The updated brief progress report for Sasan, Mundra, Krishnapatnam and Tilaiya UMPPs is enclosed for hosting the same on CEAs web site.
Central Electricity Authority Brief status of Progress of activities for Sasan UMPP
1.
SASAN UMPP-(6x660MW)
Name of Developer M/s Sasan Power Ltd. (Reliance Power Limited) Date of LOI 01.08.2007 Date of Transfer of SPV 07.08.2007 Date of signing of PPA 07.08.2007 Order of main plant 24.6.2008 Financial closure 20.4.2009 Commercial Operation Dates Unit Schedule COD as per original Power Latest COD Schedule as No. Purchase Agreement Indicated by the developer 1 06.05.2013 09.03.2013* 2 06.12.2013 30.04. 2013 3 06.07.2014 31.07.2013 4 06.02.2015 31.10.2013 5 06.09.2015 28.02.2014 6 06.04.2016 30.06.2014 * Synchronisation Levellised Tariff at the time of awardRs. 1.196 per kWhr
Land Acquired: Power Plant 3520 acres (94.47%) Captive Coal Blocks 4281 acres (56.4%). No issue pending in respect of land for power plant. Regarding coal blocks, forest land being taken in phases. NCL yet to handover the land earlier acquired by them under CBA Act. Environment and Forest Clearances: i) Environmental Clearance and Forest Clearance for main Plant: received. ii) iii) iv) Environment Clearance for Coal Mine (Mohar and Mohar Amlohri): received. Forest Clearance for Coal Mine (Mohar and Mohar Amlohri): - received. MoEF vide letter dated 23.11.2012 have accorded stage-I approval for the diversion of 965.400 hectares of forest land in favour of M/s Sasan Ultra Mega Power Project for their Chhatrasal Captive Coal Block (including 30.21 hectares of forest land for infrastructure development) in district Singrauli, Madhya Pradesh. Compliance of Stage-I conditions is yet to be completed.
2.
Project Progress
-1-
Power Plant BTG All six Units boiler and ESP foundation completed. Over 2.3 Lakh MT of BTG material shipped by Shanghal Electric. Unit # 3: Synchronized 0n 9.3.2013.. Unit #2: Boiler hydro test completed. Boiler pressure parts erection progress in Unit # 2,#1, #4. Unit #6 Boiler structure erection nearing completion. Turbine Generator (TG) Deck casting completed for Units# 2,# & #4 column lift in progress for Unit #1, # 5 & #6. More than 30,000 MT out of 58,803 MT Power House Building (PHB) and Bunker Structure erection completed for all 6 units.
Coal production commenced. Over 10.76 million cubic meter OB removed. Rope Shovel (43M3): 4 Nos commissioned. Large size Dozer(850-240HP)13 Nos commissioned, Graders (280 HP): 5 Nos commissioned. Dumpers (240 MT): 18 Nos commissioned. Drills (250 mm-160mm):8 Nos commissioned. Water spriklers(70 KL): 4 Nos commissioned. Dragline assembly in progress.
Critical Area: Completion of coal conveyor system from mine to power plant.
-2-
2.
Mundra UMPP (5x800MW) Name of Developer Coastal Gujarat Power Limited (Tata Power Company Ltd.) Date of LOI 28.12.2006 Date of Transfer of SPV 24.4 .2007 Date of signing of PPA 23.4.2007 Order of main plant 15.5.2007 Financial closure 24.4.2008 Commercial Operation Dates Unit No. 1. 2. 3. 4. 5. Schedule COD as worked out COD as per latest progress based on Power Purchase report Agreement Aug. 2012 7.3.2012(A) Feb. 2013 30.7.2012(A) Aug. 2013 27.10.2012(A) Feb. 2014 21.1.2013(A) Aug. 2014 Sept,2013 Synchronized on 4th March, 2013.
Unit-5: -
Leveliised Tariff at the time of award- Rs. 2.26 per kWhr 45% non escalable fuel comp. Land Acquired Power Plant 3222 acres. (almost 100%) Environment and Forest Clearances: Environmental Clearances and Forest Clearances for main plant: Environmental Clearances and Forest Clearances for Coal mines: Status of Commissioning Unit-1 Unit-2 Unit-3 Unit-4 Unit-5 COD achieved on 7.3.2012. COD achieved on 30.7.2012. COD achieved on 27.10.2012. COD achieved on 21.12013. Synchronized on 4th March, 2013. obtained. Not Applicable
-3-
3.
Krishnapatnam UMPP (4x1000MW) Name of Developer - Coastal Andhra Power Limited (Reliance Power Limited) Date of LOI 30.11.2007 Date of Transfer of SPV 29.1 .2008 Date of signing of PPA 23.3.2007 Order of main plant (BTG) October, 2010 Financial closure 07.07.2010. Commercial Operation Dates Schedule COD as worked Revised COD scheme COD as per latest out based on Power as per supplemental/ progress report Purchase Agreement Amended PPA (27.10.2010) 1. @ September, 2013 June 2013 2. April, 2014 Oct.2013 3. October, 2014 Feb. 2014 4. April, 2015 June 2014 5. October, 2015 Oct 2014 6. Feb 2015 * * Unit configuration revised from 5 x 800 MW to 6 x 660 MW. @ The developer has stopped the construction work at the project site citing new Regulation of the Govt. of Indonesia as the reason which prohibits sale of coal, including sale to affiliate companies, below bench mark price. Levellised Tariff at the time of awardRs. 2.33 per kWhr.
Unit No.*
Land Acquired: Power Plant -2546 Acres (97%) Environment and Forest Clearances: Environmental Clearances and Forest Clearances for main plant: Environmental Clearances and Forest Clearances for Coal mines: Applicable obtained. Not
Status 90% Boundary work completed. Leveling of site in Main Plant completed. Piling work carried out for Chimney, CW pump house and TG foundation. Ground improvement works done for Cooling Tower Area. Approach road constructed, Area drains, plant roads, permanent stores were taken-up for construction. APSPDCL vide letter dated 15.3.2012 has issued termination notice to CAPL stating that in view of the defaults and anticipatory breach having no alternative, the procurers together decided and elect to terminate the agreement and same shall come into effect from 7th day of receipt of this notice. CAPL vide letter dated 24.3.2012 intimated that they had approached the High Court of Delhi. APSPDCL vide letter dated 20.4.2012 informed that procurers filed counter affidavit on 16.4.2012. The Delhi High Court has dismissed the petition of CAPL on 2.7.2012. CAPL has approached Division Bench, Delhi High Court as well as Indian Arbitrator Council for Arbitration. The matter is sub-judice.
-4-
4.
Tilaiya UMPP (6x660MW) Name of Developer Power Limited) Date of LOI Date of Transfer of SPV Date of signing of PPA Order of main plant -
- Jharkhand Integrated Power Ltd. (Reliance 12.2.2009 7.8 .2009 7.8.2009 Jan, 2011.
Financial closure- In-principle ECB approval for US $ 2 billion received from RBI. Discussion with Domestic & International Banks/FIs are in advanced stage. Commercial Operation DatesUnit No. 1. 2. 3. 4. 5. 6. Schedule COD as worked out based on Power Purchase Agreement May 2015 Oct. 2015 March 2016 August 2016 Jan 2017 June 2017 COD As per latest progress report Construction yet to start
Levellised Tariff at the time of award- Rs. 1.77 per kWhr Land Acquired: Power Plant - 470Acres (19.5%), Captive Coal Block - Nil
Environment and Forest Clearances: i) Environmental Clearance and Forest Clearance for main Plant: Received. ii) Environment Clearance for the Kerandari B&C block: - TOR obtained. EIA study completed. EAC has considered the proposal in its meeting held on 18th Sept, 2012. iii) Forest Clearance for the Kerandari B&C block: - Proposal submitted at State forest department. Status: Pillaring work completed for project boundary. Mining Plan has been approved by Ministry of Coal. EPC contract executed with R-Infra. BTG tied up with SEC China. However NTP is yet to be issued to BTG supplier as land is yet to be handed over.