Svetsaren 1 2009
Svetsaren 1 2009
Svetsaren 1 2009
PCS
= Welding station costs, including labour cost [Euro/h] X Cycle time reduction [s] / 3600
Calculation of consumables cost increase per component
The consumable cost increase, when using cored wire instead of solid wire, is around 0.002
Euro/g. Per component this amounts to:
CCI
(1) = 0.002 Euro/g X GWM
Alternatively, the consumables cost increase per component can be calculated through the wire
feed, which can be retrieved from the wire feed unit or from the welding parameter log of the power
source. The effective consumable usage per component is obtained by multiplying the length of
wire used per component by the specific weight of the wire (7.8 g/m for OK Tubrod 14.11). This
method has the advantage that burn-off and spatter loss is also taken into account.
CCI
(2) = 0.002 Euro/g X WFc X SWW
Calculation of welding cost savings per component.
C
= PCS - CCI(1/2)
Fabrication of axle components
The following example is based on data obtained from an automotive indudtry application. .
A robot station with a cost of 60 Euro/h, operator included, is used to weld overlap joints in 2mm
plate at a travel speed of 12mm/s (72cm/min), using G3Si1 1.0mm solid wire. The total weld length
per component is 2500mm. The weight of weld metal per component is 300g (weight difference
welded and non-welded). The arc time is 208s (2500 mm / 12 mm/s).
With OK Tubrod 14.11 1.2mm, the travel speed increases to 25mm/s (150 cm/min) reducing the
arc time per component to 100s (2500mm / 25mm/s). Idle time (robot movements, turning of
manipulators) remains the same.
The cycle time reduction due to the use of OK Tubrod 14.11 1.2mm amounts to 108s, giving a
production cost reduction of:
PCS
= 60 Euro/h X 108s / 3600 = 1.80 Euro
The consumables cost increase per component due to use of cored wire is:
CCI
= 0.002 Euro/g X 300g = 0.60 Euro
This gives a cost saving per component of:
C
= 1.80 0.60 Euro = 1.20 Euro/kg
Calculating with a total cycle time, including idle time, of 240s (solid wire) and welding costs,
including consumables of 4.50 Euro/component, the above brings a saving of about 27%.
Figure 6. OK Tubrod 14.11 1.2mm.
Conclusion
The example shows that productivity can be
significantly increased at lower total welding
costs, notwithstanding the higher
consumables costs of OK Tubrod 14.11
1.2mm. Not taken into account is an extra
saving on shielding gas. Although cored wires
are welded with a slightly higher gas flow rate
at about 15 l/min, this is more than
compensated by the much shorter arc time.
The higher productivity is not the only benefit
fabricators derive from OK Tubrod 14.11.
Better weld quality results in additional cost
advantages. ESAB offers fabricators an
excellent opportunity to fullfil their needs for a
more cost efficient welding solution.
Table 2. The following symbols are used in the
calculation formula:
Symbol Unit Explanation
PCS
Euro Production cost saving per
component
G
WM
g Weld metal weight per
component
CCI
Euro Consumables cost increase
per component due to use of
cored wire
W
Fc
m Wire feed per component
SW
W
g/m Specific weight of wire
C
Euro Cost saving per component
36 - Svetsaren no. 1 - 2009
Svetsaren no. 1 - 2009 - 37
Acknowledgement
Thanks are extended to Mr. Robert Clifford, AO,
Chairman of Incat Board, and also Mr. Maurice
Harvey, R&D, Shipyard and Welding Manager for
permission to take and use photographs and
write this article. The photographs were taken by
the author over several visits to Incats shipyard
and ships over several years. Other photographs
of completed vessels in service were made
available for use in this article by Incat.
The luxuriously appointed Natchan Rera and
Natchan World have been custom-designed to
carry up to 800 passengers per voyage, although
the standard Incat 112m catamaran design can
accommodate up to 1500 people and 355 cars,
or 193 cars and 450 lane-metres of trucks. A
3000 tonne fast ferry of this type has the same
passenger and car carrying capacity as a 10,000
tonne conventional steel vessel. The Natchan
sisters passage takes two hours - about half the
time of a conventional vessel - allowing twice the
number of voyages, daily.
These Made in Australia, 112.6m long, 30.5m
Panamax wide, 3.9m draft vessels, are capable
of weathering full sea state conditions and must,
justly, be called ships. They are also amongst the
largest welded aluminium constructions ever built.
Incat Australia
A visit to Incats shipyard, today, might find them
busily building hull 66 after earlier last year
making rush delivery of Natchan World, to meet
Higashi Nihon Ferrys urgent operational service
requirements. That rush delivery left Incats
three-ships-long final assembly building empty for
the first time since being built. Incats first 74
metre, all-aluminium high speed wave piercing
catamarans, accommodated 198 dead weight
tonnes. The 112 metre vessels accommodate
more than 7 times that amount. From 74m to
78m, then 86m, 91m, 96m, 98m and now 112m
The worlds largest, most
fuel-efficient, diesel powered high
speed catamaran ferries - Natchan
Rera and Natchan World have
recently entered service, plying the
Tsugaru Straight between Honshu
and Hokkaido islands, in Japan.
Built half a world away, by Incat,
in Hobart, Tasmania, these two
aluminium vessels are affectionately
known as hull 64 and hull 65.
JERRY MIRGAIN, ESAB GLOBAL ALUMINIUM PRODUCT LINE & ALCOTEC INTERNATIONAL SALES
Welded Transport at Sea
The aluminium Ferries to Hokkaido
Figure 1. Nachan Worlds highly efficient wave piercing bows produce very low wake. Figure 2. Spacious passenger areas on Nachan Rera and Nachan World.
Figure 3. Incats genesis: the 1975 Derwent River
Tasman Bridge disaster created an urgent need for
Hobart ferry service.
Figure 4. Weld designs for heavy sections include milling
radii to relocate welds from fillet to butt positions.
Figure 5. To match butt weld leg dimensions and facili-
tate even heat distribution heavier legs are tapered.
Run-off tabs are used as appropriate.
Figure 6. Mr. Maurice Harvey, Incats welding manager,
inspects hull 65 forecastle work.
Figure 7. Hull 64, Nachan Rera, clears Tasman Bridge,
Hobart, bound for open sea.
Figure 8. Uniform welding techniques, throughout the
yard, produce uniform weld bead appearance and
uniform weld quality.
38 - Svetsaren no. 1 - 2009
designs, Incat now has 29 such vessels in service
around the world, capturing an estimated 40%
global market share.
Incat anticipates increasing global demand for
such vessels, not only from Europe and the
Atlantic but, in future also from Asia and the
Pacific. A joint venture partnership exists with
Bollinger Shipyards, USA, with whom Incat are
presenting their specially designed vessels for
possible future military logistics service.
Since its founding, in 1975, by Robert Clifford,
A.O., the company has taken an interesting
voyage to arrive at its current position.
- The first ferry was built to operate in the
Derwent River, in Hobart, filling an urgent river
crossing need after a section of the Tasman
Bridge was destroyed in a shipping accident, in
1975 - virtually cutting Hobart in half. When the
bridge reopened, two years later, the direction
of Mr. Cliffords business changed from
operating to building ferries.
- The catamaran type vessel was chosen from
the outset but demands for operation on
longer, open water crossings, challenged Incat
to develop their wave piercing hulls.
- Incat was one of the earliest builders in the high
speed ferry business to design and build
all-aluminium vessels. Aluminium provides light
weight without sacrificing strength.
The exceptional dent resistance and toughness
of aluminium contributed to seaworthiness and
safety, while its high corrosion resistance
reduced maintenance and overhaul expenses.
Incats avant-garde ship design and building
methods evolved, in-house, through repetition,
monitoring, maintenance and adoption of
accumulated improvements from vessel to vessel.
Additionally, Incat has built symbiotic partner
relationships with many of its key vendors
including Pacific Industrial Supplies, ESAB and
AlcoTec for supply of aluminium welding wire.
Originally, the principal material used to build Incat
wave piercing vessels was aluminium base alloy
5083, which is traditionally welded with its
companion welding filler material 5183. A few
years ago, Incat evaluated and then adopted
5383 alloy as a replacement base material to
5083. The improved strength of this material
allowed further design enhancements but placed
additional weld quality, strength, and porosity
control demands on the filler metal to be used.
AlcoTec worked with Incat to provide a 5183 type
welding wire with tighter controlled porosity limits,
chemistry, and diameter than described by
nominal Standards Australia or American Welding
Society specifications.
In 100% radiographed welds, joints are typically
designed to avoid fillets, by milling radii on heavy
corner sections and butt welding. Techniques such
as material tapering to match butt weld thickness
and using run-off tabs, are commonly employed.
Uniform welding techniques assure uniform weld
appearance and quality throughout the yard. As
the business was developing, Incat worked with
the state of Tasmania to establish a Technical and
Further Education campus adjacent to site. Here,
welders were taught the principles of aluminium
Figure 9. The 5383 base material with higher strength to
weight than 5083 material, is welded with 5183 type
welding wire from AlcoTec.
Figure 12. Rigid wave piercing bows have some skin
sections up to 25mm.
Figure 15. Incats final assembly building hull troughs
are flooded for hull 65 to slip the shed.
Figure 13. To manage propulsion nozzle flange distortion
welding operations are performed before milling.
Figure 14. At the final assembly location panamax
width hull 65 fully occupies Incats 112m design shed
height and width.
Figure 10. Separately mounted superstructure visible
above sturdy sea frame cross bracing.
Figure 11. Rubber mounts isolate superstructure from
sea frame.
Svetsaren no. 1 - 2009 - 39
welding - alongside Incats own company welding
techniques - before being allowed to weld in the
yard. Interestingly, carpenters were often the
preferred choice of candidate for training as they
were considered to be easier to train, correctly,
rather than undertake retraining of steel welders!
Welders are the first-in-line for quality assurance
control. If any operator experiences a problem or
observes a possible discontinuity, they are
expected to stop welding and involve yard
supervision in evaluating the situation. Such
methods and policies ensure Incats cost-effective
quality control and productivity.
Design features
Generally, as each vessel has slightly different
topside requirements from a base vessel design,
Incat produces a standard sea-frame for the main
hull. This sea-frame has strength stiffness and
integrity separate from the superstructure. Since it
is desirable to separate passenger spaces and
bridge from the machinery and dynamics of a
vessel transiting the open ocean at 75km/hr, the
superstructures are separate structures mounted
on rubber brackets on the sea-frame.
Along with the centre forward bow, the wave
piercing bows are important elements in the ships
design. The hydrodynamics and aerodynamics of
these bows demand that they be particularly rigid
elements. There are areas in these bows where
the skin thickness is up to 25mm.
The ships propulsion jet room assemblies are
welded aluminium, as are the propulsion nozzle
connecting flanges. To avoid distortion, the
flanges are welded first and then milled in place.
The Holy Grail of Passenger Transportation
As with other forms of passenger transportation, the
Holy Grail all are seeking is the right combination of
safety, speed, comfort and efficiency. It seems clear
that for high speed ferry design and construction,
Incat may have their Holy Grail in sight. As partners,
Pacific Industrial Supplies, ESAB Australia and
AlcoTec Wire Corporation, are pleased to have been
able to contribute to Incats quest.
ABOUT THE AUTHOR:
JERRY MIRGAIN LIVED 25 YEARS IN AUSTRALIA AND HAS
HAD A LONG RELATIONSHIP WITH INCAT. HE REMAINS
A MEMBER OF THE WELDING INSTITUTE OF AUSTRALIA
- ALUMINIUM WELDING PANEL, AND IS ON THE
EDITORIAL COMMITTEE OF THE AUSTRALASIAN
WELDING JOURNAL. HE JOINED ESAB, IN 1984,
AS CONSUMABLES DIVISION MANAGER IN AUSTRALIA.
HE NOW RESIDES IN USA AND HAS DUAL
RESPONSIBILITY AS ALUMINIUM GLOBAL PRODUCT
LINE MANAGER FOR ESAB AB AND AS
INTERNATIONAL SALES MANAGER FOR ALCOTEC.
40 - Svetsaren no. 1 - 2009
Figure 1. Shock absorber cross-section.
Svetsaren no. 1 - 2009 - 41
of the absorbers are MAG welded with 1.0mm
diameter EN 440: G3Si welding wire in
82%Argon/18% CO
2
shielding gas protection.
Weld metal consumption per housing averages
6g which, at a daily production of 45,000
absorbers, equates to 270 kg. The MAG process
is fully automatic, the equipment consisting of two
4-head, one 3-head, four 2-head and two 1-head
installations, and a robot. In total, 22 welding
heads are to be fed with welding wire.
Before the introduction of Marathon Pac, the
company used wooden spools with 100kg or
200kg welding wire with a mechanical pay-off
Figure 2. Shock absorber housings with welded
assembly ring.
Sochaux-Montbliard is the cradle of Peugeot,
the leading brand of PSA Peugeot Citron the
automotive company with 14% market share in
Europe and over 5% worldwide. Here, in 1810,
the Peugeot brothers, descendents of a family of
millers, converted a corn mill into a steel foundry
to supply springs to the local clock industry. Soon
the portfolio was extended with bandsaws, tools,
coffee mills, frames for hoop skirts and,
eventually, in 1886, the production of bicycles in
the city of Montbliard.
The private car venture started in 1889, when the
company exhibited a steam driven three-wheeler
at the Paris world exhibition. A chassis factory
was built in 1912, in Mandeure, and in the same
year Peugeot bought the land on which the UMS
factory stands, today. Some 12,500 people are
employed on the 265 hectare site. Activities are
two-fold: deep-drawing, assembly and painting of
chassis in one section; mechanical construction,
development and testing in another section. In
addition to suspension systems, the UMS factory
produces some 45,000 shock absorbers a day -
mainly for Peugeot Citron cars, but also for other
brands (altogether 180 models).
Automated production
Car suspension system shock absorbers -
regarded as safety components - have high weld
quality demands (Figures 1 and 2). The housings
The UMS factory in Sochaux-
Montbliard, in the French province
of Franche-Comt, produces
suspension systems for Peugeot
and Citron cars. Introduction of
ESAB Marathon Pac bulk wire
systems has improved productivity
and reduced fabrication costs.
3% more shock absorbers for PSA
Peugeot Citron
JOEL PERRIN, ESAB FRANCE, PARIS
Figure 3. Wooden spool with 100 or 200kg welding wire
and a mechanical pay-off system.
Automated production benets from Marathon Pac
42 - Svetsaren no. 1 - 2009
ABOUT THE AUTHOR:
JOEL PERRIN IS KEY ACCOUNT MANAGER AT ESAB
FRANCE, PARIS.
system (Figure 3). It involved a rather complicated
method of wire feeding, consumed a lot of space
and hindered operations. Whats more, the
dimensions of the spool remained the same - full
or empty and they needed to be transported
and stored before being returned to the supplier.
The main reason for considering Marathon Pac,
however, is that the welding wire from the
previously used wooden spools maintains the
mechanical deformation (cast & helix) it receives
when it is spooled onto the spools. The result is
the so called dog-tailing of the wire extension
when the wire leaves the contact tip. This is a big
problem in automated production with precisely
pre-programmed weld paths, resulting in wrongly
positioned welds and increased contact tip wear.
Towards the end of 2005, the idea emerged for a
production test using one Marathon Pac drum on
the SERDA 2 production line - motivated by
ESABs claim that this system overcomes the
dog-tailing problem.
The Marathon Pac system
ESAB France supplied a Marathon Pac drum with
250kg of 1.0mm diameter OK Autrod 12.51 and
installed it on the SERDA 2 line, to run a test until
the drum was empty. Success was so
overwhelming that production management
immediately ran a wider test and, soon after,
introduced Marathon Pac at all welding stations.
Wire in Marathon Pac is pre-twisted before being
spooled into the drum, to compensate for the
limited mechanical deformation it receives in the
spooling process. As a result, the wire extension
is virtually straight when the wire leaves the
contact tip for exact positioning of the weld.
This results in better weld quality and lower defect
rate. It also reduces contact tip wear and the
associated maintenance of the welding gun,
resulting in less downtime.
No accessories are needed for the supply of the
wire. The system works with the wire feed unit,
which is less subject to wear because of low
feeding forces.
PSA UMS Sochaux also purchased a number of
Marathon Pac accessories - lifting yokes, trolleys
and re-inforced liners with quick connectors - for
easier internal transport, installation and reduced
maintenance.
Figure 4 shows how the Marathon Pacs are
positioned for a four-head welding installation
(not visible). The liners are arched over the
pathway and are in this way easily accessible
for maintenance. Available in lengths from 0.6m to
12m, they are adaptable to any workshop
situation. The spare drum (in the foreground) is
ready to be installed when one of the four
connected drums is empty.
OK Autrod 12.51 is a high quality copper-coated
welding wire with a more stringent chemical
analysis than required by the European norm
G3Si. This assures consistent mechanical
properties from delivery to delivery.
Increased production
PSA UMS Sochaux calculates a 3% increase in
shock absorber housing production resulting from
the use of Marathon Pac, compared with the
wooden spools. This is due to significantly lower
downtime for spool exchange and, annually, 60
hours less downtime for maintenance a
significant figure in automated mass production.
Figure 5. Marathon Pac connected to a robot.
Figure 4. Four active Marathon Pacs, and a spare supplying a four-head installation for the welding of shock absorber
housings.
Svetsaren no. 1 - 2009 - 43
New track is embedded on noise reducing rubber
pads, which also give better electro isolation and
less vibration. One disadvantage with concrete
embedded rails is that they are not so easily
re-placed as rails embedded in cobblestones or
tarmac.
In Riga, tramways last 20 to 25 years, depending
on the intensity of traffic. Tramway curves wear
faster than straight track because of side-wear,
depending on the radius and frequency of use.
Tramtrac
TM
II
For Rigas Satiksme, the ESAB Tramtrac II welding
tractor provides a cost-efficient solution for
repairing curves embedded in either concrete or
tarmac, avoiding more costly total replacement.
In addition, other parts susceptible to wear, such
as tram stops and switches, can be repaired
efficiently with this portable system based on the
FCAW process using self-shielded wires.
The FCAW process allows Tramtrac II to be small
and ultra lightweight. It is easily stored and used
from, for example, a pick-up truck, together with
a petrol/diesel generator and welding power
source. The tractor can be hand-carried and is
easily installed and removed from the rail,
allowing welding to take place between
successive trams.
The FCAW process gives Tramtrac II a high
deposition rate and a high duty cycle, due to
quick installation and easily removed slag.
Tramtrac II is operator friendly with a four-wheel
drive carriage that rides the single rail, a wire
feeding unit for 1.2 or 1.6mm wires and
adjustable traction wheels to fit most worn
flanges and railheads. The control box, on top of
the feeder encasement, features clearly marked
symbols for wire feed speed, travel speed and
SIA Rigas Satiksme is a publicly
owned body that operates public
transport and vehicle hire in the
Latvian capital Riga and its
surrounding areas, which has over
700,000 inhabitants. It is the
largest provider of public transport
in Riga, operating buses,
trolleybuses and trams. Trams are
one of the citys principal modes of
transport, with Rigas Satiksme
operating 252 trams on 11 routes
across the city with a length of 120
km. In 2010 they will start using
modern, low-floor trams on one
city route, for which the
infrastructure is now being pre-
paired.
JANIS CERBULIS, RIGAS SATIKSME, AND MARIS ZVIRBULIS, ESAB, RIGA, LATVIA
Tramtrac
TM
II rail repair solution for
Rigas tramways
Figure 1. Small, lightweight and portable. Tramtrac
TM
II applied on tram rails in the streets of Riga together with the
OrigoMig
TM
410 power source.
44 - Svetsaren no. 1 - 2009
ABOUT THE AUTHOR:
MARIS ZVIRBULIS IS COUNTRY MANAGER FOR ESAB IN
LATVIA.
JANIS CERBULIS IS CHIEF TRACK DEPARTMENT AT
RIGAS SATIKSME, RIGA, LATVIA.
start and stop welding functions, as well as wire
inching.
The curved slide on which the welding head is
located enables easy and exact positioning of the
wire extension between 0 to 65, while the
horizontal and vertical slides enable positioning in
the x- and y-planes. Tramtrac II takes a 42V AC
control voltage from an Origo Mig 320 or 410
power source featuring 40 voltage settings.
Control and welding cables 10 metres in length
- allow the tractor to travel a distance of up to
17m when the power source is positioned close
to the rail.
Consumables
The need to weld embedded grooved rails in
cities makes preheating of rails impossible. With
rail grades ranging from 700A (R220) to 900A
(R260), consumables for difficult to weld steels
are recommended with a weld deposit that can
accommodate high carbon migration without
cracking. ESAB OK Tubrodur 15.65 and
OK Tubrodur 14.71 are two wires that have been
successfully used by tramway repair contractors
for many years. Once the beads have been
Figure 2. The curved slide on which the welding head is located enables easy and exact positioning of the wire extension.
Figure 3. Deposited weld before and after slag removal.
deposited, there is no need to grind to the final
profile of the rail.
Rigas Satiksme uses 1.6mm diameter OK
Tubrodur 15.65 (Table 1) for the repair of the
Russian T62 type tram rails, which are very
common in Riga. The rutile, self-shielded cored
wire has a very good weldability and excellent
slag detachability.
The weld metal is austenitic-martensitic
work-hardening (Figure 4), with excellent metal to
metal abrasion and impact resistance.
Table 1. Product data Tramtrac
TM
II and OK Tubrodur consumables
Tramtrac II Control voltage Power Welding speed Dimensions (l x w x h) Weight without consumables
36-46 V AC 90W 30-100 mm/min. 600 x 300 x 150 mm 12 kg
Ordering
information
Tramtrac
TM
II Connection cable 10m Origo MIG 410 Origo MIG 320 Magnetic earth return cable &
clamp
OK Tubrodur
14.71, 1.6mm
OK Tubrodur 15.65,
1.6mm
0814 721 880 0457 360 884 0349 302 408 0349 303 562 0000 500 415 1471 167 730 1565 167 730
Classifications & approvals Typical chemical composition all weld metal (%) Hardness HB
OK Tubrodur 14.71 C Si Mn Cr Ni as welded work hardened
Type: Rutile
Polarity: DC+
EN14700 T Fe 10
0.03 0.5 5.1 19.1 8.7 200 400
A stainless rutile 18.8.6Mn, self-shielded cored wire for cladding and joining 13% Mn steels and steels with limited weldability. It is also useful for buffer
layers prior to hardfacing. Supreme welding characteristics and excellent slag detachability.
Classifications & approvals Typical chemical composition all weld metal (%) Hardness HB
OK Tubrodur 15.65 C Si Mn Cr Ni Mo as welded work hardened
Type: Rutile
PolarityL: DC+
EN14700 T Fe 9
0.03 0.6 13.5 15.5 1.8 0.8 250 450
A stainless rutile self-shielded cored wire depositing a martensitic-austenitic, work hardening deposit, used for the rebuilding of mild, low-alloy and 13%Mn
steels. The weld metal combines excellent metal to metal abrasion and impact resistance. Supreme welding characteristics and excellent slag detachability.
Svetsaren no. 1 - 2009 - 45
Figure 4. Cross section of rail repaired with Tramtrac II.
Table 2. Typical weld metal composition of two samples welded with OK Tubrodur 15.65
C Si Mn P S Cr Ni
% % % % % % %
Rail 0.28 0.25 1.43 0.021 0.028 0.024 0.02
Weld 0.31 0.19 10.7 0.014 0.012 8.0 0.05
46 - Svetsaren no. 1 - 2009
Fabrication of truck axles at Arvin Meritors Cameri plant.
Figure 1. Typical heavy truck rear axle, with disc brakes. Figure 2. Starting point of the hot pressing line.
Svetsaren no. 1 - 2009 - 47
Perfect welding for truck axle housings
of buses and trolley buses, and of engines for the
first Cucciolo motor bicycles, began.
In 1953, Cansa was absorbed into Fiat and in
1968, the Cansa name disappeared, and the
company became Fiat, then Fiat Veicoli Industriali
and, subsequently, Iveco. During this time, the
Cameri plant became involved in bus production
and assembly, receiving the bus chassis and
manufacturing the framework, which was
mounted, plated, painted, fitted-out with interior
furnishings and road testing operations. At the end
of the Seventies, bus production moved to
Southern Italy.
The recent years
In Cameri, where the plant had been significantly
enlarged in the meanwhile, a refurbishment
project began, leading to the creation of a
joint-venture between Iveco and the American
giant Rockwell International: Omevi was founded
and the Cameri plant became the centre for the
manufacture of axles for medium-heavy vehicles.
The involvement of Rockwell resulted in a
significant technological evolution, in which the
Cameri plant gained state-of-the-art production
and control equipment. At the beginning of the
Acknowledgement
We thank Alberto Caramellino, Manufacturing
Engineering Manager and Fedele Bozzella,
Manufacturing Engineer, at the Commercial
Vehicle Systems Division of Meritor HVS for
facilitating this article.
The origins of the Cameri plant go back some
100 years. Established in 1909 both as a flight
school and an airport, the early days were rather
humble: a wooden, single-floor house for the
offices, and a wooden aircraft hangar. In 1912,
the Turinese artist and painter, Giuseppe
Gabardini, who had already designed several
innovative aircraft including the Idroaeroplano and
the Gabarda monoplane, took over the plants, the
airport and the flight school.
Operations ceased between 1929 and 1932, when
Gabardini resumed activities on behalf of the
government, overhauling and inspecting fighter and
bomber aircraft. After Gabardinis death, in 1936,
Cansa took over management, including overhaul
and inspection activities for Fiat aircraft, and also
engine assembly. These activities again ceased in
1944, when the Cameri workshop produced
disparate products such as bicycles, electric
heaters and kitchen furniture. In 1946, production
With products in virtually every
vehicle on the road, ArvinMeritor is
a leader in advanced solutions that
focus on enhancing vehicle stability
and reducing harmful emissions.
The companys 100,000 m
2
plant
in Cameri, Italy, has around 600
employees and produces axle
housings for trucks built by world
leading manufacturers such as
Iveco, Renault and Volvo and
must, of necessity, be robust and
of the very highest quality. A
recent decision to adopt ESAB
AristoRod 12.50 wire for exclusive
use in the plant has resulted in
significant improvements for the
production and assembly
processes.
CESARE FONDRINI, ESAB SALDATURA SPA, MESERO, ITALY.
Figure 4. The two halves tack-welded.
Figure 5. Full penetration by one-sided welding.
Figure 3. Hot-pressed parts ready to be welded together.
48 - Svetsaren no. 1 - 2009
Nineties, manufacturing lines were reorganised
and redesigned with the integration of more and
more automated equipment.
In 1997, Rockwell International was split. The
Automotive sector assumed the name Meritor
and the Cameri plant changed its name to Meritor
HVS Cameri SpA. Meritor was strongly focused
on Europe. It had acquired the Lindesberg Volvo
plant, in Sweden, devoted to the manufacture of
axles. It also acquired the Lucas Varity Brakes
Division, with a plant in England. Headquarters
were established in Amsterdam, some functions
were centralised and the Aftermarket Europe
Division was created, with offices in Zurich.
The merger of industry leaders Arvin Industries
and Meritor Automotive in July 2000 created
ArvinMeritor, now one of the worlds largest
automotive component manufacturers and
suppliers, with 36,000 employees and 140 plants,
worldwide. Arvin brought to the merger an
international reputation as one of the leading
manufactures of automotive components, in
particular products for drive control, filters and
exhaust gas systems. Meritors strength was as a
world leader in the light vehicles sector, its
portfolio comprising axles, brakes, transmissions,
driving systems, transmission axles, roof systems
and suspensions.
Current production
ArvinMeritor has an important presence in
Europe, because its main customers Iveco,
Renault and Volvo are the biggest world
manufacturers of trucks, says Alberto
Caramellino, Manufacturing Engineering Manager,
Commercial Vehicle Systems Division of Meritor
HVS Cameri. Our plant has the largest
ArvinMeritor design team outside the United
States, followed in importance by the Lindsberg
team in Sweden, and the Lyon plant where cast
iron closed axle housings are produced.
In Cameri, we produce the fabricated axle
housing that is hot pressed and then assembled.
All the component parts are wire welded, with the
exception of the wheel hub, which is friction
welded.
Axle design is fully contained within the Cameri
plant. The design and the sizing of drive-shafts,
ring gears, pinions, planetary gears, satellites and
carriers (the cast iron parts that enclose the
differential gear) are our responsibility from
beginning to end, comments Fedele Bozzella,
Manufacturing Engineer, Commercial Vehicle
Systems Division of Meritor HVS Cameri.
All products are tested within the plant by our
specialised testing department. Generally, we
tend to have highly automated lines, with the
exception of some niche production that still
requires manual operations.
In both welding and hot pressing departments,
the manufacturing lines are based on sequential
architecture. The only functions that require the
intervention of an operator are the loading of
parts at the beginning of the line and middle line
positioning by robots and magnetic systems of
parts that will form the axle and end of line
inspection systems (sizes, welding quality,
aesthetic appearance, etc). The influence of
welding on the quality of the finished product is
critical, says Mr. Bozzella.
A fundamental process
In the Cameri plant, welding is clearly a process
of paramount importance. Our product can be
likened to a vessel composed of nine assembled
pieces, it must be robust and consistent with
specifications, reports Mr. Bozzella. All the
welds must be sealed and some of them are also
safety welds. The welding wire is an essential
component for quality production.
This is the background to the decision to adopt
Figure 8. Robotic welding of customisation.
Figure 7. Good appearance of all welds.
Figure 6. After welding, the axle housing is clean.
Figure 9. Rear axles ready to be assembled.
Svetsaren no. 1 - 2009 - 49
ABOUT THE AUTHOR:
CESARE FONDRINI IS PRODUCT MANAGER MIG/MAG
AND MARATHON PAC WIRES AT ESAB SALDATURA
SPA, MESERO, ITALY.
ESAB AristoRod 12.50 wire, but how was this
choice achieved?
Our decision stemmed from dissatisfaction
with the quality of the wire we were previously
buying from a historical supplier, says Mr.
Bozzella. The supplier began to have
significant quality problems. Moreover, new
requirements were arising, such as having
clean, spatter-free welding. We also wanted to
reduce fume emissions, especially in the
tacking and setup positions. Finally, we had a
further problem to solve: the wire we were
previously using was copper-coated and it was
inclined to peel off, the loose external particles
then obstructing the wire feeding system. This
was causing line stoppages that we wished to
eliminate.
The company, therefore, started looking for an
alternative that would eliminate the problem. We
were aware of technical features of AristoRod wire
and, in May 2008, reached the decision to adopt
this wire, adds Mr. Bozzella.
AristoRod 12.50 is a copper-free wire that, thanks
to the unique ASC (Advance Surface Technology)
surface treatment allows smooth wire feeding,
without friction and residues.
We were immediately able to verify that ESAB
AristoRod 12.50 wire fully eliminated welding
spatter and was satisfactory in all its other
features, says Mr. Caramellino. For its part, ESAB
also provided two bulk drums with wire
straighteners. The production lines were stopped
for fitting the welding positions and, following early
tests, very satisfactory results were achieved. We
could clearly see that the wire behaviour was
excellent: no spatter could be seen with the naked
eye, he stresses.
Other benefits became immediately apparent.
For instance, with the new AristoRod wire there
was no need to change the optimised welding
parameters. Both simple and more complex
welds immediately appeared perfect, concludes
Mr. Bozzella. For example, in a given step of the
working cycle we must execute a joint with weld
metal support. In practice, the material is grooved
and a welding ream is realised at the inside weld.
This is a very important joint for us and with the
AristoRod wire we are able to perfectly execute it.
Also, productivity has been significantly increased
because the AristoRod wire never causes any
problems.
The adoption of AristoRod 12.50 also produced
other benefits, such as improved arc stability,
better welding appearance and lack of spatter.
A single standard
AristoRod 12.50 wire, in 475 kg Marathon Pacs,
is used for all automatic and semi-automatic
welding at the Cameri plant. The only variant is
the diameter: on automatic machines 1.6mm
diameter is used; while in manual operations,
from simple tacking welds to more sophisticated
welds, 1.2mm diameter is used. Manual welding
with 1.6mm wire would mean using currents
greater than 380A at 32V, with a very strong
thermal radiation and tiring of the operators. In
the line, on the other hand, currents of 420-470A
at 32-34V are reached for specific welds and
currents of 360A at 30-32V for other simpler
procedures on softer materials. Finally, in the axle
housing assembly operations, currents are varied
depending on the part to be welded; the range,
both for deep and surface passes, is typically 310
to 360A to guarantee consistent penetration
inside the box.
The advantages can be clearly seen by all: after
welding, the axle housing is very clean and
requires no manual trimming operations; excellent
penetrations are achieved; and productivity has
been improved.
An ABB Flexarc cell with ESAB welding kit was up and running
in one weekend
STIG ANDERSSON, ESAB AB, GOTHENBURG, SWEDEN.
50 - Svetsaren no. 1 - 2009
Robotisation need not necessarily
be a long winded process with
many costly obstacles on the road.
Not with careful planning and the
right partners and correct
solutions. At Volvo Construction
Equipment AB, Cab Division, in
Hallsberg, Sweden, they decided
to robotise the welding of a variety
of components for the construction
of cabins one was the wheel
fenders or mud screens. Partners
in Volvos robotisation project were
ABB, ESAB and robot integrator
ROBOT AKADEMIN AB, all working
closely with the Volvo technicians
and production personnel.
The production of cabs for heavy wheel loaders
and dumpers is one of the main applications at
Volvo Construction Equipment AB, Cab Division.
These cabins reflect the Volvo brand and all it
stands for quality, safety and environmental
care. Volvo assembles the cabs from many
individually produced components which mostly
require welding. This also applies for the mud
screens which, until recently, where produced
manually with semi-automatic MAG welding. As
part of a broader project to reduce manufacturing
costs, Volvo decided to robotise also this part of
the production and purchased a third Flexarc
robot cell equipped with ESABs Aristo Robot
package to be installed by ROBOT AKADEMIN
AB a concept that had worked extremely well
with earlier robot projects.
The Flexarc robot cell
ABBs Flexarc cell (Figure 1) is the ideal solution to
the robotisation needs of Volvo Construction
Equipment AB, Cab Division. It fulfills their most
important requirements being compact in space,
easy to program and start-up and equipped with
state-of-the-art welding equipment. The cells
make optimum use of the space available, and
Volvo takes short-cut to robotised
welding
Svetsaren no. 1 - 2009 - 51
unit. The Aristo Mig robot package is described in
detail on page 25 of this issue of Svetsaren.
Volvo Construction Equipment AB, Cab Division
currently has three Flexarc robot cells in opera-
tion: one Flexarc K and one Flexarc R cell - both
equipped with IRB 1600 robots - and one Flexarc
D cell with an IRB 2400 robot. The last is used for
producing the mud screens.
From manual to robotic welding over the
weekend
The speedy installation and start-up of the robot
cell for mud screens is a good example of the
user-friendliness of the Flexarc robot cell. On
Friday at 1 o clock manual production stopped
and specialist robot integrator ROBOT
AKADEMIN AB started to install the robot cell and
program it in co-operation with the Volvo
operators. By Monday morning the robot cell to
weld mud screens was completely ready for
production.
The mud screens are made of relatively thin steel
sheet and assembled with forty short welds
Figure 1. The Flexarc robot cell quick to install and
move between departments.
Figure 2. Mud screen assembled with short intermittent welds with good cosmetic appearance.
can be positioned close to other production units
for an efficient work-flow.
Flexarc includes all the components necessary for
productive robotic arc welding - single or
multi-robots, the IRC5 robot control system,
unique error handling software, positioners and
Volvos preferred choice of welding equipment -
ESAB.
Plug and play
All components of the Flexarc cell are mounted
on a common base, eliminating the need for
on-site engineering work. Software has been
pre-configured for simple setup. All the customer
needs to do is unwrap the package, place the cell
in the desired location, connect the power cable,
air pressure and shielding gas hoses, program the
robot and start working. The Flexarc cell can be
moved within or between different production
facilities, which enables flexible production.
The whole system is designed to be efficient and
cost-saving. There are time saving options built-in
such as the ability to develop new programs
offline, via ABBs Robot Studio (using a virtual
replica of the robot) while the actual robot remains
in operation.
Simplified fault management saves time and
money. For example if a weld error occurs, the
operator doesnt have to enter the cell. The robot
will automatically direct the torch to a service
window and after maintenance by the operator
it moves back to where it stopped and
re-strikes the arc.
Volvo Construction Equipment AB, Cab Division,
in Hallsberg, has a strong preference for ESAB
welding equipment and specifies all robot cells to
be equipped with the ESAB Aristo Mig robot
package, ensuring the latest inverter welding
technology. The package consists of:
The Aristo Mig 4000iw or 5000i inverter.
The Aristo W8 interface which communicates
with ABBs IRC5 robot control unit.
The Robofeed 3004w ELP encapsulated wire
feeder.
Cable packages.
The Marathon Pac bulk drum with robot quality
welding wire and separate bobbin holder.
The control unit of the welding package has been
integrated in ABBs IRC5 robot control unit, so
that all programming is accomplished within the
52 - Svetsaren no. 1 - 2009
(Figure 2 and 3). The robot cell is equipped with a
positioner with fixtures on both sides for
simultaneous robotised assembly welding and
manual tack welding of the next mud screen.
Shielding gas is Mison 8 and the welding wire
advised by ESAB for this application is OK Autrod
12.64 diameter 1.0mm. It is an AWS A5.18:
ER70S-6 type wire with a slightly higher
manganese and silicon content for increased weld
metal strength and is classified G4Si1 according
to EN 440. More important for this application,
however, is the softer arc and the lower sensitivity
to surface impurities, giving smooth and sound
welds. The wire is fed from Marathon Pac bulk
drums containing 250kg of welding wire (Figure 4).
Essential to the successful robotised welding,
according to ROBOT AKADEMIN AB, is the
avoidance of arc blow. The solution was found in
low-voltage pulsing for which the programming
features of the Aristo Mig 5000i power source
were extremely well suited. This setting is like
balancing on the edge. The pulse parameters are
so low that the arc type gets close to short arc
welding the objective is to keep the work piece
cold and give spatter no chance to adhere. The
result is remarkable. Any spatter formed simply
rolls away, leaving the work piece clean.
The side for manual tack welding is equipped with
an Aristo Mig 4000i power source with an Aristo
Feed 3004 wire feed unit. The MA6 panel on the
power source provides the most advanced weld-
ing functions available from ESAB, including the
full library of synergic lines.
The production cycle time was brought down
from around 20 minutes with manual welding to
just 5-6 minutes with robotised welding. It should
be noted that, in this case, the robot is not used
at full speed because the front loading and
tacking are limiting factors.
Figure 5. Manual tack welding. Aristo Mig 4000i power source located outside the Flexarc cell.
Figure 4. Aristo Mig 5000i inverter and 275kg Marathon
Pac installed outside the Flexarc robot cell.
Figure 3. Overview of mud screen assembled with many
short welds.
ABOUT THE AUTHOR:
STIG ANDERSSON IS AREA SALES REPRESENTATIVE AT
ESAB AB, SWEDEN.
Svetsaren no. 1 - 2009 - 53
brand, but can flexibly respond to demands of
several product lines, regardless of brand. This
centralised efficiency now makes them one of the
industrys lowest cost producers of lift trucks and
components, including replacement parts for
other manufacturers trucks.
NMHG Mexico
As part of the group restructuring plan, in 1997
the subsidiary facility NMHG Mexico, S.A. de C.V
started production in Ramos Arizpe, Mexico to
manufacture lower cost forklift frames for other
facilities in North America. Since the start up in
this plant, the company has used GMAW-P as
the main welding process in state-of-the-art
robotised cells.
NMHG has a team-oriented environment where
employees can expand their skills and meet their
career goals. Employees are encouraged to be
key contributors. That is why Juan Francisco
Limones, responsible for welding processes and
robotic equipment in Ramos Arizpe facility,
decided to initiate an investigation on how to reduce
welding cost associated with unexpected
equipment downtime due to poor performance of
Just five years after its launch, the advantages of
ESABs OK AristoRod copper-free welding wire
are being widely recognised in a variety of
industries around the world, making it a truly
global product. In this article, ESAB Mexico
reports on the great improvements achieved by
NMHG Inc.
NMHG is one of the three core businesses of
NMHG Industries, Inc., a publicly-held company
with headquarters in Cleveland, Ohio.
World Leaders
NMHG designs, engineers and manufactures
materials handling equipment, including
warehouse trucks, counterbalanced trucks and
large capacity cargo and container handling
trucks. All lift trucks are marketed under the
Hyster
and Yale
and Yale
retail dealerships,
NMHG operates wholly-owned dealerships in
certain markets.
Today the people and facilities that make up
NMHG do not support just one product line or
At the Mexican plant of fork lift
frame producer NMGH, the use of
ESAB OK AristoRod copper-free
MAG wire is driving down costs
and improving productivity.
RICARDO MADRIGA AND JUAN JOSE LOPEZ, ESAB MEXICO, S.A. DE C.V., MONTERREY, MEXICO
Fork truck maker
boosts productivity with
ESAB OK AristoRod
54 - Svetsaren no. 1 - 2009
copper-coated to copper-free wire will generate
potential cost savings up to 19% that includes cost
reduction in MAG gun spare parts and downtime.
All those who know the welding process at the
NMHG facility in Ramos Arizpe realise the
inconvenience from the use of copper-coated
wires. The gradual build-up of copper dust and
flakes can cause clogging in the feed system and
copper-coated wire. Mr. Limones found that welding
cost had been affected by frequent equipment
stoppage and that copper-coated wire was
responsible for higher welding costs due to elevated
consumption of contact tips, diffusers and liners.
ESAB Advice
Mr. Limones called in the ESAB region sales
representative Ricardo Madrigal who immediately
proposed the OK AristoRod 12.50 copper-free
GMAW wire in Marathon Pac bulk package as a
superior alternative to the competitors
copper-coated wire.
AristoRod 12.50 is a copper-free wire that, thanks
to the unique ASC (Advance Surface Technology)
surface treatment, allows smooth wire feeding,
without friction and residuals
Cost Savings
After an exhaustive test of OK AristoRod in several
robotised welding cells, Mr. Limones gathered all
the information required to compare process costs.
He has estimated that the change from
Figure 1. Forklift frame welded with GMAW-P process, using OK AristoRod 12.50
copper-free wire, diameter 1.2 mm in 90% Ar/10% CO
2
shielding gas. The low spatter
level helps to keep the weldment, fixtures and welding equipment clean.
Figure 2. Two octagonal Marathon Pacs with OK AristoRod 12.50
(AWS class ER70S-6) copper-free wire installed behind a robotised welding cell
25 feet away from the contact tip without feeding issues.
It all adds up to better overall productivity
Svetsaren no. 1 - 2009 - 55
removed the biggest contributor to the clogging
of guns and liners and, with it, a major cause of
production stoppages and increased cleaning
schedules. In addition, greater arc stability results
in less spatter, improved weld quality and finish
and, consequently, leads to reduced need for
weld cleaning.
Welding operators and supervisors can clearly
see the advantages of ESAB OK AristoRod at
every stage of the welding process:
Low contact tip wear means fewer replacement
stops.
Consistent feedability means improved
production speed.
Lower feed force required for long distance feeding.
Fewer maintenance stoppages due to absence
of dust and flakes in liners.
Fewer spatters due to better arc stability.
Higher welding quality.
Juan Francisco Limones and Ricardo Madrigal
are continuing with this investigation and now
gathering the information to quantify the cost
reduction due to improvements in welding quality
and less cleaning time two other advantages
observed during application of ESAB OK
AristoRod 12.50 a product that creates savings
in a global marketplace.
lead to increased spatter and poor weld finish
and, eventually, to a complete breakdown of the
welding process.
Regular maintenance and cleaning of the feed
system is absolutely necessary to avoid feeding
problems. However, this is time consuming and
particularly costly as it causes downtime of the
robotic welding systems. By removing the dust
and flaking associated with copper, ESAB has
Figure 3. Typical filets welds are 6, 8 and 10 mm in leg
length.
Figure 4. Juan Francisco Limones (right) and Ricardo Madrigal (left).
ABOUT THE AUTHORS:
RICARDO MADRIGAL IS SALES REPRESENTATIVE AT
ESAB MEXICO, S.A. DE C.V., MONTERREY,
MEXICO.
JUAN JOSE LOPEZ IS APPLICATION ENGINEERING
MANAGER AT ESAB MEXICO, S.A. DE C.V.,
MONTERREY, MEXICO.
Hydro Automotive Norway speeds-up robotic welding of
aluminium cross beams for BMW 1-series
56 - Svetsaren no. 1 - 2009
Hydro Automotive AS, based in Raufoss, Norway
is part of the Automotive Structures division of
Norsk Hydro a group with production sites in
Norway, Sweden, the US, France, the UK,
Denmark and Germany. It specialises in the
fabrication of aluminium components and
supplies major car manufacturers such as Saab,
Renault, BMW, Jaguar, Porsche and Audi.
There are six Kuka robot stations for various
automotive components and a manual station for
repairs all using AlMg4.5 Mn0.7 type MIG
welding wire. Two years ago, Hydro Automotive
stopped using 7kg wire spools on the wire
feeders, after advice from ESAB, and changed
over to the new ESAB MarathonPac with 141kg
of OK Autrod 5183 high quality welding wire.
Since the changeover the company has enjoyed
efficient storage and handling of consumables,
savings on downtime for spool exchange, a lower
repair rate, gas cups that require less cleaning
and - above all increased production output.
This article examines the scale of that production
improvement.
By simply changing over from 7kg
wire spools to ESAB MarathonPac
bulk drums for all its robot
stations Hydro Automotive AS
obtained a substantial increase in
production output. In this article,
auditing of the station that produce
the cross beams for BMWs
1-series personal cars, has shown
dramatic improvements
BEN ALTEMHL, EDITOR OF SVETSAREN
How many more BMWs come
out of a Marathon Pac?
Figure 1. Welding station for cross beams.
Svetsaren no. 1 - 2009 - 57
The robot station
Cross beams for the BMW series 1 personal car
are produced at a station with two robots welding
two sides of the beam simultaneously (Figure 1).
The beam consists of a box structure to be
connected, on both sides, to a node for
connection to the chassis. During welding, a new
component is manually loaded on the other side of
the turntable, which rotates along its length axis.
Increased output from Marathon Pac
Hydro Automotive and ESAB calculated the
savings due to the use of MarathonPac bulk
drums, instead of the previously used 7kg wire
spools. These required, on average, 15 minutes
for spool exchange for each of the two robots
which have equal weld metal consumption.
The weld metal consumption per robot/year is
4900kg, or 9800 for the complete (two robot)
welding station.
Table 1 gives a welding cost calculation for the
use of 7kg wire spools versus Marathon Pac.
With spools, 700 spool changes per robot/year
are needed (1400 for the welding station). This
gives a total replacement time per year of 350
hours. For the same annual weld metal
consumption, Marathon Pac requires a total
replacement time of 17.5h. At an operational cost
for robot and operator of 200Euro/h, this reduced
downtime equals a saving of 68,250 Euro/year.
For Marathon Pac with robot quality aluminium
wire, fabricators pay a higher price/kg than with
Figure 2 shows the welding procedure for this
component, welded with the pulse MIG process. Sides
and corners are rotated into best position and welded
with pre-programmed parameters. Power sources, and
the Marathon Pacs are placed outside the robot cell.
This, for reasons of safety and convenience, is common
practice in the automotive industry (Figure 3). The robots
are equipped with push-pull wire feeders on the torch.
Figure 3. Robot operator programming outside the robot cell.
58 - Svetsaren no. 1 - 2009
Reduced downtime and rejects
A second important saving obtained by Hydro
Automotive is a scrap rate of rejected
components which is reduced from 0.5 to 0.3%.
The major reason for this reduction is the
continuous supply of 141kg of wire without
abrupt ending in the middle of a welding
sequence, as frequently occurs with 7kg spools.
There is a window in the drum where the operator
can easily see when the drum is almost empty
and stop the station smoothly in time.
In addition, the company reports less rejects
because of a more stable process with reduced
spatter.
This calculation shows the savings for one robot
station. Marathon Pac, however, is applied at all
six stations where similar cost savings are
obtained. It is also important to note that there
may be a slight difference in the consumables
price per kg.
How many more BMWs come out of a
Marathon Pac?
This interesting question can, of course, not be
answered in this article. However, what can be
shown is how many more BMW cross beams can
be produced, due to the use of Marathon Pac.
The clocked cycle time for each cross beam is
47 seconds (33 sec welding + 14 sec turning).
The duty cycle of the station is 65%.
The use of Marathon Pac brings (350-17.5) x
3600 x 65%= 778,050s extra net robot time,
which equals 16554 extra BMW cross beams a
year on which a full sales profit is earned. For
Hydro Automotive, this has been a major step in
their lean manufacturing practice needed to sur-
vive in the highly competitive automotive industry.
7kg spools. For aluminium wire, in general,
0.5 Euro/kg is an average which can be used in
calculations. In the case of Hydro Automotive, this
would result in an extra consumables cost of
4,900 Euro/year, which must be deducted from
the savings on downtime.
Table 1. Cost calculation for Hydro Automotive robot station. Weld metal consumption: 4900kg/robot/year
Type of packaging 7kg spools Marathon Pac Cost difference
Weight of wire (kg) 7 141
Wire consumption per year (kg) 9800 9800
Number of spool changes/year 1400 70
Total replacement time /year (min.) 21.000 1050
Total replacement time /year (h) 350 17,5
Cost related to spool replacement
Operational cost robot+ operator (Euro) 200 200
Cost for spool replacement/year (Euro) 70.000 1750 68.250
Additional cost for Marathon Pac
Extra purchasing price/kg (Euro) 0,5
Extra purchasing price/year 4.900
Figure 4. Each Marathon Pac is filled with high quality aluminium welding wire, and uses a special reverse coiling tech-
nology to ensure the wire comes out straight and perfectly positioned, resulting in greater process stability and a signifi-
cantly reduced risk of spatter. Use of the ESAB pear ensures that the wire can never get entangled during wire feeding.
ABOUT THE AUTHOR:
BEN ALTEMHL IS TECHNICAL EDITOR WITHIN
ESABS CENTRAL MARKETING COMMUNICATION
DEPARTMENT AND EDITOR IN CHIEF OF
SVETSAREN.
Svetsaren no. 1 - 2009 - 59
Panel (MMC) functions Origo
TA23
Origo
TA24
Welding methode MMA/TIG X X
Remote on/off X X
ESAB 2-program function - X
HF or LiftArc start X X
2/4-stroke X X
Gas pre/post-flow X X
Slope up/down X X
Pulsed TIG - X
Micro Pulse TIG - X
Digital amp-meter X X
Digital V/A-meter - X
Arc force (MMA) (X) (X)
Hot start (MMA) (X) (X)
Droplet welding (MMA) (X) (X)
ArcPlus II (MMA) X X
Product News Equipment
The new Origo/Aristo range of CC/CV welding machines has been designed to give the high level flexibility
required by such market sectors as energy and civil construction. All the new Origo and Aristo machines are
supplied with proven ESAB control units that enable different weld types to be produced. The units also enable
many process parameters to be set before welding starts. This facility also allows the parameters to be changed
during welding.
NEW RANGE OF MULTI-OPTION MACHINES WILL
TRANSFORM ARC WELDING
Origo
TM
Tig 3001i, TA23/TA24 -
for advanced industrial use and
for repair and maintenance
Pulsed TIG welding- easy control of
heat input and the weld pool (Origo
TM
TA24).
ESAB 2-program function provides
the opportunity to pre-program and
change program during actual welding
for increased productivity (Origo
TM
TA24).
Strong, reliable 300A inverter power
source - one machine for all types of
demanding applications.
Easy to use - parameter presentation
easy to understand.
HF or LiftArc start in TIG.
MMA welding handles all electrodes
up to 5mm.
ArcPlus II better welding characteris-
tics in MMA, simplifies work and gives
better weld quality with less after treat-
ment.
True MMA welding Hot start and Arc
force setting.
Applications
Repair and maintenance
General fabrication and civil construction
Process industry
Shipbuilding and offshore
Power generation
Transport and mobile machinery
Panel (MMC) functions Origo
TM
A22
Origo
TM
A24
Welding method MMA/TIG X X
Welding method MIG/MAG (CV) X
Remote ON/OFF X X
Selection of electrode type X
Arc Force (x) X
Hot start (x) X
Droplet welding (x) (x)
Min current setting TIG (x) (x)
Step-less inductance (CV) X
Digital amp-meter X
Digital V/A-meters X
Memory, 2 set X
60 - Svetsaren no. 1 - 2009
Origo
TM
Arc 4001i, A22/A24 -
optimum welding solutions
Outstanding welding characteristics -
high efficiency, high quality welding.
Efficient Man Machine Communication
by user-friendly Origo
TM
A22 and A24 control
panels.
The Origo A24 allows the choice of
electrode type: rutile, basic or cellulosic for
optimal welding qualities and has an easy to
read digital display to indicate current/voltage.
Adjustable Arc force and Hot start to
optimise the welding (Origo
TM
A24).
Enclosure class IP 23.
Dust filter to handle tough, dirty environ-
ments by prevent grinding-dust and metal
particles from entering the machine.
Market Segments
Civil construction and field erection
Energy generation
Pipeline contractors
Earth moving and mining
Offshore and shipbuilding
(Hire fleets)
Applications
Outdoor heavy installation on site
Outdoor maintenance and repair on site
Svetsaren no. 1 - 2009 - 61
Panel (MMC) functions MA23 MA24
2/4 stroke X X
Gas pre/post flow X X
Digital V/A-meters X X
Gas purge/wire inching X X
Memory 3 set X X
QSet
TM
X
Crater filling X
Creep start X
Pre-programmed synergic lines X
Origo Mig 3001i and 4001i, A24
- MIG 3001IW/4001IW - optimum
welding solutions
Reliable, smooth starts and ends supported
by efficient Hot-start and crater fill functions.
Efficient Man Machine Communication
by the user-friendly Origo
TM
MA23 and
MA24.
Wide range of pre-programmed synergic
lines in MA24.
Memory for three parameter sets.
ESAB LogicPump, secures automatic start
of water pump when a water-cooled welding
torch is connected.
TrueArcVoltage System, measures the
correct arc voltage value independent of the
length of the connection cable, return cable
or welding torch.
Dust filter to handle tough, dirty environ-
ments and avoid grinding-dust and metal
particles inside the machine.
QSet - automatic setting of short arc
parameters
Market Segments
Civil Construction & Field Erection
Energy Generation
Pipeline Contractors
Earth Moving and Mining
Transport Equipment
Offshore and Shipbuilding
(Hire Fleets)
Applications
Auto-repair
General metal fabrication
Tack welding
Civil construction
Mobile machinery
Pipe workshops
Panel (MMC) functions Aristo
TM
U6
Aristo
TM
U8
2
Aristo
TM
U8
2
Plus
QSet
TM
X X X
2/4 stroke X X X
Crater Filling X X X
Creep start, Hot
start and adjustable
burn-back time
X X X
Gas pre/post flow X X X
Digital V/A-meters X X X
Pre-programmed
synergic lines
X (60) X (92) X (>230)
Gas purge/wire inching X X X
Memory, 10 set X
Memory, 255 set X X
Pulse/synergicpulse X X X
Limit editor, set and
measurment values
X X
Create synergic lines X
SuperPulse
TM
X
Production statistics X
Auto save mode X
62 - Svetsaren no. 1 - 2009
Aristo
TM
Mig 3001i/4001i and
Mig 3001iw/4001iw - optimum
welding solutions
2/4 stroke, simplifies handling of the weld-
ing torch.
Creep start, gas pre-flow and hot start
provide a soft and more direct start with less
spatter.
Crater filling, adjustable burn-back time
and post gas provide a smooth finish,
extend the lifetime of the contact tip and
guarantee no cracks at the end.
Pre-programmed synergic lines, to
ensure optimum settings with a wide choice
of materials, wire dimensions and gas com-
binations.
Possibility to create synergic lines
(Aristo U82)
Memory for 10 (Aristo
TM
U6) or 255
(Aristo
TM
U8
2
) parameter sets
Quick connectors - shortest possible set-
up times.
ESAB LogicPump, secures automatic start
of water pump when a water-cooled welding
torch is connected.
TrueArcVoltage System
TM
, measures the
correct arc voltage value independent of the
length of the interconnection cable, return
cable or welding torch.
SuperPulse, the welding process with the
ability to control heat input (Aristo
TM
U8
2
).
QSet - automatic setting of short arc
parameters
Market Segments
Advanced mild and stainless steel fabrication
Advanced aluminium fabrication
QA Applications
Prefabrication of Ni based material
Advanced mild and stainless steel fabrication
Advanced aluminium fabrication
QA Applications
Prefabrication of Ni based material
Svetsaren no. 1 - 2009 - 63
Aristo U8
2
The new way to
connect your
welding universe
Leading-edge R&D and close cooperation
with key industries throughout the world has
placed ESAB at the forefront of welding
technology. The introduction of the radical
Aristo U8
2
control unit presents a whole
new universe of welding possibilities:
enhanced functionality, extended
communication and WeldPoint a logical,
user-friendly Windows-based interface.
Whatever the application, MIG/MAG (manual,
mechanised or robotised) welding, TIG or
MMA, the Aristo U8
2
unit will do the job. And its
add-on modular design and preselected synergic
lines for special materials ensure exceptional
flexibility. Designed as forward compatible,
ongoing software upgrades will keep WeldPoint
and the Aristo U8
2
control unit future-proof.
Why wait? Its time to master the welding uni-
verse!
Aristo U8
2
Basic version featuring all essential functions.
Forward compatibility assured through future
software upgrades.
Support manual and mechanised applications
Extended range of languages
Large display
Dials to adjust wire feed speed and voltage
Dial to scroll menu
USB connector
QSet
Limit editor set and measured values
Release pulse
LAN (via Aristo W8
2
)
WeldPoint
Basic package synergic lines (92)
Aristo U8
2
Plus
Complete software suite with full functionality.
Support manual and mechanised applications
17 languages, including Chinese
Large display
Dials to adjust wire feed speed and voltage
Dial to scroll menu
USB connector
QSet
Limit editor set and measured values
Release pulse
LAN (via Aristo W8
2
)
WeldPoint
Complete package synergic lines (>230)
SuperPulse
Filemanager
Auto save mode
User defined synergic lines
Production statistics
User friendly
The new-generation Aristo U8
2
creates a whole
new universe of possibilities maximum
functionality, minimum complexity. Five function
buttons, single menu and Enter button and three
setting wheels cover every option. Large, bright
easy-view LED display and knurled setting wheels
for simple gloves-on, visor-down operation.
Aristo U8
2
or Aristo U8
2
Plus, the all-new U8
2
control unit is the key to a fully integrated welding
system. Full USB connectivity and a broad choice
of advanced Aristo W8
2
add-on modules for
comprehensive Fieldbus (DeviceNet, CANopen or
Profibus) and LAN (Ethernet) communication.
Optional synergic-line packs for special materials.
Multilingual
In the global welding community, ESAB
technology is the benchmark for flexibility,
efficiency and consistent quality. Ingenious
software, intuitive interfaces and logical controls
have greatly simplified the welding process. Even
so, language remains critical in understanding and
utilizing the full potential of such advanced
welding systems.
With an expanded memory and updated display,
the Aristo U8
2
supports seventeen world
languages, including Russian and Chinese (with
original Cyrillic and Chinese characters). Manuals
available in all seventeen languages. The Aristo
U8
2
: say goodbye to poor displays and confusing
manuals.
64 - Svetsaren no. 1 - 2009
SuperPulse
Promoting partial solidification of the weld pool
between each pulse, the SuperPulse
function improves control of the weld pool and
solidification process, for a higher quality result.
Essentially, the process involves a programmed
changeover between two MIG/MAG settings, in
which time intervals are determined by the
primary and secondary-phase time settings.
SuperPulse benefits include reduced sensitivity
to variations in the root gap, better control of the
weld pool during position welding, better control
of penetration and penetration profile, and
reduced sensitivity to uneven heat evaporation.
WeldPoint
Our new proprietary WeldPoint software puts
back office operations up front! Ideal for the
multiple robotic welding lines typical of the
automotive industry, WeldPoint can enhance,
monitor and maintain consistent weld quality from
the welding or production engineers PC.
Simultaneous connection of up to ten welding
machines via TCP/IP, with sophisticated display
and storage of all weld data. All weld schedules
and production statistics, with the quality log,
error log, system configuration, limit setting and
measure limits, can be converted into HTML or
text format for export. Other innovative advances
include an online quality-data viewer (real-time
quality data from each welding machine, with
automatic or manual update) and an online
weld-schedule editor. You can also view
downloaded weld data set files, as well as
combining different weld data sets to form an
entirely new set.
QSet
Set and forget! A few seconds test welding, and
the short arc stabilizes as you watch. The QSet
function sets and stores the optimal welding
parameters automatically, maintaining consistent
arc stability, regardless of wire-feed speed. You
can move the contact tip away from the welding
seam in sharp corners and other tight spaces
without losing the ideal arc. Change of wire spool
and/or gas mixture? All it takes is another test
weld to optimize the parameters again. These
consistent welding results mean less spatter, less
cleaning and higher productivity.
Speedy set-up
One-knob control
No preset synergic lines
Automatic arc optimization
Less spatter, less after treatment
Increased productivity
Svetsaren no. 1 - 2009 - 65
The GMH joint tracking controller together
with ESAB servo slides and a sensor unit
forms a robust and easy to use joint tracking
system for automatic welding.
The GMH system minimises repair welding
and adjustments after welding thanks to that
the arc is always in the optimal position. The
general quality will be kept on an even level
and the operator does not need to focus on
the weld head and its position.
The operator can then keep an eye on the
entire installation and contribute to a non-
interrupted welding production by adding flux
and prepare for changing the wire spool well
in advance.
System contents
The welding head is mounted on a motorised
double servo slide where the head can be
moved up-down and left-right. The sensor is
the most vital part in the system which gives
information to the control system how to
adjust the slides to keep the arc in the optimal
position. There are a number of different
mechanical sense fingers for different applica-
tions. Inductive sensors can also be used.
Operation
The operator uses the joystick to guide the
welding head and mechanical sensor finger
into correct position. No programming at all is
required. The unit is set in track mode and the
welding can start.
Curved details can as long as they are within
the working range of the servo slides be weld-
ed fully automatic with GMH as the guiding
tool.
Applications
Shipbuilding (panels, sub-components)
Power generation (wind towers, boilers, ves-
sels)
Infrastructural components (beams, bridges)
Off-road vehicles (excavators, dump trucks)
GMH is available in three versions:
With control panel on the front
Suitable for ESABs A2 / A6 tractor automats and
A2 / A6 beam travelling carriage. Automatic
solutions with short distance between welding
head and GMH control box and where the
operator has a good overview of weld joint and
welding head without moving around.
With remote control (no panel on the front)
Suitable for Column & Booms and large automatic
installations with long distance between
welding head and GMH control box and when
the operator must move around in order to get
a good view of the welding joint.
Without control panel and remote control
Suitable for customized solutions where the
customers own remote control is adapted
to the GMH control box.
GMH -AUTOMATIC JOINT TRACKING
SYSTEM FOR MOST JOINT TYPES
Product News Automation
Easy to use, no programming required
Robust
Flexible with a remote control
Very short set-up times
Convenient for the operator
Minimises operator errors.
66 - Svetsaren no. 1 - 2009
Product News Automation
The PAV control box together with the servo
slides forms a manual positioning system for
the welding head
PAV
The PAV system makes it easier to keep the
welding head in optimal position and it also
makes it easier for the operator to make a
good job with less welding faults and costly
repairs.
The operators ergonomic safety is in focus.
The PAV allows the adjustment of the welding
head to be done fully remotely. There is no
need to climb or stretch to reach and operate
the manual slides for adjustment of weld
positions. The operator can all the time keep
the focus on the welding process and do
adjustments just by using the joystick.
By using the PAV with the controls mounted
on the remote box the operator can be more
flexible and move along a larger object and
still have full control over the position of the
welding head.
Operation
A PAV control box can control one or two
servo slides. With the joystick on the control
box or the remote control you can manually
control the movement of the welding head up/
down or left/right. With a push button you can
choose between low or high speed of the
movement. When high speed is activated the
push button lights up.
Applications
Shipbuilding (panels, sub-components)
Power generation (wind towers, boilers,
vessels)
Infrastructural components (beams, bridges)
Off-road vehicles (excavators, dump trucks)
PAV is available in three versions:
With control panel on the front
Suitable for ESABs A2 and A6 beam travelling
carriage. Automatic solutions with short distance
between welding head and PAV control box and
where the operator has a good overview of weld
joint and welding head without moving around.
With remote control (no panel on the front)
Suitable for Column & Booms and large automat-
ic installations with long distance between welding
head and PAV control box and when the operator
must move around in order to get a good view of
the welding joint.
Without control panel and remote control
Suitable for customized solutions where the
customers own remote control is adapted to the
PAV control box.
PAV- POSITIONING SYSTEM
Operator friendly
Ergonomic
Easy to use
Shorter set-up times
Higher quality
Improved working environment
Figure 2. ESABs shield gas technology, in which a
secondary gas is used alongside the plasma gas
Figure 1. m
3
plasma
TM
with torch PT36
Svetsaren no. 1 - 2009 - 67
Product News Cutting
ESABs m
3
plasma
TM
cutting system,
introduced in 2006 and described in
Svetsaren 1/2006, enables high-quality
precision cutting and marking and high
current/thick plate cutting with the same
PT-36 plasma torch - replacing up to three
single-purpose torches while consuming
fewer wear parts.
m
3
plasma
TM
offers an unsurpassed level of
reliability, economy and productivity.
The system now features a number of
innovations that widen the application scope
and enhance cutting quality:
PT-36 torch, upgradable for very thick
stainless steel and aluminium.
Use of a secondary gas around the
plasma arc.
R2 mode for round top edges.
Suitable for underwater cutting.
m
3
plasma
TM
continues its advance
Small to medium-sized metalworking and
manufacturing companies can now benefit
from the advantages of plasma cutting thanks
to the constant enhancements and ever-falling
costs of the technology. In terms of precision,
speed, flexibility and economy, modern
plasma cutting is unsurpassed. The potential
of the m plasma
TM
cutting system is such
that it will establish plasma cutting as a viable
process with new customer groups. It is a
complete high-performance system that is
quick and easy to install, demands little in
terms of operation and maintenance, offers a
broad range of functions and can assist the
full automation of the cutting process,
including marking and labelling.
The characteristics of m plasma
TM
The PT-36 torch can handle cuts in the widest
variety of geometrical shapes, bevel cutting
with a weld bevel angle of 0 to +/- 45 as well as
the most common marking and labelling tasks -
without changing tools. The cutting area depends
on the m plasma
TM
current source used (cutting
current 30 200A, 35 400A, 35 600A
according to version) and ranges between two
and a maximum of 60mm in construction steel,
stainless steel and aluminium. As an option, the
PT-36 plasma torch can be upgraded for cuts up
to 150mm in stainless steel and aluminium.
The m plasma
TM
system is ESABs first use of
so-called shield gas technology, in which a
secondary gas (eg, oxygen or nitrogen) is used
alongside the plasma gas, circulating around the
arc and providing it with a protective, stabilising
shell. The result is an exceptionally fine, accurate
arc that has greater density and stability in
comparison to conventional processes, and leads
to higher cutting speeds, more precise cut edges
and brilliant cut surfaces.
NEW FEATURES FOR M
3
PLASMA
TM
CUTTING SYSTEM
Figure 3. R2- a new quality mode for varnished
components.
68 - Svetsaren no. 1 - 2009
The latest generation of Columbus.NET
programming software enables quick, easy
creation of even the most complex cutting
programs. This ESAB innovation is based on
the Microsoft .NET developer platform and
thus has an ensured future. Companies that
invest in .NET are safeguarding their
investment against future technological
changes. COLUMBUS.NET is a genuine 32-bit
program and runs under the Windows XP and
Vista operating systems.
The practical advantages of the new software
include the option of fully automated program
and nesting generation. According to adjusted
values and criteria, Columbus.NET
automatically selects the flame-cut parts,
provides the nesting and technology data and
selects the most suitable plates. For weld
edge preparation - an increasingly important
function - the operator can choose between
bevel types V, X, Y and K. With Columbus.
In many cases, underwater cutting is a
sensible alternative to dry cutting with less
noise, reduced emission of dust, aerosols and
UV and a smaller heat affected zone around
the cut. m
3
technology allows underwater
plasma cutting; even marking and labelling is
no problem.
The R2 mode (Radius 2) is designed to meet
the specifications of the International Maritime
Organisation (IMO) for the standardised
curvature of round top edges of varnished
components. This mode in particular shows
the close connection between ESAB and the
international shipbuilding industry.
Another innovation with the m plasma system
is the option to pre-select, and switch
between, four different quality levels even
during the cutting process. (see Table).
NET, individual bevel types, with contours cut up
to five times, can be produced. The graphic user
interface is extremely helpful, especially where
different cutting and marking tools are combined.
The operator can see at a glance how Columbus
operates all tool combinations and automatically
generates the required traverse paths between
different tools. Operating errors are virtually ruled
out thanks to an ingenious plausibility check.
Columbus.NET also displays the entire program
structure in Columbus Explorer, arranged
optionally on one or two screens.
ESAB also announces an enhanced PDM
(production data management) system for use as
a data link between production and existing
planning systems. PDM connects existing
systems via interfaces, thus creating consistent
and current data transparency. Optimal integration
into production planning can be achieved by
connection to the COLUMBUS programming
system. For that purpose, control of the
workflows within the production process (control
station technology) has also been integrated into
the modular functionality of PDM. The PDM
system thus creates ideal conditions for reducing
operating costs, shortening cycle times and
increasing overall productivity. Instead of
impractical, cost-intensive local solutions, PDM
ensures that the whole production process
becomes transparent from planning through
production all the way to delivery.
SPECIAL SOFTWARE FOR AUTOMATIC
CUTTING PROCESSES
COLUMBUS.NET AND PDM FROM
ESAB
Svetsaren no. 1 - 2009 - 69
Product News Cutting
SAFESET is an ESAB contribution to easier
working, improved productivity and enhanced
operating safety. It is a new, complete range
of products for the central gas supply of
plasma cutting lines. The key components of
the modular-structured system are various
drawing stations in a space-saving panel
designed for wall mounting close to the
cutting machine. They are connected via a
loop system to the central store (single
cylinders, cylinder bundles or tanks), which is
located outside the working area. Precisely
attuned to each type of machine, the drawing
stations provide optimal gas pressure and
ease of operation right next to the
workstations.
SAFESET, A COMPLETE RANGE OF
PRODUCTS FOR CENTRAL PLASMA GAS
SUPPLY
QUATTROJET - THE INNOVATIVE
OXYFUEL TORCH
This monitoring system enhances the
safety of operators and workforce, the
environment and machinery - whilst
also improving the quality of automatic
cutting.
To ensure the correct distance between
the cutting nozzle and blank,
QUATTROJET features integrated
height sensing, thus eliminating the
need for an additional sensor system
installed separately on the torch.
Conventional systems such as spacer
rings wear out very quickly and thus
need regular replacement.
Other features of the compact, slim
QUATTROJET oxy fuel torch are an
internal ignition system protected
against dirt and damage, and a device
for rapid, tool-free nozzle changes.
ESAB has introduced QUATTROJET - a
completely new type of oxy fuel flame-cut-
ting system that makes this process even
more economical and paves the way for full
automation.
With automatic flame monitoring, the new
QUATTROJET oxy fuel torch recognises
any possible cutting break and
automatically stops the gas supply. So,
unlike traditional systems, the cutting
machine does not require permanent
monitoring by an operator, while fuel gas
and oxygen cannot escape unhindered.
The flame monitoring responds to any
faults in the cutting material or
disturbances to the cutting tool.
GL OBAL SOL UT I ONS F OR L OCA L CUS T OME RS EV ERYWHERE
It does not matter if our customers operate in
China, Germany, US, Brazil or Sweden. Wherever
in the world you buy ESAB products, these are
produced in accordance with the same global
EHS standards where occupational and product
health & safety always comes rst. Let us show
you what a well managed company can do for you!
Visit us at www.esab.com
Setting new
global standards
We have now gained OHSAS 18001
group certication from DNV. Our group
Environmental, Health & Safety Manage-
ment System was already IS14001 certi-
ed. This is believed to be the most com-
prehensive certication achieved by any
global company to date. It includes all
production operations, sales and central
functions within ESAB at 1 July 2007.
You will benet
wherever you are
b
o
x
i
n
f
o
r
m
a
t
i
o
n
.
c
o
m
ESAB AB
Box 8004 S-402 77 Gothenburg, Sweden
Tel. +46 31 50 90 00. Fax. +46 31 50 93 90
www.esab.com