Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Dec 08

Download as pdf or txt
Download as pdf or txt
You are on page 1of 31

PETRONAS TECHNICAL STANDARDS

DESIGN AND ENGINEERING PRACTICE

ON-LINE PROCESS STREAM ANALYSIS - ANALYSER HOUSES

PTS 32.31.50.13 DECEMBER 2008

2010 PETROLIAM NASIONAL BERHAD (PETRONAS) All rights reserved. No part of this document may be reproduced, stored in a retrieval system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the copyright owner

PTS Circular 2008


PTS No: Publication Title: Base PTS Version: 32.31.50.13 On-line Process Stream Analysis Analyser Houses <Release 13>

This revision of PTS 32.31.50.13- On-line Process Stream Analysis Analyser Houses has been updated incorporating PETRONAS Lessons Learnt, Best Practice and new information issued by relevant industry code and standards. All updates in the document are highlighted in italic font. The previous version of this PTS August 2005 will be removed from PTS binder/ e-repository from herein onwards.

Document Approval

Summary of Changes Section 1.3.2 Specific abbreviations and definitions Changes Modified the definition of Alarm Added: FAT Factory Acceptance Test MCT Multiple Cable Transit STEL Short Term Exposure Levels Lower Explosive Limit (LEL) Upper Explosive Limit (UEL) 2.4 Health, Safety and Envinronment (HSE) Considerations 4.3 Construction and Layout Requirements Added: section 3.3 with flow rate to analyzer maximum no more than 20NL/h. Ventilation requirements (see 6.2)

PREFACE

PETRONAS Technical Standards (PTS) publications reflect the views, at the time of publication,of PETRONAS OPUs/Divisions. They are based on the experience acquired during the involvement with the design, construction, operation and maintenance of processing units and facilities. Where appropriate they are based on, or reference is made to, national and international standards and codes of practice. The objective is to set the recommended standard for good technical practice to be applied by PETRONAS' OPUs in oil and gas production facilities, refineries, gas processing plants, chemical plants, marketing facilities or any other such facility, and thereby to achieve maximum technical and economic benefit from standardisation. The information set forth in these publications is provided to users for their consideration and decision to implement. This is of particular importance where PTS may not cover every requirement or diversity of condition at each locality. The system of PTS is expected to be sufficiently flexible to allow individual operating units to adapt the information set forth in PTS to their own environment and requirements. When Contractors or Manufacturers/Suppliers use PTS they shall be solely responsible for the quality of work and the attainment of the required design and engineering standards. In particular, for those requirements not specifically covered, it is expected of them to follow those design and engineering practices which will achieve the same level of integrity as reflected in the PTS. If in doubt, the Contractor or Manufacturer/Supplier shall, without detracting from his own responsibility, consult the owner. The right to use PTS rests with three categories of users: 1) 2) 3) PETRONAS and its affiliates. Other parties who are authorised to use PTS subject to appropriate contractual arrangements. Contractors/subcontractors and Manufacturers/Suppliers under a contract with users referred to under 1) and 2) which requires that tenders for projects, materials supplied or - generally work performed on behalf of the said users comply with the relevant standards.

Subject to any particular terms and conditions as may be set forth in specific agreements with users, PETRONAS disclaims any liability of whatsoever nature for any damage (including injury or death) suffered by any company or person whomsoever as a result of or in connection with the use, application or implementation of any PTS, combination of PTS or any part thereof. The benefit of this disclaimer shall inure in all respects to PETRONAS and/or any company affiliated to PETRONAS that may issue PTS or require the use of PTS. Without prejudice to any specific terms in respect of confidentiality under relevant contractual arrangements, PTS shall not, without the prior written consent of PETRONAS, be disclosed by users to any company or person whomsoever and the PTS shall be used exclusively for the purpose they have been provided to the user. They shall be returned after use, including any copies which shall only be made by users with the express prior written consent of PETRONAS. The copyright of PTS vests in PETRONAS. Users shall arrange for PTS to be held in safe custody and PETRONAS may at any time require information satisfactory to PETRONAS in order to ascertain how users implement this requirement.

TABLE OF CONTENTS 1. 1.1 1.2 1.3 1.4 2. 2.1 2.2 2.3 2.4 3. 4. 4.1 4.2 4.3 4.4 4.5 5. 5.1 5.2 5.3 5.4 5.5 6. 6.1 6.2 6.3 6.4 6.5 6.6 6.7 7. 7.1 7.2 7.3 8. 8.1 8.2 8.3 8.4 8.5 9. 9.1 9.2 9.3 9.4 9.5 INTRODUCTION ........................................................................................................1 SCOPE........................................................................................................................1 DISTRIBUTION, INTENDED USE AND REGULATORY CONSIDERATIONS .........1 DEFINITIONS .............................................................................................................1 CROSS-REFERENCES .............................................................................................2 GENERAL...................................................................................................................3 PURPOSE OF ANALYSER HOUSES ........................................................................3 BASIS OF DESIGN.....................................................................................................3 BASIC DESIGN STANDARDS ...................................................................................4 HEALTH, SAFETY AND ENVIRONMENTAL (HSE) CONSIDERATIONS ................4 LOCATION OF ANALYSER HOUSES ......................................................................5 CIVIL ENGINEERING ASPECTS OF ANALYSER HOUSES ...................................6 GENERAL ...................................................................................................................6 BUILDING STANDARDS............................................................................................6 CONSTRUCTION AND LAYOUT REQUIREMENTS.................................................6 ADDITIONAL REQUIREMENTS FOR PRE-FABRICATED ANALYSER HOUSES .....................................................................................................................8 FURNITURE ...............................................................................................................8 ELECTRICAL ENGINEERING ...................................................................................9 GENERAL ...................................................................................................................9 DISTRIBUTION SWITCHBOARDS AND TERMINAL BOXES...................................9 POWER SUPPLY CONNECTIONS ...........................................................................9 EARTHING................................................................................................................10 LIGHTING .................................................................................................................10 VENTILATION AND AIR CONDITIONING OF ANALYSER HOUSES ...................11 GENERAL .................................................................................................................11 ARTIFICIAL VENTILATION ......................................................................................11 NATURAL VENTILATION.........................................................................................12 ABSENCE OF ARTIFICIAL VENTILATION..............................................................12 AIR INTAKE SYSTEM AND DUCTING REQUIREMENTS......................................12 VENTILATION FAN REQUIREMENTS ....................................................................13 HEATING ..................................................................................................................13 ANALYSER HOUSE PROTECTION........................................................................14 GENERAL .................................................................................................................14 GAS DETECTION.....................................................................................................14 ANNUNCIATION, SAFEGUARDING AND IPF CLASSIFICATION..........................15 UTILITIES AND FACILITIES....................................................................................17 GENERAL .................................................................................................................17 AIR AND WATER .....................................................................................................17 VENT AND DRAIN SYSTEMS .................................................................................17 ADDITIONAL UTILITIES...........................................................................................17 COMPUTERS AND TELECOMMUNICATION .........................................................18 INSPECTION AND TESTING...................................................................................19 GENERAL .................................................................................................................19 BUILDING .................................................................................................................19 UTILITIES, VENT AND DRAIN SYSTEMS ..............................................................19 HEATING, VENTILATION AND AIR CONDITIONING SYSTEMS...........................19 INSPECTION CHECKLIST.......................................................................................20

10. 10.1 10.2 10.3 10.4 10.5 11. 12. 13.

MARKING FOR IDENTIFICATION AND INFORMATION.......................................21 ANALYSER HOUSE NAMEPLATE ..........................................................................21 ANALYSER HOUSE WARNING NOTICES .............................................................21 NAMEPLATES FOR VENT, DRAIN AND CONDENSATION SYSTEMS ................21 NAMEPLATES FOR STEAM SUPPLY ....................................................................21 NAMEPLATES FOR DETECTION OF LOW-FLOW VENTILATION AIR.................21 RECORDS ................................................................................................................22 MATERIALS TO BE SUPPLIED BY THE PRINCIPAL ...........................................23 REFERENCES .........................................................................................................24

32.31.50.13 December 2008 Page 1 1. 1.1 INTRODUCTION SCOPE This PTS specifies requirements and gives recommendations for the design, construction and climatic conditioning of analyser houses. The scope of this PTS is further defined in section 2.2. Excluded from the scope of this PTS is the design and construction of premises without an artifical means of maintaining a non-hazardous area, such as walk-in shelters for analyser systems. The design of such premises and their analyser systems shall comply with PTS 80.00.10.10. This PTS is a revision of the PTS with the same number dated December 1998. 1.2 DISTRIBUTION, INTENDED USE AND REGULATORY CONSIDERATIONS Unless otherwise authorised by Shell GSI and SIEP, the distribution of this PTS is confined to companies forming part of the Royal Dutch/Shell Group or managed by a Group company and, if necessary, to Contractors and Manufacturers/Suppliers nominated by them. This PTS is intended for use in oil refineries, chemical plants, gas plants, exploration and production facilities and, where applicable, supply and distribution installations. When PTSs are applied, a Management of Change (MOC) process should be implemented; this is of particular importance when exisiting facilities are to be modified. If national and/or local regulations exist in which some of the requirements may be more stringent than in this PTS the Contractor shall determine by careful scrutiny which of the requirements are the more stringent and which combination of requirements will be acceptable as regards safety, environmental, economic and legal aspects. In all cases, the Contractor shall inform the Principal of any deviation from the requirements of this PTS which is considered to be necessary in order to comply with national and/or local regulations. Based on the potential impact on design, construction and maintenance costs, the Principal may decide to consult with the Authorities concerned with the object of obtaining agreement to follow this PTS as closely as possible. 1.3 1.3.1 DEFINITIONS General definitions The Contractor is the party which carries out all or part of the design, engineering, procurement, installation, and commissioning or management of a project or operation of a facility. The Principal may sometimes undertake all or part of the duties of the Contractor. The Manufacturer/Supplier is the party which manufactures or supplies equipment and services to perform the duties specified by the Contractor. The Principal is the party which initiates the project and ultimately pays for its design and construction. The Principal will generally specify the technical requirements. The Principal may also include an agent or consultant, authorised to act for the Principal. The word shall indicates a requirement. The word should indicates a recommendation.

32.31.50.13 December 2008 Page 2 1.3.2 Specific abbreviations and definitions alarm an audible and/or visible means of indication to panel operator an equipment malfunction, process deviation, or abnormal condition requiring a response building with a specific closed room containing more than one analyser which may be connected to a process installation, together with associated electrical equipment and auxiliary devices
NOTE: NOTE: Laboratories are not included in this definition.

analyser house

artificial ventilation

method of mechanical movement of air to reduce the potential concentration of flammable gases or vapours in the analyser house; such ventilation may also be used to maintain the pressure inside the analyser house above the external ambient pressure Central Control Room Field Auxiliary Room Factory Acceptance Test function comprising the Initiator function, logic solver function and final element function for the purpose of preventing or mitigating hazardous situations volume ratio of flammable gas or vapour in air below which an explosive gas mixture will not be formed Multiple Cable Transit Process Gas Chromatograph operation of passing a quantity of air or inert gas through a room and its associated ducts in order to reduce to a safe level, any concentration of flammable gas or vapour which may be present Short Term Exposure Levels The volume ratio of flammable gas or vapour in air above which an explosive gas mixture will not be formed situation where the required air flow and, if applicable, the required pressure cannot be maintained inside the analyser house complete installation required to produce artificial ventilation

CCR FAR FAT Instrumented Protective Function (IPF) Lower Flammable Limit (LFL)/ Lower Explosive Limit (LEL) MCT PGC Purging

STEL Upper Flammable Limit (UFL)/ Upper Explosive Limit (UEL) ventilation failure

ventilation system

1.4

CROSS-REFERENCES Where cross-references to other parts of this PTS are made, the referenced section is shown in brackets. Other documents referenced by this PTS are listed in (13).

32.31.50.13 December 2008 Page 3 2. 2.1 GENERAL PURPOSE OF ANALYSER HOUSES The main purpose of an analyser house is to ensure continuity of operation of analyser systems with high reliability by providing an improved operating environment for them and protecting them from the weather. The operating environment of analysers is affected by the: area classification; environmental conditions, mainly temperature, dust, saliferous ambient air and humidity; sample handling, conditioning and recovery; effective maintenance.

As analyser houses are complex and therefore expensive to construct and maintain, they contribute significantly to the Total Cost Of Ownership. They shall therefore only be erected when strictly required and their size shall be optimised in accordance with this PTS. The suitability of cheaper alternatives, e.g. a walk-in shelter, shall be checked. The selection of eithera walk-in shelter, a site-erected analyser house or a pre-fabricated analyser house (with all analyser systems installed) shall be evaluated in terms of Total Cost of Ownership. 2.2 BASIS OF DESIGN This PTS specifies the design and construction of analyser houses with respect to: maintaining a non-hazardous area; providing protection in the event that the means to maintain the non-hazardous area fail; procedures for maintaining the installed electrical safety protection measures; maximum and minimum limits for climatic conditioning, if required; verification and testing of installed instrumented protective systems.
NOTE: Hazardous situations created by external toxic gas atmospheres shall be dealt with separately in each individual case.

Requirements and recommendations are given for the design, construction and operation of systems for artificial ventilation of analyser houses, their associated equipment such as air ducts, and the auxiliary devices necessary for providing and maintaining the required pressure above ambient.
NOTE: For the purposes of this PTS, analyser houses are assumed to have forced artificial ventilation systems. Induced ventilation systems shall not be used.

Hazardous situations arising from the toxicity of gases and vapours that have to be handled shall be the subject of a special study, on the basis of which the appropriate measures shall be decided on and submitted to the Principal for approval. Hazardous situations arising from products in the process environment around the analyser house shall be addressed in the plant hazard study during the preliminary and final design study (see 2.4).

32.31.50.13 December 2008 Page 4 2.3 BASIC DESIGN STANDARDS The following standards shall apply in conjunction with this PTS: IP 15 for ventilation requirements of analyser houses and adjacent sample conditioning areas; IEC/TR 60079-16 for the procedures to achieve a safe area inside the analyser house that satisfies IP 15; IEC 61285 for maintaining the integrity of the analyser house and its surrounding. 2.4 HEALTH, SAFETY AND ENVIRONMENTAL (HSE) CONSIDERATIONS The following HSE measures shall be taken to ensure that the interior of the analyser house can be classified as non-hazardous under normal operating conditions: The quantity of flammable materials entering the interior of the analyser house shall be kept to a minimum. This shall be achieved by applying PTS 32.31.50.11 section 3.3 with flow rate to analyzer maximum no more than 20NL/h. An efficient air ventilation system shall be provided to continuously dilute accidental internal releases of flammable gases or vapours, if any, to below the levels recommended in IEC/TR 60079-16.
NOTE: To ensure that electrical equipment does not create a hazardous condition if the ventilation system fails, additional precautions shall be taken (see 5.1, 6.7 and 8.1).

Provision of systems for safe disposal of waste material. For example, if the vent gas from analyser houses is continuously contaminated with hydrocarbons, then an environmentally acceptable and safe means of disposal of this vent gas shall be provided (8.3). Provision of fire protection features as described in PTS 34.17.00.32.

32.31.50.13 December 2008 Page 5 3. LOCATION OF ANALYSER HOUSES Analyser houses shall be located in a non-hazardous area or a Zone 2 area. Analyser houses shall not be located in a Zone 0 area or a Zone 1 area. In addition to the requirements of IEC 61285, the location: shall be at least 15 m away from furnaces; shall be such that the vibration level does not exceed that specified for the equipment accommodated inside the analyser house; shall be free from spills of water and process liquids.
NOTE: Locations under pipe bridges or other structures shall be avoided.

32.31.50.13 December 2008 Page 6 4. 4.1 CIVIL ENGINEERING ASPECTS OF ANALYSER HOUSES GENERAL An analyser house typically comprises: the analyser room, which shall have forced ventilation to make it by design a normally non-hazardous area, and sample handling area(s) on the outside of the longest wall(s), back-to-back with the analyser(s) inside. These areas shall be designed so that the area classification shall not become more hazardous than Zone 2 (4.3).

4.2

BUILDING STANDARDS The construction of analyser houses shall be in accordance with PTS 34.17.00.32. and one of the following: in accordance with Standard Drawing S 17.001, for tropical and mild climates; or in accordance with Standard Drawing S 17.002, for temperate and cold climates; or fully enclosed construction if specified by the Principal.
In case of doubt regarding the classification of the local climate, the Principal shall be consulted.

NOTE:

In addition to the above, the following aspects shall be taken into acount in the building design: 4.3 discharging vapours to the vents (8.3); connection of drains to a dedicated collection sump or vessel located near the analyser house (8.3); potable water supply whose piping and fittings shall be designed to prevent back-siphon effect (8.1); material for sink (4.3); a fire call button shall be fitted outside the main entrance door; gas alarm beacon and horn (Table 1); alarm annunciator panel at door(s) (Table 1); sample gas recovery system (8.3).

CONSTRUCTION AND LAYOUT REQUIREMENTS This PTS deviates from IEC 61285 on the following subjects: spare space (as specified below);

In addition to IEC 61285 and IEC/TR 60079-16, the following aspects shall be considered. Openings in the analyser house shall be provided for electrical power and instrument signal cables to enter and leave the building. These shall be in the corners of walls at floor or ceiling level via Multiple Cable Transit (MCT) blocks and with the armouring earthed at these points. ventilation air inlet duct(s) (6.5); ventilation air outlet ducts (6.5); sample and utilities inlet and outlet lines; and any other services specified by the Principal.

The minimum walk space between fixed obstacles shall be 850 mm, taking into account the constraint that cabinet doors may be locked in the open position on one side at a time.

32.31.50.13 December 2008 Page 7 The internal length shall suit the number of analysers to be installed plus a further 10 % or spare space for one analyser. There shall be sufficient clearance between cabinets and equipment to allow maintenance access. Door dimensions shall allow free access for analysers and analyser racks and shall be 0.90 m wide and 2.10 m high. Doors shall be blast resilient, fitted with door closers and laminated safety glass window. The emergency door shall be clearly labelled on both sides and fitted with a panic bar. Rooms shall have exits at both ends if flammable or toxic materials are stored or handled therein. For small analyser houses, the Principal is to be consulted. Space (the "sample handling area") shall be reserved on one or both outside walls of the analyser house for the installation of sample conditioning systems and a sample gas recovery system and should allow the analysers and sample conditioning systems to be installed back-to-back. The length and height of this sample handling area shall be the same as that of the analyser house. The unobstructed walk space shall be 750 mm minimum. The degree of weather protection of the sample handling area depends on local conditions and the required indoor climate but shall include at least a full canopy. Sample handling areas shall be: of fully open construction, for use in tropical and mild climates (see S 17.001); or of partly enclosed construction, to provide protection for sample handling components against cold weather conditions and snow (see S 17.002). A 50 % open wall space will provide adequate (natural) ventilation; or of fully enclosed construction if specified by the Principal.

Sufficient space shall be provided inside the analyser house for the installation of a sink, work bench and auxiliary equipment such as control units and, if required, recorders, signal converters, printers, computer terminals, etc. The material of the sink shall be suitable for the samples to be handled. In view of the possibility of accumulation of hydrocarbon spills, drain pits are not allowed inside the analyser house but shall be located outdoors instead. Door sills shall be flush with the floor to prevent tripping hazards, and to allow any hydrocarbon spills to be flushed to the drain pit outside. The roof shall be "nominally flat" with a slope of at least 1:100. No equipment (e.g. an HVAC unit) should be installed on the roof; if it is, the analyser house shall be provided with a permanent ladder on the outside, a galvanised steel catwalk for access to the roof and a roof railing for personnel safety. Structures on the outside of the analyser house shall be steel, unless other flame retardant materials are approved by the Principal.

32.31.50.13 December 2008 Page 8 4.4 ADDITIONAL REQUIREMENTS FOR PRE-FABRICATED ANALYSER HOUSES Concrete shall be used as the material for pre-fabricated analyser houses, except that alternative construction materials, such as stainless steel, galvanised steel or glass-reinforced epoxy (GRE), may be used if approved by the Principal. Design and finish shall be based on a 20-year lifetime. Finish and packaging shall be able to withstand open deck sea freight transport if applicable. Lifting lugs shall be provided for handling, shipping and installation. The design shall be such that the completed analyser house is capable of withstanding the loads imposed by lifting, shipping and other loads described below. Building design calculations shall meet PTS 34.00.01.30. and PTS 34.17.00.32. The Supplier shall supply drawings showing the required layout of foundation beams and location of bolting to foundation and shall submit structural and/or civil design calculations as specified in the order. Calculations shall be in SI units and in the English language. 4.5 FURNITURE Analyser houses shall be equipped at least with a work bench.

32.31.50.13 December 2008 Page 9 5. 5.1 ELECTRICAL ENGINEERING GENERAL The design and construction of the electrical installation and the selection of the electrical equipment shall be in accordance with the requirements of PTS 33.64.10.10., including requirements for lightning protection. Electrical facilities inside the building shall have a type of protection suitable for a Zone 1 hazardous area unless an alternative is specified by the Principal. All electrical facilities inside the building that are not suitably protected for a Zone 1 hazardous area shall be connected via IEC 60309 compliant industrial socket outlets which shall be automatically isolated by an alarm and trip initiation system if a ventilation failure occurs (see 7.1).
NOTE: For adequate types of protection for use in gas hazardous areas refer to IEC 60079-14.

5.2

DISTRIBUTION SWITCHBOARDS AND TERMINAL BOXES The electrical equipment in the analyser house shall be fed from the nearest electrical substation or switch room via a distribution board preferably inside the analyser house. If located outside the analyser house, it shall be either freely supported with a weather cover or installed against that part of the wall that is protected from the weather. Segregated compartments shall be provided for:non emergency power distribution panel for electrical apparatus and heating and cooling equipment; emergency power distribution panel for analysers, heat tracing, telecommunications, ventilation fan(s), lights and gas detectors (if any).

To limit the number of electrical feeders into the analyser house, all equipment should be powered from the emergency power distribution board. Junction boxes shall be provided for: signal wiring termination; and alarm signal wiring termination.

At least 10 % spare capacity shall be provided in junction and terminal boxes. All wires shall be identified at each termination with suitable wire markers that correspond to the appropriate wiring diagram. 5.3 POWER SUPPLY CONNECTIONS Electrical apparatus suitable for operation in the hazardous area shall be connected via isolation switches unless hazardous area socket outlets are specified by the Principal. Test equipment, electrical tools and electrical equipment without adequate protection for the hazardous area shall be connected to the electricity supply via general-purpose industrial type socket outlets only. The supply to these outlets shall be controlled by the instrumented protective system of the analyser house (7.3).

32.31.50.13 December 2008 Page 10 5.4 EARTHING An earth-loop of 70 mm2 earthing conductors shall be installed inside the analyser house and shall be connected to the plant earth ring.
NOTES: 1. Signal cable shields shall be earthed at a single point to the instrument earth in the Control Room. 2. Cable armouring shall either be earthed via the MCT blocks or bonded when entering the house. 3. The integrity of intrinsically safe electrical apparatus shall be retained.

Metal parts of the building shall form one continuous electrical earthing arrangement, and shall be bonded to the 70 mm2 earth-loop. The earth-bar of the switchboard, unless it is installed elsewhere (e.g. in the nearest substation/FAR/CCR), shall be bonded to the 70 mm2 earth-loop and the earth bar of the supply substation. 5.5 LIGHTING The luminaires used inside and outside the analyser house shall be fluorescent and of the same design as those used in the plant. Inside lighting shall be suitable for a Zone 1 hazardous area. Permanent lighting shall be controlled by switches installed at each entrance door. Emergency lighting shall be provided by self-contained lighting fixtures or by the plant emergency lighting system. The lighting fixtures shall be located inside the building above each door entrance. The illumination level inside the building shall be at least 400 lx in accordance with PTS 33.64.10.10., and shall be provided by at least two lighting fixtures. A single light shall be installed above each door entrance and at least two lighting fixtures shall be installed in each sample handling area. Exterior lighting shall be controlled from the nearest sub-station lighting panel or, if this is not possible, by a photocell, but with a delay timer with an adjustable period of no longer than 30 min.

32.31.50.13 December 2008 Page 11 6. 6.1 VENTILATION AND AIR CONDITIONING OF ANALYSER HOUSES GENERAL The purpose of ventilation and air conditioning is to provide: a safe operating environment for equipment and personnel; the required climatic conditions for optimal equipment performance.

Artificial ventilation of the interior of an analyser house is required to achieve either: dilution ventilation: the dilution of flammable gases and/or vapours that may accidentally escape from equipment inside the analyser house to a non-hazardous level around any potential means of ignition; or overpressure ventilation: to prevent flammable and toxic gases from the outside atmosphere entering the internal of the analyser house; or both dilution ventilation and overpressure ventilation, for analyser houses located in an area where hydrocarbons are processed.

Dilution ventilation and overpressure ventilation shall comply with PTS 80.00.10.10. The ventilation and air conditioning system shall comply with PTS 31.76.10.10. Construction shall be in accordance with IEC/TR 60079-16 and this PTS. Despite the absence of primary grade sources of release inside well-designed analyser houses, the ventilation shall not be downgraded to a lower standard that would fail to create the right conditions for a non-hazardous area inside the analyser house. 6.2 6.2.1 ARTIFICIAL VENTILATION Dilution ventilation Dilution ventilation is only practical if the maximum possible rate of release is positively restricted. Therefore, the total amount of flammable fluids flowing to any analyser accommodated inside the analyser house shall be limited by a properly adjusted excess flow valve in accordance with PTS 32.31.50.11. A limited flow of 100 L/h (at standard conditions) covers the need of most gas analyser applications. The ventilation rate shall be at least the greater of the following fresh air changes: 20 m3 per hour per analyser (including those already installed and those projected for future spares); five volume changes per hour.

As far as practicable, the flow through the analyser house shall be uniform and shall not leave any stagnant pocket of air where flammable mixtures may develop. An internal ventilation fan may provide an economical method to obtain efficient dispersion. The adequacy of the dilution ventilation shall be checked against the maximum possible rate of release, taking into account the nature and hazard of the flammable material. For a liquid sample, the vapour load produced by the maximum possible rate of release shall be taken as the basis of this check.

32.31.50.13 December 2008 Page 12


Note: In this way the total release of all possible sources can be contained and diluted to a level even lower than that specified in IP 15 when the flammable material is propane at ambient conditions. In the rare event that the above specified ventilation rates are insufficient, appropriate measures shall be taken (e.g. redesign) to regain a nonhazardous classification of the analyser house.

6.2.2

Overpressure ventilation The pressure differential of the analyser house with respect to ambient shall be controlled to 50 Pa under normal design conditions and shall be at least 25 Pa under minimum flow conditions (e.g. due to filter fouling). A local indicator and an alarm shall be provided.

6.3

NATURAL VENTILATION Other premises that rely on natural ventilation, such as walk-in shelters and enclosed cabinets, shall be subject to area classification in accordance with IP 15. Sample handling areas adjacent to the analyser house fall into this category and shall be designed so that they are not more severe than Zone 2.

6.4

ABSENCE OF ARTIFICIAL VENTILATION Enclosed analyser houses requiring no artificial ventilation shall comply with the requirements for non-hazardous areas.

6.5

AIR INTAKE SYSTEM AND DUCTING REQUIREMENTS The air intake shall be through a stack provided with a rain hood and wire mesh bird screen. The air shall be drawn from a non-hazardous area and the air intake shall be located at least 1 metre outside a hazardous area. The diameter of the stack and intake duct shall be sized to limit the air velocity inside the stack and ducting to a maximum of 8 m/s. Inlet ducts shall be airtight and shall not pass through Zone 0 or Zone 1 areas. Inlet ducts shall have connections for flow meters and flammable gas detectors with a test gas connection. A filter shall be installed in the inlet air ventilation system so that it is easily accessible for cleaning or replacement. The size of the filter shall be sufficient to require cleaning or replacement not more than once per fortnight (or once per week in very dusty, e.g. desert, environments) under the maximum dust conditions expected. In cold climates measures shall be taken to prevent the filter from freezing up, e.g. by means of a slipstream from behind the ducting-mounted heater. Air shall enter the analyser house at ceiling level from ducting via openings with adjustable flow diverters to facilitate a proper direction and flow of air throughout the analyser building. The ducting material shall be corrosion resistant, e.g. hot-dip galvanized steel. The ventilation air shall escape from the analyser house through vertical ducts at two opposite corners of the analyser house, via exits with adjustable openings. The inlet and exit port areas of the flow diverters and exits shall be adjustable to enable the flow direction and overpressure to be trimmed during commissioning and later during normal operation.

32.31.50.13 December 2008 Page 13 Openings in the air outlet ducting shall be flush with the floor and ceiling to allow escape of gases and vapours both heavier and lighter than air. The size of the ducting shall be such that air velocities inside will not create noise levels that exceed the acceptable limits specified in PTS 31.10.00.31. Outlet stack openings shall be higher than any equipment (e.g. HVAC equipment) installed on the roof of the analyser house. Outlet stack openings to atmosphere shall be fitted with rain hoods and wire mesh bird screens. To prevent any adverse effects of outside wind direction and velocity on the ventilation and overpressure inside the analyser house, Nelson hoods or devices with similar features shall be installed on the openings of outlet stacks/ducts. 6.6 VENTILATION FAN REQUIREMENTS Ventilation should be by means of dual centrifugal or axial fans with blades of non-sparking material and each driven by a 100% capacity directly coupled motor. The ventilation equipment shall be mounted inside the analyser house or outside (if suitably protected). The fans shall be located outside the sample handling area. Motors positioned inside ducting or elsewhere inside an analyser house shall have a type of protection suitable for operation in a Zone 1 hazardous area. The protection of motors installed outside the house shall be in accordance with the classification of the outside area. The power supply to the fan motor shall be independent of all analyser house safety trip circuits. Control circuits shall be provided for the alternate running of the fans to equalize operational hours. The fan speed shall not exceed 2500 r/min. The fan support and casing construction shall be sufficiently rigid to prevent resonance and vibration (the bearing support shall be part of the fan casing). 6.7 HEATING If duct heating is installed inside the ducting of an overpressure ventilation system, it shall be de-energised in the event of ventilation failure if the heater is not suitably certified to continue operation in Zone 1. In all other cases the duct heating shall be de-energised upon ventilation failure if there is a risk of damage due to overheating.

32.31.50.13 December 2008 Page 14 7. 7.1 ANALYSER HOUSE PROTECTION GENERAL The ventilated analyser house and personnel inside shall be protected against hazardous situations. In the event of ventilation failure or loss of overpressure inside the house, the system shall initiate the appropriate alarm and isolate the electricity supply to general-purpose type convenience outlets. The safeguarding systems of ventilated analyser houses shall comply with IEC/TR 60079-16. Instrumented protective functions shall be classified and implemented in accordance with PTS 32.80.10.10. For typical IPF classes relating to analyser houses, refer to (7.3). 7.2 GAS DETECTION The selection, location and mounting of gas detectors shall be done in accordance with PTS 32.30.20.11. 7.2.1 Air intake The presence of flammable gas at the point of fresh air intake of the ventilation system shall be monitored in accordance with the overpressure ventilation requirements of IP 15. The gas detector(s) shall either monitor the air flowing through inlet ducting or the atmosphere in the direct vicinity of the fresh air intake point. If mounted in or adjacent to the inlet air ducting, they shall be fitted so that the prevailing flow profiles and air speed inside the ducting do not adversely affect either representative sampling or the accuracy of analysis. The detector(s) shall be easily accessible for maintenance purposes and a test gas connection shall be provided If it is considered credible for toxic gas to enter the analyser house, a toxic gas detector shall be installed, mounted in the same way as the flammable gas detectors. If it is considered credible for inert gas to enter the analyser house, an oxygen deficiency detector shall be installed, mounted in the same way as the flammable gas detectors. 7.2.2 Inside the analyser house The design specifications of the ventilation air system in this PTS and good installation and maintenance procedures normally make it unnecessary to detect accidental releases of flammable and toxic vapours inside the analyser house. Gas detection is therefore only required if, under abnormal conditions (which are not covered by IP 15), the release of significant amounts of gas is credible. If flammable gas detectors are required, they shall be located in the direct vicinity of the controlled outlet openings of the ventilation system inside the analyser house. If toxic gas detectors are required, they shall be located at positions where leakage into the analyser house is most likely to occur in case of failure or mis-operation. 7.2.3 Flammable gas detection Infra-red types of gas detectors should be used in preference to catalytic types, unless the flammable gas species are not detectable by infra-red types. The detection of hydrogen/air mixtures in analyser houses where hydrogen is used for the operation of Process Gas Chromatographs (PGC) is not normally required.

32.31.50.13 December 2008 Page 15

7.2.4

Toxic gas detection Site maintenance instructions for analysers and sample handling systems containing toxic vapours or liquids shall prescribe adequate precautions for normal working and for preventing accidental releases of vapours and liquids. Toxic gas detection is then not required if Short Term Exposure Levels (STEL) are not exceeded for a period of more than 10 hours per year, unless otherwise advised by the responsible HSE function.
NOTE: If continuous toxic gas detection is still considered necessary, it should be taken into account that if the toxic gas concentration in flammable vapours is less than 1 % molar composition, a flammable gas detector set at an alarm level of 10 % LFL/LEL would normally be sufficiently sensitive to give an early warning for the toxic gas constituent and the flammable gas.

If the presence of toxic gas is considered credible, a rubber pass-through grommet shall be installed, e.g. in one of the entrance doors, to allow probing of the atmosphere with a portable gas detector. Nitrogen hazard If a large amount of nitrogen could be present inside the analyser house O2 detectors shall be installed to monitor and alarm on low oxygen in air level. 7.3 ANNUNCIATION, SAFEGUARDING AND IPF CLASSIFICATION Table 1 is a typical IPF classification matrix for a ventilated analyser house with overpressure and dilution ventilation, i.e. flammable gas detection in the fresh air intake, ventilation flow and door entrance. Also included are toxic gas detection in the fresh air intake and flammable and toxic gas detection inside the analyser house. Their IPF classification and other additional safeguards that may be deemed necessary shall be classified on a case-by-case basis.

32.31.50.13 December 2008 Page 16 Table 1 IPF classification matrix for an analyser house
CCR CAUSE
SIL class panel alarm

inside / outside AH
flashing / rotating beacon normal operating (off)

LOCAL ANNUNCIATION PANEL ANALYSER HOUSE (at each entrance)


convenience outlets isolated ventilation failure door alarm flammable gas toxic gas

EXECUTIVE ACTION
isolate convenience outlets stop ventilation and / or HVAC

Evacuation command from CCR Trip from CCR Ventilation failure Doors open Flammable gas air intake Flammable gas inside Toxic gas/N2 air intake Toxic gas/N2 inside

2 2 1 2 (if D) 1 # # #

A A B B A A A A

A A C C C C A A

A A B B A A A A

A* C* D* C* C* -

B C* A* -

B -

A A -

A A

A C D C C -

C A -

CODES:
A B C D * #
NOTES:

= = = = = =
1. 2. 3. 4. 5.

immediate action/annunciation upon activation of initiator action/annunciation delayed 60 s following activation of initiator action/annunciation delayed for one fresh air change upon activation of initiator, i. e. 12 min for five air volume changes per hour same as for C, but only if door is located in hazardous area (ref. IEC/TR 60079-16) codes marked with * follow executive action or status IPF class shall be assigned on a case-by-case basis
A local annunciation panel shall be installed at each entrance door. The analyser house protection system shall be designed so that power to all non-protected functions, e.g. general purpose type convenience outlets, can be switched on only after the ventilation system has been operating for at least 5 fresh air changes, i.e. 60 minutes in the case of 5 changes per hour. An audible alarm for fire or gas shall be heard inside the analyser house. It shall not be installed inside the house. The above matrix is a minimum requirement. Pitch of the audible alarms and duration, colours of flashing/rotating beacons and other details shall be as specified by the Principal. The SIL classes shown in the matrix are typical. Each individual case shall be checked against specific project requirements.

32.31.50.13 December 2008 Page 17 8. 8.1 UTILITIES AND FACILITIES GENERAL Gas and liquid utilities connected to the analyser house shall always terminate in a system consisting of at least an isolating valve, a filter or strainer, a pressure controller and inlet and outlet pressure indicators. All utility lines shall be connected so that the product they contain cannot be contaminated by process liquids, gases or vapours.
NOTE: Sometimes potable water or refinery cooling water is used for cooling of process products. It is therefore essential that water supplies are protected against contamination from these products due to a cooling coil failure.

8.2

AIR AND WATER Instrument air supply shall be in accordance with PTS 31.37.00.11. Water supply shall be in accordance with PTS 34.17.00.32. and shall enter the house at a different position to the electricity supply. A siphon breaker or breaker vessel shall be installed immediately downstream of the main shut-off valve of water supplies (e.g. potable, cooling).

8.3

VENT AND DRAIN SYSTEMS Vent and drain systems for analyser houses shall be in accordance with PTS 32.31.50.11. If required, the vent gas recovery system shall be installed outside the analyser house. Regular liquid samples shall be returned into the process stream only. If this requirement cannot be met, the Principal shall be consulted. Hydrocarbon liquids that cannot be returned to the process, e.g. those resulting from maintenance activities or from incidents (drips), shall be discharged into either the plant hydrocarbon recovery system or a dedicated collection sump or vessel. Water effluent (possibly oil contaminated) shall be discharged into a dedicated collection sump or vessel in accordance with PTS 34.17.00.32. In order not to poison the biological mass of waste water treatment systems, chemically contaminated water shall be collected in a dedicated sump or vessel.

8.4

ADDITIONAL UTILITIES The following additional utilities shall also be provided as appropriate, if required by the type of analysers to be installed in the analyser house: tool air; nitrogen; hydrogen gas (as a carrier gas for PGC); Low Pressure steam; Medium Pressure steam (15 bar); condensate supply and return lines; cooling water;

32.31.50.13 December 2008 Page 18 refrigerated water supply and return; drain (liquid sample recovery) system (e.g. effluents that may not be returned to the sites oil contaminated drain system).
1. 2. All flammable utility lines shall have main shut-off valves. They shall be grouped together in the vicinity of, but at least 2 metres away from, the analyser house. They shall be clearly identified, e.g. by means of a red label. All non-flammable utilities shall have a main shut-off valve which may be installed on the outside wall of the analyser house.

NOTES:

Headers for liquids (water etc.) and flammable gas utilities shall be installed on the outside wall of the analyser room and branched off via holes in the walls to the analysers requiring that utility supply. The uncontrolled release of liquids or flammable utility gases in the event of a line rupture inside the analyser room shall be prevented by an excess flow check valve in the branch connection before it enters the room. The flow of flammable gas per analyser shall not exceed 100 L/h or twice the amount required for the analyser, whichever is greater. 8.5 COMPUTERS AND TELECOMMUNICATION The means for direct voice communication with the control room shall form part of the design and shall comply with Zone 1 requirements. The analyser room and the layout thereof shall be designed to allow the use of personal computers and other, usually general-purpose type, microprocessor based equipment that is required for the control and maintenance of analyser systems. Connection to the plantwide Local Area Network shall be provided.

32.31.50.13 December 2008 Page 19 9. 9.1 INSPECTION AND TESTING GENERAL Inspection and testing shall comply with PTS 62.10.08.11. Pre-fabricated analyser houses, complete with analysers systems and sub-systems installed, shall be subject to Factory Acceptance Testing (FAT). 9.2 BUILDING The building shall be inspected to verify compliance with PTS 34.17.00.32. 9.3 UTILITIES, VENT AND DRAIN SYSTEMS The utility piping and the drain and vent piping shall be inspected to verify compliance with PTS 31.38.01.11. 9.4 HEATING, VENTILATION AND AIR CONDITIONING SYSTEMS The general inspection and testing of HVAC systems shall be in accordance with PTS 31.76.10.11 and PTS 62.10.08.11 (for supporting instrumentation). Tests shall be conducted on site with portable gas detectors to confirm that no flammable or toxic gases are released or are entrained with the ventilation air.

32.31.50.13 December 2008 Page 20 9.5 INSPECTION CHECKLIST All inspections and tests shall be performed against the applicable specifications and drawings. The inspection shall include at least the following items: area classification of the location; documentation and drawings; selection of materials, tagging and nameplates shall be inspected during all phases of inspection; dimensions; compliance with design of installation (entrance, exits facing in right direction, etc.); architecture (location of HVAC unit, analyser room, sample handling area(s), gas and liquid recovery systems, etc.); framework construction; insulation of walls, roof and doors; wall construction; wall penetrations and sealing for ducts and piping; roof construction; floors; doors and locks; air intake stacks and ducts; exhaust ducts, exits, vents and drains; air and water supplies; other utilities, including the gas and liquid recovery system, steam supply, nitrogen supply etc.; electrical system (capacity, switch boards, power distribution boards, signal termination boxes, alarm signal termination boxes, convenience outlets, wiring termination etc.); earthing; lighting; HVAC unit and/or ventilation system; ventilation fans; alarm and trip initiation systems; gas detectors, if installed; alarm beacons; cable trenches / cable entries, conduits; any other details forming part of the project; functional inspection of ventilation flow pattern on site, e.g. by means of smoke dispersion test.

32.31.50.13 December 2008 Page 21 10. 10.1 MARKING FOR IDENTIFICATION AND INFORMATION ANALYSER HOUSE NAMEPLATE Nameplates shall be in accordance with the requirements of PTS 32.31.00.32., but as amended below. Nameplates shall be screwed or nailed to their supports, not glued. Similar to the following example, a nameplate showing the analyser house number shall be attached to the outside of both doors: ANALYSER HOUSE NUMBER - AH 12 The letters in the above notice shall be at least 20 mm high. 10.2 ANALYSER HOUSE WARNING NOTICES The following notices shall also be displayed at both doors; the second notice shall display only the appropriate statements selected from those shown in the example below: ANALYSER HOUSE PROTECTED BY FORCED VENTILATION WARNING Doors must be kept closed CAUTION: Risk of H2S CAUTION: Flammable material may only be introduced into the analyser house if specifically permitted and recorded. CAUTION: Do not enter the building when status lights indicate the possible presence of flammable or toxic vapour inside, unless the prescribed precautions are taken. The capital letters in the above notice shall be at least 20 mm high, with the lower case letters to scale.

10.3

NAMEPLATES FOR VENT, DRAIN AND CONDENSATION SYSTEMS Drain, vent and, if applicable, condensate systems shall be clearly identified with nameplates and by colour coding.

10.4

NAMEPLATES FOR STEAM SUPPLY Nameplates shall indicate the nominal pressure and temperature of the steam.

10.5

NAMEPLATES FOR DETECTION OF LOW-FLOW VENTILATION AIR The flow detection device on the main inlet ducting shall be clearly marked and its housing should be painted bright red.

32.31.50.13 December 2008 Page 22 11. RECORDS All relevant details of the analyser house and equipment, including the HVAC system if applicable, shall be suitably recorded. The records shall contain at least: the Local Authoritys certificate, if applicable; a list of analysers installed inside the building, and their type of protection; a copy of the electrical safety certificates; specific records of each analyser, including testing procedures; draining procedure for devices, vents and drains; Manufacturer's recommended maintenance and test procedures for the HVAC system, if applicable; a list of test equipment kept inside the analyser house; layout of equipment, piping, cables and drains; a copy of ventilation system acceptance tests; a copy of the Principal's instructions for testing and test frequency; a copy of the latest tests and inspection results; a detailed start-up and commissioning schedule for HVAC equipment (if applicable) in accordance with PTS 31.76.10.10.

32.31.50.13 December 2008 Page 23 12. MATERIALS TO BE SUPPLIED BY THE PRINCIPAL Accessories for personnel safety shall be supplied by the Principal if required by site regulations. For example: an eye wash unit, to be located outside the analyser house, near the sample handling area; fire blankets; fire extinguishers.

32.31.50.13 December 2008 Page 24 13. REFERENCES In this PTS, reference is made to the following publications:
NOTES: 1. Unless specifically designated by date, the latest edition of each publication shall be used, together with any amendments/supplements/revisions thereto. 2. The PTSs and most referenced external standards are available to Shell users on the SWW (Shell Wide Web) at http://sww05.europe.shell.com/standards.

SHELL STANDARDS Noise control (amendments/supplements to ISO 15664) Instrument air supply Piping - general requirements Heating, ventilation and air conditioning for plant buildings Installation, testing and balancing, and commissioning of HVAC systems Fire, gas and smoke detection systems Instruments for measurement and control On-line process stream analysis - sample conditioning Classification and implementation of instrumented protective functions Electrical engineering guidelines Minimum requirements for structural design and engineering Design and engineering buildings Inspection and functional testing of instruments Area classification (Amendments/supplements to IP 15) STANDARD DRAWINGS: Typical analyser house for tropical areas Typical analyser house for non-tropical areas BRITISH STANDARDS The Institute of Petroleum Model Code of Safe Practice, Part 15, Area classification code for petroleum installations
Issued by: The Institute of Petroleum, 61 New Cavendish Street, London W1M 8AR, United Kingdom

PTS 31.10.00.31. PTS 31.37.00.11. PTS 31.38.01.11. PTS 31.76.10.10. PTS 31.76.10.11. PTS 32.30.20.11. PTS 32.31.00.32. PTS 32.31.50.11. PTS 32.80.10.10. PTS 33.64.10.10. PTS 34.00.01.30. PTS 34.17.00.32. PTS 62.10.08.11. PTS 80.00.10.10.

S 17.001 S 17.002

IP 15

32.31.50.13 December 2008 Page 25 INTERNATIONAL STANDARDS Electrical apparatus for explosive gas atmospheres: Part 14: Electrical installations in hazardous areas (other than mines) Part 16: Artificial ventilation for the protection of analyser(s) houses Plugs, socket-outlets and couplers for industrial purposes Industrial-process control - safety of analyser houses
Issued by: Central Office of IEC (sales dept.) 3, Rue de Varemb 1211 Geneva 20 Switzerland.

IEC 60079-14 IEC/TR 60079-16 IEC 60309 IEC 61285

Last page of this PTS

You might also like