC)

10E-19

APPENDIX 10E: CONTROL ENGINEERING DESIGN CRITERIA

Pressure gauges will be provided with either a blow-out disk or a blow-out back. Alternately, separate safety valves may be used. Pressure gauges will have acrylic or shatterproof glass faces. Differential pressure instruments will normally be of the manometer type, either liquid-filled, bellows, or force-balance type according to requirements. Pressure gauge elements in contact with process fluid will normally be 316 stainless steel, except where the process requires a special material. Elements above 1,000 psig will be bored instead of drawn with threaded and backwelded connection to the socket and tip. Bronze elements will normally be used for air service. Sockets and tips will be stainless steel for stainless steel bourdon tubes, and brass for bronze bourdon tubes, in accordance with manufacturers standards. Overpressure protection will be 1.3 times the maximum tube rating to prevent permanent set or loss of calibration from continuous overpressures. For services of 0 to 60 psi and below, wide bourdon tubes will be furnished with external gauge protectors. Gauges will be vacuum protected. Ranges will be so specified that the gauges normally operate in the middle third of their scales. Gauges on pump discharges will be specified for over-range protection beyond the pump shut-in pressure or relief valve setting. Gauges on vessels will be specified for overrange protection not less than 1.2 times the vessel design pressure. Cases for gauges in the process area and in process service will be solid front, phenolic with a screwed ring, or plastic turret type with a snap ring. Outdoor cases will be weatherproof, and metal cases will be protected with weather-resistant black paint. Indoor instruments (inside buildings) are not required to have weatherproof cases. Weep holes will be provided on the case bottom of all gauges located in humid areas unless the case already has sufficient ventilation. Diaphragm protectors will be used where necessary to protect gauges from corrosive fluids. They will have 0.5-inch NPT screwed or flanged connections in accordance with piping specifications.

10E3.5.4 Temperature Instruments


Temperature elements and dial thermometers will be protected by thermowells except when measuring gas or air temperatures at atmospheric pressure. Temperature test points will be equipped with thermowells fitted with caps or plugs. Dial thermometers will have 5-inch diameter (minimum) dials and white faces with black scale markings and be every-angle type and bimetal actuated. Dial thermometers will generally be visible 10 feet from an operators normal stance at floor level (viewing area) and be resistant to Project atmospheres. If a thermocouple is inaccessible, the leads will be brought to an accessible junction box. Thermocouples (if used) will be dual-element, ungrounded, spring-loaded, Chromel-Constantan (ANSI Type E) or Chromel-Alumel (ANSI Type K) for general service.

10E-20

PO062006001SAC/344005/062560001 (HBRP_APP10E.DOC)

APPENDIX 10E: CONTROL ENGINEERING DESIGN CRITERIA

Thermocouples general application will normally be magnesium-oxide insulated sheathed type. Thermocouple will be constructed with a 316SS sheath of 0.25-inch diameter. Thermoelectric properties, temperature limits, and limits of error of thermocouples and thermocouple extension wires will conform to ANSI Standard MC 96.1. Identification of thermocouples will be by a wired-on metal tag indicating the code or tag number. Thermocouple heads will be the cast aluminum type with an internal grounding screw. Conduit connection will be 0.75-inch. Connection to the thermocouple assembly will be 0.5-inch NPT. In general, temperature instruments will have scales with temperature units in degrees Fahrenheit. Exceptions to this are electrical machinery resistance temperature detectors (RTDs) and transformer winding temperatures, which are in degrees Celsius. RTDs will be either 100-ohm platinum type or 10-ohm, copper, three-wire circuits (R100/R0-1.385), and ungrounded. The element will be spring-loaded, mounted in a thermowell, and connected to a cast aluminum head assembly. Thermal-filled system instruments will be gas or liquid filled stainless steel capillary type. Material will be a minimum of ANSI Type 304 stainless steel machined from bar stock in a tapered configuration. Other materials may be specified as required by the piping specifications. The alloy used will meet the process metallurgical requirements. The temperature process connections will be 1-inch NPT where screwed connections are allowed by the piping classification. Where flanged connections are required by the piping classification, they will be designed to mate against a 1.5-inch raised face or ring joint flange in accordance with the piping specifications. Weld in thermowells will be at least 1-inch diameter. Special protecting tubes for high temperature applications of chrome iron, incoloy, or other special materials will be used as required by the temperature and the process materials. Thermowells in combining streams will be a minimum of 10 pipe diameters downstream of the junction for liquid services and 30 pipe diameters for vapor services. Brass plug and chain will be provided with all test wells. Thermowells will be designed to avoid root stress failure due to vibrations induced by wake vortices. Where the standard thermowell is designed to withstand the maximum fluid velocity permitted in the piping design standards, individual wake frequency calculators are not required. Dials of 3-inch diameter may be used in mechanical equipment lube and seal oil service or other auxiliary service. Installation of thermocouples, thermowells, test wells, and thermometers will be in accordance with utility and good engineering practice unless otherwise specified.

PO062006001SAC/344005/062560001 (HBRP_APP10E.DOC)

10E-21

APPENDIX 10E: CONTROL ENGINEERING DESIGN CRITERIA

10E3.5.5 Level Instruments


Reflex-glass, liquid-free, or magnetic level gauges (Penberthy or equal) will be used. Sump pump motors will be controlled by displacer or float-type level switches supplied by the sump pump manufacturer. Level transmitters for measuring the level in storage tanks vented to atmosphere will generally be the flange-mounted differential pressure type flush diaphragm and will be equipped with local indication as well as central control room indication. Differential pressure type level instruments will normally be used for all services except for vacuum services. When differential pressure type instruments are to be mounted at or below the taps, they will be furnished with zero elevation or suppression adjustment. External displacement type instruments will normally conform to the following: Material will normally be fabricated carbon steel, with stainless steel displacer and Inconel torque tube. Where vessels are of alloy construction, body material will be equivalent or better. Air fins or heat insulators will be used at operating temperatures above 400F and below 0F for displacers with pneumatic pilots. Where displacers with electronic transmitters are used, they will have air fins or heat insulators above 250F and below 0F. Connections will normally be 1.5-inch flanged with bottom-side and top-side connections. Flange ratings will be in accordance with vessel trim specification. Rotatable heads will normally be specified.

Transmitter Output will be 4 to 20 ma dc. Direct operated type level controls (e.g. ball float, mechanically linked valve) will be used on utility service only. Special level problems will arise periodically and will require special level measuring devices such as internal displacers or floats, bubblers, and electronic types (capacitance, ultrasonic, nuclear, conductive, or electrical resistance).

10E3.5.5.1 Liquid Level Columns (Bridles)


Liquid level bridles will be used to minimize the number of vessel nozzles where numerous level instrument connections are made to the same vessel The bridle upper connection will be flooded with process fluid for interface measurements The top and bottom connections of the bridle will be made directly to separate nozzles that are not connected to vessel inlet or outlet nozzles. The bottom connection of the level bridle will be located a minimum of 2 inches higher than the top of the vessel outlet when vessel discharges from the bottom. Level bridle piping will not have bends that will trap dirt or water.

10E-22

PO062006001SAC/344005/062560001 (HBRP_APP10E.DOC)

APPENDIX 10E: CONTROL ENGINEERING DESIGN CRITERIA

10E3.5.5.2 Storage Tank Instruments


Tape gauges will be provided. Water tanks will be equipped with flange-mounted level transmitters with local indication. Fuel tanks will be equipped with flange-mounted smart transmitters and a servo-controlled displacer gauge or approved equal. Tanks containing fuel and hazardous material will have instrumentation that can be tested without draining of contents.

10E3.5.6 Level Gauges


Typically, magnetic follower-type level gauges will be provided except for steam drum and supplier skids. Supplier skids will use the suppliers standard devices where suitable for heavy industrial use. Where glass gauges are provided by skid suppliers, gauge and ball checks will be provided. All vessels other than storage tanks, where actual level or interface level is measured for indication or control, will have a level gauge. Alloy construction (normally 304 stainless steel) will be used for all wetted parts where the application requires it, and on applications below 20F. Frost protection will be provided where operating temperatures are below 32F. Visibility will cover the operating range of the level instrument(s). In alarm and shutdown service, the visibility will normally cover the range of all level instruments including the shutdown point. Level glasses will be visible from grade, platform, or the related instrument. Connections of gauge glasses will normally be 0.5-inch or 0.75-inch NPT female top and bottom. Other connection orientations may be used where required. Where necessary, level glass cocks will meet vessel trim specifications and will be considered a combination block valve and safety shut-off cock. They will have a 0.75-inch solid-shank NPT male inlet with 0.5-inch or 0.75-inch NPT female spherical union gauge connection. A ball check will be furnished. Where standard gauge valves do not comply with the applicable piping standard, gate valves and ball check valves will be substituted. The gate and check valves will be installed in the horizontal line to the vessel, with tees provided for vents and drains.

10E3.5.7 Flow Elements Flow Nozzles and Venturis


Flow transmitters will be the differential pressure type with the range matching (as closely as practical) the primary element. Linear scales and charts will be used for flow indication and recording. Differential-pressure-type instruments will normally be used for flow measurements where suitable for the application.

PO062006001SAC/344005/062560001 (HBRP_APP10E.DOC)

10E-23

APPENDIX 10E: CONTROL ENGINEERING DESIGN CRITERIA

Flow transmitters will be the essentially zero volume displacement differential pressure type. Bodies will normally be carbon steel with stainless steel internal trim, unless other materials are required for the particular services. Overrange protection equal to the body rating will be provided. Wherever possible, the maximum differential range in inches of water will not exceed the static absolute pressure in psia in a compressible fluid application. Span will be continuously adjustable over at least a 5:1 ratio. Variable area flow meters may be used for small flow rates where local indication is required. They may also be used where rangeability, nonlinearity, viscosity, or the hazardous nature of the fluid makes the differential-pressure-type instrument unsatisfactory. They will normally be the armored type with magnetic pick-up, except for water and air below 200 psig and 1-inch-or-smaller lines where glass tubes may be used. All glass tube area meters will have front and rear plastic guard plates. Positive displacement meters will be used to measure those flows where a highly accurate integrated flowing quantity is desired.

10E3.5.8 Flow Elements Orifice Plates


Orifice plates of the square-edged concentric type will be specified except where unsatisfactory for the application. Plate dimensions will conform to ASME MFC-3M. Weep holes will be provided in steam and gas flow installations where there is possible condensation or in liquid flow where there is possible gas entrainment. Materials will normally be Type 304 stainless steel unless special materials are required for the service. For gas and vapor service, the differential pressure range in inches of water normally will not exceed the static absolute pressure in psia. Orifice bores will be calculated using ASME MFC-3M and ISO 5167. Flange taps will normally be used in accordance with ASME MFC-3M. For special alloys and 14-inch-and-larger pipe sizes, in 150-psi classification, throat taps may be used. One-half-inch NPT is the normal tap size for 300 psi through 600 psi flange rating. Three-quarter-inch is the tap size for 900 psi through 2,500 psi flange rating. Where threaded connections are not permitted by the pipe class, socket weld connections will be used. The minimum orifice flange rating will be 300 psi ANSI except for lines 14 inches and larger, where 150 psi ANSI is the minimum. The use of higher rated flanges, or of facing type, will be as called for in piping specifications. Ring-type plate holders will be manufacturers standard plate mounting. Ring facing will be oval ANSI standard unless otherwise required by piping specifications. Orifice taps for horizontal pipe runs will normally be oriented horizontal for clean liquids and steam, and vertical-up for gases. Venturi tubes, low-loss tubes, and flow nozzles will be used where high-pressure recovery is necessary and/or where only low inlet pressure is available.

10E-24

PO062006001SAC/344005/062560001 (HBRP_APP10E.DOC)

APPENDIX 10E: CONTROL ENGINEERING DESIGN CRITERIA

Averaging pitot tubes will be used where the pipe diameter is too large for acceptable orifice plate design in applications such as pump minimum flow bypass control, or where normal straight pipe requirements are not met. The element may have two pipe diameters of straight pipe upstream and downstream mounted in a plane parallel to the maximum disturbance. Other types of flow elements should be considered where their use is desirable and the above-mentioned elements are not applicable. Integral orifice meters (combination primary element-measuring device) will normally be used for meter runs of less than 1.5 inches with a suitable strainer upstream of the meter. Eccentric type orifice plates will be used for fluids containing two phases. The eccentric-type orifice plates will have the bottom of the orifice bore flush with the bottom ID of the pipe. Eccentric orifice plates will be used only in horizontal runs.

10E3.5.9 Annunciators, Alarm Switches, and Electrical Devices


Annunciator design will be in general accordance with ISA RP-18.1 Specifications and Guides for the Use of General Purpose Annunciators. Switches and shutdown for alarms and interlock systems will be used for on-off applications only. When outdoor installations are required, they will meet the area classification and be weatherproof. Switches in equipment shutdown service, where practical, will be directly connected to the process. Wiring for switches will be two conductors and will not use the common wire technique. Switch contacts will be specified as two single-pole double-throws (Form C) wherever the double mechanism does not induce unacceptable dead band. However, only one function per enclosure will be specified (i.e., alarm only or interlock only). On shutdown circuits, the second contact on the enclosure may be used for alarm, but proper signal separation will be maintained in the conduit system. Switch action for alarms, shutdowns, and interlocks will normally be closed circuit at normal operating conditions and open circuit for abnormal condition. Level switches will normally be the external float cage type with 1-inch NPT socket weld or screwed connections. Body material and rating will conform to piping specifications. Internal trim will be stainless steel unless other materials are required for the service. Level switches in alarm services may be receiver switches when there is a level transmitter as part of the system. Pressure switches for direct connected process and utility service will normally be diaphragm or bourdon-tube type with materials suitable for the service. They will meet the required electrical classification and will have micro switches. Connection sizes will normally be 0.5-inch NPT. Temperature switches, locally mounted in Division 1 or 2 locations, will be filled system bulb type or expansion type. They will meet the electrical classification and will have micro switches. Separable sockets will be furnished. Temperature switches mounted in the central

PO062006001SAC/344005/062560001 (HBRP_APP10E.DOC)

10E-25

APPENDIX 10E: CONTROL ENGINEERING DESIGN CRITERIA

control room or on a local panel will normally be thermocouple actuated with cold-junction compensation and be completely adjustable. Flow switches for direct operation by process fluids may be of the sight flow, rotameter, or paddle type for low accuracy requirements. Orifice plate and differential-pressure type will be used for high accuracy requirements. Solenoid valves will normally be used as pilots to actuate other instruments directly connected to process fluids. Valve bodies for solenoid valves will follow the piping specifications when used in process lines. Manufacturers standard brass will normally be used on air service. When outdoor installations are required, they will meet the area classification and will be weatherproof. Preferred voltage rating is 120 Vac. Coils for solenoid valves will be hi-temp molded and encapsulated and specified for continuous duty at rated voltage and frequency. Coils for direct current will be supplied with internal spike suppressors.

10E3.5.10 Process Analyzers and Analyzer Systems


This section does not apply to CEMs. All analyzers are to be completely piped, interconnected, and checked out for proper functional operating conditions. Complex process stream analyzer systems will be installed in a waterproof cabinet, enclosed house, or shelter. These will include the following provisions: Enough working space will be allowed for proper maintenance of the analyzers within the house. Analyzer houses and cabinets will be of metal or fiberglass construction and equipped with a door, lock, and key. These enclosures will be located as close to the process sample points as practical. More than one analyzer measuring and sample system may be installed in a single enclosure if the sample line length is within the analyzer manufacturers specifications.

All necessary calibration and operating gases will be provided including gas cylinders and regulators. CEMS equipment will be according to manufacturers recommendations. Analyzers requiring gases for continuous operation will be provided with dual facilities for uninterrupted service. Calibration standards and facilities will be supplied for zero and span check where specified. Protected outdoor storage racks adjacent to the analyzer houses will be provided for the carrier and calibration gas cylinders (including inventory) and their associated regulators. Process sample regulators will also be located on the outside of the analyzer houses.

The sample systems will be designed to deliver clean, representative samples to the analyzers at the proper temperatures, pressures, physical conditions, and flow rates.

10E-26

PO062006001SAC/344005/062560001 (HBRP_APP10E.DOC)

APPENDIX 10E: CONTROL ENGINEERING DESIGN CRITERIA

All wetted components will be 316 stainless steel, or equivalent, unless other materials are required to minimize contamination and corrosion. Main line class pipe may be used in high-temperature samples. Appropriate measures will be taken to prevent plugging of sample lines due to freezing, condensation, or solids. Where sample recovery systems are required, provision for drains will be made in the building design. Transportation time from sample point to analyzer will be less than 2 minutes for chromatographs and less than 1 minute for other analyzer types. Fast circulating loops and/or bypass lines will be used to achieve fast response times except where such a design would cause EPRI guidelines to be violated or sample composition to be changed. For fuel gas samples, the pressure will be reduced at the sampling point to increase the velocity through the sample system and reduce time lag (except in CEMS equipment where the manufacturers recommendation are to be followed). All sample and bypass lines will have flow indicators, such as rotameters. Bypass flows and discarded samples will be routed to chemical safe drains or vented safely to atmosphere. Adequate facilities will be provided to protect against unwanted backflow, overpressure, or other abnormal conditions. When sample conditioning components require heating, they will be located inside a heated and insulated cabinet or enclosure.

The analyzer and sample system will be vendor assembled and pretested in the vendors shop before shipment, unless otherwise specified. Electrical wiring of analyzers will conform to the National Electrical Code and applicable local codes. For large instruments such as analyzers that cannot be mounted in an explosion-proof box, air purging may be required. ISA RP-12.4 should be followed. If possible, the analyzer houses should be mounted in nonhazardous areas. Process control loops that include an analyzer will normally be cascaded. In some cases where the analyzer output is continuous and not delayed, direct control may be provided. Holding circuits will be provided when the analyzer output is intermittent. The output of this device may be used for trend recording in addition to providing a signal for a control loop. Converters to provide a current or pneumatic output will be provided if required.

Reciprocating non-control measurements will be available through the DCS/PLC, if possible. Such information will include the following: Bearing metal thermocouples Bearing drain thermocouples

PO062006001SAC/344005/062560001 (HBRP_APP10E.DOC)

10E-27

APPENDIX 10E: CONTROL ENGINEERING DESIGN CRITERIA

Generator RTDs Non-contacting vibration probes

10E3.5.11 Pressure and Temperature Switches


Field-mounted pressure and temperature switches will be provided in either NEMA Type 4 housings or housings suitable for the environment. In general, switches will be applied such that the actuation point is within the center one-third of the instrument range.

10E3.6 Instrument Air and Service Air Systems


Branch headers will be provided with a shutoff valve located at the takeoff from the main header. The branch headers will be sized for the air usage of the instruments served, but will be no smaller than 3/8 inch. Each instrument air user will have a shutoff valve and filter located at the instrument. Each service air user will have a shut-off valve. Instrument air of suitable quality will be provided for calibration of CEMS oxygen analyzers. A minimum of 10 service air connections will be provided around the Project locations will be coordinated with the Owner.

10E3.7 Field-Mounted Instruments


Where practical, field-mounted instruments will be grouped together. They will be mounted in areas accessible for maintenance and relatively free of vibration and will not block walkways or prevent maintenance of other equipment. Field-mounted instruments will be of a design suitable for the area in which they are located. Freeze protection will be provided as required. Individual instrument supports will be prefabricated, off-the-shelf, 2-inch pipe stand type. Individual field instrument sensing lines will be run in horizontal and vertical lengths that do not affect signal response. In general, local control loops will use a locally mounted indicating controller (pressure, temperature, and flow). In general, liquid level controllers will be the indicating, displacement type with external cages. Instrument racks and individual supports will be mounted to concrete floors, to platforms, or on support steel in locations not subject to excessive vibration.

10E3.7.1 Instrumentation - General Design


All instruments and equipment will be installed in a manner that ensures reasonable protection against mechanical damage, wetting, and extremes of heat or cold. Instrumentation will be handled at all times so as to protect it from damage to the internal mechanisms. Instrumentation will be stored in accordance with the manufacturers recommendations until installation. Final locations and orientations must be selected for

10E-28

PO062006001SAC/344005/062560001 (HBRP_APP10E.DOC)

APPENDIX 10E: CONTROL ENGINEERING DESIGN CRITERIA

accessibility, repair, and calibration in place, for easy access to the rear of the instruments (if needed), and for disconnection without resorting to cutting, burning, or welding. Instrument supports will not be mounted on or connected to handrails, stairways, or machinery or to any equipment subject to movement under load. All pipe-mounted temperature and pressure indicators and bridle-mounted level gauges will be mounted so as to provide direct visual readings from operating decks and accessibility for maintenance. If pipe-mounted instruments are subject to freezing, they will be appropriately freeze protected. Electronic process transmitters will be two-wire. Temperature, pressure, and differential-pressure transmitters, switches, and transducers will be mounted on either stands or racks or in local instrument cabinets as long as instruments are properly protected, including environmental protection (heat traced). Instruments that can be logically grouped will be installed on racks or in local instrument cabinets. Instrumentation, accessories, and all other equipment will be located and mounted such that calibration, maintenance, and removal work can be performed on any one piece of equipment without disturbing another. Adequate clearance will be provided so that calibration, adjustments, and connections are easily accessible without need of instrument removal. All instrument covers will be provided with adequate clearance space for removal. Equipment will be arranged such that work can be performed easily, without need for special tools. Instruments and manifold valves will be easily accessible for calibration. All pressure and differential-pressure transmitters will be installed with instrument manifolds. All differential transmitters will be installed with three-valve or five-valve manifolds. Two valve manifolds will be used for all static pressure transmitters. Orifice flanges and flow nozzles or venturis will be oriented such that taps are horizontal, neither above nor below the centerline of the pipe. Flow orifice plates will be installed only after applicable piping has been flushed or blown down. Each pressure connection, except for relief valves, will have a root valve. Double block and bleed valves are required for relief valves that would require an entire plant outage to service. Each temperature connection will have a well that will withstand the maximum system pressure and whose velocity rating to withstand vibration exceeds the maximum fluid velocity to which the well may be subjected. Thermocouple material will be compatible with the main process pipe material. All external electrical connections of junction boxes and cabinets will be made to terminal blocks. The wiring and terminal blocks for different voltage classes will be physically separated in order to minimize electrical noise and hazard to personnel. Terminal blocks will be provided with marker strips. Instruments will be mounted in a manner that prevents vibration effects. Snubbers or other suitable damping devices will be provided for pulsating services.

PO062006001SAC/344005/062560001 (HBRP_APP10E.DOC)

10E-29

APPENDIX 10E: CONTROL ENGINEERING DESIGN CRITERIA

10E3.7.2 Instrument Cabinets and Local Control Panels 10E3.7.2.1 Local Instrument Cabinet Installation
Instrument cabinets will be secured to structural steel or to concrete. Cabinets will be electrically grounded. Bolting to bare or galvanized metal will be used for attaching a ground strap. Instrument cabinets will have sufficient clearances for the required blowdown piping and headers, door swing radius, etc., and the cabinets will be completely accessible for maintenance. The cabinets will be installed and anchored in place so that they are level, plumb, and properly aligned in accordance with the above mounting requirements. Cabinets will not be supported by handrails. All instrument line penetrations into instrument cabinets will be through bulkhead fittings (couplings). Bulkhead couplings will be supplied on instrument cabinets for each instrument location. Top entry of instrument cabinets or instrument cabinet junction boxes is prohibited. Bottom entry is the preferred method for conduits.

10E3.7.2.2 Local Instrument Cabinets


Local instrument cabinets will be constructed of high-quality galvanized commercial 12 gauge sheet steel plate or stainless steel, flat and free of pitting. All cabinet sections will be continuous with no weld joints. Welding will join seams between assembled sections. Cabinet doors will have 3-point latches. The cabinets will be provided with thermostatically controlled heaters and fully insulated for freeze protection and humidity control. The cabinets will be designed to maintain an inside temperature of 30F with an ambient temperature of 0F. Each cabinet will contain an instrument air supply bulkhead. All instrument air supply lines will contain tubing valves for isolation purposes. Every air supply will contain a valved outlet for maintenance uses.

10E3.7.2.3 Cabinet Painting and Coating


All sheet steel used in the construction of the cabinets (except stainless steel) will be suitably painted.

10E3.7.2.4 Instrument and Control Wiring and Instrument Cabinet Wiring


Instrumentation and control wiring will be installed in accordance with the requirements of the Electrical section. Both ends of each wire will be identified with labels that are indelibly imprinted on heat-shrunk plastic tubing. Wire identification will consist of a from-to device identifier.

10E3.7.2.5 Painting and Coating


Where galvanized coating has been removed or degraded due to cutting, welding, scratches, etc., it will be refinished to original manufacturers specifications.

10E-30

PO062006001SAC/344005/062560001 (HBRP_APP10E.DOC)

APPENDIX 10E: CONTROL ENGINEERING DESIGN CRITERIA

The Contractor will touch up all equipment finish paint coats damaged while under the control of the Contractor. The Contractor will use paint of the original specification color and finish.

10E3.7.2.6 Marking
The Project will include stamped stainless steel tags for process root valves, each instrument, and panel or cabinet.

10E3.7.7 Instrument Tubing and Piping 10E3.7.7.1 Instrument Tubing


Tubing usage will be permitted for the following applications: Inside local instrument cabinets At a pneumatically-operated final control element Sample lines When properly protected and supported from root valve to instrument

All tubing will be ASTM 213 type 316 stainless steel (except in acid service), both seamless and annealed and properly rated for temperature and pressure applications. Copper tubing will be ASTM B-75 and will be permitted only for instrument air service inside instrument cabinets and (individual) branch applications. Tubing will be installed so that sags and low spots are avoided. All tubing cuts will be made with a roller-type tubing cutter and will be deburred. All tubing bends will be made with an approved mechanical bender to avoid flattening of the bends. All tubing fittings will be compression type, Parker Hannifin CPI or Swagelok. The use of flared-type fittings will not be accepted and is strictly prohibited. Pipe dope or Teflon tape will not be used on the tubing-side threads of compression fittings. Tubing runs requiring support will be run in Tube Track. Each instrument sensing line will terminate with a main line class blowdown valve mounted adjacent to or below the instrument cabinet. Instrument sensing lines for draft measurements and other very low-pressure and differential-pressure measurements will be 1-inch minimum O.D. Instrument sensing lines for other pressure and differential pressure measurements will be 0.5-inch minimum O.D. The length of the sensing lines will be kept as short as possible to minimize instrument sensing errors Tubing used to connect instruments to the process line will be 3/8 inch OD x 0.049 WT seamless soft annealed copper ASTM B-75 (Instrument air service) or 3/8 inch OD x 0.065 WT SS seamless ASTM A-213 or A-269 Type 316 RB 80 Hardness as necessary for the process conditions. Instrument tubing fittings will be the compression type. One manufacturer will be selected for use and be standardized as much as practical throughout the Project. Differential pressure (flow) instruments will be fitted with three-valve manifolds, while two-valve manifolds will be specified for other instruments as appropriate.

PO062006001SAC/344005/062560001 (HBRP_APP10E.DOC)

10E-31

APPENDIX 10E: CONTROL ENGINEERING DESIGN CRITERIA

Instrument installation will be designed for correct sensing of process variable. Taps on process lines will be located in such a manner that sensing lines do not trap air in liquid service or liquid in gas service. Taps on process lines will be fitted with a shutoff (root or gauge valve) close to the process line. Root and gauge valves will be main-line class type valves. Instrument tubing, including freeze protection, will be supported in both horizontal and vertical runs as necessary. Expansion loops will be provided in tubing runs subject to high temperatures. The instrument tubing support design will allow for movement of the main process line.

10E3.7.3.2 Instrument Piping


Instrument piping, when required for proper protection, will be in accordance with the main process piping design. Instrument pipe wall thickness will be based on the main process pressure and temperature design. Piping runs will be installed with continuous slopes to process connection or instrument connection as required. Instrument line pipe will be bent whenever possible.

10E3.7.3.3 Instrument Tap Installation Criteria


Each instrument tap will have a main line class root valve. Instrument pressure taps in horizontal process piping should generally be mounted on the top centerline where the process is air or gas. When the process is steam or a liquid, instrument pressure taps should generally be mounted on the side centerline of the process pipe. There will not be any instrument taps on the bottom of process lines. Instrument pressure taps will be located such that there is undisturbed flow in the area of the tap. Thus, there should not be any device or component that could cause flow disturbance for a distance of at least 10 pipe diameters upstream and downstream distances should be no less than one foot. Thermowells should generally be mounted on the top center line of horizontal process piping. Thermowells should generally be located at least 5 pipe diameters or one foot (whichever is greater) downstream of any instrument pressure tap or flow tap.

10E3.7.3.4 Piping Supports


Hangers and supports will be located such that sags and low spots in piping are avoided. The design will consider the relative motion that may exist between pieces of equipment due to thermal expansion and/or vibration. The Project will include expansion loops where required.

10E3.7.4 Air Piping, Fittings, and Pneumatic Devices


All instrument air piping will have low point drains, and all vertical risers will have collection pots and drains. Instrument air secondary branch headers for the supply of instrument air to analog control equipment will not be used to supply solenoid-valve-operated air cylinders.

10E-32

PO062006001SAC/344005/062560001 (HBRP_APP10E.DOC)

APPENDIX 10E: CONTROL ENGINEERING DESIGN CRITERIA

An air filter pressure regulator with outlet gauge will be supplied for each individual instrument air user. The air filter pressure regulators will be mounted on the instrument air piping near the end user using a flexible hose connection between the regulator and the end user. All instrument air piping and tubing will be purged of extraneous material by blowing clean, dry, oil-free air through the system before final connection. All pipe-threaded fittings will use either Loktite, pipe sealant with Teflon, or Teflon tape to seal the connection. The use of lead-base pipe dope is not acceptable.

10E3.8 Sampling and Analysis


Grab samples will be used to monitor for any deviation from control limits so that corrective action can be taken.

10E3.9 Project Siren System


The Contractor will provide a plant siren system, which will provide a sound level minimum of 5dB above ambient levels throughout the plant. Consideration will be given to which type of loudspeaker is more suitable for the environment to which it will be subjected.

10E3.10 Instrument Calibration


All field-calibrated instruments will be calibrated per manufacturers specification after installation at the site. Calibration sheets will be completed and handed over to the Owner for records and for future use. All instrumentation used in testing will be calibrated within 60 days of a test.

10E3.11 I&C Maintenance Shop Requirements


An I&C shop in the maintenance area will provide for I&C maintenance. The power feeds to the I&C Shop will not share a breaker with feeds to welding machines or to mechanical equipment in the machine shop.

PO062006001SAC/344005/062560001 (HBRP_APP10E.DOC)

10E-33

You might also like